PLTMG MERAUKE 20 MW
SITE INSTRUCTION
Originator : Action by :
……………… …………………………….
PT. WIKA Subcont : ………………….
Section / Area :
Document/Drawing ref :
Title :
Description :
Issued for : Reply Notice
Raised by , Acknowledge,
Yusuf Kurniawan
Manager ………… Project Manager
Copy of answered to Originator
INSTRUCTION
Date :
……………………. , 2017
Responsible,
Kurniawan
Subkont : …………..
CONSORTIUM WIKA
PLTMG MERAUKE 2
MERAUKE
PUNCH LIST
1 General (GE): *
Preparation (PR): * Report No : KBT-PL-WIKA-QAC-
*
*
Reference Drawing No.:
Balance of Plant (BP): *
2 Location :
4 Inspection Items :
Contractor
NO Item Chek PT. WIKA
Prepared
OWNER CONSULTANT
PT.PLN
Witness Approved
Notes:
* : Chose according to Unit/Area
RTIUM WIKA - WRK
MERAUKE 20 MW
MERAUKE
PUNCH LIST
.:
HANDOVER INSPE
4 Inspection Items :
NO Item Chek
Subcontractor
…………………………………….
QC / SPV
Notes:
* : Chose according to Unit/Area
ortium Wika - WRK
G MERAUKE 20 MW
MERAUKE
DOVER INSPECTION
FILE No : WC-851E03-QAC-…………..-HO02-………….
FORM : HO-002
Minute:
ACCEPTABLE
PT.Wijaya Karya (Persero) Tbk …………………………………
OK NO OK NO
Contractor
PT.Wijaya Karya ( Persero ) Tbk
( …………………………………………………… )
QC / SPV
Consortium Wika - WRK
PLTMG MERAUKE 20 MW
MERAUKE
Date : Hour :
Month : Minute :
Year :
Signature :
5 Client's Comment:
Client Inpection Witness:
Applicable
Not Applicable
1. ……………………………………………1. ………………………
2. ……………………………………………2. ………………………
3. ……………………………………………3. ………………………
Remarks :
Notes:
* : Chose according to Unit/Area
tium Wika - WRK
MERAUKE 20 MW
MERAUKE
Date :
Time :
:
:
CONSULTANT PT.PLN
Approved Witness
1. ………………………………………………
1. ………………………………………
2. ………………………………………………
2. ………………………………………
3. ………………………………………………
3. ………………………………………
Consortium Wika - WR
PLTMG MERAUKE 20 MW
MERAUKE
3 Inspection Items :
Signature
Name
6 Content of Inspection :
7 Client's Comment:
Client Inpection Witness : Aplicable / Not Applicable
1. ……………………………………………
1. ……………………
2. ……………………………………………
2. ……………………
3. ……………………………………………
3. ……………………
Remarks :
Notes:
* : Chose according to Unit/Area
um Wika - WRK
MERAUKE 20 MW
MERAUKE
Hour: Minute:
ONTRACTOR SUPERVISOR OWNER
rtium WIKA - WRK PT.Rekadaya Elektrika PT.PLN
Reviewed Approved Witness
th : Year : Hour : Min :
1. ……………………………………………1. …………………………………………….
2. ……………………………………………2. …………………………………………….
3. ……………………………………………3. …………………………………………….
INSPECTION RECORD
BENCHMARK & GRID LINE
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Survey work
Signature
6 Content of Inspection:
7 Result of Inspection
Actual Allowable
Design Value Judgment
Measure Tolerance
BENCHMARK
X Coordination ± 2 mm
Y Coordination ± 2 mm
Level ± 2 mm
Protection
GRID LINE
X Direction ± 2 mm
Y Direction ± 2 mm
8 Client's Comment:
3 Inspection Items:
Pile Bearing Capacity
7 Result of Inspection
8 Client's Comment :
*
Balance of Plant:
Name
Signature
6 Content of Inspection:
7 Result of Inspection
Design Actual
Pile No. Allowable tolerance Judgment
Value Measure
Pile – 1
Pile – 2
8 Client's Comment:
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Earth Work
Excavated area
A B
C D
7 Result of Inspection
Allowable
Design Value Actual Measure Judgment
tolerance
Excavated Level ±20mm
A ±20mm
B ±20mm
C ±20mm
D ±20mm
E (Center) ±20mm
8 Client's Comment:
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Earthwork (Foundation Gravel Base)
Gravel area
7 Result of Inspection
Design Actual
Allowable tolerance Judgment
Value Measure
Gravel Base Level
A -30 ~ +10mm
B -30 ~ +10mm
C -30 ~ +10mm
D -30 ~ +10mm
E (Center) -30 ~ +10mm
8 Client's Comment:
INSPECTION RECORD
EARTHWORK (BACKFILLING)
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Earthwork
7 Result of Inspection
8 Client's Comment:
16 Wt. of pan g
22 Compaction % =(20)/(21)x100%
1E03-QAC-……-IR08-….…
……………………..
PT. PLN
1485.17 1485.17
1.4820 1.4820
1.33 1.33
FIELD DENSITY TEST SAND CONE METHOD
Sampel Description : File No. : WK-851E03-QAC-……-IR08-….…
Form ID : IR-008
Sampel Location : Date :
Witness PLN
Name
Signature
16 Wt. of pan g
22 Compaction %
INSPECTION RECORD
EARTH WORK (BACKFILL FINISHED LEVEL)
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Earth Work
Backfilled Area
A B
C D
7 Result of Inspection
Design Actual
Allowable tolerance Judgment
Value Measure
Excavated Level
A ±20mm
B ±20mm
C ±20mm
D ±20mm
E (Center) ±20mm
8 Client's Comment:
INSPECTION RECORD
CONCRETE WORK (LEVELING CONCRETE)
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (Leveling concrete)
7 Result of Inspection
Design Actual
Allowable tolerance Judgment
Value Measure
Leveling Concrete Level
A ±10mm
B ±10mm
C ±10mm
D ±10mm
E (Center) ±10mm
8 Client's Comment:
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (Position)
7 Result of Inspection
Center of Building
X Coordination ±2mm
Y Coordination ±2mm
8 Client's Comment:
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (Rebar & Formwork)
2. Formwork
Inside Dimension
Finished Level
3. Anchor Bolts
Position
Level
4. Embedded Metal
Position
Level
7 Result of Inspection
PT. WIKA PT. PLN
Allowable tolerance Judgment
Date Sign Date Sign
Rebar
Diameter As per drawings
Number As per drawings
Spacing As per drawings
Cover As per drawings
Lap Length Exceed length
Formwork
Anchor Bolts
Embedded Material
Position As per drawings
Level As per drawings
8 Client's Comment:
REVIEWED/WITNESSED
ITEM DESCRIPTION PT. WIKA PT. PLN / PT. Rekadaya
DATE SIGN DATE SIGN
1 FORM WORK - DIMENSION ALIGNMENT COLUMN
- FORM OIL COATING WALL
- STABILITY BEAM
- TOP ELEVATION SLAB
- CHAMPER, SPACER Pile Cap
PHT
REMARK :
LOCATION : DATE :
STRUCTURE NAME : QUANTITY :
ELEVATION :
PLACING TEMP. :
REQUIRED CURIN:
CIVIL : : DATE :
PIPING : : DATE :
MECHANICAL : : DATE :
ELECTRICAL : : DATE :
SURVEY : : DATE :
PT. WIKA
ENGINEERING : : DATE :
QUALITY CONTROL : : DATE :
REMARK :
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (After Pouring)
3 Inspection Items:
7 Result of Inspection
Note: Type “A” for exposed to view & Type “B” for exposed to earth as per ACI 309
8 Client's Comment:
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (After Pouring)
7 Result of Inspection
Refer to Attachment
8 Client's Comment:
CHARACTERISTIC OF MATERIALS
Specific Gravity
Condition SSD
Water Content (%) 4.944 1.534
Absorption (%) 1.678 2.558
Mix Proportion (Volume = 0,5 m3)
Mix Design Proportion
Adjustment (Absorption of Aggregate)
Trial Mix Design
3
Merauke, ………………
Approved by, Reviewed by,
PT. PLN Consortium Wika - WRK
Kg/m3
%
%
% bwc
gr/cc
gr/cc
gr/cc
gr/cc
gr/cc
TOTAL
REMARK
(Kg/m3)
( ...........................)
INSPECTION RECORD
STEEL STRUCTURE WORK
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Steel Structure Work (Before Erection)
7 Result of Inspection
Design Actual
Allowable tolerance Judgment
Value Measure
Column Number
C1 ±3.0mm
C2 ±3.0mm
C3 ±3.0mm
C4 ±3.0mm
C5 ±3.0mm
C6 ±3.0mm
C7 ±3.0mm
8 Client's Comment:
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Steel Structure Work (During Erection)
1. Column Alignment
2. Rectilinear of Beam
3. Level of Floor Girders
4. Inclination of Structures
5.Deformation of Structures
7 Result of Inspection
Actual
Design Value Allowable tolerance Judgment
Measure
Min of (L/1000+3mm or
Rectilinear of Beam
10mm)
Min of (H/4000+7mm or
Inclination of Structures
30mm)
8 Client's Comment:
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
1. Span
2. Differential level between two Rails
3. Inclination of Rail
7 Result of Inspection
Actual
Design Value Allowable tolerance Judgment
Measure
Span Min of (H/1000 or 10mm)
8 Client's Comment:
COMPRESSIVE
DATE OF DATE OF AGE AREA WEIGHT SLUMP MAXIMUM
NO LOCATION CODE STRENGTH
POURING TEST (DAYS) (CM)2 (KG) (CM) LOAD (KG)
fc' (KG/CM2)
Notes:
COMPRESSIVE STRENGTH AT
TESTING KG/CM2 REMARKS
TEST DAY 28 DAYS
MERAUKE,……………………..2017
Prepared by,
SUBCON
(………………………………………)
INSPECTION RECORD
Bonna Pipe Installation
FILE No. : WK-851E03-QAC-……-IR23-….…
Form ID : IR - 023
1 General:: *
Preparat: *
* Reference Drawing No. CB-
*
Balance of Plant: *
2 Work: Bonna Pipe Installation
3 Inspection Items:
Signature
6 Content of Inspection:
1. Pipe Diameter
2. Position
3. Elevation
7 Remarks:
Allowable
Pipe No. Design Value Actual Measure Judgment
Tolerance
Pipe -1
X Coordination
Y Coordination
Elevation
Pipe - 2
X Coordination
Y Coordination
Elevation
9 Client's Comment:
3 Inspection Items:
Signature
6 Content of Inspection :
7 Result of Inspection :
Design Actual
Allowable tolerance Judgment
Value Measure
Cement Type Cement Type V
Surface Condition
Consolidation No Honeycomb
Color No different color
Voids Refer to note below
8 Client's Comment:
17 16-Dec-2009 8:00 - - - - - - -
18 10:00 - - - - - - -
19 12:00 - - - - - - -
20 14:00 - - - - - - -
21 16:00 - - - - - - -
22 18:00 - - - - - - -
23 20:00 - - - - - - -
24 22:00 - - - - - - -
25 17-Dec-2009 8:00 - - - - - - -
26 11:00 - - - - - - -
27 14:00 - - - - - - -
28 17:00 - - - - - - -
29 18-Dec-2009 8:00 - - - - - - -
30 11:00 - - - - - - -
31 14:00 - - - - - - -
32 17:00 - - - - - - -
33 19-Dec-2009 8:00 - - - - - - -
34 11:00 - - - - - - -
35 14:00 - - - - - - -
36 17:00 - - - - - - -
Total Temperature ( oC )
No Date Time
Hours Bottom 1 Middle 2 Top 3 Surface
37 20-Dec-2009 8:00 - - - - - - -
38 11:00 - - - - - - -
39 14:00 - - - - - - -
40 17:00 - - - - - - -
41 21-Dec-2009 8:00 - - - - - - -
42 11:00 - - - - - - -
43 14:00 - - - - - - -
44 17:00 - - - - - - -
45 22-Dec-2009 8:00 - - - - - - -
46 11:00 - - - - - - -
47 14:00 - - - - - - -
48 17:00 - - - - - - -
Notes:
a. The difference temperature between top and surface are not larger than 20 o Celcius
b. The difference temperature between layer to layer are not larger than 25 o Celcius
ECTION RECORD
TEMPERATURE RECORD
…………………………………………
…………………………………………
4
Ambient Weather
- -
- -
- -
………………………………………………………………………………………..
Temperature ( oC )
4 Ambient Weather
-
-
-
-
-
-
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
Temperature ( oC )
4 Ambient Weather
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
INSPECTION SHEET FOR FORMWORK & ANCHOR BOLT BEFORE CONCRETE POURING
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
a -5 ~+20mm
I1 b B
A -5 ~+20mm
b -5 ~+20mm
a
A B -5 ~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
PLAN
x3 ± 1mm
x4 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
SECTION
L4 ± 3mm
Elevation
H1 0 ~+5mm
H2 0 ~+5mm
H3 0 ~+5mm
H4 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Signature
INSPECTION SHEET FOR FORMWORK & ANCHOR BOLT BEFORE CONCRETE POURING
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
L4 ± 3mm
Elevation
H1 0 ~+5mm
H2 0 ~+5mm
H3 0 ~+5mm
H4 0 ~+5mm
H5 0 ~+5mm
H6 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
x5 ± 1mm
x6 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
L4 ± 3mm
H1 0 ~+5mm H5 0 ~+5mm
H2 0 ~+5mm H6 0 ~+5mm
H3 0 ~+5mm H7 0 ~+5mm
H4 0 ~+5mm H8 0 ~+5mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
x5 ± 1mm
x6 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
y7 ± 2mm
y8 ± 2mm
Elevation X ± 2mm
H3 0 ~+5mm Y ± 2mm
H4 0 ~+5mm L3 ± 3mm
H5 0 ~+5mm L4 ± 3mm
Elevation
H6 0 ~+5mm
H7 0 ~+5mm H1 0 ~+5mm
H8 0 ~+5mm H2 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
FILE No. :
FORM ID: IR – 014
1 General: *
Preparation: *
* Reference Drawing No.
*
Balance of Plant: *
2 Work: Concrete Work (Before pouring)
7 Result of Inspection
Allowable
Design Value Actual Measure Judgment
tolerance
8 Client's Comment:
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
PLAN
x3 ± 1mm
x4 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
SECTION
L4 ± 3mm
Elevation
H1 0 ~+5mm
H2 0 ~+5mm
H3 0 ~+5mm
H4 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
L4 ± 3mm
Elevation
H1 0 ~+5mm
H2 0 ~+5mm
H3 0 ~+5mm
H4 0 ~+5mm
H5 0 ~+5mm
H6 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1a ± 1mm
x1b ± 1mm
x2 ± 1mm
x3a ± 1mm
x3b ± 1mm
x4 ± 1mm
x5a ± 1mm
x5b ± 1mm
x6 ± 1mm
x7a ± 1mm
x7b ± 1mm
x8 ± 1mm
y1a ± 1mm
y1b ± 1mm
y2 ± 1mm
y3a ± 1mm
y3b ± 1mm
y4 ± 1mm
y5a ± 1mm
y5b ± 1mm
y6 ± 1mm
y7a ± 1mm
Elevation y7b ± 1mm
H3 0 ~+5mm y8 ± 1mm
H4 0 ~+5mm X ± 2mm
H5 0 ~+5mm Y ± 2mm
Elevation
H6 0 ~+5mm
H7 0 ~+5mm H1 0 ~+5mm
H8 0 ~+5mm H2 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
x5 ± 1mm
x6 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
y7 ± 2mm
y8 ± 2mm
Elevation X ± 2mm
H3 0 ~+5mm Y ± 2mm
H4 0 ~+5mm L3 ± 3mm
H5 0 ~+5mm L4 ± 3mm
Elevation
H6 0 ~+5mm
H7 0 ~+5mm H1 0 ~+5mm
H8 0 ~+5mm H2 0 ~+5mm
Note: Total of (d1 + d2 + d3) shall not exceed ±10mm
Location : ......................................................
1. Inside Dimension of Formwork Date : ......................................................
PLAN
I2 L2
Design Actual Allowable
Judgment
L1 Value Measure tolerance
-5
a
I1 b B ~+20mm
-5
A
~+20mm
-5
b
a ~+20mm
A -5
B
~+20mm
l1
SECTION l2
L1
d
3 L2
d
2 Elevation
d1 ±10mm
d
1 d2 ±10mm
d3 ±10mm
Position / Coordinate
2. Anchor Bolts
x1 ± 1mm
x2 ± 1mm
x3 ± 1mm
x4 ± 1mm
x5 ± 1mm
x6 ± 1mm
y1 ± 1mm
y2 ± 1mm
y3 ± 1mm
y4 ± 1mm
y5 ± 1mm
y6 ± 1mm
X ± 2mm
Y ± 2mm
L3 ± 3mm
L4 ± 3mm
H1 0 ~+5mm H5 0 ~+5mm
H2 0 ~+5mm H6 0 ~+5mm
H3 0 ~+5mm H7 0 ~+5mm
H4 0 ~+5mm H8 0 ~+5mm
RANGE OF SLUMP
(cm)
COARSE AGG
CC/m3
RANGE OF AIR
(%)
MAX.SIZE OF
TYPE
PROPORTIONS
(%)
CEMENT
mm-mm mm-mm
WATER
SAND
DESIGN
20 10
S/A
SPECIMEN NO
AGE (days)
AVERAGE DIAMETER (mm)
SECTIONAL AREA (mm2)
AVERAGE HEIGHT (mm)
SLUMP (cm)
WEIGHT (kg)
MAXIMUM LOAD (kg)
COMPRESSIVE STRENGTH (N/mm2)S
MEAN VALUE OF COMP. STR (N/mm2)L
ALLOWABLE MIN. COMP STR. (N/mm2)L
TYPE OF FRACTURE
TESTED BY: LABORATORY/ENG. BY: M.H.I
WITNESSED BY:
REMARKS AIR %
PILE D
File No : WK-851E03-QAC-……
Form ID : PDR -001
Number of Final
Drop Distance Rebound Design Actual
Hammer Drop Penetration
(mm) Measure (mm) Capacity (T) Capacity (T)
(No) (mm)
: WK-851E03-QAC-……-PDR1-….…
Judgment Remarks
Measurement on Pile Penetration
File No : WC-851E03-QAC-……-MPP1-….…
FORM ID : MPP-001
Month Day /
Pile No. No.
Pile Type Dia. X
Driving Depth m
No. of driving
Drop Height m
Rebound mm
Penetration Depth mm
FIELD SURVEY REPORT
LEVELING
FILE NO: WC-851E03
FORM ID : SR-001
PROJECT : PLTMG MERAUKE - 20 MW SURVEYOR
LOCATION : INSTR. NO.
TASK : PAGE NO.
DATE : BLOCK
No. ELEVATION
BM BS FS IH
Point DESIGN ACTUAL
SKETCH :
DISTANCE
REMARKS
( mm )
Prepared by
CONSORTIUM WIKA - WRK
( …………………………. ) ( …………………………. )
SURVEY TOP ELEVATION OF EMBEDDED PLATE
BEFORE / AFTER CONCRETE
PT.PLN
FORM ID : SR-002
Horizontal Azimuth (a )
No Point Number Cor. Distance (d)
Deg Min Sec Deg Min Sec
Approved by Reviewed by
PT. PLN
( …………….………………. ) ( …………….………………. )
FIELD SURVEY REPORT
ACTUAL PILE COORDINATE
FILE NO. : WC-851E03-QAC-……-SR04-….…
FORM ID : SR-004
SURVEYOR
INSTR. NO.
PAGE NO.
BLOCK
E N E N E
Reviewed by Prepared by
CONSORTIUM WIKA - WRK
( …………….………………. ) ( …………….………………. )
FILE NO. : WC-851E03-QAC-……-SR04-….…
: ……………………………………………
: ……………………………………………
: …………………..of……………………
: ……………………………………………
∆ Coordinate
Elevation
E N
( …………….………………. )