Академический Документы
Профессиональный Документы
Культура Документы
www.indunatraining.co.za
No part of this book may be reproduced or transmitted in any form or by any means,
electronic or mechanical, including photocopying, recording or any information
storage and retrieval system, without permission in writing from Induna Online,
8 Buffalo Road, Gallo Manor 2052.
Table of Contents
1 Lesson 1 - Introduction and Overview: The Practical Use of FIDIC Contracts
FIDIC represents Consulting Engineers worldwide through Member Associations in over 100
countries whose members are consulting engineering firms employing some one million staff.
FIDIC publishes standard forms of agreements between Clients and Consultants and standard
forms of Contracts between Employers, Contractors and organisations or joint ventures delivering
the three basic types of Works projects via design-bid-build, design-build or turnkey project
delivery.
Founded in 1913;
Members endorse FIDIC’s statutes and policy statements and comply with FIDIC’s Code of
Ethics;
The FIDIC Short Form of Contract (Green Book, 1st Edition 1999) has been prepared with short
sentences and simple straightforward language, and is suitable when the work is uncomplicated
and the parties do not wish the complexities of the forms for major Works. The Short Form
General Conditions are only ten pages in length and the simple language assists easy translation.
It is recommended for building or engineering Works of relatively small capital value and/or short
construction time. Depending upon the type of work and the circumstances, this form may also
be suitable for Contracts of greater value, particularly for relatively simple or repetitive work.
The minor Works form of Contract was originally developed by FIDIC for projects with capital
value under US$500 000, a construction time of not more than six months, and without the need
for specialist subcontracts.
The works comprise construction but may include, or wholly comprise, electrical, mechanical
or other engineering work;
The contractor constructs the Works, irrespective of whether the design is provided by the
Employer or by his Representative (if any) or by the Contractor;
The Employer may wish to appoint an individual or firm as his Representative to carry out
certain duties; and
The Employer has optional choices for valuation and payment methods.
Larger and more complex than minor Works projects, traditional construction projects involve
civil engineering and building Works required by an Employer who, unless he carries out the
design in-house, would normally commission a Consulting Engineer to design the Works. It is to
be noted that traditional construction projects often also include some elements of Contractor
designed civil, electrical or mechanical engineering work.
When the Contract has been awarded and the work carried out, payment is made to the Contractor
on the basis of completed work. At the end of every month the work completed is measured and
then payment is calculated by multiplying the units of each work item satisfactorily completed by
the unit rate stated in the relevant Bill of Quantities. This type of Contract is often referred to as
a “remeasured work Contract”. Thus payment can also be said to be made on “inputs”, i.e. the
Contractor is paid against the inputs he delivers.
The Employer:
Appoints a Consulting Engineer to carry out the design work and prepare the Bill of
Quantities;
Appoints the Engineer to administer the Contract, monitor the construction Works and
certify payment;
Payment to the Contractor will be according to a Bill of Quantities or lump sums for
approved work done;
The Employer seeks to ensure an equitable sharing of construction risks in the contractual
arrangements, e.g. he takes the risk of unexpected adverse ground conditions and, owing
to the decision to carry a part of the construction risk, the Employer accepts that the
quantities are estimated and overruns may occur to the original Contract sum and, possibly,
the completion date.
Notes
Contracts for the supply and installation of Plant and equipment, as opposed to civil Works
construction, involve the design, manufacture, supply, installation and commissioning of specially
engineered Plant and equipment.
However, the FIDIC Yellow Book is being used more and more on Civil Engineering Projects where
the Employer requires the Contractor to undertake the design.
Larger and more complex than minor Works projects, traditional Plant projects involve the design,
manufacture, delivery, erection, testing and commissioning of mechanical and electrical Plant by
a Contractor to an outline or performance Specification prepared by the Employer.
The procurement of Works covering the supply and installation of Plant and equipment has
traditionally closely followed the same procedure as for construction Works described above,
however, with certain significant differences. The differences are due to the disparity between
the two types of projects:
Much of the Plant is manufactured off Site at a factory whereas, for construction work, the
execution of the work is for the most part carried out at Site;
The detailed design of the Plant is the responsibility of the Contractor with, usually, only
concept or preliminary design being done by the Employer;
Testing and commissioning are more comprehensive and stringent on a Plant project.
With regard to the design of the Plant and/or equipment, this is the responsibility of the
Contractor, who will design his Plant or equipment to fulfil outline or performance Specifications
set by the Employer or his consultant, normally contained in the document entitled “Employer’s
Requirements”.
The Employer:
Will appoint the Engineer to administer the Contract, monitor the design and manufacturing
activities, the installation and erection on Site and construction work and to certify payment;
and
Owing to a decision to carry a part of the construction risk, the Employer accepts that
overruns may occur to the original Contract sum and, possibly, the completion date.
In recent years there is a need for Contract forms where the emphasis is on a fixed final price
and time as an alternative to the traditional forms where the final price and time are somewhat
variable.
Also owners, investors and developers, who do not have their own technical staff capable of
designing the facility in question or who do not wish to take the responsibility of designing their
own facility, go directly to suitable Contractors to design and construct their project on a “turnkey”
basis.
Some also believe that the total implementation time can be shortened if the design work is
carried out by the Contractor during the early stages of the Contract, e.g. partly in parallel with
his mobilisation work.
The Specification provided by the Employer will be a performance type Specification, i.e. defining
the output and performance to be achieved by the facility with very little, if any, detailed
requirements.
However, turnkey projects do also include the whole range of projects from those with minimum
Specification by the Employer right through to those with very detailed and complex requirements
being specified by the Employer.
Normally the majority of the design in a turnkey project is carried out by the Contractor but, on
occasion, a substantial part of the design is provided to the Contractor by the Employer. The term
“turnkey” can perhaps be said to be more used in Europe while the substantially equivalent term
used in the US and elsewhere is “EPC”, meaning “Engineer-Procure-Construct”.
Note: For this type of project the Contractor is responsible for all the Engineering,
Procurement and Construction (“EPC”) to provide a fully equipped facility ready
for operation (at the “turn of the key”).
The Employer:
Wishes the Contractor to take total responsibility for the design and construction of the
facility and to hand it over ready to operate “at the turn of a key”;
Wishes a high degree of certainty that the agreed Contract Price and time will not be
exceeded; and
Wishes the project to be organised on a strictly two Party approach, i.e. without an Engineer;
Does not wish to be involved in the day-to-day progress of the work, provided the end
result meets the performance criteria he has specified;
Is willing to pay more for the construction of his project (than would be the case if the
Construction or Plant Contracts were used) in return for the Contractor bearing the extra
risks associated with enhanced certainty of final price and time.
The Design-Build-Operate (“DBO”) approach to contracting combine’s long term operation and
maintenance of a facility into one single Contract awarded to a single Contractor. The Contractor
will usually be a joint venture or consortium representing all the skills called for in a DBO
arrangement.
The Contractor will be responsible, not merely for providing the facility, but in fact for providing
a lasting service.
FIDIC has chosen to adopt the green-field DBO, with a twenty year operation period, and has
selected the single Contract awarded to a single contracting entity (which will almost certainly be a
consortium or joint venture) to optimise the co-ordination of innovation, quality and performance,
rather than award separate Contracts for design-build and for operation. The Contractor has no
responsibility for financing the project nor for its ultimate commercial success.
FIDIC recognises that the successful performance of a long term DBO Contract requires that the
Parties fully understand the overall time framework and the need for a long term commitment by
both the Employer and the Contractor. In trying to achieve this understanding and commitment,
it has been necessary to introduce new procedures and new terminology which are not found in
the other FIDIC Contracts.
Introduction
Each of the 1999 FIDIC Contract documents includes:
Forms (third part), e.g. Letter of Tender, Contract Agreement and Dispute Adjudication
Agreements.
General Conditions
The General Conditions are intended to be used unchanged for every project. The Particular
Conditions are prepared for the particular project to include any changes or additional clauses to
suit the local and project requirements.
Particular Conditions
Ideally a Contract is an agreement freely negotiated between two parties of equal bargaining
power with equal access to legal advice and assistance. Where there is an imbalance of bargaining
power between the parties there is a danger that the terms and conditions of the Contract become
unbalanced.
The Particular Conditions generally include the Appendix to Tender which gives essential project
information, some of which must be completed by the Employer before issuing the Tender
Documents, together with some information which must be added by the Tenderer.
Special Provisions.
Definitions
It is crucial to always have in mind the definitions and to use them carefully. When, for
example, using the word “works” the draftsmen should take into consideration that
“Works” means a different and defined thing;
Cross References
FIDIC Conditions contain many cross references which should be taken into account.
For example, it makes a great difference whether an additional claim of the Employer
has to be notified according to Sub-clause 2.5 or not. Only by reference to Sub-
clause 2.5 it is ensured that the Employer is not allowed to withhold payments out of
the certification procedure which is ruled by the Conditions;
Legal Meaning
Users should carefully check the legal meaning of any word which becomes inserted
in the Contract, if the ruling language is English. Under all circumstances it should be
checked whether the used expression is suitable for the particular circumstances;
Necessary
Any amendments to the Contract should first be examined as to whether they are
necessary or not. It happens quite often that the parties add milestone clauses to the
Contract, which are unsuitable.
Local Requirements
The Particular Conditions are prepared for the particular project and should include any
changes or additional clauses which the parties have decided to include for adaptation
for the local and project requirements.
A serious pitfall is to ignore the local requirements.
Applicable Law
The Governing Law should be stated in the Contract.
Language
Priority of Documents
It is strongly recommended to recognise and take into consideration that Sub-clause 1.5
rules the priority of the Contract documents.
The Special Provisions are the Clauses in the Contract which have been altered by the drafter of
the Contract – generally the Employer. It is not recommended to change too many clauses in FIDIC
as the Clauses are interlinked and by changing one clause will result in many other clauses having
to be changed as well.
Contract Agreement
Similar defined words and phrases are used in all 1999 Editions, the main exception being their
respective descriptions of the documents comprised in the Contract:
Forms of Security and Forms of Letter of Tender, Contract Agreement and Dispute
Adjudication Agreement;
There are example texts for six forms of securities, which are available in electronic form so
that users can conveniently use them when preparing the Tender documents:
Tender Security;
In the Construction and Plant (and DBO) Contracts, the Appendix to Tender(Contract Data)
provide a convenient checklist of all the essential data required for the various Sub-clauses;
At the end of all the 1999 Editions, the Dispute Adjudication Agreements are quite short,
because they incorporate (by reference) the General Conditions of Dispute Adjudication
Agreement appended to the General Conditions.
They each have obligations, duties and rights towards one another under the Contract and each
of these obligations, duties and rights is governed by the use of the word “shall” or “may”.
Neither Party may assign the whole or any part of the Contract to a third Party, without the prior
written agreement of the other Party to do so.
Neither party may alter the Contract unilaterally once it has been entered into.
It is essential that each Party is a legal person or entity under the law of the Country under which
it has been constituted, as only legal persons or entities can enter into Contracts.
Contractor’s Representative
The Contractor’s Representative is appointed by the Contractor to represent the Contractor on
Site in the day-to-day running of the Contract.
Certain jurisdictions require the Contractor’s Representative to possess a kind of licence or specific
experience. Should this be the case, the Particular Conditions shall incorporate these additional
requirements.
Most Contractors refer to their representative as “Site Agent”, “Site Manager”, “Project Manager”,
“Construction Manager” or some similar title. Whatever title they choose to use, the person
concerned has the complete duties and responsibilities which are assigned to the Contractor’s
Representative in the Contract and it must be made quite clear where the lines of communication
and responsibility lie.
Under the Red and Yellow Book Contracts the Employers Agent is called the
Engineer. Under the Silver and Gold Book the Employer may use an Employer’s
Representative.
This Engineer or Employer’s Representative is appointed by the Employer and should be named in
the Appendix to Tender or Contract Data so that tenderers know, when preparing their Tenders,
who the Employer is intending to appoint as his representative.
Whoever the Employer appoints must have a clear understanding of his role which is to “act for
the Employer” and in the best interests of the Employer but, at the same time, he must act with
fairness and integrity when making determinations under Sub-clause 3.5 [Determinations].
The Employer may split or divide the role of his representative but, if he does, for example, by
appointing a Design Engineer to review the design of the Works and a Supervision Engineer to
oversee their construction or installation, then each of these persons must be clearly named and
identified in the Contract and their role and authority carefully described.
The Contractor is not permitted to subcontract the whole of the Works and, if he does, then
these are grounds for the Employer to terminate the Contract;
The Contractor must obtain the consent of the Employer’s Representative prior to engaging
any Subcontractor.
Note: This is “consent” not “approval” and reinforces the point that the Contractor
is fully responsible for any actions, omissions or failures of his Subcontractors,
notwithstanding any consent.
If the Employer wishes the Contractor to use a particular Subcontractor or supplier for a particular
part of the Works (a Nominated Subcontractor) – for example to give work to a local Contractor or
to standardise on the use of equipment with other similar facilities owned by the Employer – then
he can require the Contractor to engage such persons by naming them in the Contract.
However, the Employer cannot force the Contractor to accept a Nominated Subcontractor against
whom the Contractor raises reasonable objection.
Financiers
Thus, whether financing for the project is being provided by one of the International Financial
Institutions (such as the World Bank) or governmental loans or grants, the Employer must attach
evidence of his financial arrangements to the Employer’s Requirements. Such evidence could
be in the form of copies of financing agreements or irrevocable letters of credit, sufficient for
tenderers to have confidence that funding is, or will be, in place for the complete project.
Insurers
Notes
Introduction
Definitions for the (capitalised) defined terms in the 1999 Editions of the FIDIC contracts are
extensive;
Definitions are identical across all the FIDIC forms of contract, are grouped not alphabetically but
in six different categories:
Dates, Tests;
Other definitions.
For a valid contract there must be “Offer and Acceptance”. The Contractor’s Tender or Bid is his
Offer and the Employer Accepts the Bid by means of a Letter of Acceptance – never use Letters
of Intent!!!!!!!!!!!!
The Country whose Laws will govern the Contract will normally be selected by the Employer and
will usually be his Country. It is assumed that the Contractor will have familiarised himself with
such Laws, since:
If there is an ambiguity between the Laws and the Contract the provisions of the Laws,
where they are of a mandatory nature, will overrule Contract provisions.
Including the words “agree”, “agreed” or “agreement” require the agreement to be recorded
in writing can be a trap for the unwary and would be interpreted literally in some jurisdictions.
However, absent an agreement in writing, if one Party acts on an oral agreement to their detriment
with the knowledge of the other Party, this may give rise to an estoppel.
The Statement that headings are not relevant to the interpretation of the Contract is a useful
reminder not to take them literally. Indeed, a number of Sub-clauses relate to far more than the
topic indicated by the heading. For example, Sub-clause 4.8 is headed “Safety Procedures” but
also deals with Site security and the impact of the Works on the surrounding areas. Thus, the
heading of Sub-clause 1.3 [Communications] is the cover for the only place in the Contract which
sets any time requirement for the making of a determination for the issuing of certificates.
Notes
Sub-clause 1.3 [Communications]
All “approvals”, “certificates”, “consents” and “determinations” are to be in writing, are not to
be unreasonably withheld or delayed and the acceptable form and details of addresses are to be
specified. It is important that all parties are aware of the correct address to which communications
should be sent.
One of the few exceptions is instructions which, by Sub-clause 3.3, are to be in writing, “wherever
practical”.
It is recommended however, that all instructions should be in writing as this will eliminate any
possibility of misinterpreting an oral instruction. It is also good project management.
Care must be taken by both parties to ensure that those working at the place to which
communications are to be sent are also aware of this.
The accepted forms of electronic communication will be agreed upon in the Particular Conditions
of Contract.
The final part of this Sub-clause is of particular significance. Approvals, certificates and consents to
determination shall not be unreasonably withheld or delayed. In particular, where determinations
are required by the Engineer, they shall not be “unreasonably withheld or delayed”. This is
particularly important because, for example, Sub-clause 3.5 does not provide any time limit for
the Engineer to make his determinations.
The FIDIC DBO Contract published in 2008 has included “Notices” in the definition. A notice
is a special form of communication usually associated either with a Party establishing its right
to additional compensation or giving notice to the other Party of important requirements or
instructions affecting the structure or content of the Contract or the work to be done. That is
why “Notice” is a defined term in the DBO Contract. If it is intended that instructions or other
communications, given during a meeting and recorded in the minutes of that meeting, are
intended to be notices given by one Party to the other, this intention should be clearly stated in
the minutes. By signing the minutes both parties have then accepted this provision. If this is not
properly recorded the minutes may well be construed simply as a record of a Statement made
during the meeting and have no contractual weight.
The Appendix to Tender should set out the language of the Contract. The law of the Country is
also to be specified.
In the real World few Employers will agree to a governing law other than the law of their own
Country.
It is to be noted that the General Conditions is placed relatively low in order of priority, but this
itself reflects the common law position that the written words chosen by the parties ought to have
priority, on questions of interpretation, over the printed words (or standard wording) used by the
parties. Although the final paragraph of this Sub-clause sensibly suggests that, if necessary, the
Engineer should issue clarification, there is no sanction if no such instruction is issued.
Under the Laws of many countries the Tender and Letter of Acceptance will be sufficient to create
a binding Contract between the parties and the Contract Agreement will merely further record or
confirm the terms of that Contract.
Sub-clause 1.7 [Assignment]
Neither Party can assign its interest in the Contract without the prior written agreement of the
other.
Provides for the giving of a notice by the Contractor if there is delay and/or where
information is not provided;
Provision for a further notice, after which, if there is continued default, the Contractor
is entitled to an extension of time and his Costs plus profit;
Contractor should provide the requisite notice where there is any realistic possibility of
delay or disruption resulting from late release of information.
The Employer has a right to use and copy the Contractor’s Documents during the life of the project
provided that use relates to the project.
As with Sub-clause 1.10 the Contractor may copy and use, for the purposes of the Contract only,
documents belonging to the Employer.
By definition Sub-clause 1.1.47 [Laws] means all national (or state) legislation, statutes, ordinances,
and other Laws, and regulations and by-laws of any legally constituted public authority. The
Contractor remains liable for the matters covered by the sub-clause and he must remember that
“ignorance of the law is no excuse”.
Notes
Introduction
The role of the Employer is dealt with in five Sub-clauses of Clause 2 of the 1999 Editions:
Such right to access to and possession of the Site may not be exclusive;
Access or possession to the Site may be withheld until the Contractor provides the
Performance Security required by Sub-clause 4.2.
The failure by the Employer to give access as set out in the Contract; or
If no time is specified within such time as may be required to enable the Contractor to
proceed in accordance with his programme, provided he gives notice to the Engineer the
Contractor, may be entitled to an extension of time pursuant to Sub-clause 8.4 and payment
of any Costs (including reasonable profit);
No extension of time will be granted if the Employer’s failure to give possession or access
was caused by an error or delay by the Contractor, including delay in the submission of the
Contractor’s Documents;
The Employer has the responsibility to provide access to the Site in the time stated in
Appendix to Tender. If there is no time stated in Appendix to Tender the access must be
provided in such a manner to not delay the Contractor and his programme of Works (Sub-
clause 8.3);
It is not necessary for the Employer to grant access to the whole Site right at the start.
It is sufficient to enable the Contractor to proceed unhindered in accordance with his
programme;
A failure to make the Site available might lead to the Contractor being entitled to an
extension of time and consequential Costs. As recommended in the Particular Conditions
the prudent Employer, if he recognises that it may not be able to grant access early or
exclusively, should make this clear in the Specification;
It should be noted that the Employer is only required to give the Contractor the “right”
of access to the Site. It is up to the Contractor to ensure that the means of access is
either already available in conjunction with the “right” and, if so, that it is suitable for the
Contractor’s needs, or, if not, that suitable means of access can be constructed or otherwise
provided or found by the Contractor;
If the Employer fails to make the Site available, as required by this Sub-clause, the Contractor
is entitled to be reimbursed Cost Plus Profit.
Access:
The definition of the Site is a wide one. Under Sub-clause 1.1.6.7 the “Site” is defined
as the place not only where the permanent Works are to be executed, and to which
Plant and Materials are to be delivered, but also “any other places as may be specified
in the Contract as forming part of the Site”. Therefore, it is important that all parties to
the Contract understand where these “other places” may be;
The right of access referred to here is the right to enter the Site. This is not the same
as the “Access Route” which is referred to at Sub-clause 4.15. It is the Contractor’s
responsibility to satisfy himself as to the adequacy of any access routes to the Site;
Sub-clause 2.1 is carefully qualified in that it expressly states that the Contractor will
not necessarily have exclusive rights of access and possession of the Site. It is important
that the Contractor appreciates this.
The Contractor should try to establish as part of the Tender process to what extent his
access will not be exclusive.
This Sub-clause also refers to the possibility of the Contractor being given access to
parts of the Site. It is important that the Contractor is aware of exactly which parts of
the Site will be available and when. The Contractor should check that this is made clear
in the Appendix to Tender;
As soon as the Contractor takes possession of the Site he becomes responsible for a
number of obligations whereby the Contractor becomes fully responsible for safety
and Site security.
In obtaining copies of the relevant Laws which are not readily available; and
In the making of any applications for permits, licences and approvals which the Contractor
will need to make in accordance with those Laws;
The Employer is only required to provide this assistance if so requested by the Contractor.
Co-operate with the Contractor to the limited extent provided for in Sub-clause 4.6;
Comply with the health and safety requirements set out in paragraphs (a) to (c) of Sub-
clause 4.8;
Take all reasonable steps to protect the environment both on and off the Site as required
by Sub-clause 4.18.
The Employer must give notice to the Contractor if he intends to make any material change
to his financial arrangements;
If that evidence is not provided the Contractor may, subject to the provision of the necessary
notices, suspend work or even terminate the Contract.
Thus the FIDIC Contract recognises the risk of whether the Employer is capable of paying
for the project and, in particular, for any Variations that he may order. His financial
arrangements may be requested by the Contractor and, upon such request, the Employer
should provide the information requested;
The Sub-clause thus provides a mechanism whereby the Contractor can obtain confirmation
that sufficient funding arrangements are in place to enable him to be paid;
The nature of the evidence may often depend upon the source of funding. If funding is
being provided as a loan or grant from an International Financing Institution (“IFI”), such as
one of the multilateral development banks, it should be possible to provide copies of loan
documentation evidencing the arrangements;
There is no definition, however, of what constitutes “reasonable evidence” and this may
become important in case of a dispute relating to its precise meaning due to serious
sanction that follows such failure. All that is said is that the evidence must show that the
Employer is able to pay the Contract Price in accordance with Clause 14
Simple consideration of the sub-clause in isolation suggests that there is little sanction
available to the Contractor as a result of any failure by the Employer to provide the
reasonable evidence requested. However, in accordance with Sub-clause 16.1, should the
Employer fail in the twenty-eight day period to comply with Sub-clause 2.4, the Contractor
may, after giving not less than twenty-one days’ notice to the Employer, suspend work. This
potentially gives a period of forty-nine (i.e. twenty-eight plus twenty-one) working days
before a Contractor is entitled to suspend;
If the Contractor does not receive reasonable evidence within forty-two days of giving
notice under Sub-clause 16.1 then, pursuant to Sub-clause 16.2, the Contractor is entitled
to terminate the Contract.
The notice relating to payment should be given as soon as practicable after the Employer
has become aware of the event or circumstance which gives rise to the claim;
Any notice relating to the extension of the Defects Notification Period should be given
before the expiry of that period;
The Employer must also provide substantiation including the basis of the claim and details
of the relief sought;
Once notice has been given the Engineer shall make a determination in accordance with
Sub-clause 3.5;
Any amount payable under Sub-clause 2.5 may be included as a deduction in the Contract
Price and Payment Certificates;
The Employer cannot make any deduction by way of set-off or any other claim unless it is in
accordance with the Engineer’s determination;
Notice is not required for payments due to the Employer for services under Sub-clause 14.19
or equipment under Sub-clause 4.20.
Notes
Introduction
Once a Contract is placed with a Contractor, the promoter or developer of a project is called an
“Employer” and the Consulting Engineer is referred to as the “Engineer”.
Between the Consulting Engineer and the Employer: the Contractor is not a Party;
Between the Employer and the Contractor: the Engineer is not a Party.
Engineer’s Duties
The concept of engaging a Consulting Engineer stems from the idea that, when a promoter initiates
a construction project, he is faced with many technical, commercial and legal considerations with
which he is not an expert. In civil engineering construction, in order to transform the promoter’s
ideas into reality, the method adopted by FIDIC is to engage a Consulting Engineer to carry out
the following duties:
The Engineer’s duties can be specified according to the phase of the project:
Before construction:
33 Advise the promoter on the Tenders received and on the selection of the Contractor.
During construction:
Quality control;
Monthly Payments:
Despite the diversity of the duties of the Engineer as a certifier, the most important of these is,
perhaps, his role under Clause 14 enabling him to certify monthly payments to be made to the
Contractor. These payments are essential for the smooth performance of the Contract as they
represent to the Contractor the lifeline with respect to the Contract.
The Engineer is obliged to carry out the functions described in the Contract but he has no
power to amend the Contract;
The Engineer’s authority to act derives, in the first place, from the Contract documents,
whether by express words and by virtue of powers necessarily implied from the express
words;
For certain further acts specified authority is required and that permission, required by the
Engineer from the Employer, should be set out in the Particular Conditions;
Neither any act nor omission by the Engineer shall relieve either the Employer or Contractor
of any obligation or responsibility under the Contract;
The final paragraph of this sub-clause, in a clear attempt to limit liability on the part of the
Engineer, states that any act carried out by the Engineer shall not relieve the Contractor
from any responsibility he has under the Contract, including responsibility for errors,
omissions, discrepancies and non-compliances.
These delegations must be in writing and must define the extent of the so delegated;
Unless agreed by both the Employer and Contractor, the Engineer may not delegate his
determination function under Sub-clause 3.5.
Where the instructions are oral, if they are confirmed in writing by the Contractor within two
days, then they shall be deemed to be a written instruction unless the Engineer responds to
the contrary within two days;
If the Contractor considers that the instruction in fact constitutes a Variation then it should
respond in accordance with Sub-clause 13.3.
Some Commentators are of the opinion that this time of forty-two days is too long as it
could result in the Contractor having no means of communicating his problems to the
correct person;
If the Contractor raises a reasonable objection against the proposed replacement then the
Employer must find someone else.
Sub-clause 3.5 [Determinations]
Where the Engineer is required by the Contractor to reach a determination, the Engineer is
bound to consult with both parties in order to reach agreement- this effectively means he
should obey the first Rule of Natural Justice, namely, the Audi Alterem Partem Rule;
Introduction
In simple terms the Contractor’s obligations under the Construction Contract revolve around five
main areas:
Construction and completion of the Works with due diligence and within the Time for
Completion as contemplated in the Contract;
Use of Materials, Plant and workmanship as described in the Contract and in accordance
with the Engineer’s instructions;
Provision of securities, indemnities and insurances in respect of such work during the
Contract period;
Supply of information and notices required for the execution and completion of the Works
and also for alerting the Employer whenever an event occurs which is likely to increase the
Cost of the work or the Time for Completion;
The Contractor is responsible for ensuring the supply of the necessary Plant, personnel
and other Goods and services necessary for the completion of the Works in good time in
accordance with the requirements of the Contract;
The Contractor is responsible for all Site operations and construction methods. This includes
all design of Plant and Materials to the extent required by the Contract;
A Contractor must submit, whenever required by the Engineer, details of the methods
which the Contractor intends to adopt in carrying out the Works;
The Contractor must notify the Engineer of any alterations to that method Statement;
The Contractor only has design responsibility to the extent specified in the Contract;
If the Contractor undertakes any element of design that design must be fit for the purpose
for which the designed part is intended as specified in the Contract;
Design:
The FIDIC Construction Contract is intended for use where it is the Employer who
provides the design and where it is the Contractor who constructs according to that
design. Therefore, whilst it is unlikely that a Contractor will be required to carry out
any design, it is important that this is carefully checked. This means that it is important
that the Contract as a whole (including the Specification and any Drawings or Bill of
Quantities) is carefully checked to see if there are any design obligations contained
therein;
Where the Contract specifies that the Contractor shall design any part of the Permanent
Works then the Contractor must submit to the Engineer the Contractor’s Documents in
relation to the designed portion of the Works and the Contractor shall be responsible
for this design. Any Permanent Works designed by the Contractor must be fit for the
purpose for which the Works were intended as specified in the Contract. Where the
Contractor undertakes design, the Contractor will be responsible for the fitness for
purpose of that design. This absolute obligation obviously depends on the nature of
the definition of the purposes of the Works contained in the Contract;
For fitness for purpose obligation it is important to remember that, under common law,
the fitness for purpose duty is stricter than the ordinary responsibility of a consultant
carrying out design where the implied obligation is one of reasonable competence to
“exercise due care, skill and diligence”;
If Performance Security is required then the Contractor must, at his own Cost, provide
that security to the Employer no later than twenty-eight days after receiving the Letter of
Acceptance. A copy must be sent to the Engineer at the same time.
Be in the form annexed to the Particular Conditions. If it is not it must be in a form agreed
by the Employer;
Remain valid until the Contractor has completed the Works and remedied any defects;
If the Performance Security has not been received and accepted by the Employer, the
Engineer will not issue an Interim Payment Certificate (see Sub-clause 14.6);
The Employer may only make a call on the Performance Security if:
Failure by the Contractor to extend the Performance Security beyond the expiry date if
the Works are not complete at that date;
Failure by the Contractor to remedy a default within forty-two days of being notified
of the defect;
If the Contractor wishes to replace the Contractor’s Representative the prior consent of the
Engineer must be obtained;
The Contractor’s Representative must devote the whole of his time on the Site to directing
the performance of the Contractor.
May delegate his powers provided the Engineer receives prior notice.
Sub-clause 4.4 [Subcontractors]
Unless otherwise agreed, the Contractor shall not subcontract the whole of the Works;
If the Contractor is permitted to subcontract an element of the Works then the Contractor
remains wholly responsible to the Employer for the acts of that Subcontractor as if those
acts had been carried out by him;
The prior consent of the Engineer is required for all Subcontractors, apart from suppliers
and the Subcontractors named in the Contract;
The Contractor must give the Engineer twenty-eight days’ notice of both the intended and
actual Commencement Date of any Subcontractor’s work;
This sub-clause deals with the appointment of Subcontractors. It also makes it clear that
the Contractor is wholly responsible for the performance of the Subcontractors. This
obligation extends not only to the Subcontractors he chooses to appoint but also to the
Subcontractors nominated by the Employer in accordance with Clause 5;
It is important that the Contractor appreciates how wide the obligations here are. The
Contractor is responsible for all the acts and defaults of the Subcontractors.
The Employer, and not the Contractor, will be responsible for work carried out after any
such assignment.
Sub-clause 4.6 [Co-operation]
The Contractor shall co-operate with the Employer’s Personnel, other Contractors and
personnel from public authorities to enable them to carry out their work on or near to the
Site;
If the Contractor is instructed by the Engineer to co-operate in such a way, this shall
constitute a Variation;
Subject to this the Contractor shall set out his Works from this data;
The Contractor has an obligation to check or use reasonable efforts to verify the accuracy
of the Employer’s setting out;
If any error in the setting out causes delay or Costs then the Contractor should give notice
to the Engineer within the time limits prescribed within Clause 20 and may be entitled to
an extension of time and payment of any Cost plus reasonable profit;
It is for the Engineer to determine whether the error could have been found by “an
experienced Contractor” using reasonable efforts to verify the data.
It will be assumed that the Contractor has both examined and inspected the Site and all the
available information provided to the Employer about the Site and taken that information
into account in compiling and submitting his Tender.
Tender Information:
The second part of the Sub-clause provides that the Contractor is deemed:
Deemed to have taken into account all the risks which might impact on his Tender;
The only limit on the Contractor’s obligations, as provided by this Sub-clause, is that
the Contractor will be deemed to have obtained all necessary information “to the
extent” it was “practicable (taking account of Cost and time)”.
It is for the Contractor to ensure that his Tender sum covers everything the Contractor
needs to be able to carry out the Works as required by Sub-clause 4.1.
It is only if there is an error in the Site data provided by the Employer, which is found out at
a later stage and which error it is held the Contractor could not have found out through his
own enquiries, that a Contractor may be able to make a claim for additional payment. This
is, of course, provided the Contractor has interpreted the data correctly;
The question of whether, as with Sub-clause 4.10 (and therefore unlike Sub-clauses 4.7 and
4.12), the relevant standard by which the Contractor will be judged is the “ordinary” or
the “experienced” Contractor” is a difficult one. There is nothing within the wording of the
sub-clause to suggest that the Contractor will be judged according to the standards of the
“experienced” Contractor.
The notice must describe the problem and demonstrate why it was Unforeseeable;
Upon receipt of such a notice the Engineer shall proceed to make a determination in
accordance with Sub-clause 3.5;
If the Engineer so determines the Contractor may be entitled to an extension of time under
Sub-clause 8.4 and to Payment of Cost;
Before the Engineer or Employer’s Representative finally agrees any Cost that may be due,
the Engineer must take account of whether any physical conditions were more favourable
to the Contractor than had been anticipated;
If the Engineer agrees that the physical conditions encountered were Unforeseeable,
and any instruction constitutes a Variation, then the Contractor is entitled to proceed in
accordance with Clause 13 [Variations and Adjustments] and claim additional time and
money, if appropriate;
Where the Contractor recovers additional Costs these Costs do not include an element of
profit, even though it is likely to have been necessary to carry out additional Works and
possibly to employ additional Plant and labour;
This Clause confirms the FIDIC principle of when profit is allowed. There is no profit if the
effect or circumstance was not due to the default of the Employer. In this case neither
party could have been aware of the “Unforeseeable Physical Conditions” therefore the
Contractor may only be awarded additional time and Costs.
Notes
Site access;
Special and/or temporary rights of way. This includes those routes outside the Site but
which are necessary for access to the Site;
Obtaining any facilities outside of the Site which he needs to execute his Works at his
own Cost and risk.
The Contractor is responsible for obtaining permissions to use the access route and all
necessary signage;
The sub-clause expressly provides that the Employer does not guarantee the suitability or
availability of particular access routes;
The Contractor bears all the Costs and risks associated with access.
All the Contractor’s Equipment on Site is for the exclusive use of the Works on Site;
Major items of Contractor’s Equipment may only be moved off Site with the consent of the
Engineer.
This obligation includes the environment both on and off the Site;
Emissions, surface discharges and effluent caused by the Contractor’s activities must not
exceed the greater of the values set out in the Specification or that allowed for by the
applicable Laws.
The Contractor is responsible for the Cost of using such equipment at rates to be agreed or,
if not agreed, determined by the Engineer;
The Employer is responsible for the Employer’s Equipment except whilst the Contractor is
using or controlling it;
To the extent set out in the Specification, the Employer shall provide, and the Contractor
may use, “Free-issue Materials”;
After the Contractor has inspected the “free-issue Materials”, he becomes responsible for
their use, custody and control;
A cause for concern is that Employer’s Free-Issue Material is often not provided in
accordance with the Contractor’s Programme. This Clause only gives the Contractor an
Extension of Time should this occur but does not allow the Contractor to claim “Standing
Time” while he waits for the Free-issue Material.
The format of the progress reports shall be agreed with the Engineer or Employer’s
Representative or detailed in the Specifications;
The first report shall be produced at the end of the calendar month following the
Commencement Date;
Thereafter, the reports shall be provided on a monthly basis until the Contractor has
completed all the work listed as outstanding at the Completion Date;
One of the main reasons for providing Progress Reports is so that Person’s not involved in
the project on a day-to-day basis can get a good idea of the progress that the Contractor is
making;
Authorised personnel are limited to the Contractor’s Personnel and the Employer’s
Personnel unless otherwise notified to the Contractor by the Employer or Engineer;
The Contractor’s obligation for Site Security reverts back to the Employer on Taking Over
of the Works.
The Contractor is responsible for keeping the Site tidy and otherwise free from obstruction;
On issue of the Taking-Over Certificate, the Contractor should remove his equipment off
the Site;
When the Contractor removes his equipment he should leave the Site in a clean and safe
condition;
The Contractor is permitted to retain on the Site such Goods and equipment as are required
to enable him to fulfil his obligations under the Defects Notification Period.
The Contractor shall promptly give notice to the Engineer of the discovery of any such
antiquity;
If the discovery of any such antiquity leads to delay or additional Cost, upon the determination
of the Engineer, the Contractor may be entitled to an extension of time or payment of any
Cost, but no profit.
Introduction
The use of Nominated Subcontractors is not recommended but because they are sometimes
necessary. There are three potential advantages to the Employer or Engineer:
The avoidance of participation in the co-ordination of the interface between the Nominated
Subcontractors’ and the Contractors’ Works.
If there are to be Nominated Subcontractors it is preferable for the Employer to make this
clear in the Tender documents. Then the Contractor will know exactly where he stands
when pricing for the project. If there are to be no Nominated Subcontractors this clause
should be deleted;
There are reasons to believe the Subcontractor lacks competence or sufficient finances
or resources.
Undertake to perform its work in such a way so as to ensure that the Contractor will
discharge his obligations under the Contract;
The requirement to pay the sums certified by the Employer is a mandatory one. It is also
a requirement which is policed by the requirements of Sub-clause 5.4 which enable the
Engineer to require evidence of payment by the Contractor of sums previously certified.
Unless the Contractor can provide evidence that the Subcontractor has been paid or
satisfies the Engineer that he is reasonably entitled to withhold money, and has notified
the Subcontractor of this, then the Employer will pay the Subcontractor direct;
If the Employer is forced to pay the Subcontractor direct then the Contractor must repay
that sum to the Employer.
Any payments made directly to a Nominated Subcontractor, pursuant to Sub-clause 5.4 are to be
deducted from the next Interim Payment Certificate from the main Contractor.
Introduction
This lesson covers the procedures during the construction phase of the Project. Under Lesson
Eight we will cover Clauses 6 and 7 and the very important “Time Clause – Clause Eight” is dealt
with separately in Lesson Nine.
Clause 6 covers the employment of staff and labour to carry out the Works, which is stated under
Sub-clause 6.1 to be the responsibility of the Contractor. It enumerates the Contractor’s basic
obligations with regard to the employment of labour, working hours and matters concerning
health and safety.
Sub-clauses 6.1 to 6.7 of this clause deal with the Contractor’s basic obligations with regard to the
employment of labour, working hours and matters concerning health and safety. Sub-clauses 6.8
to 6.11 cover the superintendence and behaviour of the Contractor’s staff and labour.
While all arrangements are the responsibility of the Contractor, there are certain restrictions
and conditions which he must abide by. In particular, he must comply in all respects with the
local labour Laws, which is a requirement consistent with the provisions of Sub-clause 1.14
[Compliance with Laws], which is the overall requirement for the Contractor to comply with all
Laws and regulations, etc.
Except as otherwise stated in the Specification (note that stating that Sub-clause 6.1 is subject
to the Specification means that the priority of documents in Sub-clause 1.5 is reversed), the
Contractor:
Makes arrangements for the engagement of all staff and labour; local or otherwise;
Must comply with the relevant labour Laws, including Laws related to the employment,
health, safety and emigration and shall allow personnel all their legal rights;
Shall ensure that his personnel are appropriately skilled, qualified and experienced for the
job that they were hired to do – the Engineer can request to the Contractor removal from
the Site of the unsuitable persons;
Shall submit to the Engineer the list of his personnel and equipment;
Shall provide and maintain all accommodation and welfare facilities for all of his personnel;
Shall pay his staff and is responsible for the staff’s housing, feeding and transport;
Shall ensure that no work is carried out outside normal working hours and on days of rest,
for the location of the Site, unless accepted by the Engineer;
Shall ensure the maintenance of all health and safety standards of his personnel;
Shall ensure that his personnel act in an orderly fashion and in no way act in an unlawful or
riotous fashion;
Shall supervise the plans, arrangements, directions, management, inspection and testing of
the Works, for the duration of the Works;
Shall ensure that all required and any other reasonable health and safety precautions are
taken;
The supervision must be provided by enough number of people to ensure the satisfactory
and safe execution of the Works;
Those supervising must have adequate knowledge both of the language for communications
and of the likely work that will be carried out.
Subject to Sub-clause 4.3 the “whole of the time” of the Contractor’s Representative shall
be given to directing the Contractor’s performance of the Contract;
This superintendence obligation is a wide one and might be felt to be obvious. However, by
spelling out the obligations in the Contract, the Employer, through the Engineer, is provided
with a means to keep a check on the Contractor’s performance.
The Engineer may require the Contractor to remove any person employed on the Site or
Works, including the Contractor’s Representative if applicable, who:
Persists in any conduct which is prejudicial to safety, health, or the protection of the
environment;
The sub-clause allows the Engineer to remove from Site any person employed on the Site who acts
in a way prejudicial to the carrying out of the Contract. As this sub-clause applies to “any person
employed on the Site”, it also is likely that the Sub-clause will relate to not only the Contractor’s
Personnel but also the Subcontractor’s personnel.
These details shall be submitted on a monthly basis until the Contract has completed all
work known to be outstanding at the completion as stated in the Taking-Over Certificate.
The failure by the Contractor to ensure the good behaviour of his personnel could lead to a
claim in relation to Sub-clauses 4.14, 17.1 and 18.3.
Notes
Clause 7 covers Plant, Materials, Workmanship and Testing. It deals with the requirements for the
items of Plant and Materials which the Contractor brings to the Site in order to execute the project.
It covers the Contractor’s obligations concerning the quality of his work and the procedures to be
followed for tests and in the event that an item of work fails the test. The matter of the time when
an item of Plant or Materials becomes the property of the Employer is covered at Sub-clause 7.7
and royalties are dealt with at Sub-clause 7.8.
Essentially:
The Contractor:
Is responsible for Plant, Materials and workmanship;
Shall provide all apparatus, fuel, personnel for testing the Works;
If the Contractor suffers delays and Costs owing to the Engineer’s instruction then Sub-
clause 20.1 applies allowing an Extension of Time with Cost and Profit.
The Engineer:
May vary the location of test or additional tests;
Shall give notice to the Contractor of his intention to participate at the tests.
In summary:
Plant, Materials and execution of the Works are to be in accordance with the Contract and
in proper workmanlike manner;
Inspection and testing: Employer/ Engineer is entitled to inspect and test Plant and Materials
on Site or at the location for production;
Rejection: Plant and Materials may be found defective and will have to be rejected and
replaced;
Ownership: all Plant and Materials are the property of the Employer at whichever is the
earlier of delivery to the Site or payment to the Contractor.
Sub-clause 7.4 [Testing]
FIDIC does not specify generally which tests are to be undertaken as this will vary from project to
project and contract to contract.
The tests will be specified in the Particular Conditions of Contract and in the Specifications.
Sub-clause 7.4 gives the procedures for tests that are specified in the Contract and additional
tests, which are instructed under Clause 13 (the Engineer may, under Clause 13, vary the
location or details of specified tests, or instruct the Contractor to carry out additional tests)
but does not cover Tests after Completion. Tests on Completion are covered at Clause 9
which refers back to Sub-clause 7.4;
The Contractor shall agree with the Engineer the time and place for the specified testing of
any Plant, Materials and other parts of the Works;
The Contractor shall provide all that is necessary (apparatus, assistance, documents
and other information, electricity, equipment, fuel, consumables, instruments, labour,
Materials, and suitably qualified and experienced staff, as necessary) to carry out the tests
specified;
The Engineer shall give the Contractor not less than twenty-four hours’ notice of the
Engineer’s intention to attend the tests. If the Engineer does not attend at the time and
place agreed, the Contractor may proceed with the tests unless, otherwise instructed by
the Engineer;
If the Engineer does not attend the Contractor may proceed with the tests, unless otherwise
instructed by the Engineer, and the tests shall be deemed to have been made in the
Engineer’s presence and shall be deemed to be accurate. The Contractor shall immediately
forward to the Engineer duly certified reports of the tests;
If the Contractor suffers delay because of the tests he must give notice to the Engineer,
who will then determine whether or not to grant time and/or money to the Contractor in
accordance with Sub-clause 3.5 [Determinations];
Sub-clause 7.5 [Rejection]
If, as a result of an examination, inspection, measurement or testing, any Plant, Materials
or workmanship is found to be defective or otherwise not in accordance with the Contract,
the Engineer may reject it by giving notice to the Contractor;
The Contractor must remedy the rejected item so that it complies with the Contract;
The Engineer may require a retest. If the Engineer requires the Plant, Materials or
workmanship to be retested, the tests shall be repeated under the same terms and
conditions;
If any rejection or retesting causes the Employer to incur additional Costs these will be
borne by the Contractor, subject to Sub-clause 2.5;
If the Contractor fails to rectify the item as instructed, the Employer has the right to
terminate the Contract under Sub-clause 15.2 [Termination for Contractor’s Default].
Remove from Site any Plant or Materials which are not in accordance with the Contract;
Remove and re-execute the Works which are not in accordance with the Contract;
Execute any Works required for the safety of the Works, whether because on an accident,
an Unforeseeable event, or otherwise;
The Contractor must, within a reasonable time, comply with any Engineer’s instruction;
The Contractor must comply immediately with any Engineer’s instruction to execute the
Works, which are urgently required for the safety of the Works;
If the Contractor fails to comply with the Engineer’s instruction, the Employer will be
entitled to employ other persons to carry out the instruction and claim the Costs arising
from the failure to the Contractor under Sub-clause 2.5;
In the event the Employer employs other persons to carry out the instruction then, unless
the Works instructed by the Engineer would have entitled the Contractor to payment under
the Contract, the Contractor will pay the Cost of these Works.
Provided the Laws of the Country do not provide otherwise, items of Plant and Materials
will become the property of the Employer either when:
Our law provides that a person may not sell something to another person if he does not
actually own the goods;
This can often lead to problems of ownership when Contractor’s request payment for
materials delivered to site and for which they have not paid their suppliers;
It is imperative that the Employer ascertains that the Contractor has a right to pass on
ownership of any materials claimed under this Sub-clause;
Introduction
This is one of the important Clauses in the FIDIC Suite of Contract Documents.
Clause 8 covers three essential subjects, all of which are related to the period during which the
Contractor will construct the Works:
In summary:
Commencement is within seven days’ notice and not later than forty-two days after
acceptance;
Completion date is the date for test on completion and “Taking-Over Certificate”. This is
followed by the “Defects Notification Period”. Following notification of defects there is a
period, to be agreed upon, for remedying defects and then the Performance Certificate is
issued and Performance Security is returned within twenty-one days;
Variations;
Any action caused by or attributable to the Employer or the Employer’s other Contractors
on the Site;
Delay damages are payable by the Contractor for all delays exceeding the extension of time
granted, normally a percentage of the contract Price per day with an upper limit (often
known as “liquidated damages”);
Suspension of work may be requested by the Engineer and the Contractor shall be granted
extension of time and compensation for any extra Costs;
Contractor’s programme for the Works is to be submitted by the Contractor to the Engineer.
The number of days in the Time for Completion is given in the Appendix to Tender or
Contract Data and may refer to the whole of the Works, or a designated Section of the
Works. “Day” is defined as a calendar day rather than a working day and so the number of
days includes weekends and holidays;
The Commencement Date, unless otherwise stated in the Particular Conditions, shall be
within forty-two days after the Contractor receives the Letter of Acceptance;
The Contractor shall commence the execution of the Works as soon, as is reasonably
practicable after the Commencement Date, and shall then proceed with the Works with
due expedition and without delay;
The Contractor shall proceed with his Works with due expedition and without delay.
33 The completing of all Works stated in the Contract as being necessary for the
purpose of taking over under Sub-clause 10.1.
The Time for Completion is stated in the Contract Data and is calculated from the
Commencement Date, as defined in Sub-clause 8.1, which has been established in
accordance with Sub-clause 8.1 [Commencement Date];
The Time for Completion of the Works will be inserted in the Appendix to Tender or Contract
Data. Both provide for the Time for Completion to be expressed in days. For certainty, the
parties should agree a calendar date;
The Works (or Section of the Works) will not be complete until all the necessary Tests on
Completion (as defined in Clause 9) have been successfully carried out and all the work
required for the issuing of a Taking-Over Certificate as provided for by Clause 10 has been
completed. Hence, under Sub-clause 8.2, the Contractor is obliged to complete all the work
which is required for taking over under Sub-clause 10.1, including passing the Tests on
Completion as Clause 9, before the expiry of the Time for Completion;
The reference to the completion of the Works means the completion of all the Permanent
Works and the Temporary Works as set out in the Contract. Provided these are adequately
described, all the parties to the Contract will understand what work needs to be carried
out;
If Sections of the Works are required to be completed before the overall Time for Completion
then the Sections must be described in the Appendix to Tender, together with the Time for
Completion and delay damages for each Section;
Care is required when talking about sectional completion. “Section” is defined in Sub-
clause 1.1.5.6 as being a part of the Works specified in the Appendix to Tender as a Section
(if any). Therefore, it is important that an appropriate description of any Section is set out
in the Appendix. This description should include a separate Time for Completion of that
Section together with details of the delay damages which may be allowable for failure to
meet the stated Time for Completion.
Notes
Sub-clause 8.3 [Programme]
The Contractor shall promptly give notice to the Engineer of any future events or
circumstances which may adversely affect the Works, increase the Contract Price or delay
the completion of the Works;
The Engineer may, if the Contractor gives such a notice, require the Contractor to submit an
estimate of the anticipated effect of the future event and a proposal to rectify the potential
effect under Sub-clause 13.3;
If the Engineer considers that a programme fails to comply with the Contract or is
inconsistent with actual progress, he may give due notice to the Contractor. If the Engineer
gives such a notice the Contractor must submit a revised programme to the Engineer.
Contractor’s Programme:
The programme required under this sub-clause is one of the most important documents
which the Contractor is required to produce and sometimes the Contractor is very
slow in producing his programme. Not only does the programme give a detailed time
plan of how the Contractor intends to carry out the Works but it also gives a great deal
of information about the associated events such as tests, inspections, reports – all as
mentioned in this sub-clause. Furthermore, the Contractor’s programme often forms
basic supporting evidence according to which Contractor’s claims for time extension
can be evaluated. So it is in the Contractor’s interests to ensure that the programme is
properly prepared as required by this sub-clause;
The basic purpose of the programme is to set out how the Contractor proposes to
carry out the Works. The programme must be supported by a report setting out the
methods the Contractor intends to adopt together with an estimate of the personnel
and equipment required on Site for carrying out the major stages of the Works;
Under the 1987 Red Book programmes were submitted for approval to the Engineer.
This is no longer the case. There is no requirement for the Engineer or Employer’s
Representative to approve or consent to the programme. The only action required
from the Employer’s Representative is to give notice to the Contractor in the event
that the programme does not comply with the Contract (in which event the Contractor
must submit a revised programme). If no such notice is received within twenty-one
days, the Contractor shall proceed in accordance with this programme. Therefore,
the Engineer should be careful to remember that it will accordingly be open to the
Contractor to argue that, by not rejecting a programme, the Engineer has implicitly
given his approval to it;
For each of the stages the work to be carried out by each Nominated Subcontractor;
33 A general description of the methods which the Contractor intends to adopt; and
33 Details showing the Contractor’s reasonable estimate of the number of each class
of Contractor’s Personnel and of each type of Contractor’s Equipment, required on
the Site;
33 When deciding on the form of the programme and the detail to be included, the
Contractor should allow that the programme will be used to demonstrate whether
any delay situation will cause a delay to completion.
Actions:
The Contractor is required to proceed as set out by his programme, unless he receives
notice from the Engineer stating that the programme does not either reflect actual
progress on the Site or the requirements of the Contract. Obviously this programme
will not only be used to demonstrate progress but also to demonstrate whether any
delay may cause a delay to completion. Under Sub-clause 4.21 the Contractor must
submit monthly progress reports. These must include a comparison of planned and
actual progress;
The Contractor is required to give advance notice or early warning to the Engineer of
potential events which might adversely affect or delay the Works. There is no similar
obligation on the Engineer or Employer. This requirement has a far wider application
than just in relation to the programme. The purpose is to enable the Contractor and
Engineer to work together to minimise the effects of the potential delay event. The
Sub-clause 8.3 notice is in effect an “Early Warning Notice” and gives the Engineer
the opportunity to take action to overcome the problem before the Contractor incurs
delay or additional Cost. There is no requirement for the Contractor to meet with
the Engineer to discuss the problems and possible solutions but the sub-clause does
enable the Engineer to require the Contractor to submit estimates and proposals;
The notice must be given “promptly”. Therefore, consideration must be given when
submitting such a notice as to the potential impact, if any, on the claims procedure
required by Clause 20. In other words, giving of a notice under Sub-clause 8.3 might
not suffice as a notice as required by Clause 20;
The Contractor should remember that he must revise the programme whenever it is
inconsistent with actual progress. This will include when the Contractor is both ahead
or behind schedule;
The Engineer does not approve or consent formally to programme. The Engineer has
twenty-one days to comment on the Contractor’s programme as to what extent it does
not comply with the Contract and, if no objection is raised within twenty-one days of
receipt, the programme is to be followed;
For certainty, the Employer might want to consider requiring the Contractor to provide
a revised programme whenever an extension of time is granted.
Notes
When determining each extension of time under Sub-clause 20.1, the Engineer shall review
previous determinations and may increase, but shall not decrease, the total extension of
time;
A Variation (unless an adjustment to the Time for Completion has been agreed under
Sub-clause 13.3) or other substantial change in the quantity of an item of work included
in the Contract under Clause 12;
Any act of delay, impediment or prevention caused by or attributable to the Employer, the
Employer’s Personnel, or the Employer’s other Contractors on the Site.
Sub-clause 8.4 sets out criteria under which Contractor shall be entitled to an extension of
the Time for Completion. It is not sufficient for the event to cause delay or disruption to the
Contractor’s work. The Contractor must demonstrate that it will actually delay completion.
If the Contractor fails to complete his Works within the agreed Time for Completion then
he will be in breach of Contract. Sub-clause 8.4 provides the mechanism by which the Time
for Completion can be extended, but only in certain clearly defined circumstances and only
if the Contractor takes certain steps to give notice of his considered entitlement;
It is thought that extension of time provisions are solely for the benefit of the Contractor
but in reality the opposite is often the true intent. The primary purpose of an extension
of time provision is to preserve the Contractor’s obligation to complete within a specified
time. Extending the completion date therefore preserves the Employer’s right to liquidated
damages or Delay Damages, even when by prevention the Employer has delayed the
Contractor and is responsible in part for late completion. If there is no completion date there
is no date from which Delay Damages can run. Sub-clause 8.4 only entitles the Contractor
to an extension of time, not to additional payment. Any extension of time granted will
relieve the Contractor of the obligation to pay Delay Damages to the Employer in respect
of the extension period;
There are two conditions precedent that the Contractor must comply with prior to making
a submission to the Engineer for an extension of time (i.e. if these conditions are not
complied with then any entitlement to an extension of time is lost):
It is mandatory that one of the events listed in Sub-clauses 8.4(a) to 8.4(e) must have
resulted in an actual delay in completion within the meaning of Sub-clause 10.1. It is
not good enough for the Contractor to say that there is a delay or disruption to the
Contractor’s programme;
The Contractor must give notice to the Engineer in accordance with the provisions and
time limits required by Sub-clause 20.1;
The clear intent is that only a “Delay to Completion” not a disruption will afford the
Contractor a right to an extension of time (subject always to compliance with the provisions
of Sub-clause 20.l);
The Contractor should note that the grant of an extension of time does not always lead
to an award of Cost and/or reasonable profit and there is no automatic right to such an
award. This is dependent on the event that gives rise to a claim for an extension of time and
the relevant Sub-clause. If the Contractor also seeks a claim for additional payment, a claim
has to be made under that particular Sub-clause for that additional payment in addition to
the claim being made for an extension of time;
Notes
If he has been delayed by the local authorities the Contractor may be entitled to an
extension of time (not Cost) pursuant to Sub-clause 8.4(b), provided the Contractor has
“diligently” followed the procedures of the local authorities and the delay or disruption
was Unforeseeable;
A delay or disruption will be considered as a cause of delay (and qualifying for an extension
of time) under Sub-clause 8.4 if the following conditions apply:
The Contractor has diligently followed the procedures laid down by the relevant legally
constituted public authorities in the Country;
The Contractor should note that, unless all three conditions apply, the Contractor will not
be entitled to an extension of time.
The Engineer can only do this where the reason for the delay is not for a reason which
would have granted the Contractor an extension of time as listed in Sub-clause 8.4;
The revised programme must set out the way the Contractor intends to deal with the
situation and complete within the Time for Completion;
If the Engineer does not object the Contractor shall adopt these proposals at his own risk
and Cost;
If the Employer incurs increased Costs as a result of the revised proposals, he may be
entitled to claim these Costs from the Contractor under Sub-clause 2.5;
Any Costs the Employer receives as a consequence of this sub-clause shall be in addition to
any entitlement for delay damages under Sub-clause 8.7;
This sub-clause aims to enable the Engineer to instruct the Contractor to recover time lost
and to ensure that the project is completed on time;
The Contractor is to adopt revised methods at his Cost and is liable for any Employer’s Costs
caused by revisions;
For the additional Costs incurred by the recovery measures, the Employer may submit
a claim under Sub-clause 2.5 and the Engineer will make a determination under the
procedures of Sub-clause 3.5.
The Delay Damages shall be deducted at the rate provided for in the Appendix to Tender.
The Appendix to Tender provides for the maximum amount of Delay Damages to be capped;
Unless the Contract is terminated Delay Damages are the only remedy available to the
Employer prior to completion;
The Delay Damages do not relieve the Contractor of his other contractual obligations;
To recover Delay Damages the Employer must make an application in accordance with Sub-
clause 2.5;
No Delay Damages can actually be deducted until the Final Contract price has been
ascertained. Until that has been done the actual amount of the Delay Damages cannot
be known. Hence, the sum for Delay Damages cannot be determined finally until after
agreement of the Final Statement;
The total Delay Damages will be expressed generally as a percentage of the Accepted
Contract Amount or as a monetary sum – all set out in the Appendix to Tender.
Notes
During such suspension the Contractor shall protect, store and secure such part of the
Works against any deterioration, loss or damage. If the suspension is not the responsibility
of the Contractor then Sub-clauses 8.9, 8.10 and 8.11 shall not apply (they also provide the
process to be followed if it is the Contractor’s responsibility);
The Engineer is not obliged to give the reason for the suspension but “may” notify the
cause of the suspension. A reasonable Engineer should tell the Contractor the reason and
likely extent of the suspension in order that the Contractor can decide how to meet his
obligation to “protect, store and secure” that part of the Works;
During the period of the suspension it is the responsibility of the Contractor to “protect,
store and secure” the Works (or part of the Works if the suspension only relates to a part)
against any “deterioration, loss or damage”. The sub-clause does not say who is responsible
for the Costs of undertaking this protection work;
However, from Sub-clauses 8.9 to 8.11, if the reason for the suspension is related to a
reason for which the Contractor is entitled to an extension of time under Sub-clause 8.4
then the Contractor will be entitled to make a claim for these Costs. However, if the reason
for the suspension is the responsibility of the Contractor he will equally be responsible for
these protection Costs;
If the Contractor fails to provide adequate protection, which leads to a delay on resumption
of the Works, then in accordance with Sub-clause 8.9 he will not be entitled to an extension
of time;
In addition, once work resumes the Contractor might, again if the reason for the suspension
is related to a reason for which the Contractor is entitled to an extension of time under Sub-
clause 8.4, be entitled to make a claim for the Costs of resumption. These can often be
quite considerable;
One thing which Sub-clauses 8.8 to 8.12 do not do is to require the Contractor to maintain
its staff and labour resources ready to commence work when the period of suspension
his lifted. The Contractor has to take steps to protect the Works but an Employer might
want to consider how he can ensure that key personnel in addition to the Contractor’s
Representative (who will presumably be required by Sub-clause 4.3 to remain available)
are not moved from the project. Obviously, at the very least the Contractor would look to
recover its Costs in these circumstances.
The Contractor will not be entitled to an extension of time and/or additional Cost if the
reason for the suspension is not covered by Sub-clause 8.4 and/or was a result of the
Contractor’s poor design, workmanship or Materials. The Contractor will not be entitled
to an extension of time and/or payment for Cost incurred as a consequence of any failure
on the part of the Contractor to protect the Works during the period of suspension in
accordance with Sub-clause 8.8.
The value of the payment will be the value of the Plant and Material as at the date of the
suspension.
If the Engineer does not give permission within twenty-eight days of being requested to do
so, in respect of a suspension of the entire Works, the Contractor will be entitled to give
notice of termination under Sub-clause 16.2;
If the Engineer fails to respond within twenty-eight days of any such request, in respect of a
suspension of a part of the Works, the Contractor may treat the suspension as an omission
under Sub-clause 13.
It is the responsibility of the Contractor to make good any damage in the Works which has
occurred during the period of suspension.
Notes
Introduction
Clause 9 deals with the Contractor’s duty to carry out Tests on Completion of the Works. It also
provides for a situation where the carrying out of such tests has been delayed by the Employer
and/or the Contractor or where the Works have to be retested if they fail the test the first time
round.
Sub-clause 9.4 [Failure to Pass Tests on Completion] deals with the situation where the Works,
or a Section thereof, fail to pass the Tests on Completion, even after having been repeated under
Sub-clause 9.3. The Engineer is then entitled to:
(b) If the failure deprives the Employer of substantially the whole benefit of the Works or
Section, reject the Works or Section (as the case may be), in which event the Employer shall
have the same remedies as are provided in Subparagraph (c) of Sub-clause 11.4 [Failure to
Remedy Defects]; or
For (c) the Employer may demand a reduced price by an amount that would reflect the reduced
value to him as a result of this failure (last paragraph of this sub-clause provides alternatives for
calculating that reduction).
The most drastic alternative is (b) where the Contractor is unable or unwilling to resolve the
problems encountered in the testing programme and the parties are directed to paragraph (c)
of Sub-clause 11.4 [Failure to Remedy Defects] such that if the defect “deprives the Employer
of substantially the whole benefit of the Works or any major part of the Works”. The Employer
can terminate the whole Contract or the part “which cannot be put to its intended use” and
demand his money back together with interest and the Cost of dismantling the offending work
and returning it to the Contractor.
This solution is difficult to envisage for a civil engineering or a building project and is unlikely to
occur.
The Contractor must give at least twenty-one days’ notice to the Engineer of the date on
which they will be ready to carry out the tests. Unless otherwise agreed, the tests will be
carried out within fourteen days after this date;
The Engineer must consider the tests and decide whether the Works tested have passed.
The Contractor will give notice to the Engineer under Sub-clause 7.4 and follow the Sub-
clause 20.1 procedure to claim for an extension of time and an additional payment;
If the delay lasts for more than fourteen days then, under Sub-clause 10.3, the Employer is
deemed to have taken over the Works or Section on the date when the Tests on Completion
would otherwise have been completed;
If the Tests on Completion are unduly delayed by the Contactor the Engineer may give
notice requiring the Contractor to carry out tests within twenty-one days;
If the Contractor fails to carry out the tests within the twenty-one days specified the
Employer’s Personnel can complete the tests;
If the Employer’s Personnel carry out the tests in these circumstances, they do so at the
Contractor’s risk and Cost, and will be deemed both to be accurate and to have taken place
in the presence of the Contractor.
Sub-clause 9.3 [Retesting]
If the Works do not pass the Tests on Completion, the Engineer can reject the Works and
require the tests to be repeated;
This sub-clause should be read in conjunction with Sub-clause 7.5 which provides that the
Contractor shall make good any defect and ensure that the rejected item complies with
the Contract. The tests can then be repeated. There is no limit set on how many times the
Works can be carried out.
Notes
Introduction
This clause gives the procedures to be followed when the Works are ready to be taken over by the
Employer. The procedure can apply to the Works as a whole or to any Section of the Works that
has been defined in the Appendix to Tender.
It is Sub-clause 10.1 that deals with the Employer’s taking over of any defined part or parts of the
Works, like most Contracts. However, Sub-clause 10.2 introduces a further right of takeover of the
Employer, namely a situation where the Engineer, with the permission of the Employer, may issue
a Taking-Over Certificate for any part of the Permanent Works.
Sub-clause 10.2 gives the Employer the right to take over any part of the Works at any time for
his convenience.
The Contractor may apply to the Engineer for a Taking-Over Certificate not earlier than
fourteen days before he anticipates completing the Works;
Within twenty-eight days of receiving the Contractor’s application, the Engineer may either:
If the Engineer fails to accept or reject the application within twenty-eight days and the
Works are substantially in accordance with the Contract then the Taking-Over Certificate
will be deemed to have been issued on the last day of the twenty-eight day period;
Minor outstanding work and defects may be completed after the certificate has been issued
if agreed by the Engineer;
By Sub-clause 10.1(a) the Engineer cannot refuse to issue the Taking-Over Certificate
because of “any minor outstanding work” provided the minor defect does not “substantially
affect the use of the Works or Section for their intended purpose (either until or whilst this
work is completed and these defects are remedied)”;
With this specific exclusion it is now clear that any outstanding work or defects must not
substantially affect the use of the Works for their intended purpose. However, there is no
guidance given as to the meaning of “substantially” or “substantially affect” and it will
be left to the judgment of the Engineer. The question of whether a particular item will
“substantially affect” such use will be a matter for the Engineer to exercise his judgment
but the emphasis on the use of the Works gives a clear definition of when the Works are
ready to be taken over by the Employer;
If there is any minor outstanding work this must be completed by the Contractor during the
Defects Notification Period as instructed by the Engineer under Sub-clause 11.1(a);
If the Engineer decides to reject the Works he must give reasons. The Engineer must also
specify the work required to be done by the Contractor to enable the Taking-Over Certificate
to be issued. It is the responsibility of the Contractor to complete this work before applying
for a further certificate;
The Works will be substantially in accordance with the Contract if they are free from known
defects which would prevent the Employer from taking over and making use of the project.
The procedure to establish whether or not the Works are substantially in accordance with
the Contract, in the absence of a Statement by the Engineer, is unclear and could cause
problems. The Contractor would first refer the matter direct to the Employer and then, if
necessary, to the DAB.
The Employer may not use any part of the Works until the Engineer has issued a Taking-
Over Certificate;
If the Employer does use any part of the Works prior to the issue of a Taking-Over Certificate
then:
The Employer and not the Contractor will be responsible for that part of the Works
which has been taken over; and
If the Contractor incurs any Costs as a result the Contractor shall give notice to the
Engineer and may be entitled to payment of these Costs to include reasonable profit;
If a Taking-Over Certificate has been issued for part of the Works, the rate of Delay Damages
for the remainder of the Works will be reduced;
Only the Employer has the right to decide that a certain part of the Works will be taken over
before the remainder of the Works. This discretion may be exercised when the Employer
wishes to use a part of the Works before the Works are complete. The Employer can then
require the Engineer to issue a Taking-Over Certificate and the Employer would then be
responsible for the care of that part of the Works;
The Contractor does not have a right to request that the Employer take over part of the
Works under this sub-clause. However, the Employer has the discretionary right to request
that the Engineer issue a Taking-Over Certificate for any part of the Works. The Employer
is not entitled to use any part of the Works (unless agreed as a temporary measure) unless
the Engineer has issued a Taking-Over Certificate;
The consequences of the Employer using any part of the Works before a Taking-Over
certificate is issued as set out in Sub-clauses 10.2(a) to (c) are:
The Employer will be responsible for that part of the Works which have been taken
over;
The Contractor may request that the Engineer issue a Taking-Over Certificate; and
If the Contractor incurs any Costs as a result, the Contractor shall give notice to the
Engineer and may be entitled to payment of these Costs to include reasonable profit;
The other potential problem caused by the Employer taking over parts of the Works at
an early (and unanticipated stage) relates to Delay Damages (see sectional completion in
Sub-clause 8.7). Sub-clause 10.2 recognises that where a Taking-Over Certificate is issued
in respect of a part of the Works then the Employer’s entitlement to Delay Damages is
reduced proportionally. In other words, the daily rate for any Delay Damages will be reduced
in proportion to the value of any part of the Works for which a Taking-Over Certificate has
been issued. The figure will be determined by the Engineer under Sub-clause 3.5;
Sub-clause 10.2 has introduced a further right of takeover of the Employer, namely a
situation where the Engineer, with the permission of the Employer, may issue a Taking-
Over Certificate for any part of the Permanent Works. This means that the Contractor’s
possession and responsibilities for care, safety and insurance of that particular part of the
Works come to an end. However, it would appear that a corresponding Defects Notification
Period does not start for this part upon taking over since the definition of this term under
Sub-clause 1.1.3.7 refers only to taking over certified under Sub-clause 10.1 and makes no
reference to Sub-clause 10.2. The Contractor is entitled to recover any reasonable additional
Cost accrued to him as a result of such a takeover (subject to the claims procedure of Sub-
clause 20.1).
However, the Engineer shall still require the Contractor to carry out the Tests of Completion;
Introduction
Clause 11 deals with the procedures during the Defects Notification Period, immediately after the
Works have been taken over by the Employer, when the Contractor is responsible for correcting
any defects;
The length of the Defects Notification Period is stated in the Appendix to Tender.
While a period of one year will generally be suitable for civil engineering projects, a longer period
may be required for electrical, mechanical or building services work.
This is because the Employer has occupied the Works, will be aware of any defects or other
problems and the Contractor will need to liaise with the Employer in order to carry out repairs. The
Employer will need to make the appropriate arrangements to identify any defects and designate
a representative to liaise with the Contractor. In practice, it may be convenient for these tasks to
be delegated to the Engineer.
During this period the Engineer has certain powers and responsibilities, as stated in the sub-
clauses, but no longer has the power to issue instructions for Variations (under Sub-clause 13.1
Variations can only be issued prior to the issue of the Taking-Over Certificate).
Sub-clause 11.1
[Completion of Outstanding Work and Remedying Defects]
All outstanding work should be completed by the end of the Defects Notification Period (or
as soon as is practicable thereafter);
Complete the work identified in the Taking-Over Certificate within the reasonable time
set by the Engineer;
Carry out all work required to remedy defects or damage identified by (or on behalf of)
the Employer, on or before the end of the Defects Notification Period.
Remedial work attributable to any other cause is dealt with under Sub-clause 13.3 [Variation
Procedure];
The defect or damage is notified by the Employer under Sub-clause 11.1(b). If the Contractor
can prove that the remedial work is not his liability then the Employer must be notified
promptly and the Cost for the remedial work to be paid to the Contractor and is decided by
the Engineer as a Variation, using the procedures at Sub-clause 13.3;
While category (c) above may seem to cover a wide range of problems, it is still necessary for the
Employer to establish with which obligation the Contractor has failed to comply.
The Defects Notification Period for the Works can be extended if the Works, a Section of the
Works or a major item of Plant cannot be used for the reason for which they are intended
as a result of defect or damage;
The Defects Notification Period may not be extended for more than two years;
The extended period can never be greater than the original Defects Notification Period – in
other words if the original DNP was 365 days the Employer cannot get more that a further
365 days extension of the DNP;
The notice must be given, under Sub-clause 2.5, as soon as practicable after the Employer
became aware of the circumstances and before the expiry of the period. The Engineer will
then make a determination under Sub-clause 3.5;
To establish an entitlement to an extension, the Employer must prove that the whole or a
Section of the Works, or a major item of Plant, could not be used for the purpose for which
it was intended due to a defect or damage.
If the Contractor fails to carry out required work within the time notified (or at all) then
the Employer has a series of options and a choice of action depending on the details of the
defect;
The range of remedies provided for in the case of the Contractor’s poor performance is
extensive, although it may be rare for termination (c) to be used, particularly on the partial
basis which is permitted;
The choice of action will depend on the details of the defect. The Employer can:
(a) Make other arrangements to carry out the work and claim the Cost against the Contractor,
under Sub-clause 2.5; or
(b) Accept the work including the defect and reduce the Contract Price under the procedures
of Sub-clause 3.5. This is a practical procedure and can be used when the remedial work
would cause substantial inconvenience or damage and the Employer would prefer to
accept the out-of-Specification work; or
(c) Terminate the Contract as a whole or in respect of the relevant part of the Works. This
would be a very serious action and would result in the Employer claiming substantial
sums of money from the Contractor.
The need to notify the Contractor plays a critical role in Sub-clause 11.4 and the Employer
will be required to follow the procedures set out in Sub-clause 11.4 with care before
exercising the options at (a), (b) or (c);
Notes
Is required;
The requirement shall be made by notice within twenty-eight days after the defect or
damage is remedied;
The further testing shall be carried out in accordance with the Contract but at the risk and
Cost to the Party responsible for the defect or damage;
This sub-clause envisages retesting after the completion of remedial Works in circumstances
where the remedial Works could affect the performance overall;
The requirement shall be made by notice within twenty-eight days after the defect or
damage is remedied;
These tests shall be carried out in accordance with the terms applicable to the previous
tests, except that they shall be carried out at the risk and Cost of the Party liable, under
Sub-clause 11.2;
The testing regime or Specification used for the retesting should be that which would
be attributed to any default of the Contractor;
The retesting Costs are to be borne by the Party responsible for the remedial work
itself under Sub-clause 11.2.
The Contractor has a right of reasonable access in order to comply within his obligations
under Clause 11;
The Contractor shall have such right of access to the Works as is reasonably required in
order to comply with this sub-clause until the Performance Certificate has been issued;
The Engineer can require the Contractor to search for the cause of any defect, under the
direction of the Engineer;
The Costs of search is required to be paid by the Contractor where the defect is to be
remedied at the Contractor’s Cost (as per Sub-clause 11.2);
Alternatively, the Contractor is paid his Costs and reasonable profit, to be determined by
the Engineer under Sub-clause 3.5.
The Performance Certificate is to be issued by the Engineer within twenty-eight days of the
expiry of the latest of any Defects Notification Periods;
Only the Performance Certificate will constitute deemed acceptance of the Works;
The issue of the Performance Certificate is linked to the provision of the Contractor’s
Documents.
For the purposes of the performance of any “unfulfilled obligations”, the Contract is
deemed to remain in force;
Sub-clause 11.10 does not provide a mechanism for dealing with these unperformed
obligations in a particular manner or timeframe;
In a complex project there will often be further outstanding obligations in spite of which the
Performance Certificate may be issued.
If any Plant, Materials, wreckage or rubbish remains after twenty-eight days of the
Employer’s receipt of its copy of the Performance Certificate, these can be sold or disposed
of by the Employer;
The Employer is entitled to recover from the Contractor the Costs of any such disposal, with
any surplus being paid to the Contractor;
The requirements for the Contractor’s final Site clearance may also be the subject of
regulations under the applicable law.
Notes
Introduction
This clause applies only to the Construction Contract. It is replaced in the Plant and Design-Build
Contract by the clause on “Tests after Completion”.
Clause 12 is based on the principle that the value of the Works under the Contract should be
established by gauging the amount of each item under the method of measurement referred
to in Sub-clause 12.2 (which, in turn, refers to the Contract Bill of Quantities or other applicable
Schedules of rates) and applying the appropriate rate per unit quantity or the appropriate lump
sum price under Sub-clause 12.3 [Evaluation].
So Clause 12 is written for a re-measurable Contract in which the Accepted Contract Amount is
based on estimated quantities where:
The Contractor is obliged to carry out all the work which is required by the Specification
and Drawings; and
The Contractor is paid for the actual quantities of work which he has executed;
The clause covers the procedures for the measurement and evaluation of the Works that have
been:
Executed; or
Omitted by a Variation.
If the Contract is based on a lump sum, or is on a Cost-plus or other basis, then Clause 12 must
be omitted from the General Conditions and alternative arrangements included in the Particular
Conditions.
Entries under Sub-clause 14.1 of the Guidance for the Particular Conditions includes
recommendations for Contracts on a Cost-plus or lump sum basis.
The Engineer decides that he requires a part of the Works to be measured and notifies
the Contractor;
The Contractor attends and assists the Engineer in making the measurement and
supplies any details requested by the Engineer;
If the Contractor fails to attend then the Engineer’s measurements are accepted as accurate.
Except where otherwise stated in the Contract, be the measurement of the net actual
quantity of each item of the Permanent Works;
The procedure for the actual measurement of the different work items can be standardised
for different projects and for consistency within a project by the use of a published
standard method of measurement. The FIDIC Conditions of Contract do not require the
use of a standard method of measurement but Sub-clause 12.2 states that the method
of measurement will be in accordance with the Bill of Quantities “or other applicable
Schedules”. If a standard method of measurement is required to be used then this
requirement should be stated in the Particular Conditions.
Sub-clause 12.3 [Evaluation]
If there is no rate or price for that item of work then the rate or price for similar work is to
be used;
However, a new rate or price will be appropriate if the circumstances described in Sub-
paragraphs (a) or (b) are fulfilled;
The new rates and prices are to be derived from any relevant rates or prices in the Contract,
with reasonable adjustments having regard to the matters set out in Sub-paragraphs (a)
and/or (b);
If no existing rates and prices are relevant for the purposes of the derivation of a new rate
or price then the new rate or price should be based upon reasonable Cost and reasonable
profit;
Sub-clause 12.3 requires the Engineer to agree or determine the Contract Price by applying
the measurement and the appropriate rate or price for each item. The appropriate rate or
price for the item shall be the rate or price:
The measured quantity has changed by more than the amounts stated at Sub-
clause 12.3(a) and the item is not specified as a “fixed rate item”, or
The work is instructed as a Variation under Clause 13 and there is no appropriate rate
or price in the Contract for this item;
So a new rate or price shall be appropriate for an item of work if no specified rate or price
is appropriate because the item of work is not of similar character or is not executed under
similar character or conditions as any item in the Contract;
If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived
from the reasonable Cost of executing the work, together with reasonable profit, taking
account of any other relevant matters;
Until such time as an appropriate rate or price is agreed or determined, the Engineer shall
determine a provisional rate or price for the purposes of Interim Payment Certificates.
Sub-clause 12.4 [Omissions]
The Contractor must give notice where a Variation gives rise to an omission, or element of
omission;
If the omission:
Sub-clause 12.4 therefore provides for possible compensation to the Contractor relating
to omissions to the Works. It enables the Contractor to give notice of a Cost that has been
incurred and will not be reimbursed owing to the omission of work by a Variation. The
Engineer then makes a determination under Sub-clause 3.5.
Notes
Introduction
In any construction project there will be a need to change the initial requirements as the
construction proceeds on the Site. Very few Contracts run their course without the need to
introduce Variations, making changes to the form or nature of the Works as compared to what
was foreseen at the time the Contract came into force.
Clause 13 deals with the possibility that Variations and adjustments may be made to the original
scope of the Works under the Contract. It covers the procedures for work being added to, or
omitted from, the original Contract work, together with other matters that may increase or
decrease the Contract Price.
The Engineer may need to issue further information that involves changes to the initial
requirements; or
It may be necessary to correct a mistake in the information that has been issued to the
Contractor.
The decision as to whether the Variation is to be executed lies with the Engineer. The Contractor
is not permitted to introduce Variations without an order or instruction in writing from the
Engineer (the Contractor is not permitted to change the Permanent Works unless the Engineer
has instructed or approved the Variation).
The Engineer, but not the Employer, can issue an instruction under Sub-clause 13.3. If the
Employer wants to make any changes he must request the Engineer to issue the instruction. If
the Employer gives an instruction direct to the Contractor then the Contractor must obtain the
Engineer’s confirmation and instruction before he executes the change. Strict adherence to these
requirements is essential for the Engineer to maintain technical and financial control over the
project.
The initiation of a Variation is either by way of instruction or the request for a proposal from
the Contractor;
The Contractor must perform unless he gives a notice stating that he cannot obtain the
Goods required for the Variation;
The Contractor may not of himself execute any change to the Works;
Changes to the quantities of any item of work included in the Contract (however, such
changes do not necessarily constitute a Variation);
Changes to the quality and other characteristics of any item of work changes to the
levels, positions and/or dimensions of any part of the Works;
Any additional work, Plant, Materials or services necessary for the Permanent Works,
including any associated tests;
The contractual procedures for additional and/or varied work is a difficult and important
area. There is often a complex question involved in determining in the first place
whether the work claimed by the Contractor is truly extra and/or varied, having regard
to all of the Contract Documents (and all of those things of which the Contractor is to
be regarded as having had notice when he made the Contract and put in his Tender).
The mere fact that a Contractor has carried out extra work is not itself sufficient to give
rise to a right to claim for additional payment;
A second difficult area is the question of written requests for additional work and/or
written orders, and then the consequential issue of whether and in what circumstances
the Contractor can recover payment for additional work without formal requests and/
or written orders. It will be a question of construction in each case but the requirements
for requests to be in writing – or some stipulation as to a proper written order – may
often be regarded as a condition precedent to the right to claim payments for extras.
Sub-clause 13.1 gives the Engineer the right to initiate a Variation at any time prior to the
issuing of a Taking-Over Certificate for the Works. However, the Engineer is not permitted
to initiate a Variation during the Defects Notification Period. There is no restriction on this
right to initiate a Variation (subject to the delay and/or disruptive effects of such Variation
being borne by the Employer) and the procurement of work through Variations ought to be
carried out in a particular way by the Engineer and/or the Employer;
The Contractor must carry out the Variation if instructed and has limited grounds to object.
The Contractor shall (must) comply with the instruction unless he can give good reason why
he cannot do so. The reasons for not complying are:
(i) He cannot obtain the Goods required;
(ii) The Variation will reduce safety or stability;
(iii) It will adversely affect the guarantees.
Even if the Contractor gives notice that he cannot readily obtain the Goods required, the
Engineer has the option of cancelling, varying or confirming the instructions (and thereby
ignoring the Contractor).
The proposal is prepared at the Cost of the Contractor and shall comply with the list of
requirements set out in Sub-clause 13.3 [Variations];
If there is a design element in the proposal then it is for the Contractor to ensure that the
design complies with Sub-clause 4.1;
If there is a resulting reduction in the Contract value then the fee is calculated in accordance
with the prescribed formula which clearly incentivises the making of savings;
Under Sub-clause 13.2 the Contractor may submit a written proposal to the Engineer in
respect of Value Engineering of the Works, detailing the ways in which he feels the Contract
may be completed sooner than originally planned, or the Costs of the Works may be
reduced or the efficiency may be improved;
The Value Engineering provision enables the Employer to benefit from the Contractor’s
experience and proposals;
The risk of the Value Engineering change is the Contractor’s one and any savings are split
50%/50% between the Contractor and the Employer;
Remember that Value Engineering is introduced after the contract has been entered into.
Any similar process made available to the Employer prior to the concluding of the contract
would constitute an alternative offer and not Value Engineering.
Notes
The Contractor must respond to the request, either saying why he cannot comply or by
providing a proposal for the Works, a programme proposal and a proposed evaluation;
The Engineer is then to respond, either agreeing or setting out reasons for disagreement;
The instruction is then to be issued by the Engineer and receipt acknowledged by the
Contractor;
Currency provisions in the Contract to be carried through into the evaluation of a Variation.
The powers of the Engineer in relation to the expenditure of Provisional Sums are
widely defined in Sub-paragraphs (a) and (b). Any expenditure by the Contractor shall be
substantiated as and when required by the Engineer;
A Provisional Sum can only be used for the specified purpose and any money that is surplus
to these requirements cannot be used for other work.
Sub-clause 13.6 [Daywork]
Provided a Daywork Schedule is attached as part of the Contract:
The Engineer may instruct Variations on a Daywork basis if the work concerned is of a
minor nature;
The Contractor must deliver daily Statements of the work carried out, including details
of the personnel and Materials used. The daily Statements must be counter-signed and
agreed by the Engineer.
If the Contractor considers that it will suffer delay or increased Cost it must give notice to
the Engineer within twenty-eight days as required by Sub-clause 20.1;
If the Engineer so determines, the Contractor may be entitled to an extension of time and
payment of Cost;
This sub-clause gives the possibility to increase or decrease the Cost owing to the changes
in legislation;
The sub-clause protects both parties in the event that there is a change in law (see
“Definition”), which occurs after the Base Date (see “Definition”) and which has an effect
on the Works and results in a change in Cost or programme. Normally such changes will
either increase the Cost of or delay the execution of the Works and the Contractor can
proceed according to Sub-clause 20.1 [Contractor’s Claim] to claim the extra, provided he
can substantiate his claim;
This sub-clause only applies if the adjustment data table is part of the Contract;
If this sub-clause applies, the formulae set out must be used to adjust changes in the Cost
of labour and Materials;
This sub-clause provides extensive details for the use of formulae for Cost Variations during
the Contract period;
If the Contractor fails to complete the Works within the Time for Completion, adjustment
of prices thereafter shall be made using:
Each index or price applicable on the date forty-nine days prior to the expiry of the
Time for Completion of the Works; or
The base rate reference is twenty-eight days prior to date of Tender submission.
If the Employer wishes to include provision to reimburse the Contractor for changes in
the Cost of labour, equipment, Materials, or other items then the table in the Appendix
to Tender must be completed in accordance with the provisions of Sub-clause 13.8. So
this sub-clause is applicable only if the table of price adjustment has been included in the
Appendix to Tender. Factors must be provided in Appendix to Tender for each project;
Notes
Introduction
The amount the Contractor is going to be paid, and the timing of the payment, is of fundamental
importance to both Contractor and Employer alike. The manner in which the payment is made is
traditionally dependent on the precise wording of the Contract.
Clause 14 provides the basis for the payment regime. It sets out when the amounts due are to
be paid out by the Employer. The timing of payment is primarily a commercial matter and it is
important both parties agree with the proposed procedures.
Clause 14’s fifteen sub-clauses that relate to the vital areas of price and payment cover:
Sub-clause 14.1: Contract Price may be represented through a Bill of Quantities (re-
measured) or Schedules;
Sub-clause 14.2: Anticipates that advance payment will be made and procedures provided;
Sub-clause 14.3: The Contractor to submit a Statement for application for interim payment.
Sub-clause 14.6 sets out the procedure for the issue of an Interim Payment Certificate by
the Engineer;
Sub-clause 14.7: Payment duties of Employer plus under Sub-clause 14.8 the financial
charges to be paid if Employer is late in payment (3% above discount rate of the central
bank of Country of the currency of payment);
Sub-clauses 14.10, 14.11, 14.12, and 14.13 deal with the Statement on completion,
application for Final Payment Certificate, discharge and issue of Final Payment Certificate;
Sub-clause 14.15 sets out the procedures if the payments are to be made in more than one
currency;
Sub-clause 14.11 requires the Contractor to submit Final Statement within fifty-six days of
receiving Performance Certificate;
Sub-clause 14.13 requires the Engineer to issue within twenty-eight days Final Payment
Certificate;
For a lump-sum Contract the references to measurement in Clauses 12, 13 and 14 must be omitted
or revised in the Particular Conditions. If the lump-sum form is to be adopted, the Particular
Conditions Guidance recommends several amendments.
It is the responsibility of the Contractor to pay all taxes and other fees as required. Any
quantity set out in the Bill of Quantities or other schedule is an estimated figure only;
It is the responsibility of the Contractor to submit, within twenty-eight days after the
Commencement Date, a non-binding breakdown of each lump-sum price shown in any
schedule;
The Contract Price is the amount which the Contractor actually receives and should not be
confused with the Accepted Contract Amount (see “Definition”). The Accepted Contract
Amount is fixed but the Contract Price can change and will probably increase, due to
the measurement of actual quantities, Variations and other adjustments. The Contract
Agreement states that the Employer will pay the Contractor “the Contract Price at the
times and in the manner prescribed by the Contract”.
If the advance payment has not been repaid twenty-eight days prior to the expiry date, the
Contractor must extend the validity of the guarantee;
The advance payment is repaid through percentage deductions in the Payment Certificates,
which commence when the total of certified interim payments exceeds 10% of the Accepted
Contract Amount less any Provisional Sums;
It is very common for the Employer to make some form of advance payment (sometimes
called a “mobilisation payment” or “interest-free loan”) in order to help the Contractor
with some of his early Costs and expenditures before he has reached the stage where he
can submit an Interim Payment Certificate. The amount of the advance payment needs to
be given in the Contract Data and is very often (but not always) in the order of 10% of the
Accepted Contract Amount.
• The application for interim payment must include the monthly progress report
prepared in accordance with Sub-clause 4.21;
• The application must also include the detailed supporting information set out at Sub-
paragraphs (a) to (g);
• The Statement is submitted “after the end of each month” and the sooner the
Contractor collects the necessary information and submits the Statement, the
sooner he will be paid.
Notes
If the schedule is included. The instalments must be estimated Contract values defined by
reference to actual progress;
If the Contract does not include a schedule the Contractor shall submit non-binding
estimates of the payments which he expects to become due;
The first estimate must be submitted within forty-two days after the Commencement Date;
Sub-clause 14.4 deals with a situation where the Contract states that the Contract Price is
to be paid in instalments;
If the Contract Price is to be paid in instalments, the Contract has the possibility to pay
based on Schedule of Payments. In this case the Contract must include a Schedule of
Payments, giving the timing and details of the instalments, subject to the provisions of Sub-
clause 14.1;
If the Contract does not include a Schedule of Payments then the Contractor must submit
non-binding estimates of the amount he expects will become due during each quarterly
period, with revised estimates submitted at quarterly intervals. Thus, the Employer has
an advance indication of what amounts will become payable and can arrange his finances
accordingly. Moreover, this can be very useful for the Contractor when planning and
analysing his cash flow;
The Engineer will only certify additions for Plants and Materials for payment if the
Contractor’s records are adequate;
Payment will be made in the same currency as for the rest of the Contract.
If the Employer has not received and approved the Performance Security; or
If, prior to issuing the Taking-Over Certificate, the amount to be certified would be less than
the minimum amount of the Interim Payment Certificate stated in the Appendix to Tender;
Sub-clause 14.6 deals with the issue of Interim Payment Certificates. The Sub-clause starts
by confirming the requirement expressed in Sub-clause 4.2 that the Contractor must provide
a Performance Security before the Employer is under any obligation to make payment. The
Sub-clause thereafter concentrates on the question of payments and the right, if any, for
payment to be withheld;
It is one of the roles of the Engineer to issue to the Employer an Interim Payment Certificate,
which details the amount that the Engineer believes is due to the Contractor every month,
along with any documents supporting his belief. A copy of this certificate should also be
issued to the Contractor;
This is a very important Sub-clause as it is the link between the Contractor’s application
to be paid and the Employer’s obligation to pay him, and it applies in respect of both the
Contractor’s application for payment of the Advance Payment and his applications for
interim payments;
The Engineer must decide the amount which is due to be paid to the Contractor and issue
an Interim Payment Certificate, including supporting particulars, within twenty-eight days
after receiving the Contractor’s Statement with particulars. The Interim Payment Certificate
shall state the amount due to the Contractor.
The Interim Payment Certificate, which is a “liquid document”, is binding upon the Employer
and he must make payment in full, subject to Sub-clause 14.7(b), regardless of any claim
that he may have against the Contractor.
Thus, once the Employer’s Representative receives an application he must act expeditiously
to check the application and issue the Payment Certificate. For the Advance Payment he
has fourteen days after receiving the application to issue the certificate and, in respect of
interim payments, he has twenty-eight days.
During this time he must check the application for errors or for payments which in his (the
Employer’s Representative’s) opinion are not due and then prepare and issue a Payment
Certificate for the amount which he “fairly determines to be due”. So the certificate is for
the amount which the Engineer considers to be correct, except when any amount is due
following a decision of the DAB. In such cases the amount is not subject to the opinion of the
Employer’s Representative and he must include such amount as awarded, bearing in mind
that such a decision may be in favour of the Employer and be in the form of a reduction in
the amount due to the Contractor. (Although the sub-clause does not specifically mention
it, the same would apply for arbitral awards);
If the amount of the due payment is less than the minimum amount of Interim Payment
Certificates stated in the Contract Data, the Engineer does not have to issue a certificate.
Finally, under this sub-clause, the important point is made that certification of payment, or
indeed payment itself, does not mean that the Works have been accepted or approved and
the Engineer is permitted to make any correction to any previously issued certificate that
he finds to be necessary.
Sub-clause 14.7 [Payment]
The Employer must make payment to the Contractor in accordance with the timescales set
out in Sub-paragraphs (a) to (c);
Payment is to be made into the bank account as chosen by the Contractor, as specified in
the Contract;
The Employer’s obligation is to pay the sum that is certified by the Engineer, without any
deductions;
The Contractor is not obliged to give any notice in relation to this claim for interest;
Sub-clause 14.7 is a key sub-clause that sets out the method and the timescale in which the
Employer is to pay the Contractor for work done;
This sub-clause makes it clear that once the Engineer has certified an amount as being due
for payment then the Employer must pay;
The Employer also has strict time limits within which to pay and if he fails to meet these
dates then the Contractor has rights, under Sub-clauses 16.1 [Contractor’s Entitlement to
Suspend Work] and 16.2 [Termination by Contractor], to firstly suspend work until payment
is received and then, if payment has not been received within forty-two days after the
period stated in this Sub-clause 14.8, the Contractor may terminate the Contract.
Notes
If payment is not made within fifty-six days of the submission of the Contractor’s Statement
applying for payment, the finance charges shall be calculated at a rate of 3% above the IBL
or in South Africa it would be 3% above the bank Repo rate.
If the Taking-Over Certificate is for a Section or part of the work, 40% of the value of that
Section shall be released by way of retention;
The outstanding balance for Retention Money shall be certified for payment promptly after
the expiry of the Defects Notification Period;
If any work remains to be executed, the Engineer shall be entitled to withhold certification
of the estimated Cost of this work.
FIDIC takes the view that the Contractor should also give an indication of what he believes
the final Contract Price will be and this is provided for at Sub-clause 14.10;
The Contractor shall submit to the Engineer six copies of its completion Statement within
eighty-four days after receiving the Taking-Over Certificate;
The Statement at Completion shall show the value of all work done, any further sums
considered due and estimates of any other amounts which may be due;
The Engineer shall certify in accordance with the principles of Sub-clause 14.6, i.e. fairly;
When preparing the Statement the Contractor should consider Sub-clause 14.14 which
deals with the cessation of the Employer’s liability;
The Contractor does not have his “hand on his heart” when making this assessment and
cannot be in breach if his assessment is incorrect. Therefore Contractors will generally
include all potential claims which may still have to be submitted! – Regardless of their
success or otherwise.
The draft Final Statement should show the value of all work done and the value of any
further sums which the Contractor considers due;
If the Engineer disagrees with this, the Contractor shall submit any further information as
may be reasonably required. After discussion, any disagreement must be resolved according
to the principles of Sub-clause 3.5 and Clause 20;
This important sub-clause which sets out the procedure the parties must follow in order to
settle issues of payment. As with all payment procedures, the timetable is initiated by the
Contractor.
Sub-clause 14.12 [Discharge]
The Contractor must submit with the Final Statement a written discharge confirming that
the total of the Final Statement represents the full and final settlement of all monies due
to him, including claims;
This discharge becomes effective when the Contractor has received the Performance
Security and payment of any outstanding balance.
The Final Payment Certificate states the amount finally due and the balance, if any, due to
the Contractor;
If the Contractor does not apply for a Final Payment Certificate, the Engineer must request
one;
If the application is still not made within twenty-eight days, the Engineer must issue a final
certificate having determined the sum it believes to be due.
The only exceptions relate to the Employer’s indemnity obligations or, in the cases of
deliberate default, reckless misconduct or fraud by the Employer.
This sub-clause refers to the cessation of the Employer’s liability and not that of the
Contractor;
The sub-clause limits the Employer’s liability to matters which the Contractor has raised in
his Final Statement. If they have not been mentioned the Employer has no liability in that
regard under the Contract (subject to the applicable law). It also means that the Employer
remains liable to honour any decision of the DAB regarding any matter which the Contractor
submitted to the DAB in respect of matters in the Contractor’s Final Statements, which were
not accepted by the Engineer and not included in the respective Final Payment Certificate;
In other words, the sub-clause refers to the Employer’s liability for any matter or thing
under or in connection with the Contract or execution of the Works. If the Contractor is not
satisfied with any valuation, the response to any claim or anything else whatsoever which
is related to the Contract then he must ensure that the matter is mentioned in the Final
Statement, together with an amount of money in compensation.
If no such currency is named then the default provisions Sub-paragraphs (a) to (e) will
apply;
The sub-clause must be read together with the Appendix to Tender and the FIDIC Contract
form for the Letter of Tender. These documents allow for different provisions for the
currency of payment and the documents must be clear as to the precise provisions that
will apply.
There are many provisions in a FIDIC Contract where an obligation on one Party to act or perform
is directly followed by a remedy in the event that the Party fails to act or perform as required.
This is to provide the parties with a contractual solution to deal with common failures without the
need to consult the applicable law in order to resolve the problem. The answer is in the Contract.
However, the Contract cannot address all possible failures or serious failures where the only
solution is for the other Party to be able to terminate the Contract and the provisions of Clause 15
deal with commonly arising failures by the Contractor which give the Employer the right to
terminate the Contract. Clause 16 deals with commonly arising failures by the Employer and
those for whom the Employer is responsible which give the Contractor the right to terminate the
Contract.
In summary, Clauses 15 and 16 set out the grounds which will entitle the:
Clause 15 [Termination by the Employer] covers the Notice to Correct [Sub-clause 15.1], the
reasons for termination requiring fourteen days’ notice by the Employer to the Contractor (Sub-
clause 15.2) and the Employer’s right to terminate for convenience at any time by giving twenty-
eight days’ notice (Sub-clause 15.5).
Clause 16 [Termination and Suspension by the Contractor] includes in Sub-clause 16.1 the
reasons for entitlement for the Contractor to suspend work (under Sub-clauses 14.6; 2.4 and
14 7) with twenty-one days’ notice to Employer (where the Contractor must give notice to the
Engineer for Costs and time), the reasons for termination by the Contractor (Sub-clause 16.2) and
the actions for Employer must undertake after Notice of Termination has been received from the
Contractor (Sub-clause 16.4).
Notes
This sub-clause is simply a requirement for the Engineer to notify the Contractor by
written notice if the Contractor is failing to carry out any obligation under the Contract.
If the Contractor fails to carry out any obligation under the Contract, the Engineer may by
notice require the Contractor to make good the failure and to remedy it within a specified
reasonable time. In other words, the Engineer has the right to issue a notice to the
Contractor requesting that he rectify poor performance under the Contract;
Although the giving of a notice potentially has a very significant effect, the requirement on
the Engineer is an optional one – he does not have to issue such a notice;
The receipt by the Contractor of a notice under this sub-clause needs to be taken very
seriously, as failure to rectify the failure can lead to termination by the Employer under
Sub-clause 15.2 [Termination for Contractor’s Default];
Nevertheless, as the notice (and the failure to comply with any such notice) is one of the
precursors to termination, the notice should:
State the time which the Contractor has to remedy the failure, under Sub-clause 1.3,
be in writing;
The sub-clause refers to a failure to carry out “any” obligation under the Contract. Given
that minor defects by themselves would be unlikely to amount to a sufficient breach of
Contract to justify termination, there might be thought to be a question mark over whether
the failure to remedy a minor defect will empower the Employer to exercise its right to
terminate under Sub-clause 15.2. However, it is not the nature of defect itself which
becomes relevant but the failure of the Contractor to remedy the defect when requested
to do so. The type of situation the sub-clause is attempting to deal with is not the defect
itself but the conduct in failing to remedy the defect that is important;
In common law the non-compliance with such a term after receipt of notice may amount to
repudiation regardless of the contractual effect set out in Sub-clause 15.2.
Termination and Suspension are very serious matters – Do not suspend or terminate
until you have consulted your legal team!!!
Termination is a very serious step. Parties should take legal advice whenever termination is
contemplated. Termination is likely to delay the completion and increase the Costs of the
project;
Sub-clause 15.2 deals with the mechanism of termination and sets out the circumstances
in which the Employer may terminate. The Employer shall be entitled to terminate the
Contract if the Contractor:
Fails to comply with a notice issued under Sub-clauses 7.5 or 7.6 within twenty-eight days
after receiving it;
Subcontracts the whole of the Works or assigns the Contract without the agreement;
In the first five situations the Employer may terminate the Contract once he has given
the Contractor fourteen days’ notice of such an intention. In the last two situations the
Employer can by notice terminate the Contract immediately;
The Employer must be very certain of his grounds for terminating the Contract as the
consequences of wrongful termination can be very serious. A wrongful termination may
result in a repudiation and the innocent party may find itself having to pay damages!
The Employer must therefore take care to follow any notice requirements in the Contract.
Who should the notice be served upon? Where should the notice be served? How should
the notice be delivered? The purpose of this contractual provision is to ensure that one
Party knows what the other wishes to communicate;
The contractual right to terminate exists in addition to the common law right to repudiation;
The Employer must remember that it may only terminate immediately in respect of the
insolvency or bribery as described in Sub-paragraphs (e) and (f);
For the other Sub-paragraphs (a) to (d) the Employer must give fourteen days’ notice
prior to termination. This thereby gives both parties a short period to try and resolve their
differences. The Contractor should be aware that there is nothing in Sub-clause 15.2 which
says that if the default specified in the notice is remedied then the Employer cannot still go
ahead and terminate;
Upon termination under Sub-clause 15.2 the Employer may complete the Works himself
or arrange for others (a third Party) to do so. He may also make use of the Contractor’s
Documents and Goods to effect completion. Under Sub-clause 1.1.5.2 Goods will include
equipment, Plant, Materials and Temporary Works. Provided the Contractor does not owe
the Employer any money, these must be returned to the Contractor once the Employer has
finished using them, although the Contractor must collect them at its own Cost;
There is no provision for what might happen if the Contractor refuses to comply with any
such instruction to collect his equipment. However, if the Contractor does owe money then
the Employer is entitled to sell them, accounting to the Contractor for any excess balance.
Any advance payment becomes immediately due and payable to the Employer. This must
be taken account of by the Engineer in his determination.
No payment needs to be made until the Works are complete and account has been taken
of the Employer’s entitlement (if any) to claims;
Upon termination most Employers will, if they are able, call upon the Performance
Guarantee.
Under this sub-clause the Employer is entitled to recover from the Contractor all Costs,
losses and damages incurred or suffered by the Employer as a result of the termination
under Sub-clause 15.2 [Termination for Contractor’s Default]. Normally this amount will be
deducted from the amount determined to be due to the Contractor in accordance with Sub-
clause 15.3 [Valuation at Date of Termination], and the remaining amount will be certified
in a Payment Certificate by the Employer’s Representative and duly paid by the Employer;
If the amount due to the Employer exceeds the amount determined to be due to the
Contractor under Sub-clause 15.3 [Valuation at Date of Termination] then the balance due
to the Employer may be recovered by the Employer from the Contractor as a commercial
debt;
Thus, upon termination most Employers will, if they are able, call upon the Performance
Guarantee.
Withhold any payment until any other Costs incurred by him are established;
Recover from the Contractor any losses and damages. After recovering such losses the
Employer shall pay the balance.
If the Employer terminates on this basis the Works cannot be completed by another. Thus,
this Sub-clause cannot be applied if the Employer’s intention is to remove the Contractor;
The Contractor is entitled to be paid in accordance with Sub-clause 16.3 and the Force
Majeure provisions of Sub-clause 19.6 (Engineer must determine the value of the Works
done and issue a Payment Certificate);
The most likely reason the Employer will choose to operate this sub-clause will be an
inability to fund and thereby finish the project. Such action could be for good reason (other
than Contractor’s default) such as economic restrictions or political decisions or it may be
for other reasons known only to the Employer;
The termination will take effect in twenty-eight days after the Contractor receives the
notification or the Performance Security (whichever is the latest);
This would not prevent an Employer from resuming the project at a later date if it had a
genuine alternative reason at the time of the operation of this sub-clause;
Notes
Termination and Suspension are very serious matters – Do not suspend or terminate
until you have consulted your legal team!!!
Sub-clause 16.1 provides that the Contractor may suspend work when the Contractor:
Where the Contractor does not receive from the Employer reasonable evidence, within
forty-two days after giving a notice to suspend on this account, that the Employer’s financial
arrangements have been made and are being maintained to enable the Employer to pay
the Contract Price in accordance with the Contract payment schedule (Sub-clauses 16.1,
14.6 and 2.4);
Where the Engineer fails, within fifty-six days after receiving a payment application and
supporting documents, to issue the relevant Payment Certificate.
If the Contractor suffers delay and/or incurs Cost as a result of suspending the work then, upon
giving notice to the Engineer (and subject to complying with the claims procedure of Sub-
clause 20.1), he shall be entitled to an extension of time for any such delay and/or payment of any
Costs that he has incurred, as well as a reasonable profit.
Before the Contractor can suspend, he must give twenty-one days’ notice;
The notice must be in writing and must set out the grounds for the suspension;
If the default is remedied the Contractor must resume work as soon as possible;
Where the suspension is valid the Contractor is entitled to claim for delay or Cost plus
reasonable profit in accordance with Clause 20.
(a) The Employer fails to provide reasonable evidence of his financial arrangements;
(e) The Employer fails to enter into the Contract Agreement or assigns its entire interest in
the project;
In the case of Sub-paragraphs (f) and (g) the Contractor may give immediate notice to
termination;
In the case of Sub-paragraphs a) to (e) the Contractor must give fourteen days’ notice.
The sub-clause gives the grounds under which the Contractor is entitled to terminate the
Contract;
Termination of the Contract by either Party is a very serious step and the comments given
under Sub-clause 15.2 [Termination by the Contractor], in respect of the Employer’s right
to terminate the Contract, apply equally well to this sub-clause. In this case the Contractor
must be very certain of his grounds for terminating the Contract as the consequences of
wrongful termination can be very serious;
A prudent Contractor should always seek legal advice before deciding to terminate the
Contract as the consequences of a wrongful termination can have important adverse
consequences for the Contractor;
Note: Termination is final and irrevocable. Once the Contract has been terminated
then, as a legal matter, it cannot ordinarily be unterminated or reinstated;
The ability to terminate if the Employer “substantially fails to perform” its obligations under
the Contract is likely to be the most contentious grounds for termination. The Contractor
will need to be especially sure of its grounds. The wording used is different to its counterpart
Sub-clause 15.2(b) which requires a simple demonstration of an intention not to continue
performing;
There is no definition of what “substantially fails” means. The Contractor should compare
what has been done against what the Employer has contracted to do. Of the Employer’s
contractual obligations, the most important one, as far as the Contractor is concerned, is
likely to be payment and there may be other conditions of the Contract which the Contractor
may be able to use with more certainty in the event of any failure to pay.
Sub-clause 16.3
[Cessation of Work and Removal of Contractor’s Equipment]
Upon termination the Contractor must cease work, hand over all Goods for which it has
received payment and remove any other Goods from the Site;
There is no need for the Contractor’s presence on the Site other than in the interests of
safety.
Pay the Contractor in accordance with Sub-clause 19.6, i.e. the amount of any loss of
profit or other loss or damage sustained by the Contractor as a result of the termination;
If there is any portion of the advance payment which has not been repaid to the
Employer at the time of the termination, this amount must be credited to the Employer.
Notes
Introduction
This section deals with the clauses that protect the parties of the 1999 FIDIC Contracts from
claims arising out of the project through indemnities and insurance.
Clauses 17 and 18 are closely related. They aim to protect both parties from claims arising out of
the project through indemnities and insurance.
Clause 17 [Risk and Responsibility] gives the basis for indemnities given by the Contractor and
the Employer (Sub-clause 17.1), the Contractor’s care of the Works (Sub-clause 17.2), Employer’s
risks (Sub-clause 17.3) and their consequences (Sub-clause 17.4), and the limitation of liability
(Sub-clause 17.6 ). Intellectual and industrial property risks covered in Sub-clause 17.5 fall outside
normal project risks and can be considered separately.
Clause 18 covers insurance, the last of the contractual provisions in the chain of risk, responsibility,
liability, indemnity, and insurance.
Throughout the Contract, the fact of a claim or an interim decision on a claim does not relieve
either Party of its obligations under the Contract. The justification for claims that acknowledges
some situations that were outside the control of either Party is covered by the Force Majeure
clause of Clause 19.
Introduction
Clause 17 covers a wide range of risks and responsibilities that lead to claims arising out of the
project which are covered by the indemnities and insurance.
The clause covers risk and responsibility but also encompasses other contractual provisions,
including indemnities, limitation of liability and the unrelated topic of intellectual and industrial
property rights. In fact the clause deals first with “Indemnities” and back tracks to “Responsibility”
and returns to “Risk” and finally turns to “Liability”. This illogical sequence has been adjusted in
the FIDIC DBO Contract published in 2008.
Sub-clause 17.1 [Indemnities]
Contractor will be held liable for the following risks:
Personal injury arising out of the Contractor’s design and/or execution of the Works
unless attributable to the negligence, wilful act or breach of Contract by the Employer;
Damage to property arising out of the Contractor’s design and/or execution of the
Works which is attributable to the negligence, wilful act or breach of Contract of the
Contractor or its Personnel.
Personal injury arising out of his negligence, wilful act or breach of Contract;
Losses arising as a consequence of the Employer’s right to have work executed on and/
or to occupy any land as per Sub-clause 18.3(d)(i);
Where a Party carries a risk he is required to indemnify or protect the other Party in respect
of any claims he may receive or damage or loss he may suffer as a result of such risk. Thus,
if a Party who is not liable for a risk under the Contract receives a claim from a third Party
or suffers loss or damage as a result of the risk eventuating, he is entitled to pass the claim
over to the other Party (the Party carrying the risk) to settle with the third Party or to claim
any loss or damage from the other Party or parties to the Contract;
The Contractor shall indemnify and hold harmless the Employer, Employer’s Personnel, and
their agents;
The Employer shall indemnify and hold harmless the Contractor, Contractor’s Personnel
and their agents against and from all claims, damages, losses and expenses in respect of
bodily injury, sickness, disease or death which is attributable to any negligence of one Party
or the other;
While Sub-clause 17.1 defines the risks primarily in relation to loss and damage which the
Contractor and Employer will be held responsible for, the Contractor is responsible for the
majority of the risks;
Thus, in practice, the type of risks set out in the sub-clause are those for which the
Contractor and Employer are likely to obtain insurance;
Claims for personal injury will unsurprisingly be borne by the responsible Party. There
is however one significant difference in how this sub-clause treats the Contractor and
Employer. The Employer’s obligation to indemnify in respect of personal injury is subject to
default on the part of the Employer. The Contractor’s obligation is all embracing regardless
of fault.
Remedying, at its own risk and Cost, any damage for which it is responsible.
Contractor will remain liable for any loss or damage that arises from an event, prior to
the issue of the certificates, for which the Contractor was responsible.
The Contractor is responsible for the Works after the Taking-Over Certificate is issued for
damages caused by any actions done by the Contractor;
Once the Taking-Over Certificate has been issued responsibility switches to the Employer;
The practical importance of this is that insurance responsibilities may well switch as well.
It is important that enough time has been allowed to ensure that the project is not left
uninsured;
This sub-clause makes it clear that the Contractor is responsible for remedying, at its own
risk and Cost, any damage for which it is responsible. Those Costs might ultimately translate
into delay damages if progress is delayed as a consequence. Although the Contractor will
not be held responsible for damage caused by an Employer Risk, this and Sub-clause 17.4
make it clear that, provided the proper notice it given, the Contractor must rectify that
damage.
Notes
Disorder or rioting on the part of the Contractor which arose from the conduct of the
Works is not an Employer risk.
Hostilities;
Invasion;
Rebellion terrorism;
Revolution;
Civil war;
Riot;
Munitions of war;
Explosives;
The exclusion whereby disorder on the part of the Contractor or its personnel is
understandably not an Employer risk remains;
Importantly, disorder or rioting on the part of the Contractor which arose from the conduct
of the Works is not an Employer risk;
The words “munitions of war” and “explosive Materials” have been added to the 1987
Red Book text, primarily as a reference to landmines which can take many years to be
removed;
Occupation of the Works and any design carried out by the Employer are Employer risks. It
is not immediately apparent what will constitute “use or occupation by the Employer”. The
Employer should take special care when he has more than one Contractor on Site, as this is
typically when such difficulties are likely to arise;
Forces of nature are events which are either Unforeseeable or against which the experienced
Contractor could not have been expected to take reasonable preventive measures. Sub-
clause 1.1.6.8 defines “Unforeseeable” as meaning not reasonably foreseeable by an
experienced Contractor by the date of the submission of the Tender.
The Engineer may require the Contractor to remedy the loss or damage;
Although the Contractor can recover Cost in all cases, he is only entitled to reasonable
profit in respect of Sub-paragraphs (f) and (g) of Sub-clause 17.3, items which refer to
Employer responsibility and/or fault;
This sub-clause deals with how the Contractor must proceed if an Employer Risk causes loss
or damage;
The Contractor must give notice to the Engineer of the damage caused by the Sub-
clause 17.3 risk item. The notice must be in writing and ought to define the risk and
damage caused by that risk;
The Employer must indemnify the Contractor in respect of any such claim which was the
unavoidable result of the Contractor executing the Works or as a result of the Employer
using the Works for purposes not related to the Contract;
The Contractor must indemnify the Employer in respect of any such claim arising out of its
design or Works;
The parties must co-operate together to deal with any claims that may arise against one of
the parties.
Claims for indirect or consequential loss or damage, loss of use of the Works, loss of any
Contract, or loss of profit can only be made in respect of Sub-clauses 16.4 and 17.1;
The Contractor’s total liability is capped and shall not exceed either the sum stated in the
Appendix to Tender. If there is no amount stated in the Appendix to Tender the cap on
liability is the Accepted Contract Amount;
The limitations are affected by the chosen applicable law which might in particular impose
a higher or lower liability cap or may limit the duration of any such liability;
As with any Contract, care needs to be taken in agreeing the Contract terms that relate to
a contractual liability cap;
The limitations in this sub-clause are affected by the chosen applicable law, which might
in particular impose a higher or lower liability cap or may limit the duration of any such
liability.
Notes
Introduction
Insurance is the last of the contractual provisions in the chain of risk, responsibility, liability,
indemnity, and insurance.
The provisions in Clause 19 are based on most of the required insurances being provided by the
Contractor. The Contractor will in the main be responsible for obtaining insurance cover. Insurance
is to be taken out for the benefit of the project rather than to protect a Party against the defaults
of the other.
As insurance is taken out in joint names there is little motivation for disputes to arise between the
parties as to matters covered by the policy. The same policy would pay in either outcome.
The reason that both the terms of the policies and the insurers which the Contractor intends
using must be approved by the Employer, not the Employer’s Representative, is that in most of
the policies the Employer is jointly insured so he is responsible for satisfying himself that he is
properly covered by the policy.
The requirement for the Contractor to take out insurance is an obligation, not an option since it
also provides for some of the indemnities which the Contractor is required to give the Employer.
In each case the wording “the Contractor shall effect and maintain ...”, and “shall” (see Sub-
clause 1.2 [Interpretation]) means he must take out the required insurances in accordance with
the provisions of each sub-clause.
The basic intention of the clause is that the Contractor is to arrange cover as the “insuring Party”,
unless stated otherwise in the Particular Conditions.
Insurance against loss or damage to the Works, Plant, Materials, Contractor’s Documents
and Contractor’s Equipment;
Insurance against liability for personal injury to third parties and damage to property (other
than the Works);
The sub-clauses only set out the minimum insurances required under the Contract. In most
instances, the parties may also wish to effect other insurances or others may be required by
the applicable law, for example, decennial liability insurance in France. In addition, the insurance
cover that is available is ever changing and differs from Country to Country.
To this end, the FIDIC Contracts have included the insurance that is typically available and sought
to identify some of the risks (which are included in Employer’s Risks under Sub-clause 17.3) which
may be uninsurable, as possible exclusions from the required insurances, but require them to be
insured wherever possible.
The insurance requirements do not alter the parties’ liabilities under the Contract or otherwise.
Any insurance policy taken out by the Employer must be in a form set out in the Particular
Conditions;
Any insurance payment made for loss or damage must be utilised in respect of that loss or
damage;
The insuring Party must supply proof to the other, including evidence of payment of
premiums, that the policy has been taken out;
If either Party fails to do this the other may take out an appropriate policy and seek
reimbursement for this;
Any dispute shall be decided in accordance with Sub-clauses 2.5 (although the Contractor
will in the main be responsible for obtaining insurance) and 20.1.
Sub-clause 18.1 contains the general requirements for the insurances that must be effected
and maintained under Clause 18. The particular requirements regarding the scope, extent,
amount, period, permitted exclusions and deductibles for the specific insurances are then
set out in the subsequent sub-clauses, which variously require further information to be
stated in the relevant Contract Document;
Whichever Party is responsible for arranging the insurance, the other Party is likely to wish
to have details of the proposed insurer and insurance terms, including the conditions, limits,
exclusions and deductibles, during the Tender stage (or in any event soon after) so that it
can make its own arrangement for any other insurance it may require and, in the case of the
Contractor, may take these matters into account when submitting his Tender offer;
Wherever the Employer is the insuring Party, each insurance shall be put into effect with
insurers and in terms consistent with the details annexed to the Particular Conditions;
The relevant insuring Party shall submit to the other Party evidence that the insurances
have been effected, evidence of insurance and copies of the policies;
Neither Party shall make any alteration to the terms of any insurance without the prior
approval of the other Party;
Any terms in relation to insurance agreed by the parties before the Contract will override
this sub-clause;
The obtaining of insurance cover will not limit the obligations, liabilities or responsibilities
of either the Contractor or the Employer;
The insurance for Works and Contractor’s Equipment and the insurance against injury to
persons and damage to property are required to be in the joint names of the parties, unless
agreed otherwise in the Particular Conditions.
The consequences if the obligations in respect of insurances are not complied with are
also set out Sub-clause 18.1. If the relevant Party fails to effect and keep in force any of
the insurances required under the Contract or fails to provide the required proof that the
insurances have been effected or are being maintained, the other Party may effect and
keep in force the insurances and recover the amount of any premiums paid as a result from
the first Party.
The Works must be insured for a sum not less than the full reinstatement value;
This insurance must be maintained until the date the Performance Certificate is issued;
The insuring Party shall put in place full replacement value insurance for equipment to
cover the entire period from while it is transported to the Site until it is no longer required;
The insurance must cover all loss and damage to the Works save for certain items listed as
an Employer Risk;
The insurance need not include loss or damage as a consequence of a defect in the
Employer’s design, Materials and workmanship, or parts of the Works taken over by the
Employer;
If certain insurance cover is not available at commercially reasonable terms, the Contractor
may be entitled to dispense with the requirement to insure;
The cover required until the date of issue of the Performance Certificate;
For the period after the Taking-Over Certificate has been issued for the Works, the
Contractor is required to maintain a reduced level of insurance cover for the Works, Plant,
Materials and Contractor’s Documents until the date of issue of the Performance Certificate,
i.e. during the Defects Notification Period.
Sub-clause 18.3
[Insurance against injury to Persons and Damage to Property]
Insurance against injury to persons and damage to property shall be in joint names but
effected by the Contractor;
The insurance amount shall be limited as set out in the Appendix to Tender;
The insurance amount shall include cover for loss and damage to the Employer’s property.
The requirements for insurances against personal injury of persons other than the
Contractor’s Personnel and damage to property other than the Works are set out in this
sub-clause.
Primarily relate to third Party liability. However, as with Sub-clause 17.1, these
insurances are required to cover damage to property of either of the parties other
than the Works and other property insured under Sub-clause 18.2;
It is the Contractor who is the insuring Party, unless otherwise specified in the Particular
Conditions, and these insurance provisions only apply if the minimum amount of cover
per occurrence is specified in the Appendix to Tender.
The Contractor must indemnify the Employer and Engineer in respect of any such claims
that may arise, unless they arise as a consequence of any act or neglect on the part of the
Employer or Engineer;
Notes
Introduction
Throughout the Contract the fact of a claim, or an interim decision on a claim, does not relieve
either Party of its obligations under the Contract. A justification for claims that acknowledges
some situations that were outside the control of either Party is covered by a Force Majeure clause.
A Force Majeure clause is a common feature of international Contracts. Typically, where a Party
has been prevented from performing a Contract by an event beyond its control, it will be excused
for its delay in performing the Contract or, in an extreme case, it may be excused from having
to perform the Contract at all. In some cases such Party can recover any additional Costs it had
incurred as the result of the Force Majeure event as well.
The introduction of a Force Majeure clause is more recently seen as neither necessary nor
desirable because:
Most of the risks, which now come under the definition of Force Majeure in the 1999
Construction Contract, are insurable and are required to be insured. Therefore, there is no
benefit to the Contractor in being protected by such a clause;
While it is agreed that the treatment of the risks specified in Clause 19 should be a special
one, it is erroneous to swing to the extreme end of the scale and designate them in the
category of Force Majeure, particularly when that term has legal implications in certain
jurisdictions.
Thus, in editions of the FIDIC Contracts after 1999 (notably the FIDIC DBO Contract) is to
designate an exceptional set of risks with different treatment to that given to the normal
set of risks to which the project is exposed.
Returning to the 1999 Construction Contract, the Force Majeure clause (Clause 19) may be
broken down into the following parts:
Force Majeure must “prevent” a Party from performing “any of” its obligations (thereby
expressly acknowledging the possibility of partial Force Majeure) (Sub-clause 19.2);
When this happens the Party affected must give notice within fourteen days after the
Party became aware, or should have become aware, of the event or circumstance said to
constitute Force Majeure (otherwise, the Party may have no right to claim Force Majeure)
(Sub-clause 19.2);
If execution of substantially all the Works in progress is prevented for a continuous period
of eighty-four days, or for multiple periods which total more than one hundred and forty
days, by Force Majeure, either Party may, after notice to the other, terminate the Contract
in which event the Contractor will be paid for work done only (Sub-clause 19.6); and
A Party must give notice when it ceases to be affected by Force Majeure (Sub-clause 19.3);
Sub-clause 19.7 further provides that, notwithstanding any other provision of the Contract
(including Sub-clauses 19.1 to 19.6), if:
Performance of the Contract becomes illegal (eg. as may happen should the Site
become a war zone); or
Impossible (e.g. as may happen where the Site is totally destroyed by an earthquake
or flood); or
The parties are released from performance under the applicable law (eg. under the
common law doctrine of frustration or the civil law doctrine of Force Majeure as
provided for in the applicable civil code).
The term “Force Majeure” includes the list of specific events as set out in Sub-paragraphs (i)
to (v);
This list is non-exhaustive and the events specified are examples only.
Sub-clause 19.1 gives the four conditions that must be met for an event or circumstance
to qualify as Force Majeure. Force Majeure means an exceptional event or circumstance
which:
Having arisen, such Party could not reasonably have avoided or overcome and provided
against before entering into the Contract;
Which includes events such as war, revolution, riot or strike by persons other than the
Contractor’s Personnel, radioactive contamination; and
Certain operations of the forces of nature which are also listed at Sub-clause 17.3 as
“Employer’s Risks”;
Force Majeure refers to the situation when either Party is prevented from performing
any of its obligations under the Contract;
There is a difference in the way that Force Majeure is treated in common and civil
law jurisdictions. While most civil codes make provisions for Force Majeure events, at
common law the meaning of Force Majeure is far from clear;
For Force Majeure the qualifying forces of nature are described in detail as “such as
earthquake, hurricane, lightning, typhoon or volcanic activity”. Also, an additional
event is included – a change in the Laws of the Country, or in the judicial or official
governmental interpretation of such Laws, made after the Contract becomes legally
effective. This circumstance duplicates the provisions of Sub-clause 13.7;
The sub-clause recognises that certain acts of terrorism or civil war outside of the
Country where the project is proceeding may still have a considerable effect on
progress;
Ultimately, what constitutes a Force Majeure event will depend on the circumstances
and thus the notice which the Party affected by the event is required to give by virtue
of Sub-clause 19.2 is of particular importance.
Notes
With the exception of payment obligations, the delivery of a Force Majeure notice will
excuse the affected Party from performing its obligations for the duration of the Force
Majeure event.
Envisages that the parties will work together to minimise any delay caused by the Force
Majeure event;
Notice must be given when the Force Majeure event is no longer of any effect.
The definition of the category of war events includes hostilities (whether war be declared
or not), invasion and act of foreign enemies.
Sub-clause 19.5 is an extension of Sub-clause 4.4, which provides that the Contractor shall
be responsible for the acts or defaults of any Subcontractor.
It is important that all subcontracts contain similar Force Majeure provisions to the main
Contract.
(ii) Multiple periods of more than one hundred and forty days;
Any irresistible event (not limited to Force Majeure) makes it impossible or unlawful
for the parties to fulfil their contractual obligations; or
This sub-clause grants the Party seeking exoneration the right to rely on any alternative
relief mechanism contained in the law governing the Contract. Because of this legal
advice is indispensable to ascertain the precise boundaries of Sub-clause 19.7. In the
event of this sub-clause applying the Contractor will be entitled to payment under the
same terms as Sub-clause 19.6.
The sub-clause:
Is much wider than the Force Majeure provisions of Sub-clause 19.1 and acknowledges
that situations can arise when it is impossible for the Contract to continue;
Acts as a fall-back provision for extreme events (i.e. events rendering contractual
performance illegal or impossible) which do not fit within the strict definition of Force
Majeure of Sub-clause 19.1;
If any event or circumstance outside the control of the parties arises which makes it
impossible or unlawful for either or both parties to fulfil its or their contractual obligations
or which, under the law governing the Contract, entitles the parties to be released from
further performance of the Contract, then upon notice by either Party to the other Party of
such event or circumstance:
The sum payable by the Employer to the Contractor shall be the same as would have
been payable under Sub-clause 19.6 [Optional Termination, Payment and Release].
Notes
This section covers the submission of claims and the settlement of disputes.
Introduction
Clauses 1-19 of the FIDIC Contracts deal with the rights and obligations of the Parties under the
Contract.
Clause 20 is a procedural clause and covers the submission of claims and the settlement of
disputes.
One of the principal ways that the Construction Contract covers the special contingencies of
construction projects is by providing for specified claim rights for the Contractor if and when such
contingencies arise.
While requiring the Contractor to execute the Works for an agreed price and within a specific time
period, they at the same time provide that the Contractor may have the right to claim additional
money or time or both from the Employer in specifically defined circumstances.
In addition to providing the Contractor with defined claim rights, they provide procedures for the
enforcement of those rights. For example, the Engineer has the power and authority to decide
on the Contractor’s claims in the first instance. If the Contractor is dissatisfied with the Engineer’s
ruling, the Contractor may thereafter refer it to a DAB and, if still dissatisfied, thereafter to
arbitration.
Clause 20 covers the various types of claims that the Contractor may assert under, or in connection
with, the Contract and the procedure that the Contractor is required to follow to assert claims and
to get them paid.
Legal claims, i.e. claims which the Contractor may be entitled to assert under the law
governing the Contract, the most obvious one being breach of Contract;
Contractual claims, i.e. claims which the Contractor is entitled to assert by virtue of the
specific provisions of the Contract.
However, as a general rule, during the execution of the Works it will be in the Contractor’s interest
to claim under one or more clauses of the Contract wherever feasible. This is because the Engineer
has the power and authority to decide the Contractor’s claims in the first instance.
For contractual claims there are about thirty sub-clauses specifying events which, should they
occur, will entitle the Contractor to claim from the Employer.
Regarding disputes where one or both parties do not agree with the Engineer’s determination of
a claim, early FIDIC Contracts:
Provided for administration of the Contract by the Engineer, who was required to act
impartially;
Included a requirement that any dispute must first be referred to the Engineer, as a
precondition to arbitration.
Only after the Engineer had made a decision on the dispute could it be referred to an outside
dispute resolver for amicable settlement or arbitration.
The 1999 Construction Contract has changed this procedure and introduced the DAB as the
standard procedure. Disputes have to be referred to an independent DAB as a precondition to
arbitration. The DAB renders a decision that is immediately binding on the parties whether one of
them is dissatisfied with the decision or not.
As well as covering Contractor’s Claims, Clause 20 covers the appointment and operation of the
DAB and amicable settlement and arbitration.
For the Construction Contract, the DAB is a standing (or permanent) one. In this case the DAB
must be jointly appointed by the parties within twenty-eight days of the Commencement Date.
In the case of a standing DAB, instead of seeking a decision from the DAB, the parties may also
jointly seek an opinion from the DAB on any matter relevant to the avoidance of a potential
dispute.
The latest thinking regarding DAB’s provides that this provision of a non-binding opinion is a
fundamental obligation of successful DAB’s.
Any claim to time or money will be lost if there is no notice within the specified time
limit (time barred);
Supporting particulars should be served by the Contractor and the Contractor should also
maintain such contemporary records as may be needed to substantiate claims (not time
barred);
The Contractor should submit a fully particularised claim after forty-two days;
The claim shall be an interim claim. Further, interim updated claims are to be submitted
monthly. A final claim is to be submitted, unless agreed otherwise, within twenty-eight days
of the end of the claim event;
Procedure:
This sub-clause sets the procedure to be followed by the Contractor when submitting his
claims. The procedure has three steps:
Engineer’s assessment.
The notice shall be given as soon as practicable and not later than twenty-eight days
after the Contractor became aware, or should have become aware, of the event or
circumstance;
If the Contractor fails to give notice of a claim within such period of twenty-eight days,
the Time for Completion shall not be extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be discharged from all liability in connection
with the claim.
If yes the Contractor submits a detailed claim in forty-two days that is considered as
an interim claim.
Final details are submitted twenty-eight days after the end of the effect resulting from the
event or circumstance;
Engineer’s Assessment:
Within forty-two days after receiving the particulars of a claim, the Engineer shall respond
with approval or disapproval of the claim but shall nevertheless give the response on the
principle of the claim;
The Engineer shall proceed in accordance with Sub-clause 3.5 to agree or determine the
claim;
Sub-clause 20.1 only refers to claims by the Contractor. The equivalent provision for
Employer claims is at Sub-clause 2.5 which is much less stringent in its requirements. A
list of notices under Sub-clauses 2 5 and 20.1 is to be included in the Contractor’s monthly
progress report under Sub-clause 4.21;
When disputes do arise it is of crucial importance that both parties follow the provisions
of Sub-clause 20.1 with some care. A failure to do so could quite possibly prevent a Party
from bringing a claim.
Engineer’s Responsibilities:
Under Sub-clause 20.1 the Engineer has several responsibilities:
Although the burden of proof lies with the Contractor to prove his claim, the Engineer can
require that the Contractor submit additional particulars;
The Engineer can also inspect the Contractor’s records and instruct the Contractor to keep
further records;
The Engineer must also respond within forty-two days both to the Contractor’s claim and
to a further interim claim. At the very least the Engineer must provide his comments on the
principles of the claim;
The Engineer’s determination must be made in accordance with the principle of the Sub-
clause 3.5. Thus, it must be fair in accordance with the Contract and take due regard of all
relevant circumstances.
Notices:
Sub-clause 20.1 requires that the Contractor, if it considers it has a claim for an extension
of time and/or any additional payment, must give notice to the Engineer “as soon as
practicable” and not later than twenty-eight days after the event or circumstance giving
rise to the claim. So the:
Contractor must submit his claims during the course of the project;
Initial notice at first instance does not need to indicate (for the very good reason that
usually it cannot) the total extension or payment sought;
The Contractor also needs to remember that where the effects of a particular event
are ongoing then the Contractor is specifically required to continue submitting notices
at monthly intervals;
The Sub-clause 20.1 notice is in addition to the other requirements for notices in
similar circumstances, such as the Sub-clauses that refer matters to the Engineer for
a determination under Sub-clause 3.5 and the notice that is hidden in Sub-clause 8.3.
33 Enable the Engineer to make his own observations and records of the problem;
33 Put the problem on record and make it possible for the Contractor to receive a
prompt decision on his entitlements.
Contemporary Records:
The Contractor is required to keep contemporary records to substantiate his claim. One
cannot attempt to get around this requirement by producing simple witness Statements
after the event;
The Engineer is entitled to inspect the contemporary records and to request copies. If the
Engineer has any doubts about the accuracy of the records then he should raise any queries
and give the Contractor the opportunity to discuss and justify the records.
This section covers the submission of claims and the settlement of disputes.
The composition of the DAB shall be by nomination and then joint selection;
DAB members are to be remunerated jointly by the parties with each paying half of any
fees;
The DAB shall be constituted by the number of members stated in Appendix to Tender. If
not then three members;
Each Party shall nominate one member for the approval of the other Party;
Once the two members have been agreed than the members and the parties shall agree
upon the third member, the chairman.
Either Party fails to nominate a member for the other Party’s approval;
The parties fail to agree upon the third member, the Chairman;
The parties fail to agree upon the appointment a replacement in forty-two days after a
member or the whole DAB declines to act.
The reference must be in writing and copies must be provided to the other parties and the
Engineer;
The DAB shall be entitled to whatever access it requires, including access to information
and the Site;
Unless otherwise agreed, the DAB shall reach its reasoned decision within eighty-four days;
If a Party disagrees with the decision of the DAB it should serve a Notice of Dissatisfaction;
If no such notice is served then the decision of the DAB shall become final and binding.
An arbitration may not be commenced until fifty-six days after the Notice of Dissatisfaction
has been served.
Sub-clause 20.6 [Arbitration]
If a dispute remains following the decision of the DAB, and any attempt at amicable
settlement, then that dispute is to be settled by international arbitration under the Rules
of the Chamber of Commerce or other rules specifically stated in the Particular Conditions
of Contract;
The arbitral tribunal will have full powers to open up and revise any decision of both the
Engineer and the DAB;
Provided the necessary time limits have been complied with, an arbitration may take place
during the currency of the project.
Sub-clause 20.7
[Failure to Comply with Dispute Adjudication Board’s Decision]
If a Party fails to comply with a DAB decision then the other Party may refer the failure to
arbitration in accordance with Sub-clause 20.6;
The other Party may refer the failure itself to arbitration if:
The DAB’s related decision (if any) has become final and binding;