Вы находитесь на странице: 1из 10

CRONOGRAMA VALORIZADO DE OBRA

OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
01 ESTRUCTURAS 3,348,576.81 S/.653,857.83 S/.408,033.07 S/.539,948.88 S/.639,785.68 S/251,952.01 S/477,479.14 S/264,364.16 S/113,156.02
01.01 OBRAS PROVISIONALES 15,249.42 S/15,249.42
01.01.01 SUMINISTRO Y COLOCACION DE CARTEL DE OBRA DE 2.40 x 3.60m UND 708.15 S/708.15
01.01.02 CASETA DE GUARDIANIA Y/O ALMACEN M2 3,620.16 S/.3,620.16
01.01.03 CERCO PROVISIONAL DE OBRA DE CALAMINA GALVANIZADA h=2.20m ML 10,921.11 S/10,921.11
01.02 TRABAJOS PRELIMINARES 101,009.42 S/89,657.41 S/1,640.46 S/1,706.08 S/1,706.08 S/1,706.08 S/1,706.08 S/1,771.70 S/1,115.52
01.02.01 TRAZO, NIVELES Y REPLANTEO M2 6,376.91 S/860.88 S/797.11 S/829.00 S/829.00 S/829.00 S/829.00 S/860.88 S/542.04
01.02.02 LIMPIEZA INICIAL DE OBRA M2 2,898.59 S/2,898.59
01.02.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 6,746.80 S/910.82 S/843.35 S/877.08 S/877.08 S/877.08 S/877.08 S/910.82 S/573.48
01.02.04 DEMOLICION DE EDIFICACION EXISTENTE 84,987.12 S/84,987.12
01.02.04.01 DEMOLICION DE EDIFICACION EXISTENTE C/MAQUINARIA M3 69,740.31 S/69,740.31
01.02.04.02 DEMOLICION MANUAL DE CUNETAS EXISTENTES M3 1,744.34 S/1,744.34
01.02.04.03 DESMONTAJE DE COBERTURA EN EDIFICACION EXISTENTE M2 7,329.42 S/7,329.42
01.02.04.04 DESMONTAJE DE CERCO, VENTANAS Y PUERTAS METALICAS M2 1,898.33 S/1,898.33
01.02.04.05 DESMONTAJE DE AULA PREFABRICADA EXISTENTE MANUAL M2 4,274.72 S/4,274.72
01.03 SEGURIDAD Y SALUD EN OBRA 122,505.09 S/16,538.18 S/15,313.13 S/15,925.66 S/15,925.66 S/15,925.66 S/15,925.66 S/16,538.18 S/10,412.94
01.03.01 EQUIPO DE PROTECCION COLECCTIVA GLB 3,000.00 S/405.00 S/375.00 S/390.00 S/390.00 S/390.00 S/390.00 S/405.00 S/255.00
01.03.02 EQUIPO DE PROTECCION INDIVIDUAL GLB 3,197.95 S/431.72 S/399.74 S/415.73 S/415.73 S/415.73 S/415.73 S/431.72 S/271.83
01.03.03 SEÑALIZACION TEMPORAL EN OBRA GLB 2,057.77 S/277.80 S/257.22 S/267.51 S/267.51 S/267.51 S/267.51 S/277.80 S/174.91
01.03.04 PLAN DE MANEJO AMBIENTAL GLB 114,249.37 S/15,423.66 S/14,281.17 S/14,852.42 S/14,852.42 S/14,852.42 S/14,852.42 S/15,423.66 S/9,711.20
01.04 MOVIMIENTO DE TIERRAS 521,754.59 S/228,561.88 S/84,182.79 S/157,906.22 S/38,962.49 S/12,141.21
01.04.01 CORTE DE TERRENO NATURAL CON MAQUINARIA M3 21,448.03 S/21,448.03
01.04.02 PERFILADO, NIVELACION Y COMPACTACION DE TERRENO NATURAL CON MAQUINARIA M2 16,976.14 S/16,976.14
01.04.03 PERFILADO, NIVELACION Y COMPACTACION DE TERRENO NATURAL - MANUAL M2 15,825.19 S/10,022.62 S/5,802.57
01.04.04 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS, ZAPATAS Y PISOS M3 75,226.67 S/47,643.56 S/27,583.11
01.04.05 RELLENO CON MATERIAL DE PRESTAMO AFIRMADOM PREPARADO (60% AFIRMADO + 40% HORMIGO M3 157,906.22 S/157,906.22
01.04.06 CAPA DE MATERIAL DE PRESTAMO - HORMIGON GRUESO (60% DE PIEDRA + 40% ARENA GRUESA) C M3 43,886.87 S/26,819.75 S/17,067.12
01.04.07 COLOCACION, COMPACTACION Y NIVELACION DE CAPA DE HORMIGON (CON EQUIPO LIVIANO) e=0. M2 24,558.90 S/20,224.98 S/4,333.92
01.04.08 COLOCACION, COMPACTACION Y NIVELACION DE CAPA DE AFIRMADO (CON EQUIPO LIVIANO) e=0.1 M2 26,544.80 S/18,737.51 S/7,807.29
01.04.09 CAPA DE MATERIAL DE PRESTAMO - HORMIGON GRUESO (60% DE PIEDRA + 40% ARENA GRUESA) M2 29,339.39 S/29,339.39
01.04.10 CAPA DE MATERIAL DE PRESTAMO - AFIRMADO (60% DE AFIRMADO + 40% DE HORMIGON) e=0.20m M2 13,958.48 S/13,958.48
01.04.11 COLOCACION DE TEKNOPOR DE e=4" EN VIGAS DE CIMENTACION M2 2,677.77 S/2,677.77
01.04.12 ELIMINACION DE MATERIAL EXCEDENTE A 2.00 KM DE DISTANCIA DE LA OBRA M3 93,406.13 S/59,676.14 S/33,729.99
01.05 OBRAS DE CONCRETO SIMPLE 84,732.70 S/84,732.70
01.05.01 SOLADO PROP. 1:8, e=0.10m M2 27,564.89 S/27,564.89
01.05.02 CIMIENTO DE CONCRETO CICLOPEO PROP. 1:8 + 25% P.M. M3 2,598.63 S/2,598.63
01.05.03 CIMIENTO DE CONCRETO CICLOPEO PROP. 1:10 + 30% P.G. M3 54,569.18 S/54,569.18
01.06 OBRAS DE CONCRETO ARMADO 2,147,895.54 S/218,021.29 S/302,979.00 S/360,336.53 S/618,079.55 S/230,245.88 S/251,323.06 S/80,322.48 S/86,587.76
01.06.01 ZAPATAS 231,467.71 S/196,779.35 S/34,688.36
01.06.01.01 CONCRETO F'C=210 KG/CM2 - PARA ZAPATAS M3 156,097.64 S/121,409.28 S/34,688.36
01.06.01.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - PARA ZAPATAS KG 75,370.07 S/75,370.07
01.06.02 VIGA DE CIMENTACION 92,988.35 S/21,241.94 S/71,746.41
01.06.02.01 CONCRETO F'C=210 KG/CM2 - EN VIGAS DE CIMENTACION M3 22,114.16 S/22,114.16
01.06.02.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - VIGA DE CIMENTACION KG 53,003.32 S/17,667.77 S/35,335.55
01.06.02.03 ENCOFRADO Y DESENCOFRADO DE VIGA DE CIMENTACION M2 17,870.87 S/3,574.17 S/14,296.70
01.06.03 SOBRECIMIENTO ARMADO 209,905.65 S/158,955.57 S/50,950.08
01.06.03.01 CONCRETO F'C=175 KG/CM2 - PARA SOBRECIMIENTO ARMADO M3 64,803.48 S/28,801.55 S/36,001.93
01.06.03.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - PARA SOBRECIMIENTO ARMADO KG 65,378.72 S/65,378.72
01.06.03.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO M2 79,723.45 S/64,775.30 S/14,948.15
01.06.04 COLUMNAS Y PLACAS 699,107.28 S/37,588.66 S/309,386.45 S/352,132.17
01.06.04.01 CONCRETO F'C=210 KG/CM2 PARA COLUMNAS Y PLACAS M3 198,104.99 S/198,104.99
01.06.04.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 PARA COLUMNA Y PLACAS KG 275,794.04 S/27,579.40 S/179,266.13 S/68,948.51
01.06.04.03 ENCOFRADO Y DESENCOFRADO DE COLUMNA Y PLACAS M2 225,208.25 S/10,009.26 S/130,120.32 S/85,078.67
01.06.05 COLUMNETAS 99,079.53 S/80,322.48 S/18,757.05
01.06.05.01 CONCRETO F'C=175 KG/CM2 EN COLUMNETAS M3 13,785.76 S/13,785.76
01.06.05.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - PARA COLUMNETAS KG 60,437.34 S/60,437.34
01.06.05.03 ENCOFRADO Y DESENCOFRADO DE COLUMNETAS M2 24,856.43 S/19,885.14 S/4,971.29
01.06.06 VIGAS 321,277.32 S/238,255.09 S/83,022.23
01.06.06.01 CONCRETO F'C= 210KG/CM2 EN VIGAS M3 82,557.74 S/38,526.95 S/44,030.79
01.06.06.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - PARA VIGAS KG 143,070.41 S/115,556.87 S/27,513.54
01.06.06.03 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 95,649.17 S/84,171.27 S/11,477.90
Página 1
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
01.06.07 VIGAS DE AMARRE EN MUROS 67,830.71 S/67,830.71
01.06.07.01 CONCRETO F'C= 175KG/CM2 EN VIGAS DE AMARRE M3 8,787.05 S/8,787.05
01.06.07.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - VIGA DE AMARRE KG 23,654.70 S/23,654.70
01.06.07.03 ENCOFRADO Y DESENCOFRADO DE VIGAS DE AMARRE M2 35,388.96 S/35,388.96
01.06.08 LOSA ALIGERADA 294,276.12 S/27,692.29 S/147,223.65 S/119,360.19
01.06.08.01 CONCRETO F'C=210 KG/CM2 EN LOSA ALIGERADA M3 64,287.98 S/64,287.98
01.06.08.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - PARA LOSAS ALIGERADAS KG 45,372.91 S/27,223.75 S/18,149.16
01.06.08.03 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA M2 130,719.33 S/19,607.90 S/84,967.56 S/26,143.87
01.06.08.04 LADRILLO DE TECHO 15x30x30 - LOSA ALIGERADA UND 53,895.90 S/8,084.39 S/35,032.34 S/10,779.18
01.06.09 LOSA MACIZA 99,363.20 S/99,363.20
01.06.09.01 CONCRETO F'C=210 KG/CM2 - PARA LOSA MACIZA M3 24,253.27 S/24,253.27
01.06.09.02 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 - LOSA MACIZA KG 49,288.18 S/49,288.18
01.06.09.03 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA M2 25,821.75 S/25,821.75
01.06.10 ESCALERA 32,599.67 S/32,599.67
01.06.10.01 CONCRETO F'C=210 KG/CM2 EN ESCALERA M3 11,384.29 S/11,384.29
01.06.10.02 ACERO DE REFUERZO F'Y=4,200 KG/CM2 GRADO 60 PARA ESCALERA KG 11,625.66 S/11,625.66
01.06.10.03 ENCOFRADO Y DESENCOFRADO DE ESCALERA M2 9,589.72 S/9,589.72
01.07 COBERTURAS LIVIANAS 167,580.09 S/153,615.10 S/13,965.00
01.07.01 SUMINISTRO Y COLOCACION DE TIJERAL METALICO CURVO TIPO 1 LONG=26.30M UND 34,110.40 S/31,267.87 S/2,842.53
01.07.02 SUMINISTRO Y COLOCACION DE VIGUETA METALICA TIPO VG-C ML 33,819.02 S/31,000.77 S/2,818.25
01.07.03 SUMINISTRO Y COLOCACION DE TEMPLADOR DE Ø 5/8" ML 5,009.76 S/4,592.28 S/417.48
01.07.04 SUMINISTRO Y COLOCACION DE TENSORES DE FIERRO LISO Ø 5/8" ML 4,758.00 S/4,361.50 S/396.50
01.07.05 SUMINISTRO Y COLOCACION DE COLGANTE DE FIERRO LISO Ø 1/2" ML 1,978.20 S/1,813.35 S/164.85
01.07.06 SUMINISTRO Y COLOCACION DE COBERTURA DE ACERO ALUMINIZADO (CALAMINON CU e=0.50m) M2 74,374.56 S/68,176.68 S/6,197.88
01.07.07 SUMINISTRO Y COLOCACION DE APOYOS FIJOS ENTRE COLUMNA Y TIJERAL PARABOLICO UND 1,753.60 S/1,607.47 S/146.13
01.07.08 SUMINISTRO Y COLOCACION DE APOYOS MOVIL ENTRE COLUMNA Y TIJERAL PARABOLICO UND 2,457.05 S/2,252.30 S/204.75
01.07.09 SUMINISTRO Y COLOCACION DE ARRIOSTRE DE FIERRO CORRUGADO Ø 3/8" ML 2,106.56 S/1,931.01 S/175.55
01.07.10 SUMINISTRO Y COLOCACION DE CANALETA GALVANIZADA DE 0.10x0.20x0.15mx6mm ML 6,488.32 S/5,947.63 S/540.69
01.07.11 SUMINISTRO Y COLOCACION DE BAJADA DE MONTANTE DE TUBERIA PVC Ø 3" PTO 724.62 S/664.24 S/60.39
01.08 PLATAFORMA DE FORMACION 161,825.72 S/50,834.85 S/110,990.87
01.08.01 LOSA DE CONCRETO F'C=175 KG/CM2, e=0.15m, EN PLATAFORMA DEPORTIVA Y PATIO DE FORMACIO M2 131,175.35 S/49,190.76 S/81,984.59
01.08.02 ENCOFRADO Y DESENCOFRADO DE LOSA DEPORTIVA Y PATIO DE FORMACION ML 2,630.55 S/1,644.09 S/986.46
01.08.03 JUNTA DE CONTRACCION DE LOSA DE CONCRETO e=6mm ML 26,837.07 S/26,837.07
01.08.04 JUNTA DE CONTRUCCION ASFALTICA e=1" ML 1,182.75 S/1,182.75
01.09 OTRAS OBRAS 26,024.24 S/1,096.95 S/3,917.69 S/4,074.39 S/4,074.39 S/4,074.39 S/4,074.39 S/1,813.44 S/2,898.59
01.09.01 CURADO DE ESTRUCTURAS DE CONCRETO M2 22,722.58 S/1,096.95 S/3,917.69 S/4,074.39 S/4,074.39 S/4,074.39 S/4,074.39 S/1,410.37
01.09.02 JUNTAS DE DILATACION ASFALTICA e=1" EN MURO ML 403.07 S/403.07
01.09.03 LIMPIEZA FINAL DE OBRA M2 2,898.59 S/2,898.59
02 ARQUITECTURA 2,203,624.46 S/288,861.77 S/177,443.85 S/122,506.34 S/103,659.22 S/4,660.81 S/372,876.71 S/1,133,615.75
02.01 MUROS Y TABIQUERIAS 141,089.66 S/4,660.81 S/115,570.40 S/20,858.45
02.01.01 MURO DE LADRILLO KING KONG 18 HUECOS MAQUINADO APAREJO DE CANTO M2 3,423.87 S/489.12 S/2,934.75
02.01.02 MURO DE LADRILLO KING KONG 18 HUECOS MAQUINADO APAREJO DE SOGA M2 137,665.79 S/4,171.69 S/112,635.65 S/20,858.45
02.02 REVOQUES Y ENLUCIDOS 330,033.02 S/88,008.81 S/242,024.21
02.02.01 TARRAJEO EN MUROS INTERIORES Y EXTERIORES PROP. 1:4, e=1.5cm CON CEMENTO TIPO MS M2 86,859.63 S/23,162.57 S/63,697.06
02.02.02 TARRAJEO EN COLUMNAS Y PLACAS PROP. 1:4, e=1.5cm CEMENTO TIPO MS M2 68,590.43 S/18,290.78 S/50,299.65
02.02.03 TARRAJEO EN VIGAS PROP. 1;4, e=1.5cm, CEMENTO TIPO MS M2 50,480.09 S/13,461.36 S/37,018.73
02.02.04 REVESTIMIENTO DE DERRAMES e=0.15cm PROP. 1:2 ML 11,635.59 S/3,102.82 S/8,532.77
02.02.05 TARRAJEO DE CIELO RASO PROP. 1:4, e=1.5cm M2 88,843.26 S/23,691.54 S/65,151.72
02.02.06 TARRAJEO DE ESCALERAS Y GRADERIAS PROP. 1:4, e=1.5cm M2 7,563.82 S/2,017.02 S/5,546.80
02.02.07 TARRAJEO PRIMARIO PROP. 1:4, e=1.5cm M2 16,060.20 S/4,282.72 S/11,777.48
02.03 PISOS Y PAVIMENTOS 334,372.03 S/73,217.25 S/261,154.78
02.03.01 FALSO PISO PROP. 1:8, e=4" M2 27,125.68 S/17,631.69 S/9,493.99
02.03.02 CONTRAPISO 1:4; e=3cm M2 45,812.70 S/22,906.35 S/22,906.35
02.03.03 PISO DE PORCELANATO ESMALTADO COLOR MATE PLATA DE 60x60cm M2 163,825.26 S/20,478.16 S/143,347.10
02.03.04 PISO DE PORCELANATO COLOR GRIS ANTIDESLIZANTE DE 60x60cm M2 13,350.06 S/1,668.76 S/11,681.30
02.03.05 PISO DE PORCELANATO ESMALTADO COLOR CONCRETO PLATA 60x60cm M2 72,954.86 S/9,119.36 S/63,835.50
02.03.06 PISO DE PORCELANTO ESMALTADO COLOR PLATA ANTIDESLIZANTE DE 60x60cm M2 11,303.47 S/1,412.93 S/9,890.54
02.04 ZOCALOS Y CONTRAZOCALOS 201,939.84 S/201,939.84
02.04.01 ZOCALO DE PORCELANATO ESMALTADO COLOR MATE BLANCO DE 60x60cm M2 153,759.93 S/153,759.93
02.04.02 ZOCALO DE PORCELANATO ESMALTADO COLOR GRIS DE 60x60cm M2 40,626.57 S/40,626.57
02.04.03 CONTRAZOCALO DE CEMENTO PULIDO CON IMPERMEABILIZANTE h=10cm ML 2,687.67 S/2,687.67

Página 2
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
02.04.04 CONTRAZOCALO DE CEMENTO PULIDO h=20cm ML 2,584.18 S/2,584.18
02.04.05 CONTRAZOCALO DE PORCELANATO ESMALTADO COLOR GRIS h=10cm ML 1,201.89 S/1,201.89
02.04.06 CONTRAZOCALO| DE PORCELANATO ESMALTADO COLOR MATE PLATA h=10cm ML 1,079.60 S/1,079.60
02.05 CARPINTERIA DE MADERA 955.33 S/477.67 S/477.67
02.05.01 SUM. E INST. DE PUERTA CONTRAPLACADA DE TRIPLAY 4mm, INCLUYE MARCO DE MADERA M2 724.20 S/362.10 S/362.10
02.05.02 DIVISIONES DE MELAMINE DE COLOR CON ESPESOR DE 18cm, INCLUYE ACCESORIOS/URINARIOS M2 231.13 S/115.57 S/115.57
02.06 CARPINTERIA METALICA 47,152.38 S/47,152.38
02.06.01 SUMINISTRO Y COLOCACION DE MURO CON PLANCHA DE FIBROCEMENTO DE 6mm EN INTERIOR M2 4,240.50 S/4,240.50
02.06.02 SUMINISTRO E INSTALACION DE ARCOS METALICOS CON TABLERO DE BASKET, SEGUN DISEÑO IN UND 3,719.58 S/3,719.58
02.06.03 SUMNISTRO E INSTALACION DE PARANTES METALICOS EN VOLEY, INCLUYE NET DE VOLEY UND 842.00 S/842.00
02.06.04 SUMINISTRO E INSTALACION DE BARRA DE SUJECION RECTA - Ø 32mm Y LARGO 0.90m DE ACERO UND 5,936.88 S/5,936.88
02.06.05 BARANDA METALICA TUBO GALVANIZADO Ø 2", h=0.53m ML 6,064.26 S/6,064.26
02.06.06 BARANDA METALICA TUBO GALVANIZADO Ø 2", h=0.17m ML 11,927.32 S/11,927.32
02.06.07 BARANDA METALICA TUBO GALVANIZADO EN ESCALERA Ø 2", h=0.90m ML 2,953.89 S/2,953.89
02.06.08 ESTRUCTURA METALICA DE INGRESO/INCLUYE PORTON DOBLE HOJA, REJAS Y ACCESORIOS DE UND 6,162.01 S/6,162.01
02.06.09 PASAMANO METALICO Ø 2" ADOSADO A MURO/ESCALERA ML 5,305.94 S/5,305.94
02.07 VIDRIOS, CRISTALES O SIMILARES 188,140.86 S/28,221.14 S/159,919.73
02.07.01 SUMINISTRO Y COLOCACION DE VENTANA CON MARCOS DE ALUMINIO CON VIDRIO DE 4.5mm LAMI M2 151,427.72 S/22,714.16 S/128,713.56
02.07.02 DIVISIONES DE MARCO DE ALUMINIO 2"x2" CON MELAMINE INCLUYE PUERTA/SEGUN DISEÑO CON M2 7,014.10 S/1,052.12 S/5,961.99
02.07.03 CANTONERA DE ALUMINIO Y VIDRIO DE 6mm LAMINADO ML 2,314.74 S/347.21 S/1,967.53
02.07.04 PUERTA CON ESTRUCTURA DE ALUMINIO Y VIDRIO DE 6mm LAMINADO M2 21,744.25 S/3,261.64 S/18,482.61
02.07.05 PANEL DE LISTONES DE ALUMINIO DE 2"x4"/VANO DE ESCALERA M2 5,640.05 S/846.01 S/4,794.04
02.08 CERRAJERIA 6,973.99 S/6,973.99
02.08.01 SUMINISTRO Y COLOCACION DE CERRADURA DE 02 GOLPES, PESADA FABRICACION NACIONAL UND 140.52 S/140.52
02.08.02 SUMINISTRO Y COLOCACION DE CHAPA TIPO PERILLA EN PUERTA DE MARCO DE ALUMINIO UND 2,304.90 S/2,304.90
02.08.03 SUMINISTRO Y COLOCACION DE BISAGRA DE 4" EN PUERTAS UND 2,165.40 S/2,165.40
02.08.04 BISAGRAS DE ALUMINIO DE 3", PUERTA DE MELAMINE UND 472.50 S/472.50
02.08.05 CERROJO DE ALUMINIO 2" UND 247.75 S/247.75
02.08.06 JALADORES METALICOS CROMADOS UND 665.04 S/665.04
02.08.07 JALADORES CROMADOS PARA MAMPARA DOBLE HOJA L=30cm APROX. UND 977.88 S/977.88
02.09 PINTURA 120,571.70 S/120,571.70
02.09.01 PINTURA SATINADA EN MUROS INTERIORES Y EXTERIORES M2 44,738.37 S/44,738.37
02.09.02 PINTURA SATINADA EN COLUMNAS Y PLACAS M2 25,819.22 S/25,819.22
02.09.03 PINTURA SATINADA EN VIGAS M2 16,512.85 S/16,512.85
02.09.04 PINTURA SATINADA EN DERRAMES PUERTAS Y VENTANAS M2 1,051.55 S/1,051.55
02.09.05 PINTURA SATINADA EN CIELO RASO M2 32,069.71 S/32,069.71
02.09.06 LETRAS CON ESMALTE EN INGRESO DE INICIAL - SEGUN DISEÑO GLB 380.00 S/380.00
02.10 OBRAS VARIAS 19,148.03 S/1,914.80 S/17,233.24
02.10.01 SUMINISTRO Y COLOCACION DE ESPEJO BISELADO DE 6mm/ PEGADO A MURO M2 1,970.82 S/197.08 S/1,773.74
02.10.02 JUNTA DE DILATACION CON PLATINA DE 4" x 3/16" ML 9,090.94 S/909.09 S/8,181.85
02.10.03 CARTELES DE SEGURIDAD AUTOPEGABLE (GRANDES) GLB 1,517.25 S/151.73 S/1,365.53
02.10.04 EXTINTORES EN POLVO QUIMICO SECO DE 12 KG INCLUYE ACCESORIOS UND 1,373.82 S/137.38 S/1,236.44
02.10.05 GARGOLA DE CONCRETO (INCLUYE DADO DE CONCRETO Y TUBO PVC) UND 5,195.20 S/519.52 S/4,675.68
02.11 CONCRETO ARMADO 1,525.79 S/1,525.79
02.11.01 MESON DE CONCRETO F'C=175 KG/CM2 M3 346.71 S/346.71
02.11.02 ACERO DE REFUERZO F'Y=4,200 KG/CM2 KG 302.29 S/302.29
02.11.03 ENCOFRADO Y DESENCOFRADO DE MESON DE CONCRETO M2 876.79 S/876.79
02.12 AREAS DE CIRCULACION 119,250.61 S/65,466.64 S/53,783.97
02.12.01 TRABAJOS PRELIMINARES 3,999.20 S/3,999.20
02.12.01.01 TRAZO, NIVELACION Y REPLANTEO M2 3,999.20 S/3,999.20
02.12.02 OBRAS DE CONCRETO SIMPLE 60,204.95 S/32,109.32 S/28,095.63
02.12.02.01 RAMPA DE CONCRETO F'C=175 KG/CM2, FROTACHADO 1:2 Y BRUÑADO, e=0.10m (INCL. 1.5cm DE P M2 192.18 S/102.50 S/89.68
02.12.02.02 CONCRETO EN VEREDA F'C=175 KG/CM2 SEMI PULIDO Y BRUÑADO e=0.10m M2 8,311.28 S/4,432.68 S/3,878.60
02.12.02.03 SARDINEL DE CONCRETO F'C=175 KG/CM2 DE 0.15x0.50m ML 4,490.17 S/2,394.76 S/2,095.41
02.12.02.04 SARDINEL DE CONCRETO F'C=175 KG/CM2 DE 0.15x0.20m ML 1,180.89 S/629.81 S/551.08
02.12.02.05 ENCOFRADO Y DESENCOFRADO EN VEREDAS Y SARDINELES M2 4,466.66 S/2,382.22 S/2,084.44
02.12.02.06 SUMINISTRO Y COLOCACION MANUAL DE ADOQUIN DE CONCRETO DE 10 x 20, h=4cm - PEATONAL M2 40,068.16 S/21,369.69 S/18,698.47
02.12.02.07 SUMINISTRO Y COLOCACION DE CAMA DE ARENA GRUESA h=5cm M2 1,495.61 S/797.66 S/697.95
02.12.03 CONCRETO ARMADO DE SARDINEL EN JARDINERIA 9,831.45 S/5,243.44 S/4,588.01
02.12.03.01 JARDINERIA DE CONCRETO F'C=175 KG/CM2 M3 2,543.11 S/1,356.33 S/1,186.78
02.12.03.02 CIMIENTO CORRIDO DE JARDINERIA M3 2,370.51 S/1,264.27 S/1,106.24

Página 3
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
02.12.03.03 ACERO DE REFUERZO FY=4200 KG/CM2 - JARDINERIA KG 131.44 S/70.10 S/61.34
02.12.03.04 ENCOFRADO Y DESENCOFRADO DE JARDINERIA M2 4,786.39 S/2,552.74 S/2,233.65
02.12.04 SARDINEL DE CONCRETO ARMADO 5,232.85 S/2,790.86 S/2,441.99
02.12.04.01 SARDINEL DE CONCRETO F'C=175 KG/CM2 M3 1,410.87 S/752.46 S/658.41
02.12.04.02 CIMIENTO PARA SARDINEL M3 1,627.38 S/867.94 S/759.44
02.12.04.03 ACERO DE REFUERZO FY=4200 KG/CM2 - SARINEL KG 1,617.03 S/862.42 S/754.61
02.12.04.04 ENCOFRADO Y DESENCOFRADO DE SARDINEL M2 577.57 S/308.04 S/269.53
02.12.05 GRADERIA 795.93 S/424.50 S/371.43
02.12.05.01 CONCRETO F'C=210 KG/CM2 EN GRADERIA M3 636.87 S/339.66 S/297.21
02.12.05.02 ACERO FY=4200 KG/CM2 - SARDINEL KG 11.45 S/6.11 S/5.34
02.12.05.03 ENCOFRADO Y DESENCOFRADO DE SARDINEL M2 147.61 S/78.73 S/68.88
02.12.06 OTROS 39,186.23 S/20,899.32 S/18,286.91
02.12.06.01 JUNTA ASFÁLTICA E=1" ML 676.24 S/360.66 S/315.58
02.12.06.02 SEMBRADO DE GRASS NATURAL M2 20,121.72 S/10,731.58 S/9,390.14
02.12.06.03 COLOCACION Y NIVELACION DE TIERRA DE CHACRA h=10cm M2 18,388.27 S/9,807.08 S/8,581.19
02.13 AULAS PROVISIONALES 268,410.78 S/208,761.49 S/59,649.29
02.13.01 TRAZO, NIVELACION Y REPLANTEO M2 2,969.23 S/2,969.23
02.13.02 SUMINISTRO Y COLOCACION DE MURO CON PLANCHA FIBRACEMENTO e= 6mm M2 78,835.95 S/53,608.45 S/25,227.50
02.13.03 SUMINISTRO Y COLOCACION DE VIGAS DE MADERA DE 2" x 4" ML 9,721.32 S/6,610.50 S/3,110.82
02.13.04 SUMINISTRO E INSTALACION DE PIZARRA ACRILICA (2.00 x 1.10m) INCLUYE PORTA MOTAS UND 5,422.72 S/3,687.45 S/1,735.27
02.13.05 CHAPA TIPO PERILLA CON LLAVE UND 978.72 S/665.53 S/313.19
02.13.06 SUMINISTRO Y COLOCACION DE BISAGRA ALUMINIZADA DE 4" UND 398.88 S/271.24 S/127.64
02.13.07 SUMINISTRO Y COLOCACION DE PUERTAS (1.00x2.10m) LAQUEADAS Y BARNIZADAS UND 6,055.84 S/4,117.97 S/1,937.87
02.13.08 SUMINISTRO Y COLOCACION DE CELOSIA DE ACERO GALVANIZADO EN VENTANAS M2 2,653.89 S/.1,804.65 S/849.24
02.13.09 PLANCHAS DE PROLIPROPILENO DE e=1.2mm/COLOR ROJO - INCLUYE CORREAS DE MADERA 2" x 2" M2 46,452.63 S/31,587.79 S/14,864.84
02.13.10 LOSA DE CONCRETO F'C= 140 KG/CM2, h=15cm/ ACABADO SEMIPULIDO Y BRUÑADO (INCL. ENCOFR M2 56,524.09 S/56,524.09
02.13.11 SARDINEL DE CONCRETO 0.20x0.45m, F'C=175 KG/CM2 ML 9,756.05 S/.9,756.05
02.13.12 CAPA DE MATERIAL DE PRESTAMO - HORMIGON GRUESO (60% DE PIEDRA + 40% ARENA GRUESA) M2 11,693.52 S/11,693.52
02.13.13 JUNTA DELITACION e=0.025m, h=0.15m ML 2,153.65 S/2,153.65
02.13.14 CAPA DE MATERIAL DE PRESTAMO - AFIRMADO (60% DE AFIRMADO + 40% DE HORMIGON) e=0.15m M2 5,563.30 S/.5,563.30
02.13.15 ELIMINACION DE MATERIAL EXCEDENTE A 2.00 KM DE DISTANCIA DE LA OBRA M3 9,952.12 S/9,952.12
02.13.16 CERCO PROVISIONAL h=2.50/INCLUYE PARANTE Y CALAMINA ML 6,852.05 S/6,852.05
02.13.17 PORTON DE AULAS EN CERCO PROVISIONAL DE MADERA CALAMINA-INCLUYE BISAGRAS Y ELEMEN UND 943.90 S/943.90
02.13.18 PARANTES METALICOS Ø 4" - COBERTURA LIVIANA h=6m UND 4,467.84 S/4,467.84
02.13.19 VIGA METALICA Ø 3"- COBERTURA LIVIANA ML 1,818.07 S/.1,818.07
02.13.20 MALLA RACHEL DE 85% DE SOMBRA - INCLUYE ACCESORIOS Y ALAMBRE TENSOR M2 3,812.69 S/3,812.69
02.13.21 DADO DE CONCRETO F'C=175 KG/CM2 (0.50x0.40, h=1.35m) UND 1,384.32 S/1,384.32
02.14 REHABILITACION DE AMBIENTES EXISTENTES 424,060.44 S/80,100.28 S/117,794.56 S/122,506.34 S/103,659.22
02.14.01 TRABAJOS PRELIMINARES 12,275.08 S/2,318.63 S/3,409.74 S/.3,546.13 S/.3,000.58
02.14.01.01 PICADO MANUAL DE MURO EXISTENTE PARA ENCHAPADO DE PORCELANATO M2 5,350.54 S/1,010.66 S/1,486.26 S/1,545.71 S/1,307.91
02.14.01.02 PICADO MANUAL DE CONTRAPISO EXISTENTE M2 6,924.54 S/.1,307.97 S/.1,923.48 S/.2,000.42 S/.1,692.67
02.14.02 REVOQUES Y ENLUCIDOS 15,252.21 S/2,880.97 S/4,236.73 S/4,406.19 S/3,728.32
02.14.02.01 TARRAJEO PRIMARIO PROP. 1:4, e=1.5cm M2 15,252.21 S/2,880.97 S/4,236.73 S/4,406.19 S/3,728.32
02.14.03 PISOS Y PAVIMENTOS 146,817.33 S/27,732.16 S/40,782.60 S/42,413.90 S/35,888.68
02.14.03.01 CONTRAPISO 1:4; e=5cm M2 39,988.93 S/7,553.46 S/11,108.04 S/.11,552.36 S/.9,775.07
02.14.03.02 PISO DE PORCELANATO ALTO TRANSITO COLOR PLATA MATE DE 60x60cm M2 84,665.85 S/15,992.44 S/23,518.29 S/24,459.02 S/20,696.10
02.14.03.03 PISO PORCELANATO ALTO TRANSITO COLOR CONCRETO PLATA DE 0.60x0.60m M2 17,678.04 S/3,339.19 S/4,910.57 S/5,106.99 S/4,321.30
02.14.03.04 PISO DE PORCELANATO ANTIDESLIZANTE COLOR MARRON DE 0.60x0.60m M2 4,484.51 S/847.07 S/1,245.70 S/1,295.53 S/1,096.21
02.14.04 ZOCALO Y CONTRAZOCALO 30,674.79 S/5,794.12 S/8,520.77 S/8,861.61 S/7,498.27
02.14.04.01 ZOCALO DE PORCELANATO COLOR BLANCO MATE DE 0.60x0.60 /h=1.00m M2 20,944.37 S/3,956.16 S/5,817.88 S/6,050.60 S/5,119.73
02.14.04.02 COLOCACION DE CONTRAZOCALO PORCELANTO ESMALTADO COLOR GRIS/h=0.20m x 0.60m ML 4,267.19 S/806.02 S/1,185.33 S/1,232.74 S/1,043.09
02.14.04.03 COLOCACION DE CONTRAZOCALO PORCELANTO ESMALTADO COLOR GRIS/h=0.34m x 0.60m ML 1,674.34 S/316.26 S/465.09 S/483.70 S/409.28
02.14.04.04 COLOCACION DE CONTRAZOCALO PORCELANTO ESMALTADO COLOR GRIS/h=0.10m x 0.60m ML 3,788.89 S/715.68 S/1,052.47 S/1,094.57 S/926.17
02.14.05 CARPINTERIA DE MADERA 4,974.35 S/939.60 S/1,381.76 S/1,437.03 S/1,215.95
02.14.05.01 PUERTA TIPO MACIZA C/MARCOS DE MADERA - LAQUEADO M2 4,974.35 S/939.60 S/1,381.76 S/1,437.03 S/1,215.95
02.14.06 VIDRIO, CRISTALES, ALUMINIO Y SIMILARES 48,636.37 S/9,186.87 S/13,510.10 S/14,050.50 S/11,888.89
02.14.06.01 SUMINISTRO Y COLOCACION DE VIDRIO LAMINADO DE 6mm - SISTEMA DIRECTO, INCLUYE PERFI M2 39,345.48 S/7,431.92 S/10,929.30 S/11,366.47 S/9,617.78
02.14.06.02 SUMINISTRO Y COLOCACION DE VIDRIO LAMINADO 6mm, CON MARCO DE ALUMINIO PARA PUERTA M2 9,290.89 S/1,754.95 S/2,580.80 S/2,684.03 S/2,271.11
02.14.07 CERRAJERIA 3,918.23 S/740.11 S/1,088.40 S/1,131.93 S/957.79
02.14.07.01 SUMINISTRO Y COLOCACION DE CERRADURA DE 02 GOLPES, PESADA FABRICACION NACIONAL UND 491.82 S/92.90 S/136.62 S/142.08 S/120.22
02.14.07.02 SUMINISTRO Y COLOCACION DE BISAGRA DE 4" EN PUERTAS UND 421.05 S/79.53 S/116.96 S/121.64 S/102.92
Página 4
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
02.14.07.03 JALADORES METALICOS CROMADOS UND 273.84 S/51.73 S/76.07 S/79.11 S/66.94
02.14.07.04 CHAPA METALICA PARA MAMPARA DE VIDRIO UND 1,161.12 S/219.32 S/322.53 S/335.43 S/283.83
02.14.07.05 CERROJO METALICO PARA MAMPARA DE VIDRIO UND 1,570.40 S/296.63 S/436.22 S/453.67 S/383.88
02.14.08 PINTURA 45,101.23 S/8,519.13 S/12,528.11 S/13,029.24 S/11,024.75
02.14.08.01 PINTURA LATEX EN MUROS EXTERIORES DOS MANOS/INCLUYE MASILLADO M2 12,155.48 S/2,296.04 S/3,376.52 S/3,511.58 S/2,971.34
02.14.08.02 PINTURA LATEX EN MUROS INTERIORES DOS MANOS/INCLUYE MASILLADO M2 15,917.20 S/3,006.58 S/4,421.44 S/4,598.30 S/.3,890.87
02.14.08.03 PINTURA LATEX EN VIGAS/INCLUYE MASILLADO M2 2,813.59 S/531.46 S/781.55 S/812.81 S/687.77
02.14.08.04 PINTURA LATEX EN DERRAMES/INCLUYE MASILLADO ML 1,904.80 S/359.80 S/529.11 S/550.28 S/465.62
02.14.08.05 PINTURA LATEX EN CIELO RASO/INCLUYE MASILLADO M2 12,001.42 S/2,266.93 S/3,333.73 S/3,467.08 S/2,933.68
02.14.08.06 PINTURA ESMALTE/INCLUYE MASILLADO ML 308.74 S/58.32 S/85.76 S/89.19 S/75.47
02.14.09 COBERTURA 64,204.60 S/12,127.53 S/17,834.61 S/18,548.00 S/15,694.46
02.14.09.01 MANTENIMIENTO DE COBERTURA CON LISTONES DE MADERA EXISTENTE M2 1,950.09 S/368.35 S/541.69 S/563.36 S/476.69
02.14.09.02 MEJORAMIENTO DE TECHO CON PROP. 1:5, e=3cm/ INCLUYE ADITIVO IMPERMEABILIZANTE M2 24,660.69 S/4,658.13 S/6,850.19 S/7,124.20 S/6,028.17
02.14.09.03 SUMINISTRO Y COLOCACION DE COBERTURA LIVIANA DE FIBRA VEGETAL (0.95x2.00m) M2 37,593.82 S/7,101.05 S/10,442.73 S/10,860.44 S/9,189.60
02.14.10 OBRAS DE CONCRETO SIMPLE 22,476.79 S/4,245.61 S/6,243.56 S/6,493.29 S/5,494.32
02.14.10.01 CONCRETO EN VEREDA F'C=175 KG/CM2 SEMI PULIDO Y BRUÑADO M2 4,159.43 S/785.67 S/1,155.40 S/1,201.61 S/1,016.75
02.14.10.02 FALSO PISO EN EXTERIOR-CORREDOR F'C=175 KG/CM2 e=10cm M2 4,118.05 S/777.85 S/1,143.90 S/1,189.66 S/1,006.63
02.14.10.03 SARDINEL DE CONCRETO F'C=175 KG/CM2 DE 0.20x0.50m ML 9,287.20 S/1,754.25 S/2,579.78 S/2,682.97 S/2,270.20
02.14.10.04 ENCOFRADO Y DESENCOFRADO DE VEREDAS Y SARDINEL M2 4,912.11 S/927.84 S/1,364.48 S/1,419.05 S/1,200.74

Página 5
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
02.14.11 CONCRETO ARMADO 458.40 S/86.59 S/127.33 S/132.43 S/112.05
02.14.11.01 GARGOLA DE CONCRETO ARMADO (SEGUN DISEÑO), DEBIDAMENTE TARRAJEADO Y PINTADO UND 458.40 S/86.59 S/127.33 S/132.43 S/112.05
02.14.12 OTROS 7,992.49 S/.1,509.69 S/.2,220.15 S/.2,308.95 S/.1,953.72
02.14.12.01 SUMINISTRO Y COLOCACION DE RONDON DE ALUMINIO EFECTO ESPEJO e=10cm ML 3,718.22 S/702.33 S/1,032.84 S/1,074.15 S/908.90
02.14.12.02 SUMINISTRO Y COLOCACION DE CANTONERA DE ALUMINIO e=2" ML 634.74 S/119.90 S/176.32 S/183.37 S/155.16
02.14.12.03 SUMINISTRO Y COLOCACION DE T° F°G° Ø 2" SEGUN DISEÑO ML 2,530.97 S/478.07 S/703.05 S/731.17 S/618.68
02.14.12.04 JUNTA DE DILATACION e=1" ML 939.41 S/177.44 S/260.95 S/271.39 S/229.63
02.14.12.05 MANTENIMIENTO DE VENTANAS EXISTENTES INCLUYE ACCESORIOS M2 169.15 S/31.95 S/46.99 S/48.87 S/41.35
02.14.13 GRUTA 21,278.57 S/4,019.27 S/5,910.70 S/6,147.14 S/5,201.44
02.14.13.01 TRAZO, NIVELES Y REPLANTEO M2 11.60 S/2.19 S/3.22 S/3.35 S/2.84
02.14.13.02 EXCAVACION MANUAL DE ZANJAS P/CIMIENTOS, ZAPATAS PARA GRUTA M3 170.02 S/32.11 S/47.23 S/49.12 S/41.56
02.14.13.03 COLOCACION, COMPACTACION Y NIVELACION DE CAPA DE HORMIGON PARA GRUTA (CON EQUIPO M2 7.86 S/1.48 S/2.18 S/2.27 S/1.92
02.14.13.04 SOLADO PROP. 1:8, e=0.10m PARA GRUTA M2 194.26 S/36.69 S/53.96 S/56.12 S/47.49
02.14.13.05 CONCRETO F'C=210 KG/CM2 - PARA ZAPATAS DE GRUTA M3 666.48 S/125.89 S/185.13 S/192.54 S/162.92
02.14.13.06 CONCRETO F'C=210 KG/CM2 PARA GRUTA M3 3,881.63 S/733.20 S/1,078.23 S/1,121.36 S/948.84
02.14.13.07 ACERO CORRUGADO FY=4200 KG/CM2 GRADO 60 PARA GRUTA KG 1,783.67 S/336.92 S/495.46 S/515.28 S/436.01
02.14.13.08 ENCOFRADO Y DESENCOFRADO PARA GRUTA M2 6,671.32 S/1,260.14 S/1,853.14 S/1,927.27 S/1,630.77
02.14.13.09 TARRAJEO EN MUROS INTERIORES Y EXTERIORES PROP. 1:4, e=1.5cm CON CEMENTO TIPO MS M2 92.35 S/17.44 S/25.65 S/26.68 S/22.57
02.14.13.10 TARRAJEO EN COLUMNAS Y PLACAS PROP. 1:4, e=1.5cm CEMENTO TIPO MS M2 2,838.09 S/536.08 S/788.36 S/819.89 S/693.76
02.14.13.11 ENCHAPADO DE PORCELANATO LISO COLOR NEGRO DE 0.60x0.60 EN MESAS DE CONCRETO M2 4,961.29 S/937.13 S/1,378.14 S/1,433.26 S/1,212.76
03 SANITARIAS 131,133.08 S/71,571.93 S/59,561.25
03.01 TRABAJOS PRELIMINARES 1,427.65 S/1,427.65
03.01.01 TRAZO DE NIVELES Y REPLANTEO DE RED DE AGUA Y ALCANTARILLADO ML 1,427.65 S/1,427.65
03.02 MOVIMIENTO DE TIERRAS 4,592.33 S/4,592.33
03.02.01 EXCAVACION MANUAL DE ZANJAS PARA RED PRINCIPAL DE AGUA FRIA Y ALCANTARILLADO M3 1,682.77 S/1,682.77
03.02.02 ACARREO DE MATERIAL EXCEDENTE M3 981.62 S/981.62
03.02.03 ELIMINACION DE MATERIAL EXCEDENTE A 2.00 KM DE DISTANCIA DE LA OBRA M3 659.27 S/659.27
03.02.04 SUMINISTRO Y COLOCACION DE CAMA DE ARENA FINA PARA RED PRINCIPAL DE ALCANTARILLADO M3 507.35 S/507.35
03.02.05 SUMINISTRO Y COLOCACION DE CAPA DE ARENA FINA PARA RED PRINCIPAL DE ALCANTARILLADO M3 761.32 S/761.32
03.03 INSTALACIONES DE AGUA FRIA 9,791.98 S/2,282.36 S/7,509.72
03.03.01 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP Ø 1/2" PTO 2,007.84 S/1,003.92 S/1,003.92
03.03.02 RED DE DISTRIBUCION TUBERIA DE Ø 3/4" PVC-SAP ML 636.52 S/318.26 S/318.26
03.03.03 RED DE DISTRIBUCION TUBERIA DE Ø 1/2" PVC SAP ML 346.45 S/173.23 S/173.23
03.03.04 RED DE DISTRIBUCION TUBERIA DE Ø 1" PVC-SAP ML 167.03 S/83.52 S/83.52
03.03.05 RED DE DISTRIBUCION TUBERIA DE Ø 1 1/2" PVC SAP ML 1,250.07 S/208.35 S/1,041.73
03.03.06 SUMINISTRO Y COLOCACION DE CODO 90° PVC SAP Ø 1/2" UND 946.86 S/118.36 S/828.50
03.03.07 SUMINISTRO Y COLOCACION DE CODO 90° PVC SAP Ø 3/4" UND 333.45 S/41.68 S/291.77
03.03.08 SUMINISTRO Y COLOCACION DE CODO 90° PVC SAP Ø 1" UND 8.86 S/1.11 S/7.75
03.03.09 SUMINISTRO Y COLOCACION DE CODO 90° PVC SAP Ø 1 1/2" UND 149.38 S/18.67 S/130.71
03.03.10 SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP Ø 3/4 A 1/2" UND 838.12 S/104.77 S/733.36
03.03.11 SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP 1 1/2" A 1/2" UND 19.56 S/2.45 S/17.12
03.03.12 SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP Ø 1" A 3/4" UND 21.36 S/2.67 S/18.69
03.03.13 SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP 1 1/2" a 3/4" UND 58.68 S/7.34 S/51.35
03.03.14 SUMINISTRO Y COLOCACION DE REDUCCION PVC SAP 1 1/2" A 1" UND 19.56 S/2.45 S/17.12
03.03.15 SUMINISTRO Y COLOCACION DE TEE PVC SAP Ø 1/2" UND 14.56 S/1.82 S/12.74
03.03.16 SUMINISTRO E INSTALACION DE TEE PVC SAP Ø 3/4" UND 315.02 S/39.38 S/275.64
03.03.17 SUMINISTRO Y COLOCACION DE TEE DE PVC SAP Ø 1" UND 10.24 S/1.28 S/8.96
03.03.18 SUMINISTRO Y COLOCACION DE TEE DE PVC SAP Ø 1 1/2" UND 85.20 S/10.65 S/74.55
03.03.19 SUMINISTRO E INSTALACION DE VALVULA COMPUERTA DE Ø 1/2" UND 105.24 S/13.16 S/92.09
03.03.20 SUMINISTRO E INSTALACION DE VALVULA COMPUERTA DE Ø 3/4" UND 531.85 S/66.48 S/465.37
03.03.21 SUMINISTRO E INSTALACION DE UNION UNIVERSAL DE Ø 1/2" UND 72.04 S/9.01 S/63.04
03.03.22 SUMINISTRO E INSTALACION DE UNION UNIVERSAL DE Ø 3/4" UND 210.70 S/26.34 S/184.36
03.03.23 SUMINISTRO E INSTALACION DE ABRAZADERA Ø 1 1/2" UND 141.93 S/17.74 S/124.19
03.03.24 SUMINISTRO E INSTALACION DE ABRAZADERA Ø 2" UND 77.72 S/9.72 S/68.01
03.03.25 REHABILITACION PARA LA OPERATIVIDAD DE ALMACENAMIENTO DE AGUA EN CISTERNA Y TANQUE DE A 1,423.74 S/1,423.74
03.03.25.01 SUMINISTRO E INSTALACION DE TAPON CEBADO PVC Ø 1 1/2" UND 10.71 S/10.71
03.03.25.02 SUMINISTRO E INSTALACION DE UNIÓN UNIVERSAL DE PVC DE 1 1/2" UND 64.59 S/64.59
03.03.25.03 SUMINISTRO E INSTALACION DE UNIÓN UNIVERSAL DE PVC DE 2" UND 28.20 S/28.20
03.03.25.04 SUMINISTRO E INSTALACION DE VALVULA CHECK DE BRONCE DE 1 1/2" UND 78.01 S/78.01
03.03.25.05 SUMINISTRO E INSTALACIÓN DE VÁLVULA DE PIE C/CANASTILLA DE Ø 2" UND 84.75 S/84.75
03.03.25.06 SUMINISTRO E INSTALACION DE VALVULA COMPUERTA Ø 1 1/2" UND 143.38 S/143.38

Página 6
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
03.03.25.07 SUMINISTRO E INSTALACION DE NIPLES DE 4" x 1 1/2" UND 64.70 S/64.70
03.03.25.08 SUMINISTRO E INSTALACION DE NIPLES DE 4" x 1 1/2" UND 28.68 S/28.68
03.03.25.09 SUMINISTRO E INSTALACION DE REDUCCION DE 2" A 1 1/4" UND 11.78 S/11.78
03.03.25.10 SUMINISTRO E INSTALACION DE TAPA METALICA 0.90 x 0.90m, PARA CISTERNA SEGUN DISEÑO, UND 152.80 S/152.80
03.03.25.11 SUMINISTRO E INSTALACION DE TAPA METALICA 0.60 x 0.60m, PARA TANQUE ELEVADO SEGUN UND 110.42 S/110.42

Página 7
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
03.03.25.12 SUMINISTRO Y COLOCACION DE ESCALERA DE TUBO DE F°G° Ø 1 1/2" Y PELDAÑOS DE TUBO DE F° UND 645.72 S/645.72
03.04 INSTALACIONES DE DESAGUE 19,367.99 S/969.55 S/18,398.44
03.04.01 SALIDAS DE VENTILACION DE Ø 2" PTO 471.96 S/94.39 S/377.57
03.04.02 SALIDAS PARA TUBO DE PVC SAP Ø 2" PTO 2,079.00 S/415.80 S/1,663.20
03.04.03 SALIDAS PARA TUBO DE PVC SAP Ø 4" PTO 2,296.80 S/459.36 S/1,837.44
03.04.04 RED DE DISTRIBUCION PVC SAP PARA DESAGUE DE Ø 4" ML 925.33 S/925.33
03.04.05 RED DE DISTRIBUCION PVC SAP PARA DESAGUE DE Ø 2" ML 1,344.49 S/1,344.49
03.04.06 RED DE DISTRIBUCION PVC SAP PARA TUBERIA DE DESAGUE DE Ø 6" PARA EXTERIOR ML 4,660.97 S/4,660.97
03.04.07 SUMINISTRO E INSTALACIÓN DE CODO 45° PVC SAP Ø 2" UND 156.80 S/156.80
03.04.08 SUMINISTRO E INSTALACION DE CODO 45º PVC SAP Ø 4" UND 297.22 S/297.22
03.04.09 SUMINISTRO E INSTALACIÓN DE YEE PVC SAP Ø 4" x 4" UND 340.17 S/340.17
03.04.10 SUMINISTRO E INSTALACIÓN DE YEE PVC SAP Ø 2" x 2" UND 282.17 S/282.17
03.04.11 SUMINISTRO E INSTALACIÓN DE YEE PVC SAP Ø 4" A 2" UND 334.62 S/334.62
03.04.12 SUMINISTRO E INSTALACION DE TEE PVC SAP Ø 4" UND 332.42 S/332.42
03.04.13 SUMINISTRO E INSTALACION DE TEE PVC SAP Ø 2" UND 59.00 S/59.00
03.04.14 SUMINISTRO E INSTALACION DE CODO 90° PVC SAP Ø DE 4" UND 140.53 S/140.53
03.04.15 SUMINISTRO E INSTALACION DE CODO 90° PVC SAP Ø DE 2" UND 736.03 S/736.03
03.04.16 SUMINISTRO E INSTALACION DE CODO VENTILACION 90° PVC SAP DIAMETRO Ø DE 4" A 2" UND 162.50 S/162.50
03.04.17 SUMINISTRO E INSTALACION DE TAPAS DE REGISTRO ROSCADO DE BRONCE DE Ø 4" UND 473.58 S/473.58
03.04.18 SUMINISTRO E INSTALACION DE TAPAS DE REGISTRO ROSCADO DE BRONCE DE Ø 2" UND 44.65 S/44.65
03.04.19 SUMINISTRO E INSTALACION DE SUMIDERO CROMADO REJILLA DE BRONCE DE Ø 2" UND 234.54 S/234.54
03.04.20 SUMINISTRO E INSTALACIÓN DE SOMBRERO VENTILACION PVC DE Ø 2" UND 224.16 S/224.16
03.04.21 SUMINISTRO E INSTALACION DE TRAMPA "P" PARA SUMIDERO PVC DE Ø 2" UND 157.78 S/157.78
03.04.22 SUMINISTRO E INSTALACION DE CAJA DE REGISTRO 30" x 60" INCLUYE MARCO Y TAPA UND 3,496.20 S/3,496.20
03.04.23 SUMINISTRO E INSTALACION DE TRAMPA PARA LAVADERO Ø 2" UND 90.16 S/90.16
03.04.24 SUMINISTRO E INSTALACION DE REDUCCION PVC SAP DE 4" A 2" UND 26.91 S/26.91
03.05 APARATOS SANITARIOS Y ACCESORIOS 25,531.28 S/25,531.28
03.05.01 SUMINISTRO E INSTALACION DE INODORO MODELO ONE PIECE TANQUE BAJO DE LOSA COLOR B UND 6,238.26 S/6,238.26
03.05.02 SUMINISTRO E INSTALACION DE INODORO TIPO BABY INCLUYE ACCESORIOS UND 1,051.80 S/1,051.80
03.05.03 SUMINISTRO E INSTALACION DE OVALIN LOSA BLANCA CON ACCESORIOS UND 4,057.24 S/4,057.24
03.05.04 SUMINISTRO E INSTALACION DE URINARIO SECO INCLUYE ACCESORIOS UND 6,789.30 S/6,789.30
03.05.05 SUMINISTRO E INSTALACION DE DISPENSADOR PLASTICO PARA PAPEL HIGIENICO UND 1,262.72 S/1,262.72
03.05.06 SUMINISTRO E INSTALACIÓN DE LLAVE CROMADA PUSH DE 1/2" P/LAVATORIOS INCLUYE ACCESORI UND 4,081.00 S/4,081.00
03.05.07 SUMINISTRO E INSTALACION DE LLAVE TIPO CUELLO GANSO CROMADA P/LAVADERO 1/2" UND 254.68 S/254.68
03.05.08 SUMINISTRO E INSTALACION DE LLAVE PARA JARDIN Ø 1/2" UND 166.08 S/166.08
03.05.09 SUMINISTRO E INSTALACION DE PAPELERA DE ACERO INOXIDABLE UND 1,630.20 S/1,630.20
03.06 OTROS 5,909.50 S/5,909.50
03.06.01 PRUEBA HIDRAULICA Y DESINFECCION P/TUBERIA DE AGUA POTABLE ML 2,153.83 S/2,153.83
03.06.02 PRUEBA HIDRAULICA DE REDES DE ALCANTARILLADO ML 3,755.67 S/3,755.67
03.07 DRENAJE PLUVIAL 62,300.04 S/62,300.04
03.07.01 OBRAS PRELIMINARES 62,300.04 S/62,300.04
03.07.01.01 EXCAVACION MANUAL DE RED PLUVIAL - CUNETAS M3 2,792.51 S/2,792.51
03.07.01.02 ACARREO MANUAL DE MATERIAL EXCEDENTE M3 1,628.97 S/1,628.97
03.07.01.03 ELIMINACION DE MATERIAL EXCEDENTE A 2.00 KM DE DISTANCIA DE LA OBRA M3 1,094.02 S/1,094.02
03.07.01.04 CUNETA DE EVACUACION PLUVIAL, CONCRETO F'C= 175 KG/CM2 - CEMENTO TIPO V M3 15,428.34 S/15,428.34
03.07.01.05 CUNETA DE EVACUACION PLUVIAL, ENCFRADO Y DESENCOFRADO M2 8,966.08 S/8,966.08
03.07.01.06 SUMINISTRO Y COLOCACION DE CAPA DE HORMIGON PARA CUNETA, e=0.10m M3 1,528.78 S/1,528.78
03.07.01.07 TARRAJEO DE CUNETA, PROP. 1:4 M2 5,259.83 S/5,259.83
03.07.01.08 SUMINISTRO Y COLOCACION DE JUNTAS ASFALTICA e=1" ML 663.98 S/663.98
03.07.01.09 SUMINISTRO Y COLOCACION DE REJILLA METALICA CON ANGULO DE 1 1/2" x 1 1/2" x 3/16" Y PLATIN ML 24,937.53 S/24,937.53
03.08 VARIOS 2,212.31 S/2,212.31
03.08.01 PINTURA ESMALTE SINTETICO PARA TANQUE ELEVADO Y CISTERNA M2 1,819.00 S/1,819.00
03.08.02 SUMINISTRO E INSTALACION DE CERRADURA DE 02 GOLPES UND 70.26 S/70.26
03.08.03 PICADO Y REPOSICION EN PISO EXISTENTE PARA INSTALACION DE TUBERIA DE LABORATORIO A R ML 259.56 S/259.56
03.08.04 SUMINISTRO E INSTALACION DE VALVULA DE CONTROL 1" CON BOYA FLOTADORA UND 63.49 S/63.49
04 INSTALACIONES ELECTRICAS INTERIORES Y EXTERIORES 289,995.63 S/29,209.51 S/61,386.89 S/111,012.80 S/88,386.45
04.01 TABLEROS ELECTRICOS 33,347.77 S/19,648.71 S/13,699.06
04.01.01 SUMINISTRO Y COLOCACION DE TABLERO GENERAL (TG) CJT 3,908.96 S/2,658.09 S/1,250.87
04.01.02 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION STG-1 CJT 2,036.53 S/1,384.84 S/651.69
04.01.03 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION STG-2 CJT 1,761.34 S/1,197.71 S/563.63
04.01.04 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION STG-3 CJT 1,922.36 S/1,307.20 S/615.16

Página 8
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
04.01.05 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 1.1 CJT 1,521.10 S/1,034.35 S/486.75
04.01.06 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 2.1 CJT 1,411.78 S/960.01 S/451.77
04.01.07 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 3.1 CJT 1,201.41 S/816.96 S/384.45
04.01.08 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 1.2 CJT 1,310.73 S/891.30 S/419.43
04.01.09 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 2.2 CJT 1,310.73 S/891.30 S/419.43
04.01.10 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 3.2 CJT 1,171.75 S/796.79 S/374.96
04.01.11 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 3.3 CJT 1,142.09 S/776.62 S/365.47
04.01.12 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 4.2 CJT 1,201.41 S/816.96 S/384.45
04.01.13 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 5.2 CJT 1,201.41 S/816.96 S/384.45
04.01.14 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 6.2 CJT 842.93 S/573.19 S/269.74
04.01.15 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 1.3 CJT 1,142.09 S/776.62 S/365.47
04.01.16 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION TD 2.3 CJT 1,171.75 S/796.79 S/374.96
04.01.17 SUMINISTRO Y COLOCACION DE TABLERO DE DISTRIBUCION T.P.S CJT 779.37 S/529.97 S/249.40
04.01.18 SUMINISTRO Y COLOCACION DE TABLERO DISTRIBUCION TC - AIP CJT 1,194.65 S/812.36 S/382.29
04.01.19 SUMINISTRO Y COLOCACION DE TABLERO TD-1 CJT 1,435.24 S/975.96 S/459.28
04.01.20 SUMINISTRO Y COLOCACION DE TABLERO TEB CJT 1,227.54 S/834.73 S/392.81
04.01.21 SUMINISTRO Y COLOCACION DE BUZON CONCRETO CJT 400.82 S/400.82
04.01.22 SUMINISTRO Y COLOCACION DE CAJAS BORNERAS CJT 2,448.50 S/2,448.50
04.01.23 SUMINISTRO Y COLOCACION DE CAJA DE PASE HERMETICO UND 1,603.28 S/1,603.28
04.02 CONDUCTORES, ALIMENTADORES 38,731.46 S/38,731.46
04.02.01 SUMINISTRO, EXCAVACION Y TENDIDO DE CABLE N2XOH DE 3-1x35 + 1x35mm2 DESDE MEDIDOR A ( ML 4,314.19 S/4,314.19
04.02.02 SUMINISTRO, EXCAVACION Y TENDIDO DE CABLE N2XOH DE 3-1x16 + 1x16mm2 ML 16,996.68 S/16,996.68
04.02.03 SUMINISTRO, EXCAVACION Y TENDIDO DE CABLE N2XOH 3-1x10 + 1x10mm2 ML 9,434.15 S/9,434.15
04.02.04 SUMINISTRO, EXCAVACION Y TENDIDO DE CABLE N2XOH 2-1x10 ML 5,718.70 S/5,718.70
04.02.05 SUMINISTRO, EXCAVACION Y TENDIDO DE CABLE NH 2-1x6mm2 ML 2,267.74 S/2,267.74
04.03 INSTALACION DE INTERIORES 103,041.07 S/7,728.09 S/66,976.70 S/28,336.31
04.03.01 SALIDA DE CENTRO DE LUZ PARA UN PUNTO PTO 1,661.00 S/124.58 S/1,079.65 S/456.78
04.03.02 SALIDA DE CENTRO DE LUZ PARA DOS PUNTOS PTO 3,032.40 S/227.43 S/1,971.06 S/833.91
04.03.03 SALIDA DE CENTRO DE LUZ PARA TRES PUNTOS PTO 2,166.00 S/162.45 S/1,407.90 S/595.65
04.03.04 SALIDA DE CENTRO DE LUZ PARA CUATRO PUNTOS PTO 10,424.25 S/781.82 S/6,775.76 S/2,866.67
04.03.05 SUM. E INST. DE EQUIPO LUMINARIA TIPO PANEL LED 40W, ADOSADA AL TECHO UND 27,730.17 S/2,079.76 S/18,024.61 S/7,625.80
04.03.06 SUM. E INST. DE EQUIPO LUMINARIA CIRCULAR LED DE 18W UND 9,749.84 S/731.24 S/6,337.40 S/2,681.21
04.03.07 SALIDA PARA PUNTO DE VENTILADORES DE TECHO PTO 13,211.32 S/990.85 S/8,587.36 S/3,633.11
04.03.08 SUMINISTRO E INSTALACIÓN DE VENTILADORES DE TECHO PTO 25,218.64 S/1,891.40 S/16,392.12 S/6,935.13
04.03.09 SALIDA DE CENTRO DE TOMACORRIENTE h=0.40m PTO 9,847.45 S/738.56 S/6,400.84 S/2,708.05
04.04 ILUMINACION PATIO EXTERIOR 22,870.92 S/22,870.92
04.04.01 SUMNISTRO Y MONTAJE DE POZO DE PUESTA A TIERRA, INCL. EXCAVACION CJT 9,963.00 S/9,963.00
04.04.02 SUMINISTRO Y MONTAJE DE ARTEFACTO BRAQUETE LED PARED EXTERIOR UND 1,062.48 S/1,062.48
04.04.03 SUMINISTRO E INSTALACION DE REFLECTORES LED DE 100 WATTS INCORPORADO UND 11,845.44 S/11,845.44
04.05 SISTEMA DE ILUMINACION CON PANEL SOLAR 8,768.16 S/8,768.16
04.05.01 SISTEMA DE PANEL SOLAR, INCL. PANEL BATERIA, CONTROLADOR, CABLEADO CJT 6,733.08 S/6,733.08
04.05.02 PASTORAL DE TUBO DE Fº Gº de 2" INCL. DOBLE ABRAZADERA, INCL. 01 SALIDAS DE LUMINARIAS UND 230.00 S/230.00
04.05.03 CABLE NLT DE 2x4 mm2 ML 32.80 S/32.80
04.05.04 CONECTOR TIPO CUÑA DE 06/2.5mm2 UND 46.40 S/46.40
04.05.05 ARTEFACTO LED DE 50W UND 509.84 S/509.84
04.05.06 TUBO FºGº DE Ø 4" x 5m UND 1,216.04 S/1,216.04
04.06 OTROS 7,015.14 S/7,015.14
04.06.01 SUMINISTRO Y MONTAJE DE ELECTROBOMBA Y ACCESORIOS GLB 4,762.94 S/4,762.94
04.06.02 SUMINISTRO Y MONTAJE DE ALTAVOZ EXTERIOR PATIO UND 1,883.69 S/1,883.69
04.06.03 SUMINISTRO Y MONTAJE DE TIMBRE UND 368.51 S/368.51
04.07 SISTEMA FOTOVOLTAICO PARA CAMPO DEPORTIVO 32,835.76 S/4,104.47 S/28,731.29
04.07.01 SISTEMA DE PANEL SOLAR, INCL. PANEL BATERIA, CONTROLADOR, CABLEADO CJT 29,960.15 S/3,745.02 S/26,215.13
04.07.02 SOPORTE DE PANELES SOLARES CJT 2,875.61 S/359.45 S/2,516.16
04.08 SUMINISTRO Y PRUEBAS DE RED ELECTRICA 639.19 S/155.23 S/228.28 S/237.41 S/18.26
04.08.01 PRUEBAS DE RED ELECTRICAS CJT 639.19 S/155.23 S/228.28 S/237.41 S/18.26
04.09 SUMINISTRO E INSTALACION DE REDES DATA 31,220.59 S/31,220.59
04.09.01 SUMINISTRO Y MONTAJE DE ACCESORIOS PARA SISTEMA DE DATA INTERNET (INCLUYE CONTRATO) CJT 12,992.06 S/12,992.06
04.09.02 SUMINISTRO E INSTALACION DE EQUIPO DE AIRE ACONDICIONADO DE 36000 BTU, INC. CONDENS CJT 18,228.53 S/18,228.53
04.10 TRANSPORTE DE MATERIALES 2,000.00 S/485.71 S/714.29 S/742.86 S/57.14
04.10.01 TRANSPORTE DE MATERIALES, EXPED. REPLANTEO GLB 2,000.00 S/485.71 S/714.29 S/742.86 S/57.14
04.11 SEGURIDAD EN OBRA 800.00 S/194.29 S/285.71 S/297.14 S/22.86

Página 9
CRONOGRAMA VALORIZADO DE OBRA
OBRA "REHABILITACION DE LA INFRAESTRUCTURA DE LA I.E. N° 031 VIRGEN DEL CARMEN - DISTRITO LA CRUZ - TUMBES - TUMBES
ENTIDAD GOBIERNO REGIONAL DE TUMBES Tiempo Ejecución 180 dias - Calendario
LUGAR TUMBES - TUMBES - CRUZ Costo a mes de SETIEMBRE 2019
Item Descripción Und. PRESUPUES. Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
04.11.01 SEGURIDAD Y SALUD EN EL TRABAJO GLB 800.00 S/194.29 S/285.71 S/297.14 S/22.86
04.12 INSTALACION ELECTRICAS PRELIMINARES 8,725.57 S/8,725.57
04.12.01 INSTALACION ES ELECTRIICAS EN AULAS PROVISIONALES CJT 7,888.79 S/7,888.79
04.12.02 RETIRO DE POSTE EXISTENTE EN DESUSO CJT 464.54 S/464.54
04.12.03 DEMOLICION DE PISO CONCRETO PARA PASE CONDUCTORES CJT 372.24 S/372.24
05 MOBILIARIO Y EQUIPAMIENTO 181,207.03 S/181,207.03
05.01 MOBILIARIO EDUCATIVO 119,508.94 S/119,508.94
05.01.01 MODULO MOBILIARIO PARA ALUMNO (MESA) UND 35,250.00 S/35,250.00
05.01.02 MODULO MOBILIARIO PARA ALUMNO (SILLA) UND 27,025.00 S/27,025.00
05.01.03 SILLA DE MADERA PARA DOCENTE UND 960.00 S/960.00
05.01.04 ESCRITORIO DE MADERA PARA DOCENTE UND 7,150.00 S/7,150.00
05.01.05 ESTANTE UND 9,100.00 S/9,100.00
05.01.06 PIZARRA ACRILICA DE 1.40 x 3.00m (ALTO x ANCHO) UND 6,730.46 S/6,730.46
05.01.07 SILLAS APILABLES METALICAS UND 5,288.40 S/5,288.40
05.01.08 MESA DE MADERA UND 9,750.00 S/9,750.00
05.01.09 SILLA DE MADERA UND 7,150.00 S/7,150.00
05.01.10 SILLA GIRATORIAS UND 203.38 S/203.38
05.01.11 ESTANTE PARA LIBROS UND 2,600.00 S/2,600.00
05.01.12 MESA PARA COMPUTO UND 6,101.70 S/6,101.70
05.01.13 SILLON PARA DIRECTOR UND 2,200.00 S/2,200.00
05.02 EQUIPAMIENTO EDUCATIVO 61,698.09 S/61,698.09
05.02.01 IMPRSSORA MULTIFUNCIONAL CON SISTEMA DE TINTA CONTINUA UND 5,394.00 S/5,394.00
05.02.02 LAPTOP I7 UND 16,129.84 S/16,129.84
05.02.03 MONITOR DE 19.5" + TECLADO + CPU UND 2,966.10 S/2,966.10
05.02.04 MICROSCOPIO UND 8,000.00 S/8,000.00
05.02.05 REFRIGERADORA UND 1,525.42 S/1,525.42
05.02.06 PROYECTOR MULTIMEDIA UND 8,930.00 S/8,930.00
05.02.07 RACK PARA TECHO PROYECTOR MULTIMEDIA UND 1,728.73 S/1,728.73
05.02.08 ECRAN UND 320.00 S/320.00
05.02.09 LIBROS - CENTRO DE RECURSOS EDUCATIVOS 16,704.00 S/16,704.00
05.02.09.01 LIBRO DE MATEMATICAS DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.02 LIBRO DE COMUNICACIONES DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.03 LIBROS DE CIENCIAS DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.04 LIBROS DE HISTORIA DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.05 LIBROS DE TECNOLOGIA DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.06 LIBROS DE RELIGION DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.07 LIBROS DE BIOLOGIA DIFERENTES AUTORES UND 1,788.00 S/1,788.00
05.02.09.08 LIBROS DE PERSONA, FAMILIA Y RELACIONES HUMANAS DIFERENTES AUTORES UND 528.00 S/528.00
05.02.09.09 LIBROS DE QUIMICA DIFERENTES AUTORES UND 1,788.00 S/1,788.00
05.02.09.10 LIBROS DE ARTE Y MANUALIDADES DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.11 DICCIONARIO UND 420.00 S/420.00
05.02.09.12 DICCIONARIO BILINGUES UND 600.00 S/600.00
05.02.09.13 DICCCIONARIOS SINONIMOS Y ANTONIMOS UND 300.00 S/300.00
05.02.09.14 REVISTAS VARIAS UND 240.00 S/240.00
05.02.09.15 HISTORIETAS VARIAS UND 240.00 S/240.00
05.02.09.16 LIBROS DE OBRAS LITERARIAS DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.17 LIBROS DE CULTURA GENERAL DIFERENTES AUTORES UND 1,080.00 S/1,080.00
05.02.09.18 LIBROS DE NUTRICION DIFERENTES AUTORES UND 1,080.00 S/1,080.00
COSTO DIRECTO 6,154,537.01 S/. 1,043,501.04 S/. 706,425.06 S/. 773,468.02 S/. 831,831.35 S/. 251,952.01 S/. 482,139.95 S/. 637,240.87 S/. 1,427,978.71 S/.
GASTOS GENERALES (10%) 615,453.70 S/. 104,350.10 S/. 70,642.51 S/. 77,346.80 S/. 83,183.14 S/. 25,195.20 S/. 48,214.00 S/. 63,724.09 S/. 142,797.86 S/.
UTILIDAD (10%) 615,453.70 S/. 104,350.10 S/. 70,642.51 S/. 77,346.80 S/. 83,183.14 S/. 25,195.20 S/. 48,214.00 S/. 63,724.09 S/. 142,797.87 S/.

SUB TOTAL 7,385,444.41 S/. 1,252,201.24 S/. 847,710.08 S/. 928,161.62 S/. 998,197.63 S/. 302,342.41 S/. 578,567.95 S/. 764,689.05 S/. 1,713,574.43 S/.
IGV (18%) 1,329,379.99 S/. 225,396.22 S/. 152,587.81 S/. 167,069.09 S/. 179,675.57 S/. 54,421.63 S/. 104,142.23 S/. 137,644.03 S/. 308,443.41 S/.

TOTAL DE PRESUPUESTO 8,714,824.40 S/. 1,477,597.46 S/. 1,000,297.89 S/. 1,095,230.71 S/. 1,177,873.20 S/. 356,764.04 S/. 682,710.18 S/. 902,333.08 S/. 2,022,017.84 S/.
AVANCE EN % 100% 17% 11% 13% 14% 4% 8% 10% 23%
% ACOMULADO 100% 17% 28% 41% 55% 59% 66% 77% 100%