SUMADHURA NANDANAM NOVEMBER 30-11-2019 MPR.

A block 7th floor roof slab completed


A block North side view A block South side view

A block 5th floor block work in progress


A-Block Progress

Toilet CPVC
Electrical Chipping
Pipe wiring
& pipe fixing with Water Proofing Screed Concrete
work
Internal Wall box
Block A Slab Concrete Block work Ceiling Plastering Plastering

Lower Basement Completed NA NA NA NA NA NA NA


Upper Basement Completed NA NA NA NA NA NA NA
Ground Floor Completed - - - - - - -

First Floor Completed - - - - - -

Second Floor Completed - - - - - - -

Third Floor Completed Completed - - - - - -

Fourth Floor Completed Completed - - - - - -


Fifth Floor Completed Under progress - - - - - -

Sixth Floor Completed - - - - - - -

Seventh Floor Completed - - - - - - -

Eighth Floor - - - - - - - -

Ninth Floor - - - -- - - - -

Tenth Floor - - - - - - - -

Eleventh Floor - - - - - - - -

Twelfth Floor - - - - - - - -

Thirteenth Floor - - - - - - - -

Fourteenth Floor - - - - -- - - -
B block North side view B block South side view

B block
Ground+14th floor Structure works completed &
14th floor block work in progress
B block 7th floor Internal wall & ceiling 1st coat
putty work in progress.
B-Block Progress

Inernal ceiling &


Electrical Chipping & Toilet CPVC Pipe
Water Proofing Screed Concrete wall 1st coat
pipe fixing with box wiring work
Internal Wall External wall Putty
Block B Block work Ceiling Plastering Plastering Plastering

Lower Basement NA NA NA NA NA NA NA NA NA

Upper Basement NA NA NA NA NA NA NA NA Na

Ground Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

First Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Second Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Third Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Fourth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Fifth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Sixth Floor Completed Completed Completed Completed Completed Completed Completed Completed Completed

Seventh Floor Completed Completed Completed Completed Completed Completed Completed Completed Under progress

Eighth Floor Completed Completed Completed Completed Completed Completed Completed Completed -

Ninth Floor Completed Completed Completed Completed Completed Completed Completed - -

Tenth Floor Completed Completed Completed - Completed Completed Completed - -

Eleventh Floor Completed Completed Completed - Completed Completed Under Progress - -

Twelfth Floor Completed Completed Under Progress - Under Progress - - - -

Thirteenth Floor Completed Under Progress - - - - - - -

Fourteenth Floor Under Progress - - - - - - - -


C block North side view C block South side View

C block
Ground+14th floor Structure work completed.
Ground+14th floor block work completed.
C block C block
7th floor Internal wall & ceiling 1st 1st,2nd & 3rd floor tile work is
coat putty work is under progress. under progress.
C-Block Progress

Inrernal ceiling &


Electrical Chipping & Toilet CPVC Pipe Flooring & Toilets
Water Proofing Screed Concrete wall 1st coat
pipe fixing with box wiring work Tiles
Putty
Ceiling Internal Wall External wall
Block C Plastering Plastering Plastering

Lower Basement NA NA NA NA NA NA NA NA Na

Upper Basement NA NA NA NA NA NA NA NA NA

Ground Floor Completed Completed Completed Completed Completed Completed Completed Completed -

First Floor Completed Completed Completed Completed Completed Completed Completed Completed Under progress

Second Floor Completed Completed Completed Completed Completed Completed Completed Completed Under progress

Third Floor Completed Completed Completed Completed Completed Completed Completed Completed Under progress

Fourth Floor Completed Completed Completed Completed Completed Completed Completed Completed -

Fifth Floor Completed Completed Completed Completed Completed Completed Completed Completed -

Sixth Floor Completed Completed Completed Completed Completed Completed Completed Completed -

Seventh Floor Completed Completed Completed Completed Completed Completed Completed Under progress -

Eighth Floor Completed Completed Completed Completed Completed Completed Completed - -

Ninth Floor Completed Completed Completed Completed Completed Completed - - -

Tenth Floor Completed Completed Under progress Completed Completed Completed - - -

Eleventh Floor Completed Completed Under progress Completed Completed Under Progress - - -

Twelfth Floor Completed Completed Under progress Completed Completed - - - -

Thirteenth Floor Completed Under Progress Under progress Under Progress Under Progress - - - -

Fourteenth Floor - - Under progress - - - - - -