CALCULATION MIX

Project Name : Asphalt Road Repair by Raise Up with CTB WR No : 386466


Location : Simpang Babinsa to Jembatan #1 Area :
Date of Prepared : November 10. 2011 Length :
Date of Spreading : Doc, No :

COMPOSITION MDD DENSITY LOOSE


No MATERIAL (%) ( Gr/cc ) ( Gr/cc )
A B C

1 Aggregate Basse Class " A " 80 2.156 1.754

2 Soil / Sandy Clay 20 1.908 1.275

3 Cement by weigth material 5

LOOSE FACTOR MATERIAL

No MATERIAL Formula = ( B : C )

1 Aggregate Basse Class " A " 1.229

2 Soil / Sandy Clay 1.496

No MATERIAL COMPOSITION COMPOSITION IN MIXTURE

1 Aggregate Basse Class " A " 80% x 100 80%

2 Soil / Sandy Clay 20% x 100 20%

3 Cement 5% from ( Aggregate + Soil ) 5% from ( Aggregate + Soil )

FROM LABORATORIUM TEST RESULT MDD ( T/M3 ) 2.204 T/M3 Mix

WEIGHT OF MATERIAL FOR 1M3 MIXING


COMPOSITION MDD MIXTURE WEIGHT
No MATERIAL A B (AxB)
(%) ( T/M3 ) Ton

1 Cement 0.05 2.204 0.110

Weight of Aggregate + Soil ( Mixture ) = 2.204 - 0.108 2.094

2 Aggregate Basse Class " A " 0.8 2.094 1.675

3 Soil / Sandy Clay 0.2 2.094 0.419

TOTAL ( Aggregate + Soil + Cement ) 2.204

Prepare By, Checked By : Reviewed/Approved By ;


QC Inspector PT.Multi Structure QA/QC PT.Multi Structure CPI Representative

Name : Name : Name :


Date : Date : Date :
CALCULATION FOR MIXING

VOLUME MIXING UNIT WEIGHT OF MATERIAL


UNIT
( Plan ) ( VOL x MDD )

10 ( M3 ) 22.04 TON

CEMENT ( 5 % x WEIGHT OF MATERIAL ) 1.102 TON

AGGREGATE BASE CLASS " A " 16.750 TON

SOIL/SANDY CLAY 4.188 TON

TOTAL ( AGGREGATE + SOIL + CEMENT ) 22.04 TON

No SOLID VOLUME OF MATERIAL WEIGHT / MDD UNIT

1 AGGREGATE BASE CLASS " A " 9.550 M3

2 SOIL/SANDY CLAY 2.195 M3

No LOOSE VOLUME OF MATERIAL WEIGHT / LOOSE FACTOR UNIT

1 AGGREGATE BASE CLASS " A " 13.627 M3

2 SOIL/SANDY CLAY 2.798 M3

COMPARE TO BUCKET EXCAVATOR : ( CAPACITY OF BUCKET EXCAVATOR = 1.0 M3 / BUCKET )

AGGREGATE BASE ''A'' ( BUCKET ) SOIL / SANDY CLAY ( BUCKET ) CEMENT ( ton )

13.627 2.798 1.102

12.4 2.5 1

Note : Untuk pelaksanaan dilapangan digunakan : 0.8 m3/ Bucket

15.5 Bucket Aggregate "A"


3 Bucket Soil
1 Tons Cement

Prepare By, Checked By : Reviewed/Approved By ;


QC Inspector PT.Multi Structure QA/QC PT.Multi Structure CPI Representative

Name : Name : Name :


Date : Date : Date :
CALCULATION FOR MIXING

VOLUME MIXING UNIT WEIGHT OF MATERIAL


UNIT
( Plan ) ( VOL x MDD )

1 ( M3 ) 2.204 TON

CEMENT ( 5 % x WEIGHT OF MATERIAL ) 0.1102 TON

AGGREGATE BASE CLASS " A " 1.675 TON

SOIL/SANDY CLAY 0.419 TON

TOTAL ( AGGREGATE + SOIL + CEMENT ) 2.204 TON

No SOLID VOLUME OF MATERIAL WEIGHT / MDD UNIT

1 AGGREGATE BASE CLASS " A " 0.955 M3

2 SOIL/SANDY CLAY 0.219 M3

No LOOSE VOLUME OF MATERIAL WEIGHT / LOOSE FACTOR UNIT

1 AGGREGATE BASE CLASS " A " 1.363 M3

2 SOIL/SANDY CLAY 0.280 M3

COMPARE TO BUCKET EXCAVATOR : ( CAPACITY OF BUCKET EXCAVATOR 0.8 M3/Bucket

AGGREGATE ''A'' SOIL / SANDY CLAY CEMENT

1M3 1.363 M3 1M3 0.280 M3 1M3 0.110 Tons

1M3 1.7 Bucket 1M3 0.3 Bucket 1M3 2.2 Zack

10 17 Bucket 10 3 Bucket 10 22 Zack

20 34 Bucket 20 7 Bucket 20 44 Zack

30 51 Bucket 30 10 Bucket 30 66 Zack

40 68 Bucket 40 14 Bucket 40 88 Zack

50 85 Bucket 50 17 Bucket 50 110 Zack

60 102 Bucket 60 21 Bucket 60 132 Zack

70 119 Bucket 70 24 Bucket 70 154 Zack

80 136 Bucket 80 28 Bucket 80 176 Zack

90 153 Bucket 90 31 Bucket 90 198 Zack

100 170 Bucket 100 35 Bucket 100 220 Zack

110 187 Bucket 110 38 Bucket 110 242 Zack

120 204 Bucket 120 42 Bucket 120 264 Zack

130 221 Bucket 130 45 Bucket 130 287 Zack

Prepare By, Checked By : Reviewed/Approved By ;


QC Inspector PT.Multi Structure QA/QC PT.Multi Structure CPI Representative

Name : Name : Name :


Date : Date : Date :
LOCATION :

Panjang 1080 Meter Material 1M3

lebar 7 Meter Cement 5% 0.110

tebal 0.2 Meter Aggregate "A" 80% 1.675

Volume 1512 M3 Soil 20% 0.419

Total 2.204

COMPOSISI : 1 M3 ( Cement + Agg "A" + Soil )

Material 1M3

Cement 5% 0.110 Tons 1 Zack 1

Aggregate "A" 80% M3 0.000 M3 0.0

Soil 20% M3 0.000 M3 0.0

Material yang di butuhkan untuk Volume = 1512 M3.

Cement Ton Cement

Aggregate "A" 1,210 M3 Aggregate A

Soil 423 M3 Soil

Note :

Density Loose for Aggregate "A" 1.754 Tons/M3

Density Loose for Soil Sandy 1.315 Tons/M3

1 Zack Cement 50 Zack

Volume Bucket 0.8 M3


Unit

Tons

Tons

Tons

Tons

Zack

Bucket

Bucket

1512 M3.

76 zack

1,210 M3

302 M3 `