ID Task Name Duration Start ober 21 March 01 September 11 February 21 July 01

10-12 25-02 13-05 29-07 14-10 30-12 17-03 02-06 18-08 03-11
1 Construction 17.09 mons Fri 15‐06‐18
2 Civil Work 11.53 mons Fri 15‐06‐18
3 Pick Up Line Profile 3.5 mons Fri 15‐06‐18
4 Spotting 1 mon Mon 10‐09‐18
5 Check survey 1 mon Tue 25‐09‐18
6 Geotechnical Investigation 4 mons Fri 15‐06‐18
7 Mobilization (Foundation Section) 9 mons Fri 15‐06‐18
8 Access Road Construction 8 mons Mon 10‐09‐18
9 Foundation Construction 9.5 mons Sun 12‐08‐18
10 Soil Resistivity Tests 8 mons Sun 12‐08‐18
11 Excavation 8 mons Mon 10‐09‐18
12 Reinforcement 7 mons Tue 09‐10‐18
13 Grounding System Installation 6.5 mons Wed 24‐10‐18
14 Concreting Shaft 6.5 mons Wed 24‐10‐18
15 Concreting Chimney 5 mons Fri 21‐12‐18
16 Installation 5.57 mons Tue 14‐05‐19
17 Tower section 5.03 mons Tue 14‐05‐19
18 Mobilization (Tower Section) 0.5 mons Tue 14‐05‐19
19 Tower Installation 4.5 mons Thu 30‐05‐19
20 Tower Greening 4.5 mons Thu 30‐05‐19
21 Stringing 4.03 mons Fri 28‐06‐19
22 Mobilization (Stringing section) 0.5 mons Fri 28‐06‐19
23 Phase Conductors Stringing 3.5 mons Sat 13‐07‐19
24 OPGW Stringing 3.5 mons Sat 13‐07‐19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 30-12-19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start ober 21 March 01 September 11 February 21 July 01
10-12 25-02 13-05 29-07 14-10 30-12 17-03 02-06 18-08 03-11
25 Shield Stringing 3.5 mons Fri 28‐06‐19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project1
Summary Manual Summary Rollup Progress
Date: Mon 30-12-19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2