Вы находитесь на странице: 1из 2

OFFSHORE FACILITIES: CONSTRUCTION AND DESIGN

Chain Failure by Bending


on Deepwater Mooring Systems

The premature rupture of mooring chains


of the Girassol buoy after only a half-year
of service was caused by bending fatigue
of the first free chain link inside the chain
hawse (fairlead). Although the mooring
system had been designed according to off-
shore industry standards, it failed because
of this bending-fatigue mode. A study of
this bending phenomenon led to a redesign
of both the top chain segment size and the
hawse connection, which now includes a
new chain-connecting arm (CCA). A new
method was developed to estimate the
fatigue damage in the chain subjected to
bending, which was used to design a new
CCA for the Girassol buoy.

Introduction
The Girassol loading buoy was installed in
September 2001 at the Girassol oil field off- Fig. 1—Girassol buoy elevation view and location of failed link.
shore Angola in 1350-m water depth. The
buoy allows export, by use of two midwater In May 2002, 235 days after buoy instal- OPB Failure Mechanism
16-in. export lines, of the stabilized crude lation, one group of anchor legs (B4, B5, Unlike a rod, a chain can be piled or laid in
oil processed onboard the floating produc- and B6) broke almost simultaneously, fol- any shape, thus a chain usually is thought
tion, storage, and offloading vessel, moored lowed 1 month later by the rupture of of as not having bending stiffness. In most
1 naut mile away. another anchor leg (B1). cases, the tension in a chain is so low that
The buoy is anchored to the seabed by The ruptures in Anchor Legs B4, B6, the links can roll or slide on each other to
means of three groups of three anchor and B1 occurred at exactly the same loca- accommodate the rotations imposed at the
legs. Before the incident, the anchor legs tion—at the fifth link of the upper chain ends of the chain by the floating body.
comprised collinear segments of 81-mm segment connected to the buoy inside a
studded chains and 130-mm-diameter standard-type curved chain hawse—while Rolling Mode. As with any articulation,
polyester ropes. Within each group, the Leg B5 broke in the upper rope segment. when the tension in the chain increases, it
legs are spread 5° apart, and the group This rope-segment rupture was caused pri- will become increasingly difficult to obtain
centers are spread 120° apart. The chain marily by an earlier accidental cut of the rotation between successive links. If the
segments are at the upper and lower ends rope through two-thirds of its section. The contact surfaces between the links were
of the anchor legs. total rupture of Leg B5 followed the rupture perfectly cylindrical, a rolling mechanism
of Legs B4 and B6 as a result of load transfer. would still be possible even for high ten-
However, the fifth link of Leg B5 was found sions. Small bending stresses would be
This article, written by Technology Editor
severely cracked, thus confirming the same generated because of the displacement of
Dennis Denney, contains highlights of paper
failure mechanism for all four legs. the point of application of the tension away
OTC 17238, “Failure of Chains by Bending
Studies identified the root cause as the from the plane of symmetry of the link.
on Deepwater Mooring Systems,” by P. Jean,
out-of-plane bending (OPB) stress (fatigue These rolling stresses can be calculated ana-
Single Buoy Moorings Inc.; K. Goessens, Total
stress), combined with tension variations, lytically, but they are too small to explain
E&P Angola; and D. L’Hostis, DV Offshore,
occurring mainly in the fifth link inside the fast failure at Girassol.
prepared for the 2005 Offshore Technology
the chain hawses. As Fig. 1 shows, Link 5
Conference, Houston, 2–5 May. Copyright
is the first link to oscillate with respect to Locking Mode. In the chain-manufactur-
2005 Offshore Technology Conference.
the Link 4, which is fixed onto the internal ing process, a proof load (between 65 and
Reproduced by permission.
curved shape of the chain hawse. 80% of breaking load) is applied to all

The full-length paper is available for purchase from the OTC Library: www.otcnet.org. The paper has not been peer reviewed.

72 JPT • FEBRUARY 2006


Fig. 2—Contact surface of 40-mm lab- Fig. 3—Failed Link 5 on Leg B6 of the Fig. 4—Girassol RCA mounting on
oratory test chain. Girassol buoy. buoy.

links. Plastic/elastic finite-element analysis • Use an appropriate “S-N” curve to cal- tension and OPB fatigue with a safety
(FEA) of two links has shown that, under culate fatigue damage. factor larger than 10. The curved chain
a tension equal to proof load, the surface • Combine tension and bending stresses stoppers with only one articulation were
of contact between the two links is perma- or damages. replaced offshore with the new RCAs in
nently deformed. The theoretical point of May 2004.
contact becomes a surface with an ellipti- OPB Fatigue Damage
cal shape, typically one-fourth the size of It is possible to determine the OPB-fatigue Conclusion
the chain diameter (Fig. 2). The surface damage from the formula for OPB stress Vessel rotations applied to a chain under
of contact has been observed on all chain in chain knowing the chain diameter, high tension can lead to high OPB stresses
links inspected. tension, and imposed fairlead-angle long- in the first links close to the chain hawse.
Once this surface is formed, the chain term distribution. By applying this meth- These OPB stresses led to the failure of
links can no longer roll and the links are odology and comparing failure times with four chains on the Girassol buoy. Lessons
locked. If a rotation is imposed on one Girassol-failure durations, it was found learned from recovered failed links, labora-
chain link, the complete chain will have to that the Det Norske Veritas (DNV) “B1” tory tests, and analytical analysis call for a
bend like a rod. FEA shows that most of the curve (for forged elements) is appropriate. change of practice in the industry.
bending deformation occurs at the contact The new design used a safety factor of 10 New rules should include a design
surface between links. The stresses gener- because OPB is a new problem requiring method to account for OPB stresses in
ated by this bending are large and can easily more investigation. chains. Sufficient data must be gathered
explain the fast failure at Girassol. to improve understanding of stresses in
An OPB moment is generated in the link Remedial Solution: chains under high tensions. Comparison
when a rotation is imposed on the chain Rod-Connecting Arms (RCAs) between this method and FEA work is
end and the links cannot roll on each other. To make sure that the top chains would not very encouraging. OPB-stress vs. inter-
OPB refers hereafter to the bending of a fail again on Girassol, the root causes of the link-angle curves presented in the paper
chain link out of its main plane (that con- failure were addressed as follows. were confirmed with FEA. A combination
taining the oval shape). It is caused by the • Reduce the bending moment at the of FEA (plastic/elastic with contact) and
application of transverse forces and OPB chain-hawse connection by use of low-fric- laboratory tests could be used to prepare
moments that are resisted by reaction forces tion bushings, double articulations, and guidelines for designers.
spread over the contact between links. long lever arms between the first chain The appropriate “S-N” curve is difficult
Each wave excites the buoy in roll and link and articulation axes. Reducing the to select. The DNV “B1-2 stdv” curve can
pitch. These rotations are imposed on the bending moment directly reduces the bend- be used for new deepwater-buoy designs.
top chain through the chain hawse, and ing stresses. The selection of this curve is supported
bending stresses are generated for each • Use a dual-articulation RCA because by the consistency between the calculated
wave cycle. It is the accumulation of these the motions of the buoy result in bending and actual failure times of Girassol chain
bending stresses that cause the propaga- both in the mooring-line plane and trans- (four failure points). Nevertheless, use of
tion of cracks in chain, ultimately causing verse to the mooring-line plane. this curve predicts OPB failure on other
failure. On Girassol, the combination of • Improve chain cathodic protection systems such as Kuito buoy. Kuito chains
constant swell excitation with high tension to prevent crack/pit initiation and reduce have been inspected after 4 years of ser-
led to a rapid failure. The photographs of fatigue-crack growth rate. vice, and no fatigue cracks were found.
the failed links on Girassol in Fig. 3 show • Reduce tension to reduce OPB stresses. Chain-failure tests are under way on
that the fracture surfaces are consistent • Increase top-chain diameter in the Girassol curved- and Kuito straight-
with bending. first links subjected to a significant OPB chain-hawse designs. The purpose of
To calculate the fatigue life of chain moment. these tests is to clarify if the curved chain
undergoing bending cycles, the authors hawse enhanced the OPB problem. If con-
propose the following. By use of the OPB-stress formulas pre- firmed by the tests, the method will be
• Calculate the long-term distribution of sented in the full-length paper, a safe con- refined to account for effect of a curved
chain-hawse angles. nection between the buoy and the chain chain hawse. Then, a less conservative
• Obtain long-term distributions of bend- was designed. The new RCA is shown in “S-N” curve and/or stress-vs.-angle curve
ing stresses by use of a bending-stress vs. Fig. 4. The chain and RCA are designed for chain bending will be derived from the
chain-hawse-angle curve. for a 20-year life, accounting for combined test results. JPT

JPT • FEBRUARY 2006 73

Вам также может понравиться