Located in the heart of the business hub and 15 km from the airport, Pearl Continental
Hotel Karachi is a preferred choice for discerning corporate and leisure travelers. Vibrant
and progressive, it retains the warmth and the spirit of Pakistan, while offering a variety
of rooms, stylish restaurants and contemporary business facilities, establishing itself as
an undisputed, premier business hotel. Whilst not forgetting that Karachi is the city of
dreams, an all-enveloping sensory roller-coaster ride which leaves you delighted and
inspired at the same time. There is a lot more to this city than what meets the eye.
Regarded as the city of lights, Karachi is strategically located on the Arabian Sea, and
boasts the largest port in Pakistan. This vibrant, teeming city is also home to a wide
spectrum of people. Karachi represents the ever-changing face of Pakistan and is a
nourishing metropolis that offers something in it for everyone.
Pearl Continental Hotel Karachi echoes the glory of the city with a myriad of choices for
today’s discerning traveler. From tasteful rooms and elegant interiors to impeccable
dining and conferencing facilities, Pearl Continental Hotel Karachi is a much sought-after
address. What makes the experience more memorable is the welcoming, dedicated staff.
1.2.1. Engineering Audit & Building Inspection of PC Hotel Karachi was carried out within the
engineering function, so as to ensure that the system is effective, efficient and
compliant to the specified standards and regulations. Following was the scope for this
Audit;
▪ Evaluate existing Engineering Setup
▪ Check the status of Preventive Maintenance
▪ Point out deficiencies and shortcomings
▪ Highlight the areas of improvement
▪ Recommendations for rectification of deficiencies
1.3.1. HVAC system of PC Hotel Karachi consists of three Absorption type Chillers (2x500TR
and 1x380TR) and one water cooled Centrifugal Chiller Make LG with 500TR capacity.
All four chillers are located in Plant Room (Basement of the building). Considering the
reduced efficiency of the HVAC equipment due to the aging factor, Split type package
units for 300TR capacity are also installed to support the system and fulfill the building
HVAC load requirements.
1.3.2. General condition of HVAC system is not up to the mark. Chilled and Condenser water
piping in the exposed environment is badly corroded, so is the case with Cooling Towers,
their frame structure, control valves, blowers and blower motors.
1.3.3. Monitoring devices on all Chilled/Condenser water system are either missing, out of
order or in need of calibration/maintenance, without these devices actual condition and
efficacy of the equipment cannot be determined. VFDs need to be installed on all Chilled
and Condenser water pumps, AHUs and Cooling Tower Blower Fan motors.
1.3.4. Dedicated cooling tower for each chiller is installed on low roof. It is evident from the
condition of the cooling towers that chemical dosing is ineffective. Out of four in total,
three cooling towers are badly affected by corrosion, pitting and microbiological growth.
1.3.5. The growth of microbiological contaminants in cooling tower water such as bacteria,
algae, and fungi, can cause corrosion and fouling of cooling tower equipment. Biological
growth can occur in any kind of cooling tower system but happens most in open-loop
systems whereby the cooling tower water is more readily exposed to the elements and
favorable environments.
1.3.6. Currently, chemical dosing into the condenser water is being done manually. Automatic
means of chemical dosing need to be adopted/studied. Treating cooling tower water
properly is essential to enhance efficiency of the system. Organic growth, fouling,
scaling, and corrosion are all challenges that can reduce plant productivity and require
costly equipment replacements down the road.
1.4.1. PC Hotel Karachi is equipped with backup support of four standby generators (CAT
1000KVA, CAT 725KVA, Cummins 1100KVA & Perkins 780KVA) are installed in the
property. These Gen Sets are well maintained and appear to be in good working order,
except Perkins (780KVA) which is less efficient with 30% efficiency. Adequate ventilation
is provided for the Gen Sets. Areas where Gen Sets are installed are easily accessible to
everyone, it is however recommended that area should be restricted to authorized staff
only.
1.4.2. Oil Circuit Breakers based High Voltage (HV) switchgears are installed inside
Transformers and LT panels Room. these High Voltage switchgears are still functional
but have already completed their useful life and now are beyond their guaranteed
support period. HV switchgears have not been tested for years. Maintenance and
repairs of these OCBs is a challenge due to non-availability of spares in the market.
Replacement of theses OCBs to be considered on top priority basis, ideally with Vacuum
Circuit Breakers (VCBs).
1.4.3. Three transformers are installed to cater the building load. One in basement and two at
ground level, Transformer # 1 & 2 are more than 30 years old and have completed their
anticipated life expectancy and are in need of replacement. Transformer # 3 has been
replaced two years ago and in perfect working order. Transformer # 2 in in worst
condition and its replacement to be considered on priority, however replacement of this
transformer will be a challenge due to the location, it is installed in confined space along
with HV Switchgears.
1.4.4. Preemptive measures against possible fire risk are insufficient in transformers’ room
and other electrical installations. Though transformers, breaker panels are adequately
grounded, lightening arresters are installed but fire risk still cannot be overruled.
Installation of adequate fire suppression system in Transformers and other electrical
panels rooms should be studied and implemented.
1.4.5. Lightning protection system to protect the building structure and equipment from the
lightning strikes is installed but won’t be effective in cane of any lightning strikes since
all arresters are missing, only copper strip travels around the building from roof top to
the earth pit. Only one arrester is installed and that too is to protect telecom (mobile
phone company) equipment.
1.5.1. Most of the Kitchen Equipment are not performing to their optimum efficiency just
because of lack of preventive maintenance. Auto Ignition system and Thermostatic
Controls of most of the Ovens, Hot Plates and Deep Fryers are not functional. It also
pertains to mention that like every other group property, PCHK kitchens are also
provided with multi burners cooking ranges with ovens. As per kitchen staff these ovens
have never been used for cooking purposes, are used for storage of food items or
cutlery.
1.6.1. PCHK Laundry plant room consists most of the equipment that has already completed
their useful life and are beyond guaranteed support period. Automatic controls and
programming cards of almost every single machine are either missing or malfunctioning,
machines are being operated manually. Maintenance and repairs of these machines is
a challenge due to non-availability of spares in the market. As a result, most of the time
equipment remains out of order for several months and in certain cases may be years.
Currently most of the laundry equipment are underperforming and have turned to be
less energy efficient. Considering worsened condition of the Laundry
machines/equipment, PCHK management has decided to revamp the entire laundry
(MEP & HVAC works includes) with induction of mostly new energy efficient
machines/equipment. Equipment placement/layout prepared by in-house. Electrical
works shall also be done by in-house engineering team, however, M/s. Y.H Associates
has been hired for HVAC, Plumbing and Fire Fighting works designs/layouts. List of
Laundry Inventory has been finalized, process has been initiated and orders have been
placed for procurement of energy efficient equipment mandatory for five-star hotel
setup.
H.V. SWITCHGEARS
2.1.1. Oil Circuit Breakers based High Voltage (HV) switchgears are installed inside
Transformers and LT panels Room. these High Voltage switchgears are still functional
but have already completed their useful life and now are beyond their guaranteed
support period. HV switchgears have not been tested for years. Maintenance and
repairs of these OCBs is a challenge due to non-availability of spares in the market.
Replacement of theses OCBs to be considered on top priority basis, ideally with
Vacuum Circuit Breakers (VCBs).
2.2.1. Just like any structure, hotels buildings are also at risk for fires, but there are specific
aspects that make their fire prevention systems and plans more complex. First, hotels
have a high occupancy load due to the many rooms and numerous guests. In addition,
unlike office spaces or apartment complexes, guests are unfamiliar with the building
and viable escape routes.
2.2.2. More than anything, the protection of life should always be the number one priority in
any situation. When it comes to fire safety systems, nothing protects life more than a
properly maintained automatic sprinkler system. Currently, automatic water sprinkler
system is not installed in any part of the building. Dummy sprinklers are installed in Tai-
Pan Kitchen and 7th floor guest rooms only, but not connected with wet risers. In order
to save lives, cut potential losses, reduce property damages, contain problem before it
rages out of control, and above all NFPA code compliance, it is recommended that
adequate fire sprinkler system installation need to be studied through competent
consultant and get the job done on top priority.
Cummins 1110 KVA CAT 1000 KVA CAT 725 KVA Perkins 680 KVA
3.3. TRANSFORMERS:
3.3.1. Three transformers are installed to cater the building load. One in basement and two at ground
level, Transformer # 1 & 2 are more than 30 years old and have completed their anticipated
life expectancy and are in need of replacement. Transformer # 3 has been replaced two years
ago and in perfect working order. Transformer # 2 is in worst condition and its replacement to
be considered on priority, however replacement of this transformer will be a challenge due to
the location, as this is installed in confined space along with HV Switchgears.
3.4.1. Currently High Voltage switchgears (Oil Circuit Breakers) are located at ground level in a
confined space, along with Transformer # 2, 3 and LT Panel # 3 originally installed at the time
of hotel construction and now are out of guaranteed support period. General appearance and
physical condition of these Switchgears is not adequate. Although, these High Voltage
switchgears are still functional but their functional, parts and controls have not been tested for
years. Maintaining these aged OCBs is a challenge due to no availability of spares in the market.
It is strongly recommended that plan should be devised for replacement of these oil-based
Switchgears with Vacuum Circuit Breakers (VCBs)
3.5.1. There are currently four (4) Main LV panels detailed as follows:
▪ LT Panel-1: Fed via Transformer No.1
▪ LT Panel-2: Fed via Transformer No.2
▪ LT Panel-3 (Old): LT Panel-3 (New) currently serves LT Panel-3 (Old)
▪ LT Panel-3 (New): Fed via Transformer No.3
LT PANEL-2
3.5.3. LT Panle-2 is also the Main DB which was originally installed in 1964 at the time of hotel
construction, fed via Transformer # 2.
Arrester for Mob. Eqpt Missng Arresters on roof top Earthing Cable
3.6.1. Lightning Arresters are installed in order to protects electronic or electrical equipment and
building structure from lightning by diverting any surges of high-voltage electricity caused by
atmospheric discharges to a ground. Lightning protection system is also installed at PCHK but
unfortunately it won’t be effective in cane of any lightning strikes since all arresters are missing,
only copper strip/wire travels around the building from roof top to the earth pits. Only one
arrester is installed and that too is to protect telecom (mobile phone company) equipment.
3.6.2. As per the provided details, total seven earth pits have been constructed for grounding purpose
at different location around the building, three of them are buried and only four pits are
checked, tested and energized.
3.6.3. Above are the images of a Breakers’ DB installed on low roof. Control breakers for AHUs,
Transfer Pumps, are very much disturbing, exposed live parts within the distribution boards
are easily accessible since DBs doors are missing/damaged, live parts are uninsulated and
exposed, so they can be touched either directly or indirectly by a conducting object are
hazardous. These breakers have never been tested for their functionality, placed loose on
roof slab. Loose live cables left unprotected around the DB. It is, therefore, strongly
recommended that replacement of this DB should be considered on priority.
3.6.5. Gas pipeline coming from the main distribution header is passing through the LV Switch room
located in the basement plant room. This pipeline is main source of gas supply for Boilers. A
bunch of cables from the switchboard is directly touching this pipeline. From Fire & Life Safety
perspective this line should be re-routed and approached to Boilers.
4.2. CHILLERS:
4.3.1. In total 42 AHUs are installed to cater the HVAC load requirements of the property. Two of
them are Fresh Air Handling Units. Following will provide an overview regarding installed base
of AHUs;
4.3.1.1. Installed Capacity:
4.3.3. Around 60% of AHUs installed in the property are between 15-50 years old. consequently,
decay in the units’ body due to rust/corrosion is obvious. Though hotel engineering is putting
utmost efforts for upkeep of these units, but still rust on coil frames, deterioration of motor
cooling fan covers, rusty drain pans, wall and ceiling panels can be seen. Despite all these issues,
units are still operational. Engineering department will have to put extra efforts to keep these
units functional, until these are replaced. Replacement of older and less efficient units needs
to be phased-out.
4.4.1. Altogether 334 FCUs are installed in the property with 129,450 CFM capacity. 50% of the FCUs
are imported mostly from USA and Malaysia, rest are locally manufactured mostly by M/s.
Habibullah. Out of 334 FCU, 164 FCUs were originally installed in 1964 at the time of
construction and still in operation. Rest of the units were replaced between 2000 to 2017.
4.4.2. Most of the motorized valves installed on chilled water line for FCUs are malfunctioning and
being replaced with new ones. So far fifty percent (50%) valves have been replaced and rest is
in progress.
Cooling Towers
4.5.2. Water treatment of the cooling tower condenser water is based on manual dosing of chemicals
directly into the basins of the cooling towers. The impact of this manual dosing arrangement is
that water quality will be random which will be unfavorable for the pipework and plant
efficiency. Organic growth, fouling, foaming, scaling, and corrosion are all challenges that can
reduce plant productivity and require costly equipment replacements down the road.
4.5.3. Several monitoring devices on closed and open water circuits are either missing, out of order
or in need of calibration/maintenance, without these devices actual condition and efficacy of
the equipment cannot be determined. VFDs need to be installed on all Chilled and Condenser
water pumps, AHUs and Cooling Tower Blower Fan motors for energy conservation, reliable
equipment operation and to reduce downtime hours.
4.5.4. Apparently, adequate means of filtration are not adopted for the condenser water to remove
debris from the open circuit condenser water system that enters via the cooling towers. It is
recommended that side stream filtration via basket strainers to be provided maintain
condenser water reasonably clean. There are strainers on the condenser water pumps but
these alone are not sufficient/effective and will require frequent and considerable effort to
clean consequently they often are over-looked.
5.1.2. Firefighting arrangements around newly renovated Marquee and Zaver hall are insufficient.
Automatic fire sprinklers are not provided in any part of the building, so is the case with
Marquee and Zaver Hall. Fire hydrants should be increased, MCPs to be installed in pre-
function areas (corridor) and inside the Marquee and Zaver Hall with adequate
signage/marking.
5.2.1. Hotel’s fire protection is via wet risers installed with fire hoses and fire extinguishers in service
and emergency exit staircases and other parts of the building. As per NFPA codes high-rise
buildings should be adequately provided with an automatic sprinkler system however, no such
system is installed at PC Hotel Karachi.
5.2.3. In total 34 number of Fire Hydrants (around building) are installed in the building. Details are
as follows;
▪ Basement = 01 No.
▪ Ground Floor = 10 Nos.
▪ Mezzanine Floor = 02 Nos.
▪ Low Roof = 02 Nos.
▪ 1st Floor to 9th Floor (each) = 02 Nos.
▪ 10th Floor = 01 No.
Before After
5.2.4. As per Fire Safety Officer, inspection of complete Fire & Life Safety system is carried out by in-
house Engineering Department. However, when a Fire Hose at 9th Floor was tested, it was really
shocking to see that water coming out of the Hose Pipe was of black color, gradually it changed
into dark brown and eventually after 25 minutes of continuous operation its color was cleared.
It reflects that it was never tested/checked before and also that internal condition of riser pipes
is not satisfactory. Fire & Safety Officer was instructed to test all Hydrants and Hose Reals one
by one and log the status. It is also recommended that Corrosion Inhibitors should be added
in the Sprinkler System closed water circuit to control scale/corrosion in the piping system.
5.3.1. Fire suppression systems are mandatory in commercial kitchens’ exhaust systems. These
systems lead from a tank of fire suppressants to a series of pipes at the end of a sprinkler system
resting above the cooking area. These units can be activated both manually and automatically
by a heat sensor. Kitchen extract canopies are not fitted with suppression systems and do not
comply with NFPA codes, except in Tai-Pan kitchen where wet chemical type suppression
system (ANSUL) is fitted but that too does not cover all hoods in Tai-Pan kitchen.
ANSUL Suppresion System in Tai-Pan Kitchen FM-200 Suppression System in Server Room
5.3.2. FM-200 Fire Suppression system is installed in Server Room. this system was installed in
January 2018 by Haseen Habib Trading. It is recommended that following areas of the building
should be provided with appropriate Fire Suppression System;
6.1.1. Strict monitoring policy has been implemented as far as equipment scheduling is concerned.
Chillers, cooling tower, exhaust fans and lights operation are being strictly monitored and
controlled by Engineering Department. As result, significant operational costs savings have
been achieved, that is really encouraging.
6.2.1. Two Cleaver Brooks boilers were installed at the hotel construction time (1963) to cater the
space heating, Laundry, Kitchen and Guestrooms hot water requirements and also steam
requirements for laundry equipment. These boilers have already completed anticipated life
expectancy period. These boilers have been in operation for more than fifty years, have been
repaired several times, tubes of Boiler #2 were replaced couple of years ago, maintenance
frequency of these boilers is on higher side (especially Boiler #2). Considering the physical
status, Management of PCHK has decided to replace Boiler #2. P.O. has been issued in favor of
M/s. Greshams (local manufacturer).
6.2.2. Walk-way/Platform is not installed on Boilers, hence, carryout maintenance jobs on boiler is a
challenge, it is there recommended that platform on Boilers need to be installed/erected.
6.3.1. Building hot water requirements are fulfilled through two Hot Water Calorifiers installed in the
basement plant room with a capacity of 3150 USG each. Source of water heating is steam
received from Boilers that passes through steam coils. Theses calorifiers are in operation for
years without any internal inspection/maintenance therefore actual condition cannot be
determined, however; as these are nearing the end of life span, therefore, replacement need
to be considered.
6.5.1. Existing water booster system of the property consists of Hydro-Pneumatic tank with a storage
capacity of 74,169 US Gallons, along with hotel’s main water reservoir of 300,000 USG capacity.
Hydro-Pneumatic tank is also equipped with manually controlled two water pumps. Tank is
pressurized through compressed air and a pressure between 65 to 70 PSI is maintained.
Currently these pumps, as mentioned, are through manual control, VFDs are also not installed
for these pumps. Hydro-Pneumatic tank has already completed anticipated life period, control
devices are outlived. Considering depreciated condition of the equipment hotel management
has decided to replace the Hydro-Pneumatic tank and pumps with a compact variable-speed
pumping system. Pumps have already been procured, installation is still awaited. However,
hooking-up and operate the new pumping system with distribution piping network that is
already beyond the anticipated life expectancy, shall always remain a challenge.
6.6.1. Main source for the water supply to the hotel building is through Karachi Development
Authority. A tank with 22,000 USG capacity is available that receives the water from the main
source (KDA) and then pumped out through Transfer pumps to main building water reservoir
located underneath the Marquee floor with total storage capacity of 348,000 USGs.
From the main storage tanks, water is pumped into the hydro-pneumatic tank that is located
in the Main Plant Room for further distribution amongst the load centers. This hydro-
pneumatic tank is pressurized through compressed air to a level enough for evenly distribution
of water throughout the building.
6.7. ELEVATORS:
▪ Quantity 02 Nos.
▪ Brand SIGMA
▪ Model Di2 - PA20
▪ Speed 2 M/Sec
▪ Capacity 1250 Kgs
▪ Year of Manufacturing 2003
▪ Year of Installation 2008
6.7.3.1. Just like Service Elevators, Cargo Elevator is also beyond guaranteed support period,
but still operational with original controls. These elevators appeared to be in
constant need of repairs. Doors and wall panel are dented. Jerk is felt during the ride.
This elevator is in need of replacement.
▪ Quantity 02 Nos.
▪ Brand LG
▪ Model MVO - 15CO
▪ Speed 1.5 M/Sec
▪ Capacity 1000 Kgs (15 Passenger)
▪ Year of Manufacturing 1995
▪ Year of Installation 1999 & 2004
6.7.4.1. Capsule elevators are manufactured by LG. these elevators appear to be in working
order and are being maintained by M/s. Ziafco through a Service Level Agreement,
on monthly basis. One elevator serves Executive Floors while other is dedicated for
10th Floor restaurants and lounge.
6.7.4.2. Programming card of the elevator malfunctioned during operation, property has had
a spare/repaired card in the store since this is very critical as well as costly item that
normally maintenance vendors normally do not have in their store. Card was
replaced by in-house engineering employee (Elevator Technician). It was noticed
with concern that elevator programming card replacement was done at 10th floor,
however, elevator technician performed the job without taking appropriate safety
measures or using any sort of Personal Protective Equipment (PPE) while sitting on
the lift car top. A minor mistake, slight of carelessness or mishandling could have
result in miserable situation. It is strongly recommended that following
recommendations need to be followed while working on elevators;
▪ Plan lift repair and maintenance activity.
▪ conduct risk assessment and prepare risk control measures for the Lift Works.
▪ Implement general precautions for Lift Works.
▪ Pay special attention to safety and health of workers along with occupants and
other personnel.
▪ Develop and implement permit-to-work systems for Lift Works.
▪ provide effective communication system, safety and health training and
personal protective equipment (PPE) to workers
Burner Lightup with piece of paper Exhaust Hood without Suppression System
7.1.1. Most of the Kitchen staff appear to be less trained and not fully conversant with the efficient
means of kitchen equipment operation.
7.1.2. As a common practice like in other group properties, kitchen staff uses paper to ignite the
burner, this is extremely safety and fire hazard, kitchen staff should be trained and strictly
instructed not to use unethical, nonprofessional and unhygienic means.
7.1.3. Maintenance of the kitchen equipment is not being done according to the five-star hotel
standards and equipment manufacturer recommendations. Auto ignition system in almost
every single equipment is either missing or not functional. So is the case with thermostatic
controls. Piece of paper is used to ignite the burner, pilot burners of most of the equipment
were not functional.
7.1.4. Kitchen hoods are not provided with adequate fire suppression systems. Piping is provided
only in Pakistani Kitchen hoods without nozzles and also pointed upward (towards hood/duct)
instead of towards fire source (burners) along with three CO2 Fire Extinguishers and all this
system is manually operated and do not confirm codes and standards for the purpose.
Gas isolation valve behind Vulcan Griller Piping for CO2 Suppression System
7.2.1.1. This Hot Plat is installed in the Main Kitchen. Oven compartment door is damaged
and fastened with piece of cloth. Auto ignition system and thermostatic controls for
the oven compartment are also not functional. Just like several other group
properties most of the kitchen staff at PCHK is not 100% familiar/trained with regards
to the efficient operation of most of the kitchen equipment.
7.2.3.1. One portion of Vulcan Oven installed in the Bakery is not functional for more than
one-year time. Auto ignition system, thermostatic controls and digital displays of this
oven are out of order. CER was raised for rectification/replacement of this oven but
was returned being unbudgeted for the previous year CAPEX, however it is included
the current budget for the year 2018-19.
▪ Make: HOBART
▪ Model: C 64 A - ML 103908
▪ Year of installation: 1992
7.3.1. This kitchen is equipped with conventional (local) gas burners (09 Nos) along with two Steam
Kettles. This equipment is installed under an extract canopy. Hood exhaust system also
appears to be inefficient since temperature in this part of the building found to be on higher
side. It pertains to mention the exhaust hoods are installed at approximate height of seven
feet (7’), whereas burners’ height is hardly 1.5 feet from the ground leaving the gap of 5.5 feet
between burners and exhaust hood. Along with confirming the efficacy of quality of exhaust
this should also be checked whether this could be one of the reasons for less efficient exhaust?
7.4.2.1. Hot Bain Marie of Skura Kitchen is out of order. Electric heating system is not
functional. As per Engineering Department, Purchase Requisition (PR) has been
raised for replacement.
▪ Griller 02 Nos.
▪ Cooking Range witH Oven 01 No.
▪ Deep Fryer 01 No.
▪ Salamander 01 No.
7.5.2. Gas shut-off valve is installed right over the Salamander. In case of fire in the kitchen, isolation
of the control valve will be a challenge. It is therefore recommended that relocation of this
valve to be studied, ideally at the entrance of Kitchen clearly marked with “GAS SHUT-OFF
VALVE” sign/tag.
7.5.3. Firefighting arrangements inside the kitchen are trifling in absence of suppression system and
sprinkler system. Only one fire extinguishers (CO2) is installed.
8.1.1. PCHK Laundry plant room consists most of the equipment that has already completed
their useful life and are beyond guaranteed support period. Automatic controls and
programming cards of almost every single machine are either missing or
malfunctioning, machines are being operated manually. Maintenance and repairs of
these machines is a challenge due to non-availability of spares in the market. As a
result, most of the time equipment remains out of order for several months and in
certain cases may be years. Currently most of the laundry equipment are
underperforming and have turned to be less energy efficient.
8.2.1. This machine is out of order for several year, it has already completed anticipated life
expectancy and now out of guaranteed support period. Above self-explanatory picture
reflects the delipidated condition of this machine. Automatic controls, safety gadgets
are missing. It was informed that in-house Engineering Team is trying to bring this
machine back into operation, estimated cost and time required is unknown. It was
informed that PCHK Engineering is putting all their efforts to maintain this outdated
equipment in-house, but this would be a useless exercise, wastage of time as well as
human and financial resources.
8.4.1. As per Laundry Manager-PCHK, Flat Work Ironer is out of order for more than three months.
Linin trolleys, bags with dirty linin and other stuff was unorderly placed around the Flat Ironer
8.5. DRYER:
8.5.1. This dryer is manually operated as automatic controls are either missing or malfunctioning.
Spares for these controls are not available in the market that’s why this equipment is
operational through manual controls.
8.5.2. Motor and drum shaft pullies are not aligned to each other, secondly these pullies are
designed for installation of two belts whereas currently only one belt is installed.
8.6.1. This machine is satisfactorily functioning with limited controls. Emergency brake is installed
but currently not functional.
8.7.1. This machine is satisfactorily functioning with limited controls and safeties. Emergency brake
is installed but not functional. Electric motor is provided with soft starter. Electric driven
motors often do require large amounts of energy when quickly accelerating to full speed. In
order to reduce inrush currents and limit torque, electric motor of this Hydro Extractor is
provided with Soft Starter. This will not only reduce the amount of energy required to initially
startup the motor but will also help protecting equipment and extending the life of a motor
by reducing motor heating caused by frequent starts and stops.
8.8.1. Two hand steam presses are not functional. Vacuum of one steam press is not working
properly. Steam leakage is also observed.
9.2.1. Carpenter shop is located adjacent to the newly renovated Marquee. Highly combustible
material like wooden panels, planks are stored in this workshop and alongside the Marquee
wall. This is highly neglected part of the building as far as precautionary measures from safety
perspective are concerned. Switches, power sockets and breakers for electric motors are
installed on wooden panels and also hanging on wooden partition walls. Neither the Smoke
sensors nor the Sprinkler System is installed. Electrical wiring for the boards and motors is
passing through the wooden sheets.
9.2.2. Only one DCP Fire Extinguisher with 2 Kg capacity is placed at the entrance and that too is
not adequately pressurized.
9.2.3. This workshop itself is a relentless threat for the Marquee. Slight of negligence and minor
spark may lead to catastrophic consequences. Responsibility rests on the Management’s
part to decide whether to relocate Carpenter Workshop at appropriate safer place or
provide with adequate safety and firefighting arrangements.
9.3.1. More or less, condition is same as the above. Both the workshops are ill organized, GI
Corrugated roof is provided for this workshop, widened gaps are visible in the roof sheets and
water comes inside the workshop during rainfall.
Engineering department acted promptly and start clearing the blockage through rigid drain
cleaning machine. During this course of action leakage occurred in the drain pipe at 9th floor
in Room # 914 and also near elevator landing area. Access ceiling panel of Room # 914 was
removed, leakage was rectified and same was done for the elevator landing area.
9.4.2. Hygienic standards in the commercial kitchen industry are rising. Kitchens won’t function
properly without a well-designed drainage and especially HACCP (Hazard Analysis and Critical
Control Point) food safety management systems may be difficult to implement without an
adequate drainage. Following provisions should be ensured for a kitchen drainage system;
9.5.1. This small room is located at ground level in BOH services corridor (Banquet Kitchen Corridor).
Linin buckled in bed sheets and table covers is unorderly kept with paper cartons. Loosen and
inadequately fixed electric wires passing all around the stored linin. PVC tape used on cable
joint instead of appropriate connectors and paper carton is placed very close to this jointed
cable. Tube light is exposed from its fixture, bracket fan was running without protecting grill
and loose extension boards were hanging on wall. It is strongly recommended that all
electrical wiring in this room to be re-done properly, all cables to be fixed in conduit, all
clean/washed lining to be stored in shelves/racks and dirty lining to be placed in order away
from the light fixtures.
9.6.2. This corridor is also provided with access from Engineering Plant Room in case of fire or
emergency. An ordinary wooden door with door handle is provided in the service corridor that
provides access to-and-from the Engineering Plant Room (Basement) through stairs, clearly
marked with “EMERGENCY EXIT”. When the door is opened from service corridor, surprisingly
illuminated “EXIT” sign was also provided inside arrowing toward service corridor. This is a bit
confusing and can be turned into mess during the emergency. Appropriated emergency exit
door to be installed (or existing one to be painted with fire retard paint, without Emergency
Exit sign from corridor), only openable from inside (Plant Room stairs side) and to be used only
during emergency.
9.8.1. FM-200 Fire suppression system is installed in the IT Server Room along with provision of
Passive Fire protection in the entire Server Room. Fireproof wall and ceiling panels are
provided considering sensitivity and significance of the equipment. Two split A/C units (2 Tons
each) are installed to maintain the required temperature along with a Dehumidifier and a
pedestal fan.
9.9.1. Old Squash Court was converted into House Keeping store. New linin, towels and bedsheets
are stored in paper cartons in this store. Access to this store is provided from ground level as
well as from low roof. Access door to this store on low roof was unlocked. Store is protected
through installation of smoke sensors and also two Fire Extinguishers. Store should be kept
under lock & key, CCTB coverage to be provided and area to be accessible for authorized staff
only.
9.12.1. Board rooms (1,2&3) are adequately maintained and equipped with projector and screen.
Lighting is adequate, access corridor is neat & clean and shining.
9.12.2. Dimmer is installed in Dilkusha Hall but not operational since the chandelier lights are not
dimmable. These light to be replaced with dimmable lights from energy conservation
perspective. Fire extinguishers were also missing/not provided in this hall.
9.12.3. Kohinoor Hall was out of order for major renovation works, currently being used as banquet
furniture store.
9.12.4. Mahnoor Hall receiving area is very hot, cooling is not effective. This is most neglected part of
the building from fire safety perspective. Not a single smoke detector is installed, fire
extinguishers are not provided, hose real also not available.
Following Guest Rooms which were ready for sale, were inspected;
▪ Room # 919
▪ Room # 823
▪ Room # 305
Junction Box full of lint and dirt MCU placed loose without cover
9.13.2. Tissue papers found inside the ceiling wrapped around the light fixture (Room # 919). This is
simply height of negligence from maintenance staff, a minor spark will lead to terrible
situation.
9.13.3. Pieces of plastic sheets are placed underneath the control valve on chilled water line to FCU
to collect the water due to condensation. this condensation occurs due to missing insulation
on this portion of chilled water piping. This is also source of causing rust on the piping. Proper
insulation of chilled water piping including valves needs to be ensured.
9.13.4. One of the more common installation problems with smoke detectors is installing them on
wall and too close to the FCU grill. As per NFPA recommendations smoke detectors should
not be installed closer than 3 feet from any supply air diffuser or return vent. If they are too
close to the supply, smoke may not reach the detector. Ideally these detectors to be
installed on ceiling.
9.13.5. Housekeeping of the inside ceiling area around FCU is very poor. Dust, dirt and lint is visible
all around. Pieces of tissue papers, cloths, plastic sheets and wrappers left inside.
Cabling/wiring is inappropriate, cables are not laid in the conduit, MCUs are placed loose
without covers, junction boxes left unprotected are very few examples.
9.13.8. “FIRE ESCAPE PLANT” posted behind the entrance door of each room appears to be
inappropriate. Actual Floor Plan along with room numbers is not displayed, just one- or two-
digit numbers are mentioned instead, for instance guest is staying in room number “901 or
919”, it is just mentioned “1 or 19” and same sheets are placed at teach floor. ” You Are Here”
sign is mentioned in the description of the plan, but actually not marked on the room number
where guest is staying.
9.14. ACKNOWLEDGEMENT:
1.6.2. Many thanks to Mr. Jeffery Scott (GM-PCHK), Mr. Wajid Ahmed (CE-PCHK) and hotel
Engineering Team for their hospitality, assistance and cooperation, and their contribution
towards making this AUDIT a purposeful exercise.