Академический Документы
Профессиональный Документы
Культура Документы
Manpower:
a. Supervisor/Consultant for Chemical Mixture -------------- 1
b. Skilled Tile Setter --------------------------------------------------- 1
c. Helper for Concrete Chipping, Grinding & Cutting -------- 2
d. Curing Time : 1 week
Detail of Activities and Construction at Project Site
1. Breaking Reinforced Concrete Slab 15cm Thk. ………. 3 Men x 6hrs.
Equipment: Air Compressor Jack Hummer and Shovel
2. Manual Excavation of Backfill Material…………………. 5 Men x 24hrs.
3. Transport & Loading Excavated material to Dumpsite Area…….. 3 Men x 5hrs.
4. Manual work: Filling of Excavated Hole for Backfill and Compaction of Sand
Material …… 3 Men x 8 hrs.
5. Carpentry & Masonry Work: Fabrication of steel reinforcement, fixing Sika
joint material, plastic …………….. 3 Men x 4 hrs.
6. Mixing and Pouring Concrete Manual Work:
Equipment: Mixer Machine, Mason Tools ……… 4 Men x 8hrs.
7. Concrete Curing: 2 Men @ 7days duration
8. Engineer Supervision: 1 Men x 5 days supervision work duration
Material Cost:
Cement: 9 bags x $5.50/bag ------------------------------ $49.50
Reinforcement Bar 4-12mm Dia. (35.54Kg.)-------------$35.00
Sand Material…… 0.645 cu. m ------------------------------$25.00
Gravel Aggregate----------- 1.29 cu. m -------------------- $50.00
Transportation, Admin and other Cost ------------------ $45.00
----------------
Total Cost = $204.50
--------------------
Grand Total Cost = $2,572.00