AZDEC BUILDERS
UST Campus, Sta Rosa, Laguna
Sir,
We are pleased to submit our best price for the supply of Labor, Materials & Equipment
for the operation of One (1) unit Deep Well #1 situated at UST Campus, Sta. Rosa,
Laguna:
Material Labor
Total
Scope of works Quantity Cost Cost
(PHP)
(PHP) (PHP)
1. Submersible pump &
motor, 30HP rated to
deliver 75 m3/hr at 82 m
TDH Brand, Grundfos
1 set 300,000.00 150,000.00 450,000.00
pump SP77-5-BB coupled
to Franklin Motor , 30
Hp. 3p, 440Volts,60HZ or
equivalent
2. Reduced Voltage
Magnetic Controller for
1 set 125,000.00 50,000.00 175,000.00
30HP motor complete
with accessories
3. Submersible cable, no. 4-
100 m. 100,000.00 50,000.00 150,000.00
3C
4. Suspension Wire 2 box 10,000.00 - 10,000.00
5. Splicing Kit 1 set 10,000.00 - 10,000.00
6. GI pipe Supreme 4” dia,
x 20ft S40 with coupling
13 pcs. 150,000.00 45,000.00 195,000.00
Brand, Supreme pipe &
France coupling Or better
equivalent
7. GI elbow, 4” dia 2 pcs. 2,000.00 1,000.00 3,000.00
8. Gate Valve 4” dia. 2 pc. 30,000.00 10,000.00 40,000.00
9. Check valve 4” dia. 1 pc. 20,000.00 15,000.00 35,000.00
10. Y-Strainer 4” 1 pc. 15,000.00 5,000.00 20,000.00
11. Dismantling Joint 4” 1 pc. 20,000.00 10,000.00 30,000.00
12. Flow Meter 4” 1 pc. 20,000.00 15,000.00 35,000.00
13. Sanitary Well 1 pc. 2,500.00 2,500.00 5,000.00
14. Sounding Tube 1 roll 5,000.00 5,000.00 10,000.00
TOTAL AMOUNT 809,500.00 358,500.00 1,168,000.00
Exclusions:
1. Installation of Electrode wire from Deep Well to cistern.
2. Installation of pipe line from Deep Well to cistern.