Академический Документы
Профессиональный Документы
Культура Документы
12
12
12
12
12
12
12
12
Location: DHAHRAN, SAUDI ARABIA Contract Completion Date: 10-Jan-23 7
6
5
4
3
2
1
Start Date: 14-Jul-19 Forecast Completion: 10-Jan-23 0 WK-13: WK-14: WK-15: WK-16:
06/Oct/2019 13/Oct/2019 20/Oct/2019 27/Oct/2019
Completion Date (Original): 10-Jan-23 Original Duration (Days): 1,276 Planned Weekly Manpower (Ave) 12 12 12 12
Forecast Completion Date: 10-Jan-23 Elapsed Duration: 172 Remaining Duration: 1,104 Actual Weekly Manpower 12 12 12 12
DEMOLITION & CONSTRUCTION WORKS: PLAN VS ACTUAL MAIN EVENTS FOR THE WEEK PROCUREMENT
Tunnel MEP demolition works is in-progress
A Demolishing B Recover Sanitary C
Rerouting of ISSUES and CONCERNS Long Lead Submittals
Domestic Water Waste Water existing storm HVAC & Low current Submittals are severely delayed. 20
water 15
Distribution Network 58
A lot of delays in Submittals and Approvals
15
14
0 * Lighting Poles
D Demolition of Electrical Line
E Recover Grey Waste FMEP in Raft Electrical Mechanical
100%
100% 100%
100% 100%
Water Network 11% Planned Submitted Approved Under Review
Plan Actual Plan Actual Plan Actual PLANNED ACTUAL APPROVED UNDER REVIEW
3 Months Look-Ahead Construction Status Egypt office Drawing Status Look-ahead Procurement Status
Actual % 17% APPROVED 2% Approved 15%