STAIRCASE MONITORING - SUMMARY

TOWER No. Repairs/Level No. of Stairs


Rectified/Level Percentage %

TOWER A 101 0 0.00

TOWER B 103 0 0.00

TOWER C 97 0 0.00

TOWER D 116 0 0.00

TOTAL= 417 0 0

PREPARED BY:
STAIRCASE-1 STATUS STAI
Surface Preparation A-Approved As D-Needs
SN. LEVEL CASTING
Noted Rectification
CASTING
DATE Planned Actual DATE
OE MZP
Start Completed
1 5th to 4th Basement 17-Feb-17 15-Jan-19

2 4th to 3rd Basement 6-Mar-17 6-Mar-17

3 3rd to 2nd Basement 8-Mar-17 8-Mar-17

4 2nd to 1st Basement 27-Mar-17 12-Apr-17

1st Basement to
5 20-Apr-17 28-Oct-17
Ground Floor
6 Ground to 1st Floor 4-Dec-17 30-Nov-17

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

STAIRCASE-2 STATUS STAIRCASE-3 STATUS


Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
Planned Actual DATE Planned Actual
OE MZP OE
Start Completed Start Completed
13-Feb-17

8-Mar-17

8-Apr-17

29-Apr-17

31-Oct-17

31-Oct-17

PREPARED BY:
STATUS STAIRCASE-4 STATUS
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Actual
MZP Planned Start OE MZP
Completed
13-Mar-17

27-Aug-17

28-Dec-17

8-Feb-18

25-Mar-18

PREPARED BY:
1st Floor to Technical
7 11-Dec-17 6-Feb-18
Floor
Technical Floor to 2nd
8 21-Mar-18 18-Jan-18
Floor
9 2nd to 3rd Floor 25-Mar-18 15-Mar-18

10 3rd to 4th Floor 13-Oct-18 9-Oct-18

11 4th to 5th Floor 31-Oct-18 17-Oct-18

12 5th to 6th Floor 13-Nov-18 1-Nov-18

13 6th to 7th Floor 5-Dec-18 14-Nov-18

14 7th to 8th Floor 16-Dec-18 26-Nov-18

15 8th to 9th Floor 29-Dec-18 10-Dec-18

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

20-May-19

PREPARED BY:
PREPARED BY:
16 9th to 10th Floor 13-Jan-19 26-Dec-18

17 10th to 11th Floor 27-Jan-19 7-Jan-19

18 11th to 12th Floor 9-Feb-19 17-Jan-19

19 12th to 13th Floor 16-Feb-19 29-Jan-19

20 13th to 14th Floor 21-Feb-19 10-Feb-19

21 14th to 15th Floor 27-Feb-19 17-Feb-19

22 15th to 16th Floor 6-Mar-19 23-Feb-19

23 16th to 17th Floor 12-Mar-19 28-Feb-19

24 17th to 18th Floor 19-Mar-19 9-Mar-19

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

PREPARED BY:
PREPARED BY:
25 18th to 19th Floor 26-Mar-19 17-Mar-19

26 19th to 20th Floor 2-Apr-19 24-Mar-19

27 20th to 21st Floor 9-Apr-19 28-Mar-19

28 21st to 22nd Floor 15-Apr-19 6-Apr-19

29 22nd to 23rd Floor 18-Apr-19 11-Apr-19

30 23rd to 24th Floor 24-Apr-19 16-Apr-19

31 24th to 25th Floor 28-Apr-19 21-Apr-19

32 25th to 26th Floor 1-May-19 25-Apr-19

33 26th to 27th Floor 5-May-19 29-Apr-19

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

PREPARED BY:
PREPARED BY:
34 27th to 28th Floor 9-May-19 2-May-19

35 28th to 29th Floor 14-May-19 7-May-19

36 29th to 30th Floor 19-May-19 12-May-19

37 30th to 31st Floor 25-May-19 16-May-19

38 31st to 32nd Floor 29-May-19 20-May-19

39 32nd to 33rd Floor 9-Jun-19 25-May-19

40 33rd to 34th Floor 15-Jun-19 30-May-19

41 34th to 35th Floor 8-Jun-19

42 35th to 36th Floor 12-Jun-19

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

PREPARED BY:
PREPARED BY:
43 36th to 37th Floor 17-Jun-19

44 37th to 38th Floor

45 38th to 39th Floor

46 39th to 40th Floor

47 40th to 41st Floor

48 41st to 42nd Floor

49 42nd to 43rd Floor

50 43rd to 44th Floor

51 44th to 45th Floor

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

PREPARED BY:
STAIRCASE-12/13/14 STATUS

Surface Preparation A-Approved As


Noted
D-Needs
Rectification
CASTING
DATE Actual
Planned Start OE MZP
Completed

PREPARED BY:
45th Floor to Lower
52 Roof Deck
Lower Roof Deck to
53 Upper Roof deck

PREPARED BY:
TOWER D- STAIRCASE MONITORING
Date As of: 24-Jun-19

PREPARED BY:
PREPARED BY:
STAIRCASE-1 STATUS STAI
Surface Preparation A-Approved As D-Needs
SN. LEVEL CASTING
Noted Rectification
CASTING
DATE Planned Actual DATE
OE MZP
Start Completed
1 5th to 4th Basement 9-Feb-17 19-Feb-19

2 4th to 3rd Basement 21-Mar-17 21-Mar-17

3 3rd to 2nd Basement 10-May-17 8-May-17

4 2nd to 1st Basement 20-May-17 17-May-17

1st Basement to
5 26-Jul-17 9-Jul-17
Ground Floor
6 Ground to 1st Floor 22-Nov-17 29-Nov-17

1st Floor to Upper 1st


7
Floor 6-Dec-17 26-Dec-17
Upper 1st Floor to
8 26-Dec-17 17-Feb-18
Technical Platform
Technical Platform to
9 24-Feb-18 31-Mar-18
2nd Floor
10 2nd to 3rd Floor 4-Apr-18 6-May-18

11 3rd to 4th Floor

12 4th to 5th Floor

13 5th to 6th Floor

14 6th to 7th Floor

15 7th to 8th Floor

16 8th to 9th Floor


17 9th to 10th Floor

18 10th to 11th Floor

19 11th to 12th Floor

20 12th to 13th Floor 16-Jan-19

21 13th to 14th Floor 23-Jan-19

22 14th to 15th Floor 2-Feb-19

23 15th to 16th Floor 19-Jan-19 9-Feb-19

24 16th to 17th Floor 28-Jan-19 19-Feb-19

25 17th to 18th Floor 6-Feb-19 28-Feb-19


26 18th to 19th Floor 11-Feb-19 9-Mar-19

27 19th to 20th Floor 20-Feb-19 18-Mar-19

28 20th to 21st Floor 28-Feb-19 24-Mar-19

29 21st to 22nd Floor 7-Mar-19 28-Mar-19

30 22nd to 23rd Floor 13-Mar-19 4-Apr-19

31 23rd to 24th Floor 21-Mar-19 11-Apr-19

32 24th to 25th Floor 26-Mar-19 17-Apr-19

33 25th to 26th Floor 1-Apr-19 28-Apr-19

34 26th to 27th Floor 9-Apr-19 4-May-19


35 27th to 28th Floor 15-Apr-19 12-May-19

36 28th to 29th Floor 22-Apr-19 16-May-19

37 29th to 30th Floor 2-May-19 27-May-19

38 30th to 31st Floor 14-May-19 10-Jun-19

39 31st to 32nd Floor 29-May-19 18-Jun-19

40 32nd to 33rd Floor 11-Jun-19

41 33rd to 34th Floor

42 34th to 35th Floor

43 35th to 36th Floor


44 36th to 37th Floor

45 37th to 38th Floor

46
38th to Lower Roof
Deck
47
Lower Roof Deck to
Upper Roof deck
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19

STAIRCASE-2 STATUS STAIRCASE-3 STATUS


Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
Planned Actual DATE Planned Actual
OE MZP OE
Start Completed Start Completed
25-Mar-17

18-Feb-19

26-Mar-18
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19
TOWER C- STAIRCASE MONITORING
Date As of: 24-Jun-19
NITORING

STATUS STAIRCASE-4 STATUS STAIRCASE-5


D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Prepara
CASTING CASTING
DATE Planned Actual DATE Planned
MZP OE MZP
Start Completed Start
14-Nov-17

28-Dec-17

23-Feb-19

29-Nov-17
NITORING
NITORING
NITORING
NITORING

STAIRCASE- 8/9/10
Surface Prepara
CASTING
DATE Planned
Start
NITORING
STAIRCASE-5 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification

Actual OE MZP
Completed
STAIRCASE- 8/9/10 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification

Actual OE MZP
Completed
TOWER B- STAIRCASE MONITORING
Date As of: 24-Jun-19

STAIRCASE-1 STATUS STAIRCASE-2 STATUS STAIRCASE-5 STATUS STAIRCASE-4 STATUS


Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
SN. LEVEL CASTING CASTING CASTING CASTING
DATE Planned Actual DATE Planned Actual DATE Planned Actual DATE Planned Actual
OE MZP OE MZP OE MZP OE MZP
Start Completed Start Completed Start Completed Start Completed
1 5th to 4th Basement

2 4th to 3rd Basement

3 3rd to 2nd Basement

4 2nd to 1st Basement

5
1st Basement to
Ground Floor
6 Ground to 1st Floor

7
1st Floor to Technical
Platform Lower Level

Technical Platform
8
Lower Level to
Technical Platform
Upper level

Technical Platform
9 Upper level to 2nd 21-Feb-18
Floor

2nd Floor to 2nd Floor


10 14-Jan-19
Technical Platform

11
2nd Floor Technical
Platform to 3rd Floor
12 3rd to 4th Floor

13
4th to 4th Technical
Platform
14
4th Technical Platform
to 5th Floor
15 5th to 6th Floor 14-Mar-19

16 6th to 7th Floor 30-Mar-19

17 7th to 8th Floor 29-Jan-19 7-Apr-19

18 8th to 9th Floor 13-Feb-19 11-Apr-19

19 9th to 10th Floor 20-Feb-19 14-Apr-19

20 10th to 11th Floor 26-Feb-19 21-Apr-19

21 11th to 12th Floor 6-Mar-19 23-Apr-19

22 12th to 13th Floor 11-Mar-19 27-Apr-19

23 13th to 14th Floor 17-Mar-19 1-May-19

24 14th to 15th Floor 23-Mar-19 9-May-19

25 15th to 16th Floor 26-Mar-19 21-May-19

26 16th to 17th Floor 9-Apr-19 13-Jun-19

27 17th to 18th Floor 14-Apr-19

28 18th to 19th Floor 17-Apr-19

29 19th to 20th Floor 20-Apr-19

30 20th to 21st Floor 22-Apr-19

31 21st to 22nd Floor 25-Apr-19

32 22nd to 23rd Floor 29-Apr-19

33 23rd to 24th Floor 6-May-19

34 24th to 25th Floor 11-May-19

35 25th to 26th Floor 27-May-19

36 26th to 27th Floor 15-Jun-19

37 27th to 28th Floor

38 28th to 29th Floor

39 29th to 30th Floor

40 30th to 31st Floor

41 31st to 32nd Floor

42
32nd to Cooling Tower
Level
43
Cooling Tower Level to
Upper Roof Level

STAIRCASE-6 STATUS STAIRCASE-11 STATUS STAIRCASE-9 STATUS STAIRCASE-10 STATUS STAIRCASE-12 STATUS

SN. LEVEL Surface Preparation A-Approved As


Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING CASTING CASTING CASTING CASTING
DATE Planned Actual DATE Planned Actual DATE Planned Actual DATE Planned Actual DATE Planned Actual
Start Completed OE MZP Start Completed OE MZP Start Completed OE MZP Start Completed OE MZP Start Completed OE MZP

1 Ground to 1st Floor

STAIRCASE-3 STATUS STAIRCASE-7 STATUS


Surface Preparation A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
SN. LEVEL CASTING CASTING
DATE Planned Actual DATE Planned Actual
OE MZP OE MZP
Start Completed Start Completed
1 Ground to 1st Floor

2
1st Floor to Technical
Platform Lower Level
Technical Platform
3
Lower Level to
Technical Platform
Technical
UpperPlatform
level
4 Upper level to 2nd 21-Feb-18
Floor
2nd Floor to 2nd Floor
5 14-Jan-19
Technical Platform
6
2nd Floor Technical
Platform to 3rd Floor
7 3rd to 4th Floor
STAIRCASE-1
Surface Preparation
SN. LEVEL CASTING
DATE Planned Actual
Start Completed
1 5th to 4th Basement 11-Mar-19

2 4th to 3rd Basement

3 3rd to 2nd Basement

4 2nd to 1st Basement


1st Basement to
5 24-Sep-18
Ground Floor
7 Ground to 1st Floor 9-Jan-19

1st Floor to Upper 1st


8 1-Apr-19
Floor
Upper 1st Floor to 1st
9 1-Apr-19
Floor Technical
1st Floor Technical to
10
2nd Floor 15-Apr-19
2nd Floor to 2nd Floor
11 29-Apr-19
Technical
2nd Floor Technical to
12 16-May-19
3rd Floor
13 3rd to 4th Floor 29-May-19

Prepared By:
14 4th to 5th Floor 6-Feb-19

15 5th to 6th Floor 20-Feb-19

16 6th to 7th Floor 2-Mar-19

17 7th to 8th Floor 10-Mar-19

18 8th to 9th Floor 18-Mar-19

19 9th to 10th Floor 27-Mar-19

20 10th to 11th Floor 2-Apr-19

21 11th to 12th Floor 8-Apr-19

22 12th to 13th Floor 18-Apr-19

23 13th to 14th Floor 27-Apr-19

24 14th to 15th Floor 23-May-19

25 15th to 16th Floor 8-Jun-19

26 16th to 17th Floor 23-May-19

27 17th to 18th Floor 8-Jun-19 06/Sep/19

28 18th to 19th Floor

29 19th to 20th Floor

Prepared By:
30 20th to 21st Floor

31 21st to 22nd Floor

32 22nd to 23rd Floor

33 23rd to 24th Floor

34 24th to 25th Floor

35 25th to Lower Roof

Prepared By:
STAIRCASE-3
Surface Preparation
SN. LEVEL CASTING
DATE Planned Actual
Start Completed
1
1st Basement to
Ground Floor
2 Ground to 1st Floor

3
1st Floor to Upper 1st
Floor
4
Upper 1st Floor to 1st
Floor Technical
5
1st Floor Technical to
2nd Floor

STAIRCASE-7
Surface Preparation
SN. LEVEL CASTING
DATE Planned Actual
Start Completed
1 Ground to 1st Floor

Prepared By:
STAIRCASE-16
Surface Preparation
SN. LEVEL CASTING
DATE Planned Actual
Start Completed
31 21st to 22nd Floor

32 22nd to 23rd Floor

33 23rd to 24th Floor TBA

34 24th to 25th Floor TBA

Prepared By:
TOWER A- STAIRCASE MONITORING
Date As of: 24-Jun-19

STATUS STAIRCASE-2 STATUS


A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
DATE Planned Actual
OE MZP OE
Start Completed
16-Feb-19

3-Oct-17

26-Mar-19

18-Apr-19

24-Apr-19

30-Apr-19

5-May-19

11-May-19

21-May-19

7-Feb-19

Prepared By:
TOWER A- STAIRCASE MONITORING
Date As of: 24-Jun-19

11-Mar-19

19-Mar-19

28-Mar-19

7-Apr-19

17-Apr-19

28-Apr-19

6-May-19

21-May-19

9-Jun-19

19-Jun-19 17/Sep/19

Prepared By:
TOWER A- STAIRCASE MONITORING
Date As of: 24-Jun-19

Prepared By:
TOWER A- STAIRCASE MONITORING
Date As of: 24-Jun-19

STATUS STAIRCASE-6/5/4 STATUS


A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
DATE Planned Actual
OE MZP OE
Start Completed

STATUS STAIRCASE-8 STATUS


A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
DATE Planned Actual
OE MZP OE
Start Completed

Prepared By:
TOWER A- STAIRCASE MONITORING
Date As of: 24-Jun-19

STATUS STAIRCASE-17 STATUS


A-Approved As
Noted
D-Needs
Rectification Surface Preparation A-Approved As
Noted
CASTING
DATE Planned Actual
OE MZP OE
Start Completed

TBA

TBA

Prepared By:
TORING

STATUS STAIRCASE-15 STATUS


D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual
MZP OE MZP
Start Completed

Prepared By:
TORING

Prepared By:
TORING

Prepared By:
TORING

STATUS STAIRCASE-10 STATUS


D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual
MZP OE MZP
Start Completed

STATUS STAIRCASE-9 STATUS


D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual
MZP OE MZP
Start Completed

Prepared By:
TORING

STATUS STAIRCASE-18 STATUS


D-Needs
Rectification Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual
MZP OE MZP
Start Completed
TBA

Prepared By:
Prepared By:
Prepared By:
Prepared By:
STAIRCASE-13 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual OE MZP
Start Completed

STAIRCASE-14 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual OE MZP
Start Completed

Prepared By:
STAIRCASE-19 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual OE MZP
Start Completed

TBA

Prepared By:
STAIRCASE-11/12 STATUS
Surface Preparation A-Approved As
Noted
D-Needs
Rectification
CASTING
DATE Planned Actual OE MZP
Start Completed

Prepared By:
Prepared By: