KLINIK KESIHATAN (JENIS 5) LENGGENG, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS

EOT NO.1 - REVISED MASTER BASELINE (4 MAY 2020)


CRITICAL PATH
ID Task Name Duration Start Finish % Schedule % Complete Finish  2020
Variance Oct Nov Dec Jan Feb Mar Apr May Jun
1 KLINIK KESIHATAN (JENIS 5) LENGGENG, DAERAH  641.5 days 7/11/17 15/5/20 77% 70% 8.5 days
SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS 

2  MILESTONE 641.5 days 7/11/17 15/5/20 0% 0% 8.5 days


4 Projek Tamat/Penyerahan Tapak 0 days 15/5/20 15/5/20 0% 0% 8.5 days 15 May 
503 CONSTRUCTION 630.5 days 22/11/17 15/5/20 68% 58% 8.5 days
519 Main Building Works 468.5 days 21/5/18 20/3/20 85% 74% 8.5 days
520 Structure Works 415.5 days 21/5/18 7/1/20 100% 99% 11.5 days
589 Roof Structure 90.5 days 3/9/19 7/1/20 100% 92% 11.5 days
590 ZONE A 90.5 days 3/9/19 7/1/20 100% 90% 14.5 days
595 Zone A2 78.5 days 17/9/19 3/1/20 100% 78% 14.5 days
597 Roof Finishes and Covering 5 days 6/12/19 2/1/20 100% 50% 14.5 days
625 Architectural Works 273.5 days 4/3/19 20/3/20 57% 25% 8.5 days
626 ZONE A 273.5 days 4/3/19 20/3/20 38% 26% 8.5 days
627 Zone A1 240 days 4/3/19 3/2/20 59% 33% 13 days
628 Internal Wall & Partition 231 days 4/3/19 21/1/20 89% 50% 13 days
630 Internal Wall Plastering 6 days 13/12/19 8/1/20 100% 25% 13 days
642 Zone A2 114.5 days 3/9/19 10/2/20 42% 31% 11.5 days
643 Internal Wall & Partition 105.5 days 3/9/19 28/1/20 67% 50% 11.5 days
645 Internal Wall Plastering 6 days 23/12/19 15/1/20 100% 25% 11.5 days
657 Zone A3 107 days 19/9/19 14/2/20 28% 31% 10 days
658 Internal Wall & Partition 98 days 19/9/19 3/2/20 44% 50% 10 days
660 Internal Wall Plastering 6 days 31/12/19 21/1/20 0% 25% 10 days
672 Zone A4 99.5 days 7/10/19 21/2/20 28% 31% 8.5 days
673 Internal Wall & Partition 90.5 days 7/10/19 10/2/20 44% 50% 8.5 days
675 Internal Wall Plastering 6 days 8/1/20 28/1/20 0% 25% 8.5 days
676 Internal Wall Tiling 6 days 28/1/20 5/2/20 0% 0% 8.5 days
677 Internal Wall Painting 3 days 5/2/20 10/2/20 0% 0% 8.5 days
788 Ancillary Building 410.5 days 24/9/18 28/4/20 76% 69% 8.5 days
789 TNB Sub Station 410.5 days 24/9/18 28/4/20 98% 87% 8.5 days
796 Roof 6 days 29/5/19 2/1/20 100% 60% 22 days
799 Door 1 day 31/12/19 31/12/19 100% 0% 14.7 days
800 TNB Sub Station Inspection & Handing  1 day 1/1/20 1/1/20 100% 0% 14.7 days
Over

835 Garaj Ambulan 196 days 29/4/19 28/1/20 43% 64% -43.3 days


841 Roof 12 days 31/12/19 15/1/20 0% 0% -43.3 days
842 Brickworks 3 days 16/1/20 20/1/20 0% 0% -43.3 days
843 Plastering 3 days 21/1/20 23/1/20 0% 0% -43.3 days
844 Painting 2 days 24/1/20 27/1/20 0% 0% -43.3 days
845 Door 1 day 28/1/20 28/1/20 0% 0% -43.3 days
846 External Works 253 days 1/4/19 19/3/20 28% 17% -26.3 days
847 Retaining Wall (Rubble Wall) 231 days 1/4/19 18/2/20 60% 70% -48.3 days
851 Retaining Wall (Rubble Wall) Zone 4 10 days 12/12/19 7/2/20 0% 25% -45.8 days
942 Prime Cost Sum 314.5 days 25/2/19 11/5/20 24% 19% 8.5 days
943 Air‐Conditioning and Mechanical  76.1 days 20/1/20 5/5/20 12% 0% 8.5 days
Ventilation System (ACMV)

944 ZONE A 67.5 days 22/1/20 24/4/20 0% 0% 8.5 days


945 Zone A1 37.5 days 22/1/20 13/3/20 0% 0% 8.5 days
947 ACMV ‐ Fitting installation 12 days 26/2/20 13/3/20 0% 0% 8.5 days
948 Zone A2 45 days 28/1/20 31/3/20 0% 0% 8.5 days
950 ACMV ‐ Fitting installation 12 days 13/3/20 31/3/20 0% 0% 8.5 days
951 Zone A3 52.5 days 4/2/20 16/4/20 0% 0% 8.5 days
953 ACMV ‐ Fitting installation 12 days 31/3/20 16/4/20 0% 0% 8.5 days
954 Zone A4 54 days 10/2/20 24/4/20 0% 0% 8.5 days
955 ACMV ‐ Ducting work 12 days 10/2/20 26/2/20 0% 0% 8.5 days
956 ACMV ‐ Fitting installation 6 days 16/4/20 24/4/20 0% 0% 8.5 days

Disediakan oleh: Pembinaan Genting Press Sdn Bhd Page 1


Disediakan untuk: JKR Negeri Sembilan
KLINIK KESIHATAN (JENIS 5) LENGGENG, DAERAH SEREMBAN, NEGERI SEMBILAN DARUL KHUSUS
EOT NO.1 - REVISED MASTER BASELINE (4 MAY 2020)
CRITICAL PATH
ID Task Name Duration Start Finish % Schedule % Complete Finish  2020
Variance Oct Nov Dec Jan Feb Mar Apr May Jun
967 Testing and Commissioning 6 days 24/4/20 4/5/20 0% 0% 8.5 days
968 OMM & As‐built Drawing 1 day 4/5/20 5/5/20 0% 0% 8.5 days
969 Fire Fighting System 76.1 days 20/1/20 5/5/20 15% 0% 8.5 days
970 ZONE A 64.5 days 22/1/20 21/4/20 0% 0% 8.5 days
971 Zone A1 37.5 days 22/1/20 13/3/20 0% 0% 8.5 days
973 Fire Fighting Fitting installation 12 days 26/2/20 13/3/20 0% 0% 8.5 days
974 Zone A2 45 days 28/1/20 31/3/20 0% 0% 8.5 days
976 Fire Fighting Fitting installation 12 days 13/3/20 31/3/20 0% 0% 8.5 days
977 Zone A3 52.5 days 4/2/20 16/4/20 0% 0% 8.5 days
979 Fire Fighting Fitting installation 12 days 31/3/20 16/4/20 0% 0% 8.5 days
980 Zone A4 51 days 10/2/20 21/4/20 0% 0% 8.5 days
981 Fire Fighting Piping Installation 12 days 10/2/20 26/2/20 0% 0% 8.5 days
982 Fire Fighting Fitting installation 3 days 16/4/20 21/4/20 0% 0% 8.5 days
983 ZONE B 72.1 days 20/1/20 29/4/20 50% 0% 8.5 days
984 Zone B1 68.1 days 20/1/20 23/4/20 50% 0% 8.5 days
986 Fire Fighting Fitting installation 2 days 21/4/20 23/4/20 0% 0% 8.5 days
987 Zone B2 70.1 days 20/1/20 27/4/20 50% 0% 8.5 days
989 Fire Fighting Fitting installation 2 days 23/4/20 27/4/20 0% 0% 8.5 days
990 Zone B3 72.1 days 20/1/20 29/4/20 50% 0% 8.5 days
992 Fire Fighting Fitting installation 2 days 27/4/20 29/4/20 0% 0% 8.5 days
993 ZONE C 62.1 days 5/2/20 1/5/20 0% 0% 8.5 days
994 Zone C1 62.1 days 5/2/20 1/5/20 0% 0% 8.5 days
996 Fire Fighting Fitting installation 2 days 29/4/20 1/5/20 0% 0% 8.5 days
997 Testing and Commissioning 1 day 1/5/20 4/5/20 0% 0% 8.5 days
998 OMM & As‐built Drawing 1 day 4/5/20 5/5/20 0% 0% 8.5 days
999 Electrical Works 314.5 days 25/2/19 11/5/20 40% 47% 8.5 days
1000 ZONE A 279.5 days 25/2/19 23/3/20 50% 50% 8.5 days
1001 Zone A1 261.5 days 25/2/19 26/2/20 50% 50% 8.5 days
1004 Electrical 3rd Fix 6 days 18/2/20 26/2/20 0% 0% 8.5 days
1005 Zone A2 254.5 days 14/3/19 5/3/20 50% 50% 8.5 days
1008 Electrical 3rd Fix 6 days 26/2/20 5/3/20 0% 0% 8.5 days
1009 Zone A3 260.5 days 14/3/19 13/3/20 50% 50% 8.5 days
1012 Electrical 3rd Fix 6 days 5/3/20 13/3/20 0% 0% 8.5 days
1013 Zone A4 266.5 days 14/3/19 23/3/20 50% 50% 8.5 days
1015 Electrical 2nd Fix 6 days 10/2/20 18/2/20 0% 0% 8.5 days
1016 Electrical 3rd Fix 6 days 13/3/20 23/3/20 0% 0% 8.5 days
1017 ZONE B 210.5 days 27/6/19 16/4/20 43% 50% 8.5 days
1018 Zone B1 198.5 days 27/6/19 31/3/20 75% 50% 8.5 days
1021 Electrical 3rd Fix 6 days 23/3/20 31/3/20 0% 0% 8.5 days
1022 Zone B2 93.5 days 29/11/19 8/4/20 0% 50% 8.5 days
1025 Electrical 3rd Fix 6 days 31/3/20 8/4/20 0% 0% 8.5 days
1026 Zone B3 99.5 days 29/11/19 16/4/20 54% 50% 8.5 days
1029 Electrical 3rd Fix 6 days 8/4/20 16/4/20 0% 0% 8.5 days
1030 ZONE C 105.5 days 29/11/19 24/4/20 8% 50% 8.5 days
1031 Zone C1 105.5 days 29/11/19 24/4/20 8% 50% 8.5 days
1034 Electrical 3rd Fix 6 days 16/4/20 24/4/20 0% 0% 8.5 days
1035 Testing and Commissioning 6 days 24/4/20 4/5/20 0% 0% 8.5 days
1036 OMM & As‐built Drawing 5 days 4/5/20 11/5/20 0% 0% 8.5 days
1038 Testing and Commissioning 78.5 days 28/1/20 15/5/20 0% 0% 8.5 days
1040 TNB 2 days 11/5/20 13/5/20 0% 0% 8.5 days
1041 BOMBA 1 day 13/5/20 14/5/20 0% 0% 8.5 days
1042 Final Building Inspection 1 day 14/5/20 15/5/20 0% 0% 8.5 days
1043 Projek Tamat/Penyerahan Tapak 0 days 15/5/20 15/5/20 0% 0% 8.5 days 15 May 

Disediakan oleh: Pembinaan Genting Press Sdn Bhd Page 2


Disediakan untuk: JKR Negeri Sembilan