Академический Документы
Профессиональный Документы
Культура Документы
BASUKIGRAHA FABRIKATAMA
DIMENSIONAL REPORT
Project :
Customer :
Item :
PO. Number : Date :
BGF-F-QC-06-REV.00
Inspected by Approved by
( ) ( )
PT.BASUKIGRAHA FABRIKATAMA
Check Sheet of Cutting Process
Project :
Customer :
Part name : Base frame
Issue date :
Date DIMENSION
NO. DESCRIPTION Material spec Qty Unit
Start Finish L*W*H
1 Perimeter Beam
2 Purlin
3 Omega Floor
4 Cable tray Support
5
6
7
8
9
10
Applied by Acknowled by
( ) Production Spv
BGF-F-Prod-02-REV.00
heck Sheet of Cutting Process
REMARKS
PT.BASUKIGRAHA FABRIKATAMA
Check Sheet of Fitting Process
Project :
Customer :
Part name : Base frame
Issue date :
Date DIMENSION
NO. DESCRIPTION Material spec Qty Unit
Start Finish L*W*H
( ) Production Spv
BGF-F-Prod-02-REV.00
k Sheet of Fitting Process
REMARKS
PT.BASUKIGRAHA FABRIKATAMA BGF-F-Prod-03-REV.00
Check Sheet of Fitting Process
Project :
Customer :
Part name : Base frame
Issue date :
Date DIMENSION
NO. DESCRIPTION Material spec Qty Unit REMARKS
Start Finish L*W*H
Applied by Acknowled by
( ) Production Spv
PT.BASUKIGRAHA FABRIKATAMA
Check Sheet of Assambly Process
Project :
Customer :
Part name : Building
Issue date :
Date DIMENSION
NO. DESCRIPTION Material spec Qty Unit
Start Finish L*W*H
Applied by Acknowled by
( Foreman ) Production Spv
BGF-F-Prod-04-REV.00
Check Sheet of Assambly Process
REMARKS