Вы находитесь на странице: 1из 4

56 MANAGEMENT DECISION 33,8

Risk and capital budgeting:


avoiding the pitfalls in using NPV when risk arises
David Brookfield
Attempts to provide an “adjusted” NPV technique as experienced in a live environment

Introduction To illustrate this point consider the following example:


The recognition of risk as an important component in
capital budget decision making has long been recognized. A company is considering investing £1,800 to enhance a
The future is uncertain and investment/project appraisal new production process that will provide reductions in
techniques that fail to recognize this fact will almost costs for the foreseeable future. However, the extent of cost
certainly lead to incorrect conclusions and erroneous reduction is dependent on the level of throughput which, in
turn, is dependent on future sales. The marketing manager
recommendations. In a recent paper[1] it was shown how
has suggested two likely scenarios which would give rise
simulation methods will help to identify the possible risks
to the following cost reductions which would arise at each
of project failure when using net present value (NPV). anniversary of the initial investment:
What is often not recognized is that NPV, itself, can lead to
erroneous conclusions in the face of uncertainty even when Scenario I: £300 p.a.
the apparent range or distribution of (uncertain) outcomes
has been recognized. What is needed is an “adjusted” NPV Scenario II: £100 p.a.
technique which properly accounts for uncertainty, as
experienced in a live environment which this article will Further information suggests that there is an equal chance
attempt to provide. Moreover, recognition of the “correct” of either scenario arising and that once the first saving is
NPV approach leads to some surprising, perhaps counter- made that this level of saving will continue for the
foreseeable future.
intuitive, results in which apparently unwelcome guests in
capital budgeting may turn out to be factors leading to
At a discount rate of 10 per cent is this a worthwhile
competitive or strategic advantage. investment? The standard expected NPV approach would
suggest the following solution:

Waiting for an answer Scenario I: 0.5 × (300/0.01) = £1,500


Recent developments in the real options literature (see Scenario II: 0.5× (100/0.1) = £500.
Dixit and Pindyck[2] for an up-to-date survey and
exposition) have suggested a use for financial options Additionally with an initial investment of £1,800 there is a
pricing theory in the wider context of investment decision positive NPV of £200. However, not all of the costs
making. In particular, if the investment decision is seen in have been incorporated into the analysis and hence a
the usual context of maximizing shareholder wealth and is recommendation to go ahead with the project might be
evaluated in terms of NPV calculations, it can be shown wrong. The ignored cost is the value of the option to wait
that the use of real option techniques enhances the which is “embedded” in the above analysis.
standard NPV methodology in situations where there is an
unreconciled dichotomy between ex ante and ex post To understand this, suppose the company waits for one
information availability. That is, when a significant degree year to see if the level of sales will rise. Based on the
of uncertainty in outcomes for the investment project, criterion that the company will only invest if the level of
such that the passage of time might contribute savings reaches £300 p.a. the expected PV of the costs now
significantly to the resolution of uncertainty. In other becomes (noting that the “present” is now one year later):
words, when the waiting game might produce substantial
benefits. Scenario I: 300/0.01 = £3,000.

Thus the NPV becomes 3,000 – 1,800 = £1,200, which is a


Management Decision, Vol. 33 No. 8, 1995, pp. 56-59 © MCB University Press £1,000/1.1 = £909 improvement on the previous NPV. This
Limited, 0025-1747 represents the value of the embedded option to wait.
RISK AND CAPITAL BUDGETING: AVOIDING THE PITFALLS IN USING NPV WHEN RISK ARISES 57

Some comments on the applicability of the approach may The formalization of the treatment of risk in investment
be made: first, while it may seem obvious that we should analysis is one of the principal benefits of the real option
not use the averaging process implied in taking expected technique. In particular, formalization involves a
values when only two one-off outcomes are likely to arise, recognition of the structure of probable outcomes over
the real value of this approach is to extend the analysis time which can be exploited for strategic investment
over many outcomes which might be repeatable; in other purposes. The probability distribution of NPV, which
words, where the expected value approach is truly valid. incorporates the valuation of flexibility, is not
Nothing changes in such a situation: embedded options symmetrically distributed as in the certainty-equivalent
can still arise. This example is highly simplified to NPV case. Consequently, the use of simple risk-adjusted
demonstrate a point. Second, ignoring the embedded rates to assess investments in which there is flexibility will
option as in the standard NPV approach ignores an undervalue investments. The asymmetry arises because
opportunity cost of waiting to invest. We avoid this cost by certainty-equivalent NPV rules ignore flexibility which
waiting to invest, which gives rise to a positive real option provides protection against future events turning out
value. Finally, if the company has to invest immediately differently from expected at the outset. This is important
there is no choice and hence there can be no option. In this in the certainty-equivalent NPV case, since certainty
case, the standard NPV approach will provide a solution equivalence often presumes an irrevocable commitment to
on which recommendations may be made. Real options an investment strategy at the outset. However, because
arise when there is an element of flexibility. investors have flexibility over subsequent strategies, the
actual risk of losses from investing are lower than
One of the potential benefits of using real option methods assumed in a certainty-equivalent NPV environment.
has been the recognition that the use of standard NPV Future losses can be avoided by not investing, for example.
techniques can lead to very wrong conclusions in the Hence, real option analysis would argue that the
presence of unrecognized embedded options. The central probability distribution of the “true” NPV is skewed to the
role of NPV techniques in financial decision making right in favour of “profitability”, or positive NPVs. In fact,
therefore makes it imperative that real option structures in the skewed distribution would not be smooth and would
investing opportunities are identified and accounted for. It be truncated to the left of the mean to produce an absolute
turns out that real options can be found in most live floor to loss exposure.
environments where uncertainty/risk, waiting, investment
irreversibility, growth opportunity, asymmetric In a sense, the recognition of real options embedded in a
information, staged investments, competitor response, financial decision alters the distribution of outcomes that
scale economies, project switching, suspension, face budget holders. This is why simulation games which
abandonment and start-up are important. In fact, we can try to emulate normally distributed outcomes do not
include just about the full spectrum of investment decision reflect the situation in a live environment. In fact, the
making, including those concerning capital budgeting. answers from such approaches are not even approximate,
The fact that standard NPV techniques do not recognize since nearly half of one side of a distribution can become
these situations – or, at least, cannot deal with them redundant.
adequately – is a measure of the caution managers must
exercise in using the technique in a real situation. In essence, therefore, real options provide a valuation of
investment opportunities over which final decisions have
yet to be made but which do not have to be made until the
appropriate time. Deciding on the appropriate time is an
extremely important question of strategy. Seen in these
Why real options correctly deal with risk in terms, the ubiquity of urgency seems less attractive. If a
capital budgeting manager can avoid making a substantial loss from
One of the first proponents of real option analysis was undertaking a project in which exit routes are non-existent
Myers[3], who identified that NPV incorrectly calculates (that is, the investment is “irreversible”), it seems sensible
the value of cash flows in an uncertain environment. His to wait if flexibility in timing is available. The real option
observations concerned the fact that NPV analysis ignores approach is one way this intuition can be formalized and
the time series interactions among contingent investments quantified.
and that, consequently, delaying investing may accrue
extra benefits. In this sense, real option analysis The value of waiting is a reflection of the costs associated
recognizes the incremental (or additional) value arising with an irreversible investment. That is, if there is an
from flexibility. The fact that flexibility gives rise to element of a sunk cost in an investment, then once the
additional value is a recognition of the altered probability investment has been made the sunk cost is incurred.
distribution of potential outcomes and its impact on risk However, waiting will always leave the investor with the
exposure. Underpinning this is the view that risk is critical power to make a decision about when to invest. Although
to investment, since without it the maximum return that this may appear self-evident, traditional NPV assessment
could reasonably be expected from an investment is the methods ignore this fact. If an investor is therefore making
risk-free rate. investment decisions on the basis of NPV, then it is almost
58 MANAGEMENT DECISION 33,8

certain that miscalculations will be made if embedded Moreover, deferring investments reweights investment
options are not recognized. In this context, the timing from the now-or-never NPV approach to one which
identification of real options helps to explain the value of recognizes the strategic benefits of waiting. Thus, while
flexibility by demonstrating that managers are not urgency is often a valued part of corporate culture, it may
miscalculating investment outcomes and are acting only mean that managers are losing money at a quicker
rationally, based on a “true” calculation of the NPV of the rate.
project.
The investment is exposed to risk
Investments need risk to offer a sufficient return to
Debunking some myths in capital budgeting shareholders beyond the risk-free rate. Real options have
Capital budgeting, expressed in terms of standard NPV greater value in the face of risk and the possibility of
techniques, leads to wrong conclusions and also leads to deferral because of the asymmetry of outcomes previously
wrong intuition concerning the investment environment. discussed.
Generally, when real options are an appropriate appraisal
technique, important points of principle may need re- The benefits of the real option approach can be seen in
evaluating. terms of the simulation experiments often undertaken to
evaluate risk. Usually, a range of values of NPV are
Algebraically, the true value of an investment is given by: calculated based on different scenarios which often
produce negative and positive outcomes. If managers can
Expanded NPV = Passive NPV + Real option value. choose to ignore the negative side of the distribution and
(The terminology is from Trigeorgis[4]). The fact that demonstrate that this is a logical thing to do, then the more
options have (mostly) positive values indicates that, variance there is in the distribution the greater is the
without consideration of the value of flexibility, traditional project’s exposure to upside potential (or positive risk).
(passive) NPV rejects too many opportunities. Even when
a real option environment is recognized, there are some If project timings and outcomes can be manipulated and
pitfalls to avoid. Perhaps the most recent and useful constructed (which is implied by flexibility) to take
extension of research has been in the compound option advantage of the risk potential, and there are financial
literature where a series of real option values emerge benefits from so doing, then it seems clear that managers
which recognize the contingent nature of investments. would want to undertake risky projects. Furthermore, the
However, it is important to realize that the addition of real riskiest of projects would be welcomed as long as they
option values in such a framework is inappropriate, unlike exhibited flexibility.
straightforward NPV additions, because of the
interactivity of option values. For instance, abandonment Interest rates are relatively high
of a project midstream rules out subsequent option values Normally fewer investments would be acceptable in such a
that would have arisen had the alternative been to situation because discount rates are also likely to be high.
continue with the project. Second order interactions may However, higher discount rates mean that the future
arise should a real option be exercised (i.e. when the project capital necessary to exercise a real option (undertaking a
is undertaken), as the scale of operations may be increased further contingent part of the project at some future date)
so that the values of other real options which are is lower in present-day terms. Thus, investments that have
dependent on capacity will be increased. Interactivity is future growth opportunities will be of particular value.
not an irrelevant side issue, since identifying the nature of
real option interaction and enumerating the consequences This observation is a consequence of the fact that, while
provides valuable information to management concerning some initial investment is nearly always necessary in
investment strategies. In sum, ignoring strategic or undertaking a project, financing a new project may be
operating flexibility leads to missed or badly judged done in stages. Staged investments offer the opportunity of
investment opportunities. expanding the number of exit routes while lowering the
present value of cash outflows.
Whether real option analysis is appropriate depends on a
few criteria. Typically, real options have value when the The impact of changing interest rates
following are important. As mentioned above, real options can arise in a variety of
situations, but their influence is not always obvious.
Investments can be deferred
The possibility of deferring an investment facilitates This point can be illustrated by an example involving
evaluation of future events when they arise and thus interest rates, as follows.
avoids costly errors (which might arise had the original
strategy been followed through). Consequently, even Suppose that the level of interest rates next period is
negative NPV investments may have worth in such a uncertain. While it is noted that discount rates are not the
scenario. same as interest rates, the interest rate terminology is used
RISK AND CAPITAL BUDGETING: AVOIDING THE PITFALLS IN USING NPV WHEN RISK ARISES 59

to highlight the fact that discount rates can change for The value of the embedded option is therefore £1,909 –
extraneous reasons. Assume current discount rates to be £1,836 = £73. If this is scaled up to reflect the quantities
10 per cent and that potential changes in interest rates likely to emerge in a live environment then considerations
mean that next period’s discount rate could change to of waiting become a financial imperative.
either 5 per cent or 15 per cent with equal probability.
Thus we observe opposing forces arising from changing
Adopting Scenario I cash flows from before as the only discount rates in that interest rate volatility enhances
possible cash flows, we have the following cost savings investment outcomes when discounted, but that the effect
from an initial investment of £1,800: encouraging investment might be outweighed by the
embedded option to wait. Care, therefore, needs to be
Scenario I: £300 p.a., in perpetuity. exercised in analysing the potential outcome of capital
The resulting NPV with discount rates at 10 per cent is budgeting proposals when discount rates are likely to
therefore £3,000 – £1,800 = £1,200. vary.

Considering only changes in interest rates we see that


discount rate volatility actually increases the present value Conclusion
of the cash inflows: The purpose of this article is to suggest that the
importance of the incorporation of risk or uncertainty into
(1/1.1) × [0.5 × (300/0.15) + 0.5 × (300/0.05)] = £3,636. investment decisions will not adequately be captured by
And the NPV = 3,636 – 1,800 = £1,836. simulation experiments which assume a now-or-never
investment strategy with the consequence that risk
The reason why this is surprising is that the expected exposure is assessed on the basis of a symmetric normal
value of next period’s discount rate is equal to this period’s distribution. This is because the value to waiting is not
discount rate at 10 per cent: evaluated in such calculations and that any investment
0.5 × 15 per cent + 0.5 × 5 per cent = 10 per cent. decisions based on such techniques might well be
seriously flawed. Technically, standard NPV techniques do
This simply recognizes the fact that discounted future not take into account the fact that the distribution of
cash flows are non-linearly related to discount rates and outcomes is truncated so as to leave investors exposed
that it is wrong to think in an “average” or “linear” way. only to upside potential.
Thus, we obtain the surprising result that interest rate
volatility favours investment. However, there is a second- The value of the real option approach, therefore, is to
order effect in terms of the consequences for the timing of highlight to managers the importance of considering
the investment. This is where we see the complications flexibility, and this might be the most significant benefit
arising. First, the two possible discount rate outcomes are above and beyond the techniques of calculation. The
evaluated in NPV terms: arithmetic only serves to demonstrate that flexibility
0.5 × [(1/1.1) × 300/0.15] = £909 should not be ignored.

0.5 × [(1/1.1) × 300/0.05] = £2,727. References


And clearly, it will only be beneficial to invest now if 1. Smith, D., “Incorporating risk into capital budgeting
discount rates fall to 5 per cent. decisions using simulation”, Management Decision, Vol.
32 No. 9, 1994, pp. 20-26.
Thus, while expected discount rates are 10 per cent, as 2. Dixit, A. and Pindyck, R.S., Investment under Uncertainty,
shown, the increase in uncertainty has created an option to Princeton University Press, Princeton, NJ, 1994.
wait which offsets the benefits of investing immediately. In 3. Myers, S., “Determinants of corporate borrowing”, Journal
fact, the investment decision is determined as (assuming of Financial Economics, No. 5, 1977, pp. 147-75.
we wait): 4. Trigeorgis, L., “A conceptual options framework for
capital budgeting”, Advances in Futures and Options
(2,727 – 0.5(1,800/1.1)) = £1,909. Research, Vol. 3, 1988, pp. 145-67.

David Brookfield is based in the Department of Economics & Accounting, University of Liverpool, UK.

Application questions
(1) How is managerial flexibility addressed in your organization?
(2) Are capital budgeting proposals in your organization flexed according to what outcomes need to be faced, and not
on the whole range of alternatives?

Вам также может понравиться