2008 2009 2010

Contract price 5,500,000 5,500,000 5,500,000

Less estimated cost


Cost to date 2,000,000 3,516,000 4,500,000
Est cost to complete 2,500,000 984,000 -
Est total costs 4,500,000 4,500,000 4,500,000

Est total gross profit 1,000,000 1,000,000 1,000,000

Percent complete 44.44% 78.13% 100.00%

2008 2009 2010


Revenue recognized 2,444,444
(5.500.000*44.44%) 4,297,333
(2,444,444)
1,852,889
(5.500.000*78.13%) 5,500,000
(4,297,333)
1,202,667

2008 2009 2010


Gross Profit recognized 444,444
(1.000.000*44%) 781,333
(444,444)
336,889
(1.000.000*78.13%) 1,000,000
(781,333)
218,667

2008 2009 2010


CIP 2,000,000 1,516,000 984,000
Material 2,000,000 1,516,000 984,000

AR 1,500,000 2,400,000 1,600,000


Billing 1,500,000 2,400,000 1,600,000

Cash 1,750,000 1,750,000 2,000,000


AR 1,750,000 1,750,000 2,000,000

CIP 444,444 336,889 218,667


Construction Expenses 2,000,000 1,516,000 984,000
Revenue from LT 2,444,444 1,852,889 1,202,667

Billing on CIP 5,500,000


CIP 5,500,000