Вы находитесь на странице: 1из 4

Code :R7410508 1

IV B.Tech I Semester(R07)Regular Examinations, November/December 2010


SOFTWARE PROJECT MANAGEMENT
(Computer Science & Engineering and Information Technology)
Time: 3 hours Max Marks: 80
Answer any FIVE questions
All questions carry equal marks
?????

1. (a) Explain the Waterfall model and five necessary improvements for this approach to work.
(b) What are the troubles frequently exhibit in the conventional S/W management approach?

2. (a) Write the advantages and disadvantages of commercial components versus custom soft-
ware.
(b) What are the three levels of software process and their attributes?

3. (a) What are the principles of modern software management?


(b) Write the short notes on pragmatic artifacts

4. (a) Explain the artifacts of Management set.


(b) Write the short notes on pragmatic artifacts

5. Explain the following check points of the process

(a) Major Mile stones


(b) Minor mile stones

6. (a) Discuss the default project organizations of S/W engineering?


(b) What are the activities of S/W management team?

7. (a) Explain the management indicators.


(b) Write short notes on process discriminators.

8. (a) Discuss any two important points of the genuine cultural transitions.
(b) Discuss any six of top 10 S/W management principles

?????
Code :R7410508 2
IV B.Tech I Semester(R07)Regular Examinations, November/December 2010
SOFTWARE PROJECT MANAGEMENT
(Computer Science & Engineering and Information Technology)
Time: 3 hours Max Marks: 80
Answer any FIVE questions
All questions carry equal marks
?????

1. (a) What are the symptoms of the projects which are destined for trouble?
(b) What are the five necessary points to improve the Waterfall model?

2. (a) What are the key processes that improve the overall software quality?
(b) Write short notes on peer inspections.

3. (a) Discuss the Engineering and production stages of software life cycle.
(b) What are the primary objectives and essential activities of a construction phase?

4. (a) Explain the artifacts of the Design set.


(b) Write the short notes on pragmatic artifacts.

5. (a) Explain the iterative planning process.


(b) Write short notes on WBS.

6. (a) What are the activities of S/W architecture team?


(b) Write short notes on change management.

7. Explain the seven core metrics of project control and process instrumentation.

8. Discuss any five important points of the genuine cultural transitions of a project.

?????
Code :R7410508 3
IV B.Tech I Semester(R07)Regular Examinations, November/December 2010
SOFTWARE PROJECT MANAGEMENT
(Computer Science & Engineering and Information Technology)
Time: 3 hours Max Marks: 80
Answer any FIVE questions
All questions carry equal marks
?????

1. (a) What are the Symptoms of the projects which are destined for trouble?
(b) What constitute a good software cost estimate?

2. (a) Explain the important trends to improve the software economics.


(b) Discuss the three levels of software process and their attributes.

3. (a) Discuss the principles of modern software management?


(b) Discuss the principles of conventional software management?

4. (a) Discuss the artifacts of the requirement set.


(b) Discuss the artifacts of the deployment set.

5. (a) What are the artifacts and life cycle emphases associated with each work flow?
(b) What are the major mile stones of software project?

6. Explain the default project organization of S/W engineering and its responsibilities

7. (a) Discuss the Quality indicators?


(b) Write short notes on process discriminators.

8. (a) Discuss any six of top 10 S/W management principles.


(b) Discuss the next generation cost models of the engineering stage.

?????
Code :R7410508 4
IV B.Tech I Semester(R07)Regular Examinations, November/December 2010
SOFTWARE PROJECT MANAGEMENT
(Computer Science & Engineering and Information Technology)
Time: 3 hours Max Marks: 80
Answer any FIVE questions
All questions carry equal marks
?????

1. (a) What constitute a good software cost estimate?


(b) What are the five necessary points to improve the Waterfall model?

2. (a) Explain the important trends to improve the software economics.


(b) What are the key processes that improve the overall software quality?

3. (a) What are the principles of modern software management?


(b) What are the primary objectives and essential activities of a transition phase?

4. (a) Discuss the artifacts of Managements set.


(b) Discuss the artifacts of the Implementation set.

5. (a) Write short notes on iteration work flow.


(b) Write short notes on WBS.

6. (a) Discuss the default project organizations of S/W engineering.


(b) Write short notes on change management.

7. (a) Discuss the quality indicators?


(b) Write short notes on process discriminators.

8. (a) Discuss any tow important points of the genuine cultural transitions of a project.
(b) Discuss the next generation cost models of the production stage.

?????