20041124
BOILER BED COIL
PITTING:
Oxygen presence in feed water reacts with boiler tube metal to form iron oxide. Results the
tube internals surface is corroded in deep groove spots called pitting.
This can happen in running condition due to excessive oxygen in feed water or due to
improper passivation.
It is normally observed near economiser feed water inlet area on running boiler and due to
improper passivation this can be observed at non drainable surface.
Cracks take place where combination of high tensile stress and corrosion fluids are present.
Cracks may be trans granular or inter granular in the tube wall.
Normally it is observed near higher external stresses like attachments
BED COIL REPLACEMENT PROCEDURE
PROCEDURE:
First of all the manhole door are opened then the start up oil firing system was disconnected
from boiler.
DEISEL LINE
PA LINE
BEVEL EDGE
DUMMY COVER
STUB/TUBE
CHAMFERING M/C
The bed coil tubes are cleaned by service air (4kg/cm2) with the help of
polyurethane sponge. It is used minimum 3 times for better cleaning.
A temporary clamp was made to hold up the bed coil for fit up.
Now the alignment procedure starts-
o First of all they got the centre between the top ring header and bottom ring header.
o Then the level of centre line and bed coil centre was checked. (It means the centre
line of the headers and bed coil should be in same level). water level used for
checking the level.
o After that they clamped the inner bed coil by the clamp, making a gap of 2-3 mm
between the stub and bed coil edge by the help of welding rod.
CLAMP
WELDING ROD
CENTRE LINE
OUTER BED COIL
BOTTOM HEADER
o After tech weld the clamp was removed and then fill up/full welding was done.
Welding specification:
TUNGSTEN INERT GAS WELDING (TIG) SHIELDED METAL ARC WELDING (SMAW)
o A “T” rod was made to measure the distance between bed coils to bed coil.
o To ensure the vertical height of bed coils, a string was holding by two workers. Then the
vertical height is measured by a plumb.
o After checking height of all bed coils, it is declared that the bed coil replacement done. Then
radiography of all joint done.