Вы находитесь на странице: 1из 210

The University of British Columbia

Electric Power Group


Department of Electrical & Computer Engineering;
Power Systems Consultants, Vancouver, Canada

Switching and Lightning


Surges in Power Systems
Hermann W. Dommel
June 2012

Email: hermannd@ece.ubc.ca
Presentation Outline 2

• Closing and re-closing operations on transmission lines (line energization)

• Reduction of overvoltages in closing and re-closing operations on


transmission lines

• Computer models for closing and re-closing operations on transmission lines

• Examples for closing and re-closing operations on transmission lines

• Lightning surges

• Example for temporary overvoltages

• Examples for subsynchronous resonance

• Example for single-line-to-ground fault on transmission lines

The University of British Columbia


Presentation Outline 3

• Example for transient recovery voltage

• Example for linear resonance after opening a transmission line in parallel


with another line

• Examples for steady-state coupling between parallel transmission lines

• Capacitor switching

• Inrush Currents

• Interruption of small inductive currents

• Real-time simulators, EMTP-type software

• Specific references, general references

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 4

• Circuit breakers at both ends I and II cannot close simultaneously.

• Therefore, the voltage


surge travelling down f open-end = 250 Hz for 300 km
the line doubles
at the open end.
1
f openend 
4
• Low impedance
termination (dotted).
1
f lowZ 
2
The University of British Columbia
Closing & Re-closing Operations on Transmission Lines 5

• In reality, overvoltage can be >2.0 p.u. because:

• not infinite source in A (therefore reflections),


• line may have "trapped charge" from preceding opening operation,
• three poles do not close simultaneously,
• there are multi-velocity waves on a three-phase line (zero-sequence
wave speed is slower than positive sequence wave speed),
• etc.

• Approximate classification (from a paper by M. Erche [1]):

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 6

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 7

• Statistical distribution
• Overvoltage is not a single value, but statistically distributed because
overvoltage depends on Vsource at instant of closing,

• three poles do not close simultaneously.

• Closing times
• Many cases must be run with different circuit breaker closing times,
that are either varied
• statistically,
• or systematically.

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 8

• Cumulative frequency distribution


from 100 closing operations on
digital computers and transient
network analyzers (TNA’s).

• 2 % value is often used


to define overvoltage with
one number

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 9

• If insulation can withstand the 2 % overvoltage value, then 98 % of switching


operations will statistically be successful.
• 2 % of switching operations may statistically cause insulator flashover.
• By opening circuit breaker and re-closing again, arc will be extinguished
(self-restoring insulation).

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 10

Voltage/time curves
• Peak instantaneous overvoltage is not enough to say whether flashover
across insulator occurs.
• Waveshape is also determining factor.
• For nice laboratory impulses,
voltage/time curves can be obtained.

• Actual waveshapes are much more


complicated, but standard impulse
waveshapes are needed for laboratory testing,
to meet impulse test standards. t2

• There are flashover models, such as the


integral method, but rarely used: 
t1
v( t )  v0 dt  F

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 11

• Events in re-closing operations


• A fault occurs, usually in one phase.
• The transmission line is de-energized (switched off at one end, then on
other end).
• On unfaulted phases, the current is capacitive when remote end is
already switched off. Therefore, current and voltage are 90 ° out of
phase.
• When current interrupts at current zero, voltage on line is at its
maximum (say, at -1.0 p.u.).
• If circuit breaker re-closes when source voltage is at its opposite
maximum (say, at +1.0 p.u.), there is a voltage change of 2.0 p.u.
• This re-closing operation with “trapped” charge produces the highest
overvoltages.

The University of British Columbia


Closing & Re-closing Operations on Transmission Lines 12

• Events in re-closing operations


• The overvoltage is now 3.0 p.u.

The University of British Columbia


Reduction of Overvoltages in Closing and Re-Closing 13
Operations on Transmission Lines

1. Controlled closing

• Contacts close at instant when voltage is close to zero across the


contacts.

• Requires some prediction of voltage across contacts.

• Prediction is easy with a sinusoidal voltage on the source side, and


• zero voltage on the line side,
• or dc voltage on the line side with trapped charge.

• Prediction is more complicated when re-closing into trapped charge


on a line with shunt reactors.

The University of British Columbia


Reduction of Overvoltages in Closing and Re-Closing 14
Operations on Transmission Lines

1. Controlled closing
• Re-closing into trapped charge on a line with shunt reactors:

• In this case, there


is a beat phenomenon
in voltage across
contacts.

• Resonance between
shunt reactors and
line capacitance
usually somewhat
below 50 or 60 Hz).

The University of British Columbia


Reduction of Overvoltages in Closing and Re-closing 15
Operations on Transmission Lines

2. Closing (pre-insertion) resistors


• Close contact I first, then II after 8 to 10 ms.
• From [1]:

The University of British Columbia


Reduction of Overvoltages in Closing and Re-closing 16
Operations on Transmission Lines
3. Metal oxide surge arresters
• At both ends
• At both ends and middle.
4. Comparison from [2] & [3] (re-closing into trapped charge with shunt reactors):
(staggered closing = close 2nd and 3rd pole 8 and 16 ms later in 60 Hz system)

The University of British Columbia


Computer Models for Closing and Re-closing 17
Operations on Transmission Lines
• Feeding network
• Simplest model is voltage source behind 50 Hz or 60 Hz “short-circuit
impedance”, both for positive sequence and zero sequence.

• This simple model is reasonable


if the feeding network is mostly
inductive, as in the case of
switching from a power plant:

The University of British Columbia


Computer Models for Closing and Re-closing 18
Operations on Transmission Lines

• Feeding network
• If the feeding network is more complicated, CIGRE recommends to
represent the lines in detail one or two substations away from the
substation where switching is done.
• Beyond the one or two substations away, use the short-circuit
impedances to represent the rest.
• Some utilities prefer to represent the large system completely in detail
(Hydro-Quebec?).

The University of British Columbia


Computer Models for Closing and Re-closing 19
Operations on Transmission Lines

• Feeding network as equivalent network


• A simplified version of an equivalent network recommended by CIGRE
uses the short-circuit impedance (resistance RSC and inductance LSC) in
parallel with the surge
impedance of the connected
lines, divided by the number
of lines, RS = Zsurge/n [4]:

• Frequency dependent network equivalent (“FDNE”) creates an R-L-C


network that has more or less the same frequency response as the
complete network, over the frequency range of interest. Starts from
frequency scan of complete network.

The University of British Columbia


Computer Models for Closing and Re-closing 20
Operations on Transmission Lines

• Feeding network as equivalent network


• H. Singh and A. Abur developed a time domain model that reaches back
more in history [5]:

it   g 0vt   g1vt  t   g 2vt  2t   ...


• This can handle travel time delays on transmission lines more easily.

• Both FDNE and the time domain model are developed from the full
system.

• If the equivalent is not used very often, it may be best to work directly
with the full system.

The University of British Columbia


Computer Models for Closing and Re-closing 21
Operations on Transmission Lines
• Circuit breaker
• Normally, the circuit breaker is represented as an ideal switch,
• with closing time specified,
• and closing taking place at the next time step n·Δt ≥ tclose, or in some
versions at n·Δt closest to tclose.
• For slow circuit breakers or circuit switchers, prestrike may have to
be taken into account.
Contacts start to close

Dielectric strength Electric closure


of contacts

t
Aiming point Voltage across
contact
The University of British Columbia
Computer Models for Closing and Re-closing 22
Operations on Transmission Lines
• Transmission line; constant parameter model
• The simplest model is the constant parameter model with constant per-
unit length parameters R’, L’, C’, both in positive sequence and zero
sequence.
• In EMTP version that I am familiar with, R’ is not really distributed,
but lumped at both ends and the middle.

• Total resistance R  R' length must be much less than


characteristic impedance Zchar .
• A truly distributed resistance is a special case of line models with
frequency dependent parameters,
R'  jL'
because Z becomes frequency dependent: Z char 
jC'
The University of British Columbia
Computer Models for Closing and Re-closing 23
Operations on Transmission Lines
• Transmission line; constant parameter model
• This model is often accurate enough for switching studies because
• frequencies are not very high (maybe to 10 kHz),
• positive sequence parameters are more or less constant in that
range.

• Zero seq. parameters are frequency dependent, but if three poles


close simultaneously, then there are no zero sequence surges.
The University of British Columbia
Computer Models for Closing and Re-closing 24
Operations on Transmission Lines
• Transmission line, frequency-dependent parameter models
• Zero sequence parameters are very much frequency dependent.

• This dependence must be taken into account if there are noticeable


zero sequence currents and voltages in the transients.
The University of British Columbia
Computer Models for Closing and Re-closing 25
Operations on Transmission Lines
• Transmission line, frequency-dependent parameter models
• F. Castellanos and J. R. Marti [6] developed a frequency-dependent line
model by lumping R   jLint ernal   in many more places along
lossless line sections, and taking the frequency dependence of these
lumped impedances into account.
• R   jLint ernal   represents the resistances and internal
inductances of the conductors and of earth return.
• For three-phase lines, these impedances are 3*3 matrices.
• It works directly in the phase domain, without having to go through
transformation between phase and mode quantities.
• Well suited for un-transposed lines.
• This approach works for underground cables as well, with minor
modifications [7].
The University of British Columbia
Computer Models for Closing and Re-closing 26
Operations on Transmission Lines
• Transmission line, frequency-dependent parameter models
• Most EMTP models are based on fitting propagation factor e-γl and
characteristic impedance Zchar(ω) in the frequency domain.
• For both positive and zero sequence, find propagation constant
 R'    jL'    jC'
• With approach of J. R. Martí [8], calculate propagation factor A(ω) = e-γl
in frequency domain, & convert to weighting function a(t) in time domain.
• Before, we picked one history term
going back τ. Now we pick more,
using a weighting function a(t).
• For efficiency, recursive
convolution is used to sum
history points with a(t).
The University of British Columbia
Computer Models for Closing and Re-closing 27
Operations on Transmission Lines
• Transmission line, frequency-dependent parameter models
• The characteristic impedance was a pure
shunt resistance Z before. Now it is
frequency- dependent.

• Approximate Z   
R '    jL'  
j C '
with an R-C circuit, as shown at right.
• Straightforward for “balanced” (perfectly
transposed) lines.
• On un-transposed lines, transformation
matrix approximated as real and constant
(not good for double-circuit lines).
The University of British Columbia
Computer Models for Closing and Re-closing 28
Operations on Transmission Lines

• Transmission line, frequency-dependent parameter models


• Much progress has been made, particularly for un-transposed lines,
mostly with phase domain based models:
• T. Noda, N. Nagaoka and A. Ametani [9] developed the ARMA model
(auto-regressive moving average).
• A. Morched, B. Gustavsen and M. Tartibi [10] developed the universal
model with vector fitting.
• B. Gustavsen [11] added many refinements.
• A. B. Fernandes and W. L. A. Neves included effects of shunt
conductance [14, 15].
• Etc.

The University of British Columbia


Computer Models for Closing and Re-closing 29
Operations on Transmission Lines

• Trapped charge
• There are various ways to represent it, depending on EMTP version.
• Simulate the line opening, wait for trapped charge to settle to dc after some
oscillations, then close again. May require long simulation time.

• In version which I use, initial conditions can be read in, which override the ac
steady-state solution values. Example for line from 1 to 2 with phases A, B,
C, read in initial voltages in 1A, 1B, 1C, 2A, 2B, 2C, and read in zero initial
currents in 1A-2A, 1B-2B, 1C-2C.

• In older versions of EMTP, and maybe ATP, you can connect special voltage
sources Vmaxcos(ωt) with a frequency of 0.001 Hz, (Tstart =
5432.0?), to approximate dc (solving directly for dc requires extensive code
changes to handle ωL = 0 and 1/ωC = ).
The University of British Columbia
Examples for Closing and Re-closing Operations on 30
Transmission Lines

• CIGRE test case for energization of 202.8 km long line from inductive
source [12]

• Source impedance (generator + transformer):


Rpos = Rzero = 6.75 Ω; Xpos = Xzero = 127 Ω at 50 Hz.
• Line: Z’pos = 0.04 + j 0.318 Ω/km at 50 Hz, C’pos = 11.86 nF/km;
Z’zero = 0.26 + j 1.015 Ω/km at 50 Hz, C’zero = 7.66 nF/km;
length = 202.8 km. Constant R’, L’, C’ assumed.
• Circuit breaker: closing times, with respect to instant when voltage in
phase A goes through zero from positive to negative;
TCLOSE-A = 3.05 ms, TCLOSE-B = 8.05 ms, TCLOSE-C = 5.55 ms.
The University of British Columbia
Examples for Closing and Re-closing Operations on 31
Transmission Lines
• CIGRE test case for energization of 202.8 km long line from inductive
source [12]

• Overvoltage at receiving end in phase B; computer results (dashed line)


superimposed on family of curves from transient network analyzer
results; time count starts when wave arrives at receiving end
The University of British Columbia
Examples for Closing and Re-closing Operations on 32
Transmission Lines
• CIGRE test case for energization of 202.8 km long line from inductive
source [12]
• This case did not have high frequencies, and constant parameter line
model and single
Π-circuit gave
almost identical
results.
• In general, I would
not recommend
Π-circuits (on
transient network
analyzers, switched
line was typically represented by cascade connection of 10 Π-circuits).
The University of British Columbia
Examples for Closing and Re-closing Operations on 33
Transmission Lines

• CIGRE test case for energization of 202.8 km long line from inductive
source [12]
• Trapped charge can increase or decrease the overvoltages.
• Depends on polarity of trapped
voltage.

Trapped charge Overvoltages


(p.u.) (p.u.)
A B C A B C
0.0 0.0 0.0 2.068 2.166 2.287
0.9 0.8 -0.8 1.368 1.538 1.342
-0.9 -0.8 0.8 3.086 3.172 3.469

The University of British Columbia


Examples for Closing and Re-closing Operations on 34
Transmission Lines

• Energization of 400 km long line through closing resistors [13]


• This was a field test by CEMIG in Brazil.
• Line was switched from a power plant. No other lines were connected.
• Line had a three-phase shunt reactor at sending end.

S
P
Sending Receiving
T end end

S
P
T

The University of British Columbia


Examples for Closing and Re-closing Operations on 35
Transmission Lines
• Energization of 400 km long line through closing resistors [13]
• Modelling: (1) Find positive and zero sequence impedances looking into
power plant (generator with Xd”) , and then model as 3
coupled impedances.
(2) Model shunt reactor as 3 coupled impedances.
(3) Model line with constant parameters.
SOURCE REACTOR
Sending Receiving
[x] end end

[x]
Vs(t)
TRANSMISSION
BREAKER LINE

The University of British Columbia


Examples for Closing and Re-closing Operations on 36
Transmission Lines

• Energization of 400 km long line through closing resistors [13]


• Voltages at sending end.

solid line: field test


dotted line: simulation

The University of British Columbia


Examples for Closing and Re-closing Operations on 37
Transmission Lines
• Energization of 400 km long line through closing resistors [13]
• Voltages at receiving end.

solid line: field test


dotted line: simulation

• Going from constant to frequency-dependent parameter models did


not improve results much.
The University of British Columbia
Lightning Surges 38

• The three main causes of lightning overvoltages:

• Backflashover: Lightning
stroke to tower or ground
wire produces overvoltage
on tower, which leads to
flashover across insulator to
line conductor

• Direct stroke to conductor

• Overvoltages induced into


line from nearby lightning
stroke to ground

The University of British Columbia


Lightning Surges 39

• Simple single-phase study [40].

The University of British Columbia


Lightning Surges 40

• Surge arrester characteristic (old silicon-carbide type with gap)

The University of British Columbia


Lightning Surges 41

• Volt-time characteristic of 220 kV insulator string

The University of British Columbia


Lightning Surges 42

• Results

The University of British Columbia


Surge Function Sources (either Voltage or Current) 43

• Surge function, double exponential: v( t )  Vmax e t


e t

• Used in impulse testing, such as in 1.2/50 μs test.

The University of British Columbia


Surge Function Sources (either Voltage or Current) 44

• Impulse shape for 1.2/50 μs test:

The University of British Columbia


Surge Function Sources (either Voltage or Current) 45

• CIGRÉ surge function, with realistic convex front [41].


v( t )  k1t  k 2t n for 90 % of the front ,and
v( t )  k3e ( t t90 ) /  1  k 4 e ( t t90 ) /  2 for the tail .

The University of British Columbia


Surge Function Sources (either Voltage or Current) 46

• Standler function [42] for convex front and for short tail, such as 8/20 μs
impulse for surge arrester testing, which cannot be represented with
double exponential function n
t  t /  
v( t )  k     e
 

The University of British Columbia


Surge Function Sources (either Voltage or Current) 47

• Heidler function (for convex front; short and long tail) [43]

v( t )  k 
t /  1
n
e t /  

1  t /  
n
1

The University of British Columbia


Surge Function Sources (either Voltage or Current) 48

• Short tail issue discussed by R. B. Standler in [42. p.87] :

• Short tails (relative to front), such as 8/20 μs current impulse for


surge arrester testing, cannot be represented with double
exponential function.
• From my own tests, the shortest tail possible with the double
exponential function, using front time defined through 10 % and
90 % values, is 8/31 μs, with
α = - 69 730
β = - 111 059
Imax = 5.893 for a crest value of Icrest = 1.0.

• The shortest tail possible with the double exponential function, using
front time defined through 30 % and 90 % values, is 8/28 μs.

The University of British Columbia


Other improvements to lightning surge studies 49

• M-phase line models*)


• I prefer lossless high-frequency approximation, with
2h D
Z surge self  60  ln , Z surgemutual  60  ln
r d
• Tower models for surges

• Models for insulator flashovers

• Surge arrester models*) Metal-oxide arresters without gaps nowadays

• Cable models*)

• Transformer models*)
_______________________________________________________
___
*) See IEEE PES Task Force on Data for Modeling System
Transients in: list of references (slide 102)
The University of British Columbia
Lightning Surges 50

• Electricité de France used a surge generator in outdoor and indoor


substations to produce fast surges of the lightning type [39].

The University of British Columbia


Example for Temporary Overvoltages 51

• Energization of a line terminated with transformer or shunt reactor


• Example from M. Erche [1]:

• This case is probably from American Electric Power Corp.


• Caused by resonances between harmonics from transformer
saturation and line capacitance.

The University of British Columbia


Example for Temporary Overvoltages 52

• Energization of a line terminated with transformer or shunt reactor

• Overvoltages can last a long time.

The University of British Columbia


Example for Temporary Overvoltages 53

• Energization of a line terminated with transformer or shunt reactor


• Nonlinear inductances do not keep peak voltages down.
• Part of the voltage around voltage zero is “cut out”, because of 90°
phase shift between flux and voltage.
• VRMS = f(IRMS) must be converted to flux linkage = f (current) (simplified
as 2-slope nonlinearity here)

• This “cut out” produces the harmonics.

The University of British Columbia


Examples for Subsynchronous Resonance 54

• Interaction between mechanical resonances on turbine-generator shaft


system and on electric network side
• Occurs at frequencies below power frequency.
• Most likely to occur on steam turbines, if a transmission line with series
capacitors is switched.
• Unlikely to occur on hydro turbines because “stiffer” with higher
resonance frequencies.
• Can also be caused by control modes in nearby HVDC terminal.

The University of British Columbia


Examples for Subsynchronous Resonance 55

• Interaction between mechanical resonances on turbine-generator shaft


system and on electric network side
• Example from General Electric Co. [17].

The University of British Columbia


Examples for Subsynchronous Resonance 56

• First IEEE benchmark model [18, 20].

The University of British Columbia


Examples for Subsynchronous Resonance 57

• First IEEE benchmark model, torque between generator & exciter.

The University of British Columbia


Examples for Subsynchronous Resonance 58

• Second IEEE
benchmark
model [19, 21].

The University of British Columbia


Examples for Subsynchronous Resonance 59

• Second IEEE benchmark model, shaft between generator and low


pressure steam turbine.

The University of British Columbia


Examples for Subsynchronous Resonance 60

• Frequency-scan for impedance seen from power plant


• Helps to see whether potential for subsynchronous resonance exists.

• Example
from [26]:

• Measured: Short circuit was applied for a few cycles. Change in Δv, Δi
transformed from time domain to frequency domain, to obtain Z(ω).

The University of British Columbia


Example for Single-Line-to-Ground Fault 61
on Transmission Lines
• When a single-line-to-ground fault occurs on a transmission line, there
will be overvoltages on the unfaulted phases (typically 1.6 p.u.)
• Frequency dependent line model is necessary, because there are large
zero sequence currents (Izero = Ipos = Ineg in fault current).
• Example [8]:

The University of British Columbia


Example for Transient Recovery Voltage 62

• When circuit breaker opens to remove the fault, a “transient recovery


voltage” appears across the contacts.
• If rate of rise is too steep or amplitude is too high, circuit breaker may
restrike or re-ignite.
• Important to include stray capacitances of transformers, busbars, etc.
• Initial rate of rise used to be a problem in gas-insulated substations.
• Example
from [13, 25].

• Fault current:

The University of British Columbia


Example for Transient Recovery Voltage 63

• For simulation, one can either simulate complete event (fault initiation,
fault clearing).

• I prefer “cancellation method”, whereby a current is injected across


circuit breaker contacts that cancels the fault current.
• Starts from zero initial conditions.
• Network need only be represented to distance away where total
travel time > tmax (no reflections coming back beyond that point).

The University of British Columbia


Example for Transient Recovery Voltage 64

• Results for fault at 1.2 km from substation:

Solid line = field test; dotted line = simulation.

The University of British Columbia


Example for Transient Recovery Voltage 65

• Initial rate of rise becomes worse if fault farther away from substation
(“short-line fault”
or “kilometric fault”).

• Fault moved from


1.2 km to 8.0 km:

• Fault current
decreases 13.7%.
• Initial rate of rise
increases.

The University of British Columbia


Example for Linear Resonance after Opening a 66
Transmission Line in Parallel with another Line

• Can be studied as a steady-state case at power frequency (60 Hz or 50


Hz)
• Best transmission line model is Π-circuit.
• For complicated transposition schemes, use one Π-circuit for each
section.
• Example from planning study at Bonneville Power Administration:

The University of British Columbia


Example for Linear Resonance after Opening a 67
Transmission Line in Parallel with another Line

• Can be studied as a steady-state case at power frequency (60 Hz or 50


Hz)
• Varying L of shunt reactor showed possibility of
resonance between coupling
capacitance and L.
• L was changed somewhat to avoid
resonance at 60 Hz.
• Resonance is more likely to occur at
harmonic frequencies in such cases.

rated current 132 A

rated inductance 6.09 H


The University of British Columbia
Example for Linear Resonance after Opening a 68
Transmission Line in Parallel with another Line

• A similar case that actually happened on a 345 kV line that was close to
an energized 138 kV line is reported in [31] and [32].

• A case of what might happen on a 765 kV line close to an energized


345 kV line is discussed in [33] for these situations:
• No transpositions on both lines.
• 345 kV line transposed.
• 765 kV line transposed.
• Both lines transposed.

The University of British Columbia


Example 1 for Coupling between 69
Parallel Transmission Lines

• Three circuits in parallel are modelled as five nine-phase Π-circuits


• Coupling is capacitive.
• Steady-
state
case.

The University of British Columbia


Example 1 for Coupling between 70
Parallel Transmission Lines

The University of British Columbia


Example 2 for Coupling between 71
Parallel Transmission Lines

• A double-circuit line is modelled as a cascade connection of twelve


six-phase Π-circuits.

• Coupling is inductive [23].

• Steady-state case.

The University of British Columbia


Example 2 for Coupling between 72
Parallel Transmission Lines

• Results from one of many tests.

The University of British Columbia


Example 3 for Coupling between 73
Parallel Transmission Lines

• From B. C. Hydro and Power Authority [24]

• Steady-state case.

• A large zero sequence voltage was induced into a 138 kV line from
adjacent 500 kV lines.

• It distorted the 2½-element revenue metering schemes of two large


industrial customers supplied from the 138 kV line.

• The two customers were overcharged 3.5% for 15 years.

• They received refunds of Can. $ 4 million.

• The metering scheme was changed.

The University of British Columbia


Capacitor switching 74

• Switching capacitances off


• When switching a capacitor or unloaded transmission line off, the
capacitance remains charged up.

• 2.0 p.u. overvoltage


across contacts half a
cycle after opening.
• Modern SF6 circuit
breakers are less likely
to restrike than older
circuit breakers.

The University of British Columbia


Capacitor switching 75

• Energization of capacitors
• Voltage on capacitor cannot change instantaneously, because it is
determined by integral: t

vt   v0  

1
i  du
C
0
Equivalent circuit for EMTP
studies.

• If voltage is originally zero, bus voltage collapses to zero temporarily


after switching on.
• Creates voltage collapse on bus, as well as high inrush currents into
capacitor bank.

The University of British Columbia


Capacitor switching 76

• Energization of capacitors
• High dv/dt, v, and i may create
problems.
• From Brunke and Schockelt [16]:

The University of British Columbia


Capacitor switching 77

• Energization of capacitors
• Reduction of transients with:
• Closing (pre-insertion) resistors.
• Synchronous (controlled) closing, close to zero voltage across
contacts.
• Current-limiting reactors in series with capacitor.

The University of British Columbia


Capacitor switching 78

• Effect remote from substation where capacitors are switched


• In case shown here, it may have caused phase-to-phase insulation
failure 56 km away in a phase-shifting transformer [22].

• Field test
and
simulation:

The University of British Columbia


Capacitor switching 79

• Back-to back switching of capacitors


• Back-to-back switching: one capacitor bank is energized, and another
capacitor bank next to it is switched on.
• This is worst condition, as seen in previous case.

• I analyzed a failure where an induction motor was switched on, close to


another running induction motor, in a pipeline pumping station.
• Both had capacitors connected for power factor correction.
• When second motor was switched on with vacuum contactor, the
contacts welded together, and contactor could no longer be opened.
• After complicated modelling of induction motors, capacitors, etc., it
turned out to be so simple I could have solved it with a slide rule.

The University of British Columbia


Capacitor switching 80

• Both induction motors were 5 m apart through a cable.


• Both had a 600 kVar capacitor, rated 4.16 kV (line-to-line), 83.3 A.
• One energized capacitor discharged into the capacitor of the motor being
switched on, through whatever inductance is between them.
• Creates a very high inrush current, which welded the contacts in this
case.

The University of British Columbia


Capacitor switching 81

• Simulation:

• A current-limiting reactor would solve the problem.

The University of British Columbia


Capacitor switching 82

• A more likely problem in such cases is overvoltages created by re-


ignitions when opening the vacuum contactor.
• This is caused by tendency of vacuum contactors or circuit breakers to
chop currents (see next slide).
• Surge capacitor on load being switched helps to prevent re-ignition (not
an issue in my case).

The University of British Columbia


Inrush Currents 83

• When an unloaded transformer is energized, high “inrush currents”


may occur that are higher than rated current.

• Cause is the nonlinear magnetizing inductance, with its nonlinear


curve for flux λ = f(i).

• Modern circuit breakers close with high speed. Closing at v = 0 is as


probable as closing at v = Vmax (slow contacts used to prestrike close to
Vmax).

• Since flux is integral of voltage


t
 ( t )   ( 0 )  v  du
0
we get 2 p.u. flux if we close
at v = 0, assuming the residual
flux λ(0) at t = 0 is zero.

The University of British Columbia


Inrush Currents 84

• Residual flux can make the inrush current higher or lower.

• There may also be high-frequency overvoltages in energizing three-


phase banks if the closing times are more than 5 ms apart. This may
have caused damages recently.

The University of British Columbia


Inrush Currents 85

• The inrush current also depends on the tap position of the load tap changer,
and by positioning it conveniently, the inrush currents can be reduced.

• If other transformers are already in operation close to the one being


energized, there is “sympathetic interaction” between them that influences
the inrush currents [35].

• By monitoring the flux in the transformer, and by controlling the closing of the
circuit breaker contacts, it becomes possible to close at just the right
moment to reduce the inrush current to very small values similar to the
steady-state exciting current ([36], [37], [38]).

The University of British Columbia


Inrush Currents 86

• Example from CIGRE Working Group [34]:

The University of British Columbia


Inrush Currents 87

• Example from CIGRE Working Group [34]:

The University of British Columbia


Interruption of Small Inductive Currents 88

• Problem is “current chopping” in circuit breaker opening

• Tendency to “chop” if current is small (because


of falling v(i) characteristic of arc, arc voltage
becomes high when current becomes low).

• Small current is not the problem, but high derivative di/dt.

• Can cause overvoltages


di
L as .
dt
• Maximum overvoltage
factors when interrupting
magnetizing currrent of
high voltage transformers [1].

The University of British Columbia


Interruption of Small Inductive Currents 89

• Can also happen when switching off reactor-loaded transformers.

• Vacuum circuit breakers have tendency to chop even at higher currents.


• For CIGRÉ reports, see [27], [28], [29], [30].

The University of British Columbia


Real-time simulators 90

Playback

A “simple” way to test protective relays is to play back


simulation results through amplifiers. There is no feedback
from relay that may cause other actions.

Real-time simulators
(not my expertise; J. R. Marti works on it in UBC).

Commercially available:
• RTDS (Manitoba, Canada)
• Hypersim (Quebec, Canada)
• OPAL (Quebec, Canada)
• etc.
The University of British Columbia
EMTP-Type Software 91

• BPA EMTP. Bonneville Power Administration may use


ATP now.

• UBC MicroTran. Owned by University of British


Columbia. Website: www.microtran.com.

• DCG/EPRI EMTP. Was developed from BPA EMTP by


Development Coordination Group and EPRI. First
commercialized as EMTP96 by Hydro One in Toronto,
Canada, then as EMTP-RV by TransÉnergie Technologies
(subsidiary of Hydro Quebec), and now by CEA
Technologies Inc. (www.emtp.com).

The University of British Columbia


EMTP-Type Software 92

• ATP (Alternative Transients Program). Free, but requires


a license. EMTP developers cannot get it.

• PSCAD and EMTDC from Manitoba HVDC Research


Centre (www.pscad.com).

• DigSILENT from Germany (www.digsilent.de).

• NETOMAC (Siemens).

• SABER for power electronics.

• SPICE, PSPICE for electronics.

• Etc.
The University of British Columbia
The End 93

Thank you for your attention!


Any Questions?

The University of British Columbia


References 94

[1] K. Ragaller, editor, Surges in High-Voltage Networks. Plenum Press, New York, 1980,
p. 63-97.
[2] K. Froehlich, C. Hoelzl, M. Stanek, A.C. Carvalho, W. Hofbauer, P. Hoegg, B.L. Avent,
D.F. Peelo, J.H. Sawada, “Controlled closing on shunt reactor compensated
transmission lines - Part I: Closing control device development - Part II: Application of
closing control device for high-speed autoreclosing on BC Hydro 500 kV
transmission line”, IEEE Trans. Power Delivery, Vol. 12, No. 2, pp. 734-746, April
1997.
[3] CIGRE Working Group 13.07, “Controlled switching of HVAC circuit breakers –
Benefits and economic aspects”, ELECTRA No. 217, pp. 37-47, Dec. 2004.
[4] CIGRE Working Group 33.02, Guidelines for representation of network elements
when calculating transients. Technical Brochure CE/SC GT/WG 02, 1990.
[5] H. Singh and A. Abur, “Multi-port equivalencing of external systems for simulation of
switching transients”, IEEE Trans. Power Delivery, Vol. 10, No. 1, pp. 374-382, Jan.
1995.
[6] F. Castellanos and J. Martí, “Full frequency-dependent phase domain transmission
line model”, IEEE Trans. Power Syst., Vol. 12, pp. 1331-1339, Aug. 1997.

The University of British Columbia


References 95

[7] Ting-Chung Yu and José R. Martí, “A robust phase-coordinates frequency


dependent underground cable model (zCable) for the EMTP”, IEEE Trans.
Power Delivery, Vol. 18, pp. 189-194, Jan. 2003.
[8] J. R. Marti, “Accurate Modelling of Frequency-Dependent Transmission Lines in
Electromagnetic Transient Simulations”, IEEE Trans. on Power Apparatus and
Systems, vol. PAS 101, No.1, pp. 147–157, January 1982.
[9] T. Noda, N. Nagaoka and A. Ametani, “Phase Domain Modeling of Frequency-
Dependent Transmission Lines by Means of an ARMA Model”, IEEE Trans. Power
Delivery, vol. 11, no. 1, pp. 401-411,January 1996.
[10] A. Morched, B. Gustavsen and M. Tartibi, “A Universal Model for Accurate
Calculation of Electromagnetic Transients on overhead Lines and Underground
Cables”, IEEE Trans. Power Delivery, vol. 14, no. 3, pp. 1032-1038, July 1999.
[11] B. Gustavsen, “Validation of frequency dependent transmission line models”, IEEE
Trans. Power Delivery, vol. 20, no. 2, pp. 925-933, April 2005.
[12] CIGRÉ Working Group 13.05, “The calculation of switching surges. Part I. A
comparison of transient network analyzer results”, ELECTRA No. 19, pp. 67-78,
Nov. 1971.

The University of British Columbia


References 96

[13] C.A.F. Cunha and H.W. Dommel, “Computer Simulation of Field Tests on the 345
kV Jaguara-Taquaril line”, (in Portuguese), Paper BH/GSP/12, Presented at “II
Seminario Nacional de Producao e Transmissao de Energia Eletrica” in Belo
Horizonte, Brazil, 1973 (English translation by D.I. Cameron).
[14] A. B. Fernandes anad W. L. A. Neves, “Phase-domain transmission line models
considering frequrency-dependent transformation matrices”, IEEE Trans. Power
Delivery, vol. 19, pp. 708 - 714, April 2004.
[15] A. B. Fernandes and W. L. A. Neves, “Transmissioin line shunt conductance from
measurements”, IEEE Trans. Power Delivery, vol. 19, pp. 722 - 728, April 2004.
[16] J. H. Brunke and G. G. Schockelt, “Synchronous energization of shunt capacitors
at 230 kV”, presented at 1978 IEEE Power Engineering Society Winter Power
Meeting, New York, N. Y., Jan. 29 – Febr. 3, 1978, paper no. A 78 148-9.
[17] D. H. Baker, “Synchronous machine modeling in EMTP”, IEEE Course Text “Digital
Simulation of Electrical Transient Phenomena”, No. 81 EHO 173-5-PWR, IEEE
Service Center, Piscataway, N.J., 1980.

The University of British Columbia


References 97

[18] IEEE Task Force, "First benchmark model for computer simulation of
subsynchronous resonance", IEEE Trans. Power App. Syst., vol. PAS-96, pp. 1565-
1572, Sept./Oct. 1977.
[19] IEEE Task Force, "Second benchmark model For computer simulation of
subsynchronous resonance", IEEE Trans. Power App. Syst., Vol. PAS-104, pp.
1057-1066, May 1985.
[20] Microtran Factsheet No. 1, “Subsynchronous Resonance - Test Case 1”, April 2003
(available on website www.microtran.com; click on “Tech Spot”).
[21] Microtran Factsheet No. 2, “Subsynchronous Resonance - Test Case 2”,
April 2003 (available on website www.microtran.com; click on “Tech Spot”).
[22] R. M. Hasibar, “Examples of electromagnetic transients studies using the BPA
EMTP”, Course Notes, EMTP Short Course, University of Wisconsin, Madison,
Wisconsin, 1987. Follow-up paper describing transformer failure: R. S. Bayless,
J. D. Selman, D. E. Truax, and W. E. Reid, “Capacitor switching and transformer
transients”, IEEE Trans. Power Delivery, Vol. 3, pp. 349-357, Jan. 1988.
[23] W. G. Peterson, R. M. Hasibar, and D. C. Gentemann, “Grand Coulee – Raver
500 kV double circuit line test July 15-16, 1980”, Div. of System Engineering,
Bonneville Power Administration, Portland, OR, U.S.A.

The University of British Columbia


References 98

[24] M. B. Hughes, “Revenue metering error caused by induced voltage from adjacent
transmission lines”, IEEE Trans. Power Delivery, Vol. 7, pp. 741-745, April 1992.
[25] H. W. Dommel, Case Studies for Electromagnetic Transients. Microtran Power
System Analysis Corp., Vancouver, Canada, Sept. 1993.
[26] M. B. Hughes, R. W. Leonard, and T. G. Martinich, “Measurement of power system
subsynchronous driving point impedance and comparison with computer
simulations”, IEEE Trans. Power App. Syst., Vol. PAS-103, pp. 619 – 630, 1984.
[27]CIGRE Working Group 13.02, "Interruption of Small Inductive Currents, Chapters 1
and 2", ELECTRA No. 72, pp. 73-103, CIGRE, Paris, Oct. 1980.
[28]CIGRE Working Group 13.02, "Interruption of Small Inductive Currents, Chapters 3,
Part A", ELECTRA No. 75, pp. 5-30, CIGRE, Paris, March 1981.
[29]CIGRE Working Group 13.02, "Interruption of Small Inductive Currents, Chapters 4,
Part A", ELECTRA No. 101, pp. 13-39, CIGRE, Paris, July 1985.
[30]CIGRE Working Group 13.02, "Interruption of Small Inductive Currents, Chapters 4:
Reactor Switching: Part B: Limitation of Overvoltages and Testing", ELECTRA
No. 113, pp. 51-74, CIGRE, Paris, July 1987.

The University of British Columbia


References 99

[31] M. J. Pickett, H. L. Manning, and H. N. Van Geem, “Near resonant coupling on EHV
circuits: I – Field investigations”, IEEE Trans. Power App. Syst., Vol. PAS-87, pp.
322-325, Febr. 1968.
[32] M. H. Hesse and D. D. Wilson, “Near resonant coupling on EHV circuits: II –
Methods of analysis”, IEEE Trans. Power App. Syst., Vol. PAS-87, pp. 326-334,
Febr. 1968.
[33] J. J. LaForest, K. W. Priest, A. Ramirez, and H. Nowak, “Resonant voltages on
reactor compensated extra-high-voltage lines”, IEEE Trans. Power App. Syst., Vol.
PAS-91, pp. 2528-2536, Nov. 1972.
[34] B. Holmgrem, R.S. Jenkins, and J. Riubrugent, “Transformer inrush current”, CIGRE
Report 12-03, 1968.
[35] H.S. Bronzeado, P.B. Brogan, and R. Yacamini, “Harmonic analysis of transient
currents during sympathetic interaction”, IEEE Trans. on Power Systems, Vol. 11,
pp. 2051-2056, Nov. 1996.
[36] J. H. Brunke, and K. J. Fröhlich, “Elimination of transformer inrush currents by
controlled switching, Part I”, IEEE Trans. Power Delivery, Vol. 16, pp. 276-280, April
2002.

The University of British Columbia


References 100

[37] J. H. Brunke, and K. J. Fröhlich, “Elimination of transformer inrush currents by


controlled switching, Part II”, IEEE Trans. Power Delivery, Vol. 16, pp. 281-285, April
2002.
[38] E. Portales and A. Mercier, on behalf of CIGRÉ Working Group A3.07, “Controlled
switching of unloaded power transformers”, ELECTRA No. 212, pp. 39-47, Feb.
2004.
[39] M. Rioual, “Measurements and computer simulation of fast transients through indoor
and outdoor substations”, IEEE Trans. Power Delivery, Vol. 5, pp. 117-123, Jan.
1990.
[40] J.R. Marti and H.W. Dommel, "Line models for lightning studies," Trans. Engineering
and Operating Division, Canadian Electrical Association, Vol. 28, 1989, 15 pages.
[41] CIGRÉ Working Group 33.01, Guide to Procedures for Estimating the Lightning
Performance of Transmission Lines. CIGRÉ Techn. Brochure Ref. 63, Paris 1991.
[42] R. B. Standler, Protection of Electronic Circuits for Overvoltages. Wiley-Interscience,
New York, N.Y. 1989.
[43] F. Heidler, "Analytische Blitzstromfunktion zur LEMP-Berechnung (analytical
lightning current function for LEMP calculations)", Paper No. 1.9, ICLP-
Proceedings, Munich 1985.
The University of British Columbia
General References 101

In addition to the specific references quoted before, advice for Electromagnetic


Transient Studies can also be found in the following publications:

IEEE Publications:
J. A. Martinez-Velasco, editor, Computer Analysis of Electric Power System Transients.
IEEE Press, Piscataway, NJ, U.S.A., 1997. Collection of papers on 619 pages.
IEEE PES Special Publication, Modeling and Analysis of System Transients. IEEE
Catalog No. 99TP133-0, IEEE Operations Center, Piscataway, NJ, U.S.A., 1998.
Put together by a Working Group chaired by A.J.F. Keri:
i Modeling and Analysis of System Transients Using Digital Programs - Introduction (A.J.F. Keri, A.M. Gole)
1. Digital Computation of Electromagnetic Transients in Power Systems: Current Status (J.A. Martinez-Velasco)
2. Modeling Guidelines for Power Electronics in Electric Power Engineering Applications (K.K. Sen and L. Tang, H. W. Dommel, K.G. Fehrle,
A.M. Gole, E.W. Gunther, I. Hassan, R. Iravani, A.J.F. Keri, R. Lasseter, J.R. Marti, J.A. Martinez, M.F. McGranaghan, O.B. Nayak, C.
Nwankpa, P.F. Ribeiro)
3. Modeling Guidelines for Low Frequency Transients (R. Iravani, A.K.S. Chandhury, I.D. Hassan, J.A. Martinez, A.S. Morched, B.A. Mork, M.
Parniani, D. Shirmohammadi, R.A. Walling)
4. Modeling Guidelines for Switching Transients ( D.W. Durbak and A.M Gole, E.H. Camm, M. Marz, R.C. Degeneff, R.P. O'Leary,
R. Natarajan, J.A. Martinez-Velasco, Kai-Chung Lee, A. Morched, R. Shanahan, E.R. Pratico, G.C. Thomann, B. Shperling, A.J.F. Keri,
D.A. Woodword, L. Rugeles, V. Rashkes, A. Sarshar)
5. Modeling Guidelines for Fast Front Transients (A.F. Imece, D.W. Durbak, H. Elahi, S. Kolluri, A. Lux, D. Mader, T.E. McDermott,
A. Morched, A.M. Moussa, R. Natarajan, L. Rugeles, E. Tarasiewicz)
6. Modeling Guidelines for Very Fast Transients in Gas Insulated Substations (J.A. Martinez and D. Povh, P. Chowdhuri, R. Iravani,
A.J.F. Keri)
7. Modeling and Analysis of Transient Performance of Protection SystemsUsing Digital Programs (A.K.S. Chaudhary and R.E. Wilson,
M.T. Glinkowski, M. Kezunovic, L. Kojovic, J.A. Martinez)
8. Bibliography on Modeling of System Transients Using Digital Programs (J.A. Martinez-Velasco and T. E. Grebe)

The University of British Columbia


General References 102

IEEE Power Engineering Society, Tutorial on Electro- magnetic Transient Program


Applications to Power System Protection. A. Tziouvaras, Course Coordinator. IEEE
Catalog No. 01TP150.
IEEE PES Task Force on Data for Modeling System Transients, “Parameter
Determination for Modeling System Transients – Part I: Overhead Lines; Part II:
Insulated Cables; Part III: Transformers; Part IV: Rotating Machines; Part V: Surge
Arresters; Part VI: Circuit Breakers; Part VII: Semiconductors”, IEEE Trans. on
Power Systems, Vol. 20, pp. 2038-2094, July 2005.

Books (compiled with help from Dr. Luis Naredo):

H. H. Skilling, Transient Electric Currents. McGraw-Hill Book Company, Inc., 1937.


H. A. Peterson, Transients in Power Systems. Dover Publications, Inc., New York,
1966 (ISBN 0-486-61685-1).
R. Rüdenberg, Electrical Shock Waves in Power Systems. Harvard University Press,
1968.
J. P. Bickford, N. Mullineux, and J. R. Reed. Computation of Power-System
Transients. IEE Monograph Series 18, Peter Peregrinus Ltd., London, UK, 1976.

The University of British Columbia


General References 103

W. D. Humpage, Z-Transform Electromagnetic Transient Analysis in High Voltage


Networks. IEE Power Engineering Series 3, Peter Peregrinus Ltd., London, UK,
1982 (ISBN 0-906048-79-6).
A. Greenwood, Electrical Transients in Power Systems, 2nd edition. John Wiley & Sons,
1992.
P. Chowdhuri, Electromagnetic Transients in Power Systems. Research Studies Press
LTD, 1996; John Wiley and Sons, Inc. (ISBN 0 86380 180 3).
L. van der Sluis, Transients in Power Systems. John Wiley and Sons, LTD, 2001 (ISBN
0 471 48639 6).
N. Watson and J. Arrillaga, Power Systems Electromagnetic Transients Simulation. The
Institution of Electrical Engineers, United Kingdom, 2003.
L.C. Zanetta Jr., Transitórios Eletromagnéticos em Sistemas de Potencia (in
Portuguese). Editora da Universidade de Sao Paulo, Sao Paulo - SP, Brazil, 2003.
Antonio E. A. Araújo and Washington L. A. Neves, Transitórios Eletromagnéticos em
Sistemas de Energia (in Portuguese). Editora de Universidade Federal de Minas
Gerais, Brazil, 2005.
Juan A. Martinez-Velasco, Power System Transients: Parameter Determination. CRC
Press LLC; 1st edition (Oct 2 2009).
The University of British Columbia
General References 104

Antonio Gómez Expósito, Análisis y operación de sistemas de energía eléctrica,


McGraw Hill, Madrid, Spain 2002.
Antonio Gómez-Expósito, Antonio J. Conejo, Claudio Cañizares, Electric Energy
Systems – Analysis and Operation. CRC Press, Boca Raton, Florida, USA, 2009.
H. W. Dommel, EMTP Theory Book, 2nd edition. Microtran Power System Analysis
Corp., Vancouver, Canada, 1992, latest update January 2005 (there is probably an
ATP edition from what I delivered to Bonneville Power Administration in 1986).
J. C. Das, Transients in Electrical Systems; Analysis, Recognition, and Mitigation.
McGraw-Hill, New York, N. Y., U.S.A., 2010.
M. A. Ibrahim, Disturbance Analysis for Power Systems. IEEE Press and John Wiley &
Sons, Hoboken, N. J., USA, 2012. This 718-page book contains many cases of
disturbances that were recorded on digital fault recorders.

The University of British Columbia


June 18, 2012
New Orleans, Louisiana

IEEE PES Short Course


Electromagnetic Transients in Power System and Insulation
Coordination Studies

Insulation Coordination
Studies

Douglas Mader
dmader@bellsouth.net

©Copyright Douglas Mader, all


rights reserved
Insulation Coordination Process

 IEC Standard 60071-1 (2010)

3rd edition published 2006 (amended in 2010)

terms and concepts defined

standard withstand values defined (up to 1200 kV)

standard tests defined

 IEEE Standards C62.82.1 (2010)

©Copyright Douglas Mader, all


rights reserved
Insulation Coordination Process

 IEC Standard 60071-2

published December 1996

application guide for 60071-1

 IEEE Standard 1313.2-1999 (R2005)

©Copyright Douglas Mader, all


rights reserved
Insulation Coordination Process

IMPORTANT TERMS
AND THEIR
RELATIONSHIPS

EMTP-RV

Representative Overvoltage
STRESS

Coordination Factor Performance Criteria


kcd
k cs

Coordination Withstand Voltage

ka
Safety Factors ks

Required Withstand Voltage


STRENGTH

Tables IEC 60071-1

Rated or Standard Insulation Level

Selection of performance
©Copyright criterion leadingMader,
Douglas to the coordination
all
factor is heart of problem
rights reserved
Insulation Coordination

The selection of the dielectric strength of equipment


in relation to the voltages which can appear on the
system for which equipment is intended, taking into
account the service environment and the
characteristics of available protective devices.

©Copyright Douglas Mader, all


rights reserved
System Characterization

Um - The highest voltage for equipment

Range I - Um < 245 kV

Range II - Um > 245 kV

©Copyright Douglas Mader, all


rights reserved
Representative Overvoltage

 For the purposes of insulation coordination,


overvoltages are divided into four classes:

 Temporary Overvoltages (power frequency)

• Phase-to-Earth and Phase-to-Phase


• Longitudinal

©Copyright Douglas Mader, all


rights reserved
Representative Overvoltage

 Next,

 Slow-Front Overvoltages

Phase-to-Earth and Phase-to-Phase

©Copyright Douglas Mader, all


rights reserved
Representative Overvoltage

 And finally…

 Fast-Front Overvoltages

 Combined Overvoltages

Phase-to-Phase
Longitudinal – in phase and out-of-phase

©Copyright Douglas Mader, all


rights reserved
Representative Overvoltage

81\211.pre

©Copyright Douglas Mader, all


Source – IEC 60071-1
rights reserved
Determining Overvoltage Stresses

After discussing the various overvoltage stresses,


their origins, and typical values, we will explore
examples of overvoltage calculation and use a
model 230 kV system and computer simulation to
illustrate

©Copyright Douglas Mader, all


rights reserved
Determining Overvoltage Stresses

 Temporary Overvoltages (TOV)

 Origins

Earth Faults (Phase-Earth)


Load Rejection

Ferroresonance

Harmonic resonance

Transformer Inrush

Machine Self-Excitation

©Copyright Douglas Mader, all


rights reserved
TOV Determines Insulation Design

 Usually, especially for long distance transmission,


load rejection following loss of system synchronism
results in the highest temporary overvoltage.
 Generally desirable to limit 1-second value to 1.5 per

unit of rated rms voltage.


 This is because the maximum TOV determines the

required rating of surge arresters. The switching and


lightning impulse protective level are determined in
turn by the arrester rating. These protective levels in
turn determine the insulation design and cost.
 Can usually be achieved by an optimum mix of series

and shunt compensation including SVC in some


cases, and avoiding low harmonic order resonances
©Copyright Douglas Mader, all
rights reserved
Representation of TOV

A one minute duration power frequency overvoltage:

- a maximum value

- a set of peak values

- a complete statistical distribution

©Copyright Douglas Mader, all


rights reserved
Determining Overvoltage Stresses

Slow-Front Overvoltages (SFOV)

 Origin

Line energization and reclosing


Faults and fault clearing

Load rejection

Switching of inductive and capacitive currents

Slow front lightning overvoltages (of minor importance)

Important particularly in range II

©Copyright Douglas Mader, all


rights reserved
Representation of SFOV

Surge Arrester Protection


- deterministic method
- truncation values if Ups > Ut
- Ups if Ups < Ut

No Surge Arresters

- deterministic method
- truncation values
- statistical method

©Copyright Douglas Mader, all


rights reserved
Statistical Representation of SFOV

 (no surge arrester limitation)

Usually characterized by a statistical (Weibull or


Gaussian) probability distribution of standard switching
impulses (250/2500 us) with the following parameters:

©Copyright Douglas Mader, all


rights reserved
Statistical Representation of SFOV

 Distribution Definition

Ue2 - overvoltage phase-to-earth in per unit


having 2% probability of being exceeded
Up2 - same as Ue2 but phase-phase
Se - standard deviation of the distribution
phase-earth in per unit
Sp - standard deviation of the distribution
phase-phase in per unit
Ut = U50 + 3S (truncation)(Weibull)

©Copyright Douglas Mader, all


rights reserved
SFOV Studies

 Per Unit Base

2
Um  phase-to-earth peak
3

©Copyright Douglas Mader, all


rights reserved
Determining Overvoltage Stresses

Fast-front Overvoltages (Lightning)

a) Begins with lightning current probability distribution


and front time probability distribution and a spacial
distribution of stroke termination points.

b) Because of separation effects, each piece of


equipment has a different representative
overvoltage which is a statistical quantity.

©Copyright Douglas Mader, all


rights reserved
Selection of Surge Arresters

TOV1
 - 1 second temporary overvoltage capability
- basis of application (ANSI)

- IEC uses 10 seconds

- gives one point on the "No-Prior-Energy"


curve

©Copyright Douglas Mader, all


rights reserved
Selection of Surge Arresters

 Determine TOV1 (10)

- use computer simulation to determine TOV envelope


and arrester energy for such origins as

- load rejection
(model complete machine and controls)
- transformer inrush
- ferroresonance
- dynamic overvoltage associated with HVDC
- determine earth fault factor from X1 X0 R0

©Copyright Douglas Mader, all


rights reserved
Selection of Surge Arresters

©Copyright Douglas Mader, all


rights reserved
Coordination Withstand Voltage

 Performance criteria, coordination factor, and the


selection of the Coordination Withstand Voltage

UCW = kC · Urp kcd  Deterministic


kcs  Statistical

 For temporary overvoltage (Power Frequency)


 Kcd = 1.0.

- main considerations are pollution and


extreme wind.

©Copyright Douglas Mader, all


rights reserved
UCW for SFOV with Surge
Arrester Limitation

For Equipment protected by surge arresters

use deterministic or conventional method


select arrester rating by temporary overvoltage


for slow front overvoltages


- by EMTP-RV studies, determine protective level


Ups at equipment

©Copyright Douglas Mader, all


rights reserved
UCW for SFOV with Surge
Arrester Limitation
 For Slow Front Overvoltages

If Ups < 0.7 Ue2  kcd = 1.1 for phase-earth


or if Ups < 0.5 Ue2  kcd = 1.1 phase-phase

If 0.7 < Ups/ Ue2  1.2 use graph (p - e)


If 0.5 < Ups/ Ue2  0.9 use graph (p - p)

This adjustment to kcd takes into account the skewing of


the probability distribution due to the control by the
arrester.

Note also that where the degree of limitation of Ue2 by


arresters is large, the limited values of Up2 can approach
2xUps. ©Copyright Douglas Mader, all
rights reserved
KCD for SFOV Limited by SA

81\211.pre

©Copyright Douglas Mader, all


Source – IEC 60071-2
rights reserved
Self-Restoring Insulation

Application of Weibull Distribution to "m"


Insulations m 1+X
5
4

Pm = 1 - (1 - P)m yielding Pm(X) = 1 - 0.5

and

Zm = Z/m1/5

and
U50m = U50 - 4(Z - Zm ) = U50 - 4Z (1 - 1/m1/5)

©Copyright Douglas Mader, all


rights reserved
Self-Restoring Insulation

81\211.pre

©Copyright Douglas Mader, all


Source – IEC 60071-2 rights reserved
Self-Restoring Insulation
Example: - 100 insulators
- For each, U50 = 1600 kV
Z = 100 kV

Then: - Zm=100 / (100)1/5 = 39.8 kV

and - U50m= U50 - 4 (Z - Zm) = 1600 - 4 x (100 - 39.8)

= 1359.2 kV
P(u)% 50 16 10 2 1 0.1 0

U (kV) 1600 1500 1475 1400 1370 1310 1200


Um(kV) 1359 1319 1308 1280 1268 1244 1200

©Copyright Douglas Mader, all


rights reserved
SFOV UCW for Unprotected Equipment

 i.e. No Surge Arrester Protection

applies in particular to slow-front overvoltages

Usually consists of self-restoring insulation

kC determined by a risk-of-failure calculation


Ut
R=  f(U) P(U) dU
U50-4z
Computer calculation (laborious)

©Copyright Douglas Mader, all


rights reserved
SFOV UCW for Unprotected Equipment

81\211.pre

Source – IEC 60071-2


©Copyright Douglas Mader, all
rights reserved
Simplified Statistical Method for SFOV

 Simplified by relating risk-of-failure to the ratio of the voltages


corresponding to two reference probabilities.

 the statistical withstand voltage

U90 = U50 - 1.3Z

 the 2% overvoltage U2

 KCS = U90 /U2

statistical coordination factor

 Choice of KCS is the key performance criteria.

©Copyright Douglas Mader, all


rights reserved
Simplified Statistical Method for SFOV

©Copyright Douglas Mader, all


rights reserved Source – IEC 60071-2
Simplified Statistical Method for SFOV

 Example  100 insulators


Let Ue2 1200 kV Se = 100kV

 For one insulator


U90(10% F.O. prob.) = 1475 kV
KCS = 1475 = 1.23
1200
R = 10-5

 For 100 insulators


U90 = 1308 kV
KCS = 1308 = 1.09
1200
R = 10-3 ©Copyright Douglas Mader, all
rights reserved
UCW for FFOV with Surge Arrester Limitation

Fast Front Overvoltages

 For fast-front overvoltages kcd = 1.0 and the


protective level at the equipment takes into
account separation effects, which can be quite
large at higher values of Um

©Copyright Douglas Mader, all


rights reserved
UCW with Surge Arrester Limitation

 For simple arrangements of equipment with close-by


arresters and terminal capacitance less than a few
hundred picofarads, we would expect the protective
level at the equipment to approach:

Ucw = Up + 2ST


Up = arrester lightning impulse protective level
S = steepness in kV/s
T = equivalent time in microseconds
= + a1 + a 2 + 
c
c = light speed in m/s (~ 300)
©Copyright Douglas Mader, all
rights reserved
Effect of Separation Distance

Source – IEC 60071-2

©Copyright Douglas Mader, all


rights reserved
Safety and Correction Factors
 Correctionand safety factors are applied to
obtain the Required Withstand Voltage

 Altitude Correction (IEC 721-2-3 (1990))

Applied to external (atmosphere-exposed)


insulation

ka = bm H m

b = e(H/8150)
} ka = e
8150

H = altitude in meters
©Copyright Douglas Mader, all
rights reserved
Exponent ‘m’ for
Altitude Correction Factor

For switching-impulse required withstand:

m is determined from the figure as a function of


UCW and the insulation configuration

©Copyright Douglas Mader, all


rights reserved
Exponent ‘m’ for
Altitude Correction Factor

81\211.pre

©Copyright Douglas Mader, all


Source – IEC 60071-2
rights reserved
Exponent ‘m’ for
Altitude Correction Factor

For lightning impulse required withstand and short-


duration power-frequency withstand voltages of air gaps:

m
 = 1

For polluted insulator continuous power frequency


withstand:

m
 = 0.5 - 0.8 (standard units - fog units)

©Copyright Douglas Mader, all


rights reserved
Mixed Insulation at High Altitudes

 If ka >1.05 the required withstand voltage of


external insulation can be greater than that for the
internal.

Example transformer winding versus bushings


Either:

- over design the internal insulation


- external insulation separately tested on a
dummy
- air clearances equal to or greater than tables
A1 - A3.

©Copyright Douglas Mader, all


rights reserved
Required Withstand Voltage
 Safety Factors

aging
unknowns

tolerances - assembly, quality control, installation

test dispersion

External Insulation kS= 1.05

Internal Insulation kS = 1.15

Then URW = ka kS UCW

* may be up to 1.2 or more for GIS in Range II


©Copyright Douglas Mader, all
rights reserved
Conversion of URW to
Standard Test Voltages

 In range I, we specify and test

short-duration power frequency withstand


lightning impulse withstand


 In range I, we must convert the required switching


impulse withstand voltage into an equivalent short-
duration power-frequency withstand voltage or
lightning impulse withstand voltage.

Table 2 of IEC 60071-2 Section 5.2 provides


conversion factors.
©Copyright Douglas Mader, all
rights reserved
Conversion of URW to
Standard Test Voltages

81\211.pre

Source – IEC 60071-2

©Copyright Douglas Mader, all


rights reserved
Conversion of URW to
Standard Test Voltages

 In range II, we specify

switching impulse withstand voltage phase-earth and


phase-phase

 lightning impulse withstand voltage

We must convert the required power frequency


withstand voltages phase-earth and phase-phase to
an equivalent switching impulse withstand voltage.

Table 3 of IEC 60071-2 Section 5.2 provides


conversion factors.
©Copyright Douglas Mader, all
rights reserved
Conversion of URW to
Standard Test Voltages

81\211.pre

Source – IEC 60071-2


©Copyright Douglas Mader, all
rights reserved
Rated/Standard Insulation Level

 Select a set of standard insulation values closest to


each of the values of URW for the various
overvoltage classifications.

 Where possible, design the insulation to


correspond to a Standard Insulation Level which is
defined as a set of rated insulation levels related as
a group to Um and corresponding to one line in the
IEC tables.

©Copyright Douglas Mader, all


rights reserved
Source – IEC 60071-1

©Copyright Douglas Mader, all


rights reserved
Source – IEC 60071-1

©Copyright Douglas Mader, all


rights reserved
June 18, 2012
New Orleans, Louisiana

Electromagnetic Transients in Power System and Insulation


Coordination Studies

Study Examples Using EMTP

Douglas Mader
dmader@bellsouth.net

1
Circuit Breakers and
Switches
EMTP Models for Circuit Breakers

 Ideal Switch

 Acts as an ideal Switch:

Impedance = 0 before current zero


Impedance =  after current zero

 Assumes - Prospective currents and voltages are


unaffected by the interruption process
itself
 Has primary use in breaker specification and

overvoltage studies 2
Circuit Breakers and
Switches

EMTP Models for Circuit Breakers

 Simple time controlled


 Closes at t ≥ t
close
 Opens at t ≥ t
open and current < Imargin or at the next
zero crossing if Imargin = 0

 Heuristic (Statistical and Systematic)


Models the externally-observed circuit breaker

operation - pole spread, restrike, reignition, prestrike


Useful for overvoltage studies (statistical overvoltage

distribution)
Interrupts also as an ideal switch

3
Circuit Breakers and
Switches

Ideal Switch – Random/Systematic

 By combining the statistical distribution of overvoltages


with the statistical properties of breakdown strength of
insulation, it becomes possible to determine a risk of
flashover or insulation failure

 Let Pd (U) be the known probability of flashover for a


known overvoltage U. and let p(U) be the probability of
occurrence of an overvoltage of magnitude U. The overall
risk of failure is then:

R= Pd(U) p(U) dU
- 4
Circuit Breakers and
Switches

Point on Wave delay

 Toffset = 1./f ((1-X) Dmin + X Dmax)


360.

 X is a random uniformly distributed number between 0 and 1

 Dmin and Dmax are the min. and max. angles


respectively of a window in a sinusoidal waveform of
frequency f

5
Circuit Breakers and
Switches

Typical Parameter Values and Practical Advice

 Typical Pole Spans 6-10 ms (3.5-5.5 for newer spring-


hydraulic mechanisms
Standard Deviation 1-1.67 ms (.6-.8 ms)
Mean Closing Time 16-20 ms

 Higher statistical overvoltages associated with larger pole


span

 Make sure minimum absolute close time after random


calculation is > 0.0

 Typically 200 shots used 6


If you have a fast machine use more for better accuracy
Circuit Breakers and
Switches

Typical Parameter Values and Practical Advice

 Select the ideal switch output tab option to get the


actual switching times of the worst case and re-run it
to observe the waveshape

 For point on wave use uniform law

 Use Gaussian law for closing times at ±3 std dev

7
Circuit Breakers and
Switches

Pre-insertion Resistors in Breakers

 Common method of reducing line switching or capacitor


switching overvoltages

 Typical Insertion Time 7-10 ms

Must be no less than twice the line travel time

 Simulated by an independent statistical auxiliary contact


in series with the resistor and a statistical main shorting
contact dependent on the auxiliary contact with mean
closing time 7-10 ms. The standard deviation of the
auxilliary contact is typically half that of the main contact.
8
Circuit Breakers and
Switches

Preinsertion Resistors

A R

A. Auxilliary Contact
B. Main Contact
R. Resistor
9
Circuit Breakers and
Switches
Test System for Lab Exercises
x"=.0546
5
4 50MVA
200
0.9PF
11kV 222MVA 1
10% 61MVAC
200
10
2 9.1%
220 kV 10% 193km
400MVA
16km 200 MVA
9.1% 0.9PF
200MVA 500MVA
7 145km 24km 12 13 200MVA

220kV 220kV 66kV 50MVAC


9.1% 11kV
11
180
9.1%
x"=.02186 500MVA 100MVA 11kV X"=.08744
6
500 220kV

11kV 220kV
97km

x"=.1421 8
290km
50 230kV SYSTEM
50MVA
9.1% 290km
GENERAL FEATURES
200 10
MVA 220kV
DRAFT\DJM\PAKGEN.PRE

0.9PF
Circuit Breakers and
Switches

Example

 Set up a statistical three phase switch to leave a


trapped charge on line 1-2 by opening and another
to reclose the line against trapped charge. (Make a
subcircuit). Obtain the overvoltage distribution at the
BUS2 end.

 Add a pre-insertion resistor to the reclosing breaker


and repeat.

 Capacitor Switching 11
Circuit Breakers and
Switches

Transient Recovery Voltage

 Breakers rated in terms of magnitude and rate of rise

 ANSI and IEC standards have now been harmonized


with IEC 62271-100, but studies for older ANSI
breakers need to respect the applicable edition of
C37

 Indoor and Outdoor breakers distinguished

 Prospective TRV envelope is best simulated by


EMTP ideal switch 12
Circuit Breakers and
Switches
Transient Recovery Voltage

 IEC Rating method is also divided into two groups at Um=100


kV, the same as ANSI.

 The 2-parameter test characteristic applies to Class S1 and S2


breakers rated at or below 100 kV and the parameter values are
obtained from Tables 1 and 2 of 62271-100:

 Uc = is a function of Um Uc

 t3 is function of Um
 t3 = T2/1.138
 td,t',u' allow for the
U'
effect of bus/breaker
capacitance
0 td t' t3
13
Circuit Breakers and
Switches

Transient recovery Voltage

 Above 100 kV, the 4-parameter test characteristic applies and


parameters are obtained from Tables 3, 4, and 5 of 62271-100:

 U1 = 0.8 Uc
 t1 is function of Um Uc

 t2 = 3t1
U1

U'

0 td t' t1 t2 14
Circuit Breakers and
Switches
Simple Circuit for Overdamped TRV

300 mH 100 km

E cos ωt
~

15
Circuit Breakers and
Switches
Simple Circuit for Underdamped TRV
With With Short Line Fault

3 mH 1 km

E cos ωt
~ .25 uF

16
Circuit Breakers and
Switches

Transient Recovery Voltage

 Important for Initial rate of rise to represent the bus


side capacitances. Distributed parameter lines may
be necessary for extensive buswork

 Breaker capability curve can be generated in Controls


and plotted against the actual TRV

 Entergy actual example

17
Lightning Overvoltages
Modeling and Analysis

Lightning Overvoltages

 Three causes - all associated with overhead lines


1. Backflashover
2. Direct Strokes to Phase (shielding failure)
3. Induced (nearby strokes to ground)

 Direct strokes to station are usually ignored because


perfect shielding via masts or wires is assumed.

 Studies focus primarily on line performance


(backflashover and shielding failure events) and
arrester application
© Douglas J. Mader 18
Lightning Overvoltages
Modeling and Analysis
 Backflashover

 Above typically about 50 kA strokes to towers or


overhead ground wires can produce voltages on the
tower high enough to cause flashover of the line
insulation.

 Steep wavefront surge imposed on the affected phase


conductor which is attenuated in steepness and
magnitude through propagation by earth resistance and
corona

 Reflections from adjacent towers and the footing act to


limit the overvoltage peak as does coupling to phase
conductors. © Douglas J. Mader 19
Lightning Overvoltages
Modeling and Analysis

Shielding Failure
 Occur when a flash misses the shield wires or tower

and terminates directly on a phase conductor.


 Prospective overvoltage at stricken point is:

I Zs
V = + V60 (t)
2
V60 = instantaneous power frequency voltage
Zs = conductor surge impedance

 Most involve strokes of a few kA but can involve


subsequent strokes of greater magnitude (<80 kA)
and steepness than first stroke but with shorter tail
© Douglas J. Mader 20
Lightning Overvoltages
Modeling and Analysis

© Douglas J. Mader 21
Lightning Overvoltages
Modeling and Analysis

© Douglas J. Mader 22
Lightning Overvoltages
Modeling and Analysis

Shielding Failure

IEEE 1243-1997 (R2008)

 S = 10•I.65 (m, kA) (Love)

 I = 0.029S1.54 (kA, m)

 ß = 0.36 + .168 In (43 - [hG+ hφ)]/2)

(hG+ h φ) /2 < 40 m

 ß = .55S h > 40 m
© Douglas J. Mader 23
Lightning Overvoltages
Modeling and Analysis

Important Parameters (CIGRE)

lI - Initial Crest Current


l
F - Final Crest Current
T - Tail Duration
h
t
d30= T30 /.6 = Rise time from 30% of peak to 90% of peak of lI
S
m = maximum steepness (at crest of lI )

 All parameters are generally approximated by log-normal


distributions

 Lightning stroke has a concave wavefront

© Douglas J. Mader 24
Lightning Overvoltages
Modeling and Analysis

T10 T30
T[us]
ITrig
Tan 10
I10

TANG
I30 (Sm)
Definition of front parameters for a
lightning current impulse of negative
polarity
I[ka]

I90

II
PEAK
IF
© Douglas J. Mader 25
Lightning Overvoltages
Modeling and Analysis

• CIGRE Distribution for Key Parameters

© Douglas J. Mader 26
Lightning Overvoltages
Modeling and Analysis
Modeling Guidelines

 Stroke Modelling

 Modelled generally as an ideal current source.

 Stroke Surge Impedance is an inverse function of


peak current (up to ~35 - 40kA)

Zst = 6897 – 158.45IF (Mazur & Ruhnke 2001)


(3000 ohms at 25 kA)

 Double exponential type models inadequate.


© Douglas J. Mader 27
Lightning Overvoltages
Modeling and Analysis
Modeling Guidelines

 Stroke Modelling

 Simulation of concave wavefront is important for


lightning protection.
Peak current amplitude
Maximum steepness at 90% of current peak.

Average steepness between 30% and 90% of

current peak.

 Tail is important
Tail duration
 (energy).
© Douglas J. Mader 28
Lightning Overvoltages
Modeling and Analysis

Concave Front
l = At + Btn
where t = time in µs
n = 1 + 2(SN -1) (2 + 1/SN)
SN = Smtf / l
tf = front time
= td30

1 l
A = 0.9 n - Sm
n -1 tn

B = 1 [Sm tn - 0.9 l ]
tnn (n-1)

tn = 0.6 tf 3SN2 /(1 + SN2 )

© Douglas J. Mader 29
Lightning Overvoltages
Modeling and Analysis

Tail
l = l1e-(t-tn)/t1 - l2 e-(t-tn)/t2
th = time to half value
t1 = (th - tn )/ ln 2
t2 = 0.1 l / Sm

l1 = t1 t2 Sm + 0.9 l
t1 -t2 t2

l2 = t1 t2 Sm + 0.9 l
t1 -t2 t1

© Douglas J. Mader 30
Lightning Overvoltages
Modeling and Analysis
Approximations
 IEEE (5 kA < l < 200 kA)

1
P
l
=
1 +
l 2.6 log I = 0.30
31

P =
1
log S= 0.20
S S 4
1 +
24

 Ramp function front at Sm to lpeak


 Ramp function tail from I
peak through th

Adequate for studies and can easily be used in hand


calculations © Douglas J. Mader 31
Lightning Overvoltages
Modeling and Analysis

For steel towers model tower as a distributed single


phase lossless line with surge impedance: (Chisholm
1985)
Ravg
Zavg = 60 In cot ( (
1 tan -1
2
h1+ h2 ))
where
r1 h2 + r2 (h1 + h2) + r3 h1
Ravg =
r1 = Tower Top Radius (m) h1 + h 2
r2 = Tower Midsection Radius (m)
r3 = Tower Base Radius (m)
h1 = Height from Base to Midsection (m)
h2 = Height from Midsection to Top (m)
(based on surge impedance of conical sections)
© Douglas J. Mader 32
Lightning Overvoltages
Modeling and Analysis

Tower Surge Impedance

 Propagation velocity in towers can vary from 70%


of light speed in broad cross-section lattice steel
towers with many cross arms to just under lighjt
speed in tall towers with narrow cross section

 Surge impedance of guy wires should be evaluated


separately and placed in parallel

 Surge impedance of a vertical wire of length h/2 is


about 10% more than that of a horizontal wire at
h/2 © Douglas J. Mader 33
Lightning Overvoltages
Modeling and Analysis

Earth Electrode Model

 Model the footing resistance and transient response



Ro = 2 g ln (11.838g2/A) (Chisholm 2001)

Ro = low current earth resistance (Ω)

g = geometric sum of length + width + depth (m)

ρ = resistivity of earth (-m)

A = total surface area of electrode (m2)

© Douglas J. Mader 34
Lightning Overvoltages
Modeling and Analysis

Earth Electrode Model

 Add a contact resistance correction term



Rc = L (Chisholm 2001)

L = total length of all the wires in the grid

 For concrete piers use the area of the concrete in


the previous equation and the contact resistance
based on the resistivity of concrete (70-250 ohm-
meters)
© Douglas J. Mader 35
Lightning Overvoltages
Modeling and Analysis
Line Insulators

 Represent by flashover in parallel with capacitance


 Capacitance for suspension units ~ 80 pF/unit

 Simulate flashover characteristic by built in leader

development, equal area integration models or


 Volt-time curve models built using controls

CIGRE volt-time curve:


V =
[ 400 + 710
]
d (kV)
t.75
d = gap in metres

0.2 µs < t < 16 µs


© Douglas J. Mader 36
Lightning Overvoltages
Modeling and Analysis
Line Insulators

 Leader Development Model:

tc = time to breakdown = ti + ts + tl
ti = corona inception time (assumed=0)
ts = streamer propagation time

1/ts = 1.25(E/E50)-0.95 (1/usec)

E = max gradient in gap before breakdown (kV/m)


E50 = average gradient at CFO

© Douglas J. Mader 37
Lightning Overvoltages
Modeling and Analysis
Line Insulators

 Leader Development Model:


For tl

dL/dt = K V(t)(V(t)/(g-L) - Eo) (kV,m)

V(t) = voltage across the gap in kV


L = leader length in m
g = gap length in m

© Douglas J. Mader 38
Lightning Overvoltages
Modeling and Analysis
Line Insulators

 Leader Development Model:

Gap Config. Polarity K(m2/kV2sec) Eo(kV/m)

Air Gaps,Post + 0.8 600


Insulators - 1.0 670

Cap and Pin + 1.2 520


Insulators - 1.3 600

© Douglas J. Mader 39
Lightning Overvoltages
Modeling and Analysis
Line Insulators

Integration Model (d < 2m):

DE =to ʃ t(UAB(t) - Uo)k dt UAB > Uo

When the area reaches DE, at t=tf , flashover is


initiated

Voltage Uo corresponds approximately to the voltage


defining the dielectric withstand of an air gap subjected
to a conventional lightning impulse of +ve polarity
© Douglas J. Mader 40
Lightning Overvoltages
Modeling and Analysis
Corona Attenuation and Distortion

 Important for proper calculation of lightning


overvoltages coming into a station from an overhead
line

 Complex phenomena - difficult to simulate accurately


over a wide range of line physical parameters

 Affects mainly the wavefront by introducing a time


delay to the peak and a reduction in the steepness
which become more pronounced with increasing
propagation distance
© Douglas J. Mader 41
Lightning Overvoltages
Modeling and Analysis

Corona Attenuation and Distortion

 Few laboratory measurements available to provide


data (Maruvada, et al IEEE 1977) - cage data only

 Most models start with the assumption of a cylinder


surrounding the conductor in corona. The cylinder
represents the boundary of the ionization (space
charge, attachment and recombination processes)

© Douglas J. Mader 42
Lightning Overvoltages
Modeling and Analysis

Corona Attenuation and Distortion

 The corona onset or inception voltage is constant for a


given conductor configuration, however time lags
associated with the electron avalanche process can
delay the onset for faster wavefronts such as lightning

 The total capacitance within the region of ionization


increases dynamically as a result of particle
redistribution

© Douglas J. Mader 43
Lightning Overvoltages
Modeling and Analysis

© Douglas J. Mader 44
Lightning Overvoltages
Modeling and Analysis
Corona Attenuation and Distortion

 Time domain models must be distributed at discrete


intervals between short (50 m or less) sections of
distributed line.

 Can be costly in terms of computer resources (time


and memory).

 A number of models similar in approach have been


prepared (Suliciu, Gary, etc.).

 EMTP-RV uses a quasi three-phase Suliciu model


© Douglas J. Mader 45
Lightning Overvoltages
Modeling and Analysis
Substation Components

 Model substation busbar sections as untransposed distributed


parameter lines between bus supports but if distance between
supports < 3m, combine sections

 Between each section lump the bus insulator and support structure
capacitance - for cap& pin:
123kV - 80 pF

400kV - 120 pF less (10-50) for post/NCI


765kV - 150 pF

 Make sure sections accurately locate major equipment

© Douglas J. Mader 46
Lightning Overvoltages
Modeling and Analysis
 Model large lumped capacitances such as

CVT = 4 - 10 nF, the higher values with lower


voltages)
Magnetic PT ~550 pF

CT = 150-1000 pF with increasing voltage

Dead Tank Breaker ~50pf each side to ground

6-10 pF longitudinal
Live Tank Breaker 5pF to ground, 10pF longitudinal

Plus any grading or TRV capacitors

Bus support structures - three phases 100 ohm Zs

- one phase 300 ohm Zs


- ground resistance 0.1 ohm
© Douglas J. Mader 47
Lightning Overvoltages
Modeling and Analysis
 Cables and GIS:

 Be careful to model short cables and GIS bus section


lengths accurately and watch out for voltage buildup
(standing waves) if any cables/bus sections can be
fed single-ended

Watch out for voltages between sheath and ground.


These are usually the most critical and should be
modeled using an untransposed cable with
transformation matrix evaluated at high frequency.
Any cross bonding and sheath ground
resistance/arrester protection must be included.
© Douglas J. Mader 48
Lightning Overvoltages
Modeling and Analysis
 Modeling Guidelines for GIS

 Bus sections are lossless DP lines with Z typically


50-60 ohms and propagation velocity about 95% of
light speed.

 Accurate overall length is important, however


rigorous spacer to spacer resolution is only
important for VFT analysis. For lightning, try to
avoid representing individual bus sections of less
than 3 metres as DP lines. Divide and lump the
spacer capacitance at each end of each bus
section.
© Douglas J. Mader 49
Lightning Overvoltages
Modeling and Analysis
 Modeling Guidelines for GIS

 spacers - ~ 20 pF
magnetic PT - ~ 100 - 300 pF (400-800 kV)

closed circuit breaker - DP line of the length of the

breaker, velocity of .95c and Z calculated from


average diameter of breaker conducting elements
from end to end. Add lumped phase-earth caps.
Open circuit breaker - same but divided at open

contact and grading capacitors across opening.


Model closing resistor as separate breaker.
Disconnectors - include length as DP line

add shunt cap of ~25-50 pF


© Douglas J. Mader 50
Lightning Overvoltages
Modeling and Analysis
 Modeling Guidelines for GIS

surge arrester capacitance ~ 100-200 pF


cable terminals ~ 60-80 pF plus length as DP line

SF6-Oil bushing ~ gas filled ~20-40 pF

~ capacitive ~ 100-300 pF
ground switch ~ 20-40 pF

Elbow - additional ~ 20-40 pF

Bus end - additional 3-5 PF for spherical shield

© Douglas J. Mader 51
Lightning Overvoltages
Modeling and Analysis
 Power transformers

 If possible use wideband transformer model esp. for


surge transfer studies where winding ratio > 10:1, if
not use the L-C matrix unless you do parametric
study

 As a minimum, model transformers as input


capacitance including bushings [typical HV-G values
of large units are 4 - 40 nF (shell) 1 - 20 nF (core)]
in shunt with surge impedance of about 5000 ohms

 Consider possible open breaker conditions and lines


out of service © Douglas J. Mader 52
Lightning Overvoltages
Modeling and Analysis

IEEE SPDC WG 3.4.11 Model


(Station Class or IEC Class 4-5)

© Douglas J. Mader 53
Lightning Overvoltages
Modeling and Analysis

© Douglas J. Mader 54
Lightning Overvoltages
Modeling and Analysis

© Douglas J. Mader 55

Вам также может понравиться