Sands InfinIT Park at Smart City,Kochi

CLIENT: SANDS INFRABUILD (P) LTD. Sunny Sunny


REPORT DATE 10-Jan-20
PROJECT MANAGEMENT CONSULTANT CBRE SOUTH ASIA PVT LTD Rainy

CONTRACTOR: KOOL HOME BUILDERS Cloudy DATA DATE 9-Jan-20

WORK PROGRESS

DESCRIPTION OF WORK TODAYS PROGRESS CUMULATIVE COMPLETED % OF COMPLETION PLAN FOR


PLAND
TOTAL / PLAND FOR THE PROGRESS UPTO
S.NO UOM TILL THIS REMARKS
BOQ Qty MONTH -Jan' 2020 LAST MONTH COMPL. FOR THE
ACTIVITY DESCRIPTION LOCATION MONTH 9-Jan-20 UPTO DATE FOR MONTH UPTO DATE 10-Jan-20
MONTH

1 Reinforcement steel Total MT 545 48 48 0.00 0.2 0.20 0.20 0.42% 0.04% 0.00

2 RCC Total Cum 6566 890 890 0 0.00 0.00 0.00 0.00% 0.00% 0.00 0%

Slabs-M-30 Cum 1843 304 304 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00

Beams-M-30 Cum 1514 221 221 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00

Staircases-M-30 Cum 726 45 45 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00

Corewalls

M-30 Cum 510 0.00 0.00 0.00 0.00 0.00 0.00% 0.00

M-40 Cum 510 0.00 0.00 0.00 0.00 0.00 0.00% 0.00

M-50 Cum 600 0.00 0.00 0.00 0.00 0.00 0.00% 0.00

M-60 Cum 863 320 320 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00

3 Formwork Total Sqm 46334 6295 6295 0 18 108 108 1.72% 0.52% 0.00

Corewalls Sqm 13,520 2,185 2,185 0.00 0 0.00 0 0.00% 0.00% 0.00

Flat slabs Sqm 11,370 1,820 1,820 0.00 0 0.00 0 0.00% 0.00% 0.00

Beams Sqm 16,284 1,990 1,990 0.00 0 0.00 0 0.00% 0.00% 0.00

Staircases Sqm 5,160 300 300 0.00 20 108.00 108 36.00% 2.09% 0.00

3 Chipping and piull out of dowel Total no 50000 5920 5920 380 145 145 525 2.45% 2.45% 10.00

no 50,000 5,920 5,920 380.00 145 145.00 525 2.45% 2.45% 10.00

MAN POWER STATUS AS ON : 10-Jan-20

S.No Name of the Agency Area of Working Carp Fitters Helpers Chipper Masons Helpers Supvsrs Un Skilled Others Scaffolding TOTAL

1 KHB North Tower 7 1 5 8 4 3 0 0 6 34

Safety, Store, Electrical, Fleet


2 KHB 2 2
etc

3 KHB Night Shift 0

Total Man Power in site 7 1 5 8 0 6 3 0 0 6 0 36

TOOLS AND PLANTS STATUS AS ON: 10-Jan-20 36


KOOL HOME BUILDERS
Project :Sands InfinIT SEZ Projects, Cochin ( Kerala)
Date 10-Jan-20

10-Jan

11-Jan

12-Jan

13-Jan

14-Jan
1-Jan

2-Jan

3-Jan

4-Jan

5-Jan

6-Jan

7-Jan

8-Jan

9-Jan
Sr. No Description
Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day
Workmen
Reinforcement Fitter 4 4 3 4 1 2 2 2
Carpenter 4 5 5 4 4 4 4 6
Carpenter /Fitter Helper 3 3 3 3 2 3 4 5
Mason
Mason Helper 4 4 5 5 6 6 5 6
Unskilled 2 2 2
Chipper 3 4 4 6 8 8 6 6
Welder
New labour
Scaffolding 4 4 4 4 5 6 6 6 6
Supervisor 1 1 1 1 1 1 2 2
Foreman 2 2 2 2 2 2 2 2
Total 27 0 29 0 29 0 23 0 11 0 30 0 32 0 0 0 31 0 35 0 0 0 0 0 0 0 0

Staf
Managers
Planning
QS
SC Billing
Engineers
Safety Manager/ Asst manager
Safety Officers
safety Supervisors/Steward
HR
Electrical
Tools & plants
Supply chain management
Accounts
surveyor
Store
Quality
Foreman/supervisor
Manpower controler
Security
Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Total of staf and Workmen 27 0 29 0 29 0 23 11 0 0 30 0 32 0 0 0 31 0 35 0 0 0 0 0 0 0 32


14-Jan

15-Jan

16-Jan

17-Jan

18-Jan

19-Jan

20-Jan

21-Jan

22-Jan

23-Jan

24-Jan

25-Jan

26-Jan

27-Jan

28-Jan

29-Jan

30-Jan

31-Jan
Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night Day Night

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 5 0 0 0 0 0 0 0 6 0 6 0 0 0 0 0 0 0

0 31 0 0 0 0 0 0 0 40 0 40 0 0 0 0 0 0 0
KOOL HOME BUILDERS
Project :Sands InfinIT SEZ Projects, Cochin ( Kerala) 10-Jan-20
Traget for Actual work done Qty Executed till date
Sr. No Description UOM BOQ TY Dec'19 for the day

1 Reinforcement MT 545.00 48.00 0 0.20

RCC Cum 2,483.00 320.00 - 0.00


2
Slabs-M-30 Cum 1,843.00 304.00 - 0.00

Beams-M-30 Cum 1,514.00 221.00 - 0.00

Staircases-M-30 Cum 726.00 45.00 - 0.00

Corewalls-M-30 Cum

M-30 Cum 510.00 - - 0.00

M-40 Cum 510.00 - - 0.00

M-50 Cum 600.00 - - 0.00

M-60 Cum 863.00 320.00 - 0.00

3 Formwork Sqm 46,333.70 6,295.00 18 108.00

Corewalls Sqm 13,520.00 2,185.00 - 0.00

Flat slabs Sqm 11,370.00 1,820.00 - 0.00

Beams Sqm 16,283.70 1,990.00 - 0.00

Staircases Sqm 5,160.00 300.00 20 108.00


Balance Qty % complete

545 0%

2,483 0%

1,843 0%

1,514 0%

726 0%

510 0%

510 0%

600 0%

863 0%

46,226 0%

13,520 0%

11,370 0%

16,284 0%

5,052 2%
Efficiency
1) Form work Date 10-Jan-20
Sr. No Description Qty UOM Remarks
1 Carpenter 4 Nos
5 sqm per carpenter
Minimum Formwork out
2 20 Sqm considered as per CPWD
required norms
3 Actual output 18 sqm
4 Output 90%

2) Reinforcement
Sr. No Description Qty UOM Remarks
1 Reinforcement Fitter 2 Nos
120kg per reinforcement
Minimum reinforcement out
2 0 MT fitter considered as per
required CPWD norms
3 Actual output 0.2 MT
4 Output 83%
PHASE- I MASONARY
Description X - TOWER W - TOWER V - TOWER U - TOWER
Clearance for Clearance for Days Clearance for Days
S.No Plastering Plastering Plastering
Floor Level X - Tower
Plnd Plnd Days Achd Achd Days Plnd Plnd days Achd Achd days Plnd Plnd days Achd Achd Days Plnd Plnd Days Achd Achd Days

17-Jan-16 30 24-Jan-16 30 3-Feb-16 30 24-Feb-16 30


1 Terrace Floor

18-Dec-15 20 25-Dec-15 20 4-Jan-16 20 25-Jan-16 20


2 17th Floor Lvl

28-Nov-15 20 5-Dec-15 20 15-Dec-15 20 3-Jan-16 20


3 16th Floor Lvl

8-Nov-15 20 15-Nov-15 20 25-Nov-15 20 12-Dec-15 20


4 15th Floor Lvl

19-Oct-15 20 26-Oct-15 20 5-Nov-15 20 24-Nov-15 20


5 14th Floor Lvl

29-Sep-15 20 6-Oct-15 20 16-Oct-15 20 6-Nov-15 20


6 13th Floor Lvl

9-Sep-15 20 16-Sep-15 20 26-Sep-15 20 19-Oct-15 20


7 12th Floor Lvl

20-Aug-15 20 27-Aug-15 20 6-Sep-15 20 1-Oct-15 20


8 11th Floor Lvl

31-Jul-15 20 7-Aug-15 20 17-Aug-15 20 13-Sep-15 20


9 10th Floor Lvl

11-Jul-15 20 18-Jul-15 20 28-Jul-15 20 25-Aug-15 20


10 9th Floor Lvl

21-Jun-15 20 28-Jun-15 20 8-Jul-15 20 6-Aug-15 20


11 8th Floor Lvl

1-Jun-15 20 8-Jun-15 20 18-Jun-15 20 18-Jul-15 20


12 7th Floor Lvl

12-May-15 20 ### 21 19-May-15 20 29-May-15 20 29-Jun-15 20


13 6th Floor Lvl

22-Apr-15 20 4-May-15 14 29-Apr-15 20 ### 13 9-May-15 20 10-Jun-15 20


14 5th Floor Lvl

2-Apr-15 20 20-Apr-15 2 9-Apr-15 20 6-May-15 9 19-Apr-15 20 22-May-15 20


15 4th Floor Lvl

13-Mar-15 20 18-Apr-15 45 20-Mar-15 20 27-Apr-15 51 30-Mar-15 20 9-May-15 60 3-May-15 20


16 3rd Floor Lvl

21-Feb-15 20 4-Mar-15 22 28-Feb-15 20 7-Mar-15 14 24-Apr-15 48 10-Mar-15 20 10-Mar-15 -1 19-Apr-15 40 14-Apr-15 20 18-May-15 21
17 2nd Floor Lvl

1-Feb-15 20 10-Feb-15 22 8-Feb-15 20 21-Feb-15 21 14-Mar-15 21 18-Feb-15 20 9-Mar-15 -23 26-Mar-15 17 26-Mar-15 20 27-Apr-15 40
18 1st Floor Lvl

12-Jan-15 19-Jan-15 -7 19-Jan-15 31-Jan-15 -12 10-Feb-15 10 29-Jan-15 14-Feb-15 -16 10-Mar-15 24 6-Mar-15 18-Mar-15 -12
19 Grnd Floor Lvl
TATA PROJECT LIM
EMC BUILDING COLUMN PROGRESS LAYO

AREA - I AREA - II

GRID 1 2 3 4 5 6 7 8

Portico slab completed-5.06m lvl.

B C4 C5 C4 C9A C9B C9 C9 C9

C C6 C7 C6 C9A C9 C9
SLAB F/w & R/F UNDER
PROGRESS BY
D.K.MEHTA FOR 21.26M
LVL.SLAB
D C6 C7 C6 C9 C9 C9
SLAB F/W & R/F UNDER
SLAB F/W & R/F UNDER
E PROGRESS BY C9 C9
SHYAMLALGUPTA
(21.26MLVL.)
F C6 C7 C6 C9 C9 C9 C9 C9

completed

G C6 C7 C6

H C9 C9 C9 C9 C9

J C6 C7 C6

L C4 C5 C4 l

INDEX

REINFORCEMENT COMPLETED

FIRST LIFT CONCRETE COMPLETED


SECOND LIFT CONCRETE COMPLETED

SLAB CONCRETE DONE

BEAM BOTTOM IN PROGRESS

SLAB SHUTTERING IN PROGRESS


OJECT LIMITED
RESS LAYOUT FOR +21.26 M LVL SLAB
REPORT DTAE 15/09/2014
DATA DATE 14/09/2014
AREA -III AREA - IV

9 10 11 12 13 14 15 16 17

C9 C9 C9 C9 C9 C9 C1 C2 C1

C9 C3 C3

C3 C3
C9 C9 C9 C9 C9 C9

C9 C9 C9 C9 C9 C9 C3 C3

C3 C3

C9 C9 C9 C9 C9

C3 C3

C8 C8 C8

C1 C2 C1