Вы находитесь на странице: 1из 16

OFFSHORE TECHNOLOGY CONFERENCE

6200 North Central Expressway


Dallas, Texas 75206
=~ OTC 1192
THIS IS A PREPRINT --- SUBJECT TO CORRECTION

Khazzan Dubai 1: Design, Construction and


Installation

By

R. S. Chamberlin, Chicago Bridge & Iron Co.

I'D Copyright 1970

Offshore Technology Conference on behalf of American Institute of Mining, Metallurgical, and


Petroleum Engineers, Inc., The American Association of Petroleum Geologists, American Institute of
Chemical Engineers, American Society of Civil Engineers, The American Society of Mechanical
Engineers, The Institute of Electri~al and Electronics Engineers, Inc., Marine Technology Society,
Society of Exploration Geophysicists, and Society of Naval Architects & Marine Engineers.

This paper was prepared for presentation at the Second Annual Offshore Technology Conference
to be held in Houston, Tex., April 22-24, 1970. Permission to copy is restricted to an abstract
of not more than 300 words. Illustrations may not be copied. Such use of an abstract should
contain conspicuous acknowledgment of where and by whom the paper is presented.

ABSTRACT located sixty miles offshore in


154 feet of water. The structure,
In early August, 1969, a the first of its kind, stores oil
15,000-ton, bottomless offshore produced from the Fateh Field.
oil storage tank was completed on Dubai Petroleum, a wholly owned
the shore of the Trucia1 Coast of subsidiary of Continental Oil
the sheikdom of Dubai. The suc- Company, operates the field for
cessful launching, towing and its partners, Dubai Marine Area
submerging of the tank were spec- Ltd. (Compagnie Francaise des
tacular operations receiving world- Petro1es and British Petroleum),
wide attention. These operations, Deutsch Erdo1-Aktiengese11schaft,
however, were preceded by extensive Dubai Sun Oil Company and Contin-
research and development programs ental Oil Company. Hispanoi1 has
to answer the many questions now replaced British Petroleum
surrounding a new or different as a partner of the DUMA group.
structure. These include tests The 15~000-ton structure (Figure
of crude and salt water, handling 1) is 270 feet in diameter and
of sludge, model test work and over 200 feet in height. It has
development of construction and no bottom and operates on the
installation techniques. water displacement principle. It
is always full with either water
INTRODUCTION or oil or a combination of the
two. Filling is accomplished by
Khazzan Dubai #1, a 500,900- placing oil in the tank above
barrel oil storage tank, placed water. The additional weight of
in service December, 1969, is the oil on the water creates an
imbalance in pressure which forces
References and illustrations at the water out of the tank through
end of paper. openings in the wall.
I-440 KHAZZAN DURAl #1: DESIGN, CONSTRUCTION AND INSTALLATION OTC 1192
The unusual structure requires STRUCTURAL DESIGN
special construction techniques
which enable it to be built on- The structural design of the
shore, launched and towed some offshore storage tank requires
sixty miles to its offshore loca- review and analysis of each
tion. The launching, towing and element under three separate
submerging were spectacular opera- conditions. The tank first must
tions that created worldwide be able to store the product
interest throughout the industry. which means withstanding the
Behind the success of the struc- buoyant effect of the oil. In
ture, however, were many years addition, it must be designed to
of meticulous study and research. resist the forces created by the
A new structure such as this environment when the tank is full
brings up unique and special oper- of oil or water. A completely
ating conditions which must be different set of conditions exists
considered. These include salt during submergence of the tank,
pickup by the oil and sludge and in certain areas high stresses
buildup at the oil/water inter- are developed that govern the
face. design.
Gaging techniques must be used Figure 2 is an engineering
to remotely monitor the oil/water drawing showing major dimensions.
interface, divert the incoming As is customary in the indus-
stream once the tank is filled or try, a 100-year storm wave with
shut down the pumps once the tank the characteristics noted in
is empty. Certain operating Table 1 was selected for design
advantages are expected: free purposes.
water will automatically precipi- The roof, a portion of a
tate to the water below the oil/ sphere, is under tension when
water interface, decreasing the the tank is full of oil. The
salt content of the crude, and membrane stress under this condi-
large buildup of wax or heavy tion is quite low and does not
ends at the interface can be govern the design. The hydrody-
removed by pumping when the tank namic loads under the design
is stripped out. wave create high compressive
The open sea location where loads in the roof when the tank
the tank is installed gives ample is full of water. The roof,
opportunities for wind to generate stiffened in two directions, is
large waves (over 39 feet in designed for the external load
height with 10-second periods). using critical buckling with a
Coupled with storm-driven currents, factor of safety of 2.0. In
these waves create tremendous addition to designing for local
forces on the oil storage tank. buckling, the roof was also
These large forces are resisted checked for overall stability
by an anchorage system consisting including a condition of non-
of 36"<1> steel piles cemented into symmetrical wave loadings. The
the sea floor. center bottle offered substantial
Sacrificial anodes were stiffness to the roof enhancing
selected for the corrosion protec- its overall stability.
tion system, but even here a The thickness of the roof
special test was performed in the plate in the area adjacent to
Gulf of Mexico to determine that the conical transition section
adequate current density was is governed by the stresses
being provided on all parts of experienced during submergence.
the heavily stiffened structure. Under this condition, these plates
A number of model tests were have high circumferential compres-
conducted to verify design assump- sive stresses,~nd a factor of
tions and determine the horsepower safety of 2.0 was used in the
required to tow the structure at design.
a reasonable speed. Model tests The shaft is designed for
were also performed to demonstrate external hydrostatic and hydro-
stability during all phases of dynamic loads, while the cone is
the submerging operation. designed for hydrodynamic loading.
OTC 1192 R. S. CHAMBERLIN I-441

These members are designed for toughness. As a criterion, the


critical circumferential buckling finished structure was to have
stresses with a factor of safety 15 foot-pounds of energy as
of 2.0 and longitudinal stress measured by Charpy V-notch speci-
allowable based on AWWA Standards mens at the operating temperature
with a 25% increase when storm which was assumed to be 50°F. To
loads are included. accomplish this, a material was
At locations where there is a selected that had a Charpy V of
discontinuity in the geometric 15 foot-pounds at O°F in the as-
shape, secondary stresses had to rolled condition. By selecting
be considered. One such area is materials with this property, the
the three-way intersection of the expected loss of ductility during
roof, cone and bottle. In these fabrication would not be enough
areas of discontinuity, all members to exceed the basic requirement
were designed to meet ASME Section for the completed structure.
III criteria for secondary stresses A modified ASTM A-442-60
for maximum allowable fiber and material was selected for the
membrane stresses. shell girder, roof, cone, shaft
Fatigue was considered in the and the upper course of the
design. Minor's law for cumulative shell of the bottle. The two
damage was used. Cyclic loading large girders at the base of the
created by waves in the open sea cone and the shaft were made from
for a 30-year period is the major ASTM 516, Grade 60 material.
factor in the fatigue analysis, Structural material and the
but the normal filling and empty- balance of the plate material
ing cycles were also considered. conformed to ASTM A-283, Grade C
The 80'~ bottle's (Figure 3) with the exception of the heavier
primary function is to assist in thickness of the pile which was
the submerging operation and, for procured to an A-36 specification.
reasons of economy, was designed Three thousand psi concrete was
for an internal pressure that used made according to ACI Speci-
would balance the external pres- fication 318-63.
sure it would experience during A combination of manual and
submergence. The bottle was automatic welding was used
designed for internal pressure, throughout with all procedures
using API Standard 620 stresses. qualified in accordance with the
During the submerging operation requirement of Section IX of the
as water is added to the bottle, ASME Boiler and Pressure Vessel
the pressure is allowed to build Code.
up but is counter-balanced by X-ray, ultrasonic and magnetic
external water pressure. However, particle examinations were used
during the latter part of submer- throughout as quality control
gence, some air is vented; so the tools. All of the inspections
net pressure does not exceed the were performed in accordance with
design pressure. the requirements of API Specifica-
The eccentric attachment of the tion 650. Critical joints consis-
piles to the structure creates ting of shaft-to-cone, roof-to-
large bending moments in addition bo~tle, roof-to-shell and radial
to shear load. The lower portion tube joints to shell and skirt
of the wall is heavily stiffened were all 100% inspected using a
to resist these high loads and combination of the previously
transfer them to the other portions described methods.
of the structure. The design did The center bottle was air
not take into account the strength tested to one and one-quarter
of the concrete encased in the toe times the design pressure.
and the wall. Reinforcing in the The dome roof and double wall
concrete was used to tie the two shell were checked for tightness
steel shell plates together. using a low pressure air test
In the early stages of design, with a soap bubble inspection of
it was decided that the material all exposed seams. In addition,
used in the structure should a low pressure vacuum test was
exhibit a certain degree of notch performed on the same elements.
I-442 KHAZZAN DUBAI #1: DESIGN. CONSTRUCTION AND INSTALLATION OTC 1192
MODEL TESTING TOWING TESTS
The large submerged offshore The basic concept of onshore
oil tank placed in relatively construction implies the need for
shallow water presented a diffi- towing the structure in the open
cult engineering problem too sea to its offshore location.
complicated for rigorous mathe- Because of the importance of this
matical analysis. As a result, requirement, towing tests were
a model test program was under- performed using a 1:48 Froude
taken. This would determine scale model.
magnitude and characteristics of A series of tests was performed
forces on the model resulting at General Dynamics' MTC towing
from wave action. basin. The model was towed at
Froude scale models were used various drafts under varying sea
for testing. This was done conditions to determine horsepower
because inertial forces are domi- requirements.
nant and the Froude number is the The towing of the completed
same for both model and the full structure was performed by two
size structure. This approach tugs, one 9,000 horsepower and
minimizes dynamic scaling errors. one 4,000 horsepower. The 60-
Three different models were mile journey required about
constructed, all scaled 1:48. fifteen hours. The actual results
Testing was done at the San compared favorably with the model
Diego Marine Technology Center tests.
(MTC) of General Dynamics Specifications required the
Corporation. The wave channel submerged storage tank to be
is 320 feet long, 12 feet wide located within 100 feet of a
and 6 feet deep. A hydraulically predetermined location. Once
operated, compound wedge wave again, this required moving the
generator is able to generate completely submerged tank by
regular sinusoidal waves over a the tugs. Model tests were per-
wide range of length and period. formed to simulate this condition
The wave profile was measured at CB&I's Research Facility in
by resistance and capacitance Plainfield, Illinois.
type wave measuring devices. The During final placement, the
probe output is processed by an two tugs were placed 180 0 apart.
oscillograph and reproduced on They maneuvered the submerged
photographic paper. tank with ease. Final location
The model is supported verti- of the tank was well within the
cally by four load cells that are tolerance - again demonstrating
used to measure vertical loads. the value of the model testing.
One load cell is used to measure
horizontal loads. A block sche- CONSTRUCTION
matic is shown on Figure 4.
A series of waves was run, one During the early phases of
with a 1.S-second period and a design, it was concluded that the
height of 9.75 inches, which cor- tank should be constructed onshore
responds to the design wave. for reasons of logic and economy.
Other waves with various lengths This approach, however, creates
and periods were used to develop the problem of moving and launch-
data to correlate the model test ing the lS,OOO-ton structure after
with theory and also to show the completion. -
influence of wave length on force. A number of different construc-
Some of the results are noted in tion and launching techniques were
Table 2. considered. The two most promis-
The horizontal and vertical ing schemes were a single or
forces measured on the model double graving dock.
varied slightly from those com- Before selecting the method,
puted. In final design the a site had to be located rela-
dynamic loads were increased 30 tively close to shore with com-
percent over those noted in Table patible onshore and offshore
2 as an added safety factor. topography.
I-443
OTC 1192 R S. CHAMBERLIN
A number of different sites TOWING AND SUBMERGING
were considered and the soil
geology tested to determine ground During towing and the first
water elevation, percolation rate phase of submerging, the struc-
and general characteristics of ture is extremely stable; since
the soil. If a single graving the circular wall cuts a large
dock were to be used~ the excava- water plane area (Figure 8). If
tion would be some 1z feet below the structure tips, the wall acts
the mean sea level which would like an outrigger on a canoe;
require constant dewatering; and the weight of the wall coming
while on the other hand, if a out of the water increases, and
double graving dock arrangement the apparent weight of the wall
were used, both the construction on the other side decreases
area and launching area would have creating a large righting force.
to retain an 8-foot head of water Once on location, submerging
while the tank is being moved begins by venting the air under
from the construction area to the the roof. This increases the
launching area. draft and the structure remains
Small pits 30 to 40 feet in stable and plumb until the outer
diameter were dug and filled with wall is submerged (draft - 31
water to determine seepage rate. feet). When this point of sub-
Dikes were also constructed and mergence is reached, the center
the surface treated with various of gravity of the structure is
materials such as a soil/cement still above the center of buoy-
mixture, asphalt compound and ancy and the structure rotates
polyethylene film. Water was about the radius of curvature
then pumped into these to deter- of the roof (180' R) lifting a
mine the leakage rate. portion of the concrete-filled
At the conclusion of the tests, wall out of the water (Figure 9)
it was decided that a double creating a righting moment.
graving dock scheme should be Venting of the air under the
used (Figure 5). The construction roof continues and the tank
area was excavated 1 foot above slowly returns to a vertical
sea level and the launching area position (Figure 10). The center
excavated 12 feet below sea level. container or bottle supports the
The structure is completely entire weight of the structure
assembled in the construction and the center of buoyancy has
area, including placement of the moved above the center of gravity.
concrete in the outer wall. Once The structure is now stable in
completed, the construction area an upright position. To continue
is diked, and water added so its submerging, water is pumped into
level is 8 feet above the construc- the bottle increasing the draft
tion area elevation. The tank is which is controlled by the buoy-
then floated and moved to the ancy provided in the cone and the
launching area (Figure 6). shaft. Pumping continues until
Once in the launching area, the structure is on the bottom
the breach is removed and the tank (Figure 11). The design is such
is ready for its trip to the sea that the draft can be controlled
(Figure 7). at any depth within the design
To float the open bottom struc- limit and all the operations
ture, air is pumped under the roof reversed to bring the structure
and pressurized until it supports back to the surface.
the weight of the tank. In this Once the structure is on the
condition~ the draft of the tank bottom, enough water is added to
is about ~ feet. The central the bottle to give it negative
container or bottle is pressurized buoyancy to hold it on location
independently of the roof with a while the piles are placed around
pressure high enough to balance the periphery. After the piles
or exceed the external water have been installed, the bottle
pressure expected during the sub- is flooded and covers removed from
merging operation. The tank is manholes in the bottle. The bottle
launched in this condition. now communicates with the volume
1-444 KHAZZAN DUBAI :/11: DESIGN, CONSTRUCTION AND INSTALLATION OTC 1192
under the roof and becomes part of A full scale pullout test was
the storage volume. performed to verify design assump-
tions and to demonstrate that
PILE DESIGN AND PLACEMENT neither a steadily applied load
nor a cyclic load caused progres-
The submerged storage tank is sive soil failures.
subjected to large dynamic forces The piles were placed from a
created by wind-driven waves and jack-up rig (Figure 12). Six
currents. In addition, the weight anchor lines were used for moving
of the structure changes with the and positioning the barge. Two
addition of oil. Table 3 shows of the lines were attached to the
the loads the tank must resist 30'~ shaft of the tank. This
while operating under severe storm procedure permitted accurate
conditions. positioning of the barge over the
A suitable site for the tank flange of the submerged tank.
was located reasonably close to A 42-inch hole was drilled 100
Dubai Petroleum's production plat- feet deep using a 24-inch tricone
form. A site investigation was bit, 32-inch hole opener and a
made. It included a hydrographic 42-inch underreamer (Figure 13).
and a seismic survey and a soil After the drilling was completed,
boring operation. The selected the pile was lowered into the
site was relatively level with a predrilled hole. It was c~mented
slope of about 1 foot in 100 feet. to the formation using a neat
The soil at the mud line consisted cement with a 28-day strength of
of sand and silt to a depth of 3,000 psi (Figure 14). The pile
about 3-1/2 feet to 8 feet below was then grouted to the structure
the mudline. A hard, well-cemented (Figure 15), with an expanding-
limestone cap rock layer with an type grout. Full scale tests of
average thickness of 5 feet under- the grouted connection were con-
lies the sea bed material. The ducted, and it was shown that
remaining stratum, extending to a the connection developed greater
depth of 100 feet, consisted of strength than the pile.
alternating layers of well-cemented
limestone, weakly-cemented limestone, OPERATIONAL CONSIDERATIONS
clay silts and sands.
Soil conditions at the site sug- Salt Pickup
gested a grouted-in-place piling
rather than a more conventional One problem crude producers face
driven piling. Experience of is contamination of their crude
others in the area confirmed this by salt. Foreign crude producers
when a driven pile had to be are faced with a specification
placed to great depths in order that permits only 10 pounds of
to develop the vertical load-carry- salt per 1,000 barrels of crude.
ing capacity required. This stringent specification
Individual piles were designed required special study, since the
to resist the maximum lateral, crude floats on the salt water
uplift and downward forces. Thirty- in the submerged storage tank.
six-inch O.D. piles were cemented The study noted that the
into the soil with a neat cement important cause of salt pickup in
that had a 28-day compressive oil is emulsification of brine in
strength of 3,000 psi. the oil. There are th~ee probable
The piles were designed for causes of such emulsification:
lateral loads by treating them as 1. Disturbance of the free
a beam on elastic fbundation. The interface between the crude oil
pile was considered fixed in the and salt water.
structure and penetrated the cap 2. Film of oil remaining on
rock 2 feet below the base of the the walls of the tank as the oil
tank. The maximum stress in the is withdrawn.
pile occurs under the moment 3. Funneling or sucking down
imposed by the maximum lateral at the outlet pipe.
load, plus an axial load acting A number of samples of crude
simultaneously with it. were tested. They demonstrated
OTC 1192 R. S. CHAMBERLIN I-445

that the flow rates expected sludge was obtained with the
throughout the structure were so properties noted on Table 5.
low that only a mild disturbance The sludge was compared with other
of the oil/water interface could published data for tank bottom
be expected. The expected flow wax/oil mixtures, and the plastic
rates would not cause emulsifica- properties estimated by extrapola-
tion. The test also demonstrated tion. With the sludge in question,
that a great deal of kinetic energy it appeared that the plastic point
must be supplied to create a true would be approximately -50°F.
emulsion between the oil and salt This indicates the wax would be
water. in the plastic stage at the opera-
To simulate the film of oil on ting temperature - even under the
the wall of the tank, a test was most severe conditions.
performed using a plastic appara- From these properties, it is
tus. The apparatus is preferen- apparent that the wax would flow
tially wet by oil as steel. would to the interface and flow freely
be. The crude sample used for the along it. The other heavy ends
experiment contained approximately would also end up on the interface
42 pounds of salt per 1,000 barrels floating on the water.
of crude. One of the experiments The inverted funnel shape of
was done at the actual linear rate the submerged storage tank has an
of movement. A second one was advantage over a conventional
done at double the rate. In each ground storage tank, because all
case the interface was recycled up of the sludge can be conveniently
and down forty times to far exceed collected at a single outlet
any anticipated recycling in the point. This permits a number of
actual tank. The results of three different methods to be considered
samples from the first run were for removing the sludge. By
noted on Table 4. mixing it with hot oil, for
It can generally be concluded example, a slurry can be obtained
that there was no salt pickup in that can be pumped in a conven-
the crude, as the discrepancy in tional manner. The second method
the results is well within testing would be to add heat through a
tolerance. coil to melt the wax in the sludge
The other possible and most and pump it out at periodic inter-
likely means of emulsification of vals. Another possible method
the oil would be at the oil outlet would be to remove it by a
where a vortex action might suck separate mechanical pumping system.
salt water with oil into a pump Another possible concern is
outlet. To circumvent this, one coating of the structure with
of the capacitance probes monitors paraffin. Others havelstudied
the interface at a point where this problem and Jorda studied
this would not occur and shuts the paraffin deposition on metal sur-
pump off. faces of different roughnesses.
He says that slowly cooled crude
Handling Sludge oil will not cause serious depo-
sition on the surface. The
Many of the crudes produced in deposition, he feels, is also
the Middle East have a high wax dependent on the nature of the
make-up. When the oil is stored, wax and the velocity past the
it undergoes slow cooling with interface. From the expected
some crystallization of the high flow rates in the tank, there
melting wax fractions which settle appeared little likelihood of
to the bottom. Sand, emulsified clogging of the holes in the oil
oil, asphalt and other impurities inlet or transfer nozzles. Some
also settle with the wax during minor deposition may occur on the
storage. In conventional ground walls of the tank, but since the
storage tanks, the bottoms have oil is cooled slowly and uniformly,
to be removed periodically to pre- the deposition will more likely
vent clogging of pipelines and end up at the oil/water interface.
decrease in storage capacity. •
A typical sample of Middle East Corrosion Protection
1-446 KHAZZAN DUBAI #1: DESIGN, CONSTRUCTION AND INSTALLATION OTC 1192
A sacrificial anode system was located at the lowest level in
selected for corrosion protection the tank. It indicates when the.
of the surface below the mean sea tank is·full and diverts the
level, both internally and exter- incoming oil flow to the other
nally. The water at the offshore storage tanks. A second probe,
location has a resistivity in the located at the upper part of the
range of 18-22 ohm-centimeters tank, indicates that the tank
and a sacrificial system has is empty of oil and shuts the
proved very workable on other pumps off.
structures located in the same Gaging tables have also been
area. provided for use with the capaci-
This structure did present one tance probe monitoring system.
unusual problem due to the size As a further check, flow meters
and spacing of the roof stiffeners record volume placed into storage
(Figure 2). The distribution of and pumped to tankers.
the current is very important in
obtaining satisfactory protection, CONCLUSION
and it was felt that the stiffeners
could possibly cause some shielding The successful installation
with an attendant poor current and operation of Khazzan Dubai
distribution. #1 is another step forward for
In view of the complexity of the offshore oil industry.
the structure, a test panel was Storage of crude at an offshore
constructed and tested. These producing area gives the producer
tests indicated a need for over- an alternate method of developing
lapping of anode zones to provide a field.
adequate current density and to In the current installation,
insure protection of all surfaces. the tank is used for storage only.
The anodes were installed on the However, in future installations
structure as suggested by the the inherent strength of the
test. Recent reports indicate a structure can be used for suppor-
satisfactory polarization and ting a platform or attachment of
current distribution at the a tanker mooring device. If
reference cells on the completed either is used, the overall value
structure. of the structure will be increased.
Model testing has proven to
Gaging be an invaluable aid during the
many phases of design of the
A number of different methods of structure. Extensive use of
gaging were considered - includ- models was made to determine
ing a specially designed float towing characteristics and sub-
capable of floating on the oil/ merging sequence. In addition,
water interface. A perforated model testing was used to confirm
tape attached to the float would design assumptions of the wave
operate a counter to indicate forces on the large submerged
liquid level in the tank. objects.
Another explored system Subscale and full scale tests
involved a set of differential were performed on the grouted
pressure transmitters to sense pile-to-structure connection. A
the interface of five different full scale pile pull-out test
elevations in the tank. The demonstrated that the expected
measurements in this system would pile loading would not cause
have been made by means of progressive soil failures.
bubblers located at specific
locations in the tank.
The selected system is a set REFERENCE
of capacitance probes capable of
detecting the oil/water interface. 1. Jorda, R. M., "Paraffin
They are placed at four different Deposition and Prevention
elevations in the tank and are in Oil Wells", Journal
monitor~d remotely on the opera- of Petroleum Technology,
ting platform. One probe is December 1966).
Table 1
Table 2

Chart depth: 154.0'


WAVE LOADS
Maximum astronomical tide: 5.9'
Height Period Horizontal Vertical
Storm tide: 1.0'
Model 9.75" 1.52 Sec. 91# 125#
Still water depth: 159.9'
Scaled to Structure 39.5' 10.5 Sec. 10,100k 13,750k
Maximum wave height: 39.0'
Period of maximum wave: 10.5 seconds
Crest elevation above bottom: 183.2'

Table 3 Table 4

ORIGINAL SAMPLE AFTER 40 CYCLES


CONDITION MAX. DOWN MAX. UPLIFT MAX. HORIZ.
Full of water 17,000k ... 0 42.0 Ibs of salt/MBbl of crude 43.4 Ibs of salt/MBbl of crude
44.4Ibs of salt/MBbl of crude 43.6 Ibs of salt/MBbl of crude
No storm
43.4 Ibs of salt/MBbl of crude 43.5 Ibs of salt/MBbl of crude
Full of oil
_. 14,000k 0 43.3 Ibs of salt/MBbl of crude (Ave.) 43.5 Ibs of salt/MBbl of crude (Ave.)
No storm

Full of water 36,500 k 2,500 k 13,300k


+100-yr. storm
Table 5
Full of oil 5,500k 33,500 k 13,300k
+100·yr. storm Water & Sediment 1%
Wax 37%
Oil 62%
Viscosity 4.38 c.s. at 2100F
Gravity 0.865 at 1400 F
Fig. 1

- 1 - - - - - --'._--~ -

L
Fig. 2 - Section through storage tank.
Uplift Strain
Gauges

Water Line

Barge Load
Strain Gauge
I MODEL --==t~

WAVE

,. 2~~~S
Amp Q AIrIG AnpO
I I I
• J I I

t ' t I I I
I
,
-----J
....
'i- ._
I
..J

CEC Oscillograph

Fig. 4

Fig. 3

Вам также может понравиться