IDNHPT-PTT-EL-003
Contents
1. Items and Materials
2. Scope
3. Code and Standard
4. Guarantee
5. Installation
6. Paint
7. Packing and Protection
8. Delivery Terms and Point
9. Submission of Documents
10. Vendor Supervisor
11. Spare Parts
12. Special Notes
13. Specification
Attachments
1. Specification List for Gear Pump (Doc.No.IDNHPT-PTT-EL-003)
2. Engineering Specification For Painting
2. Scope
□Basic design ■Spec. Sheet & DWG ■Detailed design ■Procurement ■Fabrication ■Painting
□Authority Application (If Necessary) ■Vendor’s Factory Inspection ■Attendance Inspection
■Transportation (at Site) □Installation at site
4. Guarantee
If any failures are found before twelve (12) months from the date after completion of Performance
Tests, Vendor shall promptly make good or renew such Defects or remedy the Defects at its own cost
and expense to the satisfaction of the Client.
Vendor warrants and guarantees that all the Material supplied shall conform to the requirements of
all applicable laws and codes, product liability laws, safety measures and warning indication.
Warning shall be also shown on operation manual.
5. Installation
Anchor bolts/nuts shall be provided by vendor, which will be installed in concrete foundation.
Bolt-dia., length and material shall be considered by vendor.
6. Paint
Carbon Steel Portion : Painting to be applied as per attached Engineering Specification For
Painting.
Vendor shall provide touch-up paint with the mentioned above.
9. Submission of Documents
1) Approval for Design
Vendor shall submit specification of supply equipment. Vendor shall not start fabrication at
their factory without approval by Customer and/or Purchaser.
2) The following number of copies shall be submitted in principle.
Supply Equipments Data 4 copies (Customer 2 copies, HPT 1 copy, Return to Vendor 1 copy)
Test and Inspection Report 4 copies (1 original and 3 copies)
Record Documents 4 copies (Customer 2 copies, HPT 2 copies)
1 Auto CAD data file for all drawings
3) Vendor shall submit Minute of Meeting in each Meeting between HPT and Vendor.
4) Lifetime for spare parts shall be mentioned on spare parts list.
5) Vendor shall submit any documents as specified in this Specification within the date HPT
required.
6) Operation manual shall be revised correctly and submit to HPT, if HPT find any conflict,
faults under pre-commissioning and commissioning.
7) Vendor shall submit additional documents where HPT and Vendor for discuss about additional
requirements and mutually agreed items are mentioned.
8) Language in all documents and drawings submitted shall be written in English.
9) Vendor shall submit deviation list.
Otherwise, all the Vendor’s specifications are deemed to meet the Purchaser’s specifications.
REGEND: “◎“ marked items shall be supplied before delivery. “○“ Applicable.
Specification for Gear Pump Spec. No. IDNHPT-PTT-EL-003
13. Specification
1) Vendor shall provide explosion-proof equipment/instruments/parts etc. which is applicable for the
following Hazardous Area Classification.
Hazardous Area Classification.
NEC article 500,
ClassⅠ, Division1, Group D
→ PU-1202A,PU-1203A