Вы находитесь на странице: 1из 21

Coal Loading Operation from Pit Stock Pile

through hauling road and dump to Pelindo Stock


Pile and Loading to Barge

BLACK GOLD ENERGY INDONESIA


MINING OPERATION AT RENGAT
INDRAGIRI HULU
RIAU-INDONESIA
Pit Stock Pile
80km Hauling

Coal getting

Pelindo stock pile

Stocking and crushing


Dolphin Arrangement of Jetty

Dolphin to Accommodate
7000 DWT Barge
Jetty Operational
 Effective operating hours coal getting to pit stock pile receciving = 360 hours
 Effective operating hours loading to DT at pit stock pile = 360 hours
 Effective operating hauling from pit stock pile to Pelindo = 360
hours

 Hauling distance from Primanusa to Pelindo is 80 Km


 Coal charasteristics :
 Bulk density : 0,85T/M3
 Boulder size : 400 to 300 mm
 Crush Coal size : 0-50 mm
 Stock Pile requirements
 Pit Stock Pile estimate for 7 days minimum
 Pelindo stock pile expected to received 60,000 mt as Standby Stock Pile.
 Loading operational 4 hours/ each 7,000 DWT barges
 Working hours 20 hours/day
Survey and Engineering Study
 River SURVEY /BED – BASIC ENGINEERING DESIGN
 Bathy metri, 35 km a long of river from Kuala Cenaku to Tembilhan
 Monitoring of water level at three points of area for 15 days
 Hydrometrics – Check water elevation
 Current meter
 Sedimentation check
 Weather Station – measure wind speed and rain leverages
 Cross section of river surrounding of loading jetty
 Hydrology

 Loading Jetty/Stock Pile and Coal Handling System – Sub structure – Basic Engineering Design
 Topography for 12 Ha of area
 Bathymetry Survey
 Soil Investigation : deep bore hole and sondir and laboratories test for soil for total of 12 point
 Conceptual design – Civil- for Sub structure and Loading Jetty, mechanical refer to Coal Handling
Design
 Utilities building
 Reclamation and soil improvement study and calculation for Pressure load of stock pile up to
60,000 MT
 Barging Study from Kuala Cenaku up to Mother Vessel
Coal loading onto 10 DT
at Pit Stock pile
10 Tons DT through 80 km
hauling road to Pelindo stock
pile
Coal Dump at Pelindo
Stock Pile
From stock pile coal to
be crush,and load to
barge with conveyor
Loading operation to
the barge
Pelindo Stock Pile and Laoding Facility
MESS,OFFICE AND HOUSING AT PELINDO STOCK PILE
Flow of coal Laoding at Pelindo Stock Pile

1 2

3 4
Raw Coal number 1 and 2
with 30,000 MT
Capacity/each total of Stockpile no.2
60,000 MT

Stockpile no.1

Weight bridge

Hauling truck entering


Pelindo stock pile
Raw Coal then load to
chain feeder and crushing

Conveyor No. 2

Conveyor No. 1
Indragiri River

Raw Coal load onto Stockpile No


feeder breaker and
roller crusher then
through tranfer 6
conveyor load to
loading conveyor
2000t/hours

5 Stockpile No

4
Conveyor Parts : 3
1. Feeder Breaker 2 1
2. Chain feeder
3. Vibrating Screen
4. Roller Crusher
5. Transfer Conveyor
6. Hopper
7. Loading Conveyor
Indragiri River
Dolphin

Laoding to 7,000 mt barge


with loading conveyor 2000
t/hours capacity
Scope of Responsibility for Pelindo Stock Pile Development

Land clearing and dozing 11 ha area to be used – Pelindo or BGE


Reclamation and soil stabilization for stock pile – Pelindo or BGE
Fencing all Pelindo property Pelindo or BGE
Permit for Constrction for Jetty/CHF Pelindo or BGE
If new Amdal need to be done Pelindo or BGE
Construction of all facilities,stock pile,CHF,Jetty
Soil protection at edges of river
Presented By BGE Construction Team

 Autocad drawing by : Ir. Aan Pujiandi


 Animation by : Robby Kurniawan S.Kom

 Flow diagram by : Ir.Adi Sumanto

 Thanks for viewing this presentation

Вам также может понравиться