Вы находитесь на странице: 1из 17

Miami Pedestrian Bridge Collapse:

Computational Forensic Analysis


Ran Cao, S.M.ASCE 1; Sherif El-Tawil, F.ASCE 2; and Anil Kumar Agrawal, M.ASCE 3

Abstract: On March 15, 2018, a pedestrian concrete truss bridge in Miami, Florida, collapsed during construction. The failure of this
bridge caused multiple casualties and raised many serious concerns regarding the design and construction of the bridge, including the
emerging concept of accelerated bridge construction (ABC). The causes of failure of this bridge have not yet been comprehensively
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

investigated. This paper used high-fidelity computational simulation to investigate the behavior of critical structural members of the bridge
during construction. Four important construction stages (prestressing, transportation, relocation, and retensioning) were simulated to iden-
tify dominant factors that could have contributed to the failure of the bridge. A recent investigation report from the National Transportation
Safety Board (NTSB) attributed the collapse to flawed design at the failed joint at the northern end of the bridge, but the specific sequence
of mechanisms that led to collapse was not identified. Based on simulation and demand/capacity analysis, this work shows that the hori-
zontal component of the retensioning force overcame the resistance of the joint and caused it to slide with respect to the deck. As sliding
progressed, dowel action between the deck and joint became fully mobilized, crushing and damaging concrete locally within the joint and
the deck. The evolving damage (to the cold joint and adjacent joint and deck concrete) prompted more sliding and led to a vicious cycle
that culminated in the collapse of the entire bridge. Parametric studies investigated the effects of the coefficient of friction at the cold joint,
prestressing forces in the deck, and retensioning forces applied to the northern diagonal member on the collapse behavior of the bridge. The
results from the analysis and simulations provide important insights into the collapse mechanism and highlight lessons that could be learned
for preventing similar catastrophic failures in the future. DOI: 10.1061/(ASCE)BE.1943-5592.0001532. © 2019 American Society of Civil
Engineers.

Introduction According to the preliminary report from the NTSB (2018c), work-
ers were retensioning tendons in diagonal Member 11 when the
Fig. 1 is a rendering of the planned FIU-Sweetwater UniversityCity bridge collapsed (Fig. 4).
pedestrian bridge. The completed bridge had the look of a cable- The Federal Highway Administration (FHWA) has collaborated
stayed bridge with a pylon and multiple cables attached to the with the NTSB to test and evaluate the construction materials col-
canopy. However, the main span of the bridge was designed as lected from the collapse site, including samples of concrete, steel
a concrete truss bridge, which was self-supporting without the bars, and one of the posttensioning rods. After initial tests, no sig-
cables, i.e., the pylon and cables were just for aesthetic purposes. nificant issues were found in the material samples per NTSB
The use of concrete trusses in bridges is rather uncommon because reports (NTSB 2018a, b). A preliminary investigation also was con-
it requires prestressing truss members undergoing tension, because ducted by the NTSB on the recovered bridge deck from the north
concrete is weak in tension. The construction of the entire bridge end (NTSB 2018c). Reinforcement bars were found to be em-
was scheduled to be finished by early 2019 and was built using the bedded correctly as prescribed in the design drawings. The NTSB
accelerated bridge construction (ABC) method. After being precast also released several photographs showing cracks in the joint area
near the highway, the main span of the bridge was transported and of diagonal Member 11, which occurred before relocating the main
placed on the bridge piers by two transporters on March 10, 2018. span of the bridge from the ground to the bridge piers (NTSB
Fig. 2 shows the bridge during transportation. On March 15, 2018, 2018a, c). The development of these cracks continued after the re-
5 days after the relocation, the main span of the bridge collapsed location of the main span. Based on the latest report from NTSB
onto US Route 41 (Fig. 3). This accident resulted in six fatalities (2018b), the design of the concrete joint at the north end was
and at least eight injuries (NTSB 2018c). The collapsed span was deemed unconservative. The flawed joint design echoed the col-
around 53-m (174-ft) long and weighed 862 Metric tons (950 t). lapse of the I-35 truss bridge in 2007, in which joint failure also
was considered to be the main cause of the collapse (NTSB 2008;
1
Graduate Student, Dept. of Civil and Environmental Engineering, Hao 2010). The significance of joint design for concrete truss
City College of the City Univ. of New York, New York, NY 10031 (cor- bridges was highlighted in many studies (Jung et al. 2010; Xue
responding author). ORCID: https://orcid.org/0000-0002-7075-9800. et al. 2011; Berman et al. 2012).
Email: rcao000@citymail.cuny.edu Although the NTSB (2018b) investigation identified Member
2
Professor, Dept. of Civil and Environmental Engineering, Univ. of 11’s joint as a likely cause for failure, the report was not clear
Michigan, Ann Arbor, MI 48109. about the specific set of mechanisms or sequence of processes
3
Professor, Dept. of Civil and Environmental Engineering, City College
that led to failure. The objective of this study was to critically evalu-
of the City Univ. of New York, New York, NY 10031.
Note. This manuscript was submitted on May 1, 2019; approved on
ate the design of this bridge and study the possible failure mech-
October 7, 2019; published online on November 7, 2019. Discussion anisms through high-fidelity finite-element (FE) simulations. A
period open until April 7, 2020; separate discussions must be submitted detailed FE model of the bridge was created based on as-built draw-
for individual papers. This paper is part of the Journal of Bridge ings (FIU 2017a) and run on the LS-DYNA version R10.0.0 plat-
Engineering, © ASCE, ISSN 1084-0702. form (Hallquist 2006). Four different construction stages were

© ASCE 04019134-1 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 1. Rendering of the FIU pedestrian bridge.

Fig. 2. (a) Aerial photo of bridge location (imagery © 2019 Google, imagery © 2019 Maxar Technologies, Map data © 2019 USGS); and (b) photos
of the FIU pedestrian bridge during construction (image reprinted from FIU 2018).

Fig. 3. Collapse scene of the pedestrian bridge. (Reprinted from NTSB 2018c.)

simulated, namely prestressing, transportation, relocation, and re- collapse resistance of the bridge. The parameters considered in-
tensioning. After developing a theory of how the collapse initiated cluded the coefficient of friction at the cold joint connecting
and progressed, parametric studies were carried out to investigate Member 11 to the deck, the level of prestressing forces in the deck,
how various influential parameters could have influenced the and the level of retensioning forces applied to Member 11.

© ASCE 04019134-2 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Fig. 4. Initial collapse occurred in the north end. (Images courtesy of Instagram/@o2webdev.)
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 5. Damage mode of the cold joint before and after relocation. (Images reprinted from NTSB 2018a, c.)

Critical Review of Bridge Design Calculations with other related documents, available on their website (FIU,
Facilities Management 2019). A review of the design calculations
According to the NTSB (2018b), the collapse of the bridge was provided by FIU showed that the northern end joint of the bridge
attributed to design errors made in the joint at the northern end was a construction joint, i.e., cold joint. The cold joint was de-
of the bridge. However, the specific design flaws or the failure signed to connect Truss member 11, Member 12, and the deck
mechanism of the joint were not identified in NTSB reports. (Fig. 6). In the calculation document, the shear force across the cold
“In this case, a firm was hired to independently review the bridge joint was reported to be computed from a FE analysis. However, the
design for errors. However, the review conducted by this firm did cold joint was not found to be explicitly modeled in the FE model.
not evaluate the nodes of the bridge truss where they connected
Instead, Members 11 and 12 seemed to have been merged with the
with the bridge deck and canopy nor did it consider the multiple
deck rather than in frictional contact with the deck in the as-built
stages the bridge construction involved” NTSB (2019b). Fig. 5
shows physical evidence at the damaged concrete joint from the situation. In addition, the boundary condition of the main span of
NTSB investigation. Concrete cracking developed in the heel of the bridge was supposed to be simply supported (before the pylon
Member 11, which appeared to be caused by the sliding of the joint connection), but a sketch of the design model (Fig. 6) did not look
(Fig. 5). In addition, a diagonal crack developed in the concrete like a traditional simply support boundary condition, raising ques-
deck adjacent to Member 12, signifying a potential punching shear tions about the accuracy of the demand calculations. For example,
failure mode. Based on the observations from Fig. 5 and the NTSB Fig. 7 shows the shear force and compression force at the northern
studies, a critical review of the joint design was conducted in this end joint of the bridge calculated by the designer (FIU 2017b). The
study, mainly focusing on the capacity of shear friction, punching calculation results of the forces acting on the joints in Fig. 7 do not
shear, and blowout damage of the concrete joint. seem to be correct based on the geometry of the joint. Hand cal-
culations by the authors showed that the shear demand at the
Superstructure Design Provided by FIU northern end joint should be 9,168 kN, which is over twice the
In response to public records requests, Florida International shear force of 4,390 kN calculated by the designer. The compres-
University has made the design calculations of the bridge, along sion force on the joint was calculated to be 5,509 kN by the authors

© ASCE 04019134-3 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 6. Sketch of the FE model of the bridge before pylon connection.


(Adapted from FIU 2017b.)
Fig. 8. Detailing of the cold-joint model.

cold joint, the coefficient of friction was assumed to be 1.0 per


ACI (2011).
The frictional capacity of the joint surface is calculated by
Eq. (1), where Fp is the prestressing force in Member 11, FG is
the axial force in Member 11 due to gravity (self-weight), and
α is the inclination angle of Member 11 with the horizontal surface

f ¼ μðFp þ FG Þ sin α
¼ 1.0 × ð2,491 þ 8,205Þ × sinð31°Þ ¼ 5,509 kN ð1Þ

The dowel action associated with the rebars contributes to the


shear capacity of the cold joint. Dowel capacity is computed by
considering the bars as steel shear studs in a composite structure
composed of the deck on one side and the joint connecting
Members 11 and 12 on the other side. Per AISC (2010), the shear
strength of anchors, Qn , is calculated by Eq. (2), where Asa is the
cross-sectional area of the stud (mm2 ); f c0 is the compressive
Fig. 7. Interface shear design of the northern end zone by the designer.
strength of the concrete (MPa); Ec is the modulus of elasticity
(Data from FIU 2017b.)
of the concrete (MPa); Rg and Rp are 1.0 and 0.75, respectively,
for solid slabs; and Fu is the minimum tensile strength of the stud
(MPa). The dowel capacity was estimated to be 3,109 kN [Eq. (2)].
The capacity in Eq. (2) does not incorporate a strength-reduction
(as discussed subsequently) and was close to the design force of factor because this was an assessment exercise and not a design
5,485 kN. exercise
pffiffiffiffiffiffiffiffiffiffi pffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
Qn ¼ 0.5Asa f c0 Ec ¼ 0.5×10,012× 58×36233 ¼ 7257 kN
Shear Capacity of Construction Joint
> Rg Rp Asa Fu ¼ 1.0×0.75×10,012 mm2 ×414 MPa ¼ 3,109 kN
In the final plan of the bridge (FIU 2017a), construction joints were
present between the truss members and the slabs (deck and can- Qn ¼ 3,109 kN ð2Þ
opy). During construction, the concrete deck, trusses, and canopy
were cast separately and in a sequence, i.e., the deck was cast first, The shear capacity of the cold joint, C, is equal to the sum of the
then the truss and the canopy. Because the concrete batches were frictional and dowel capacities
cast at different times, construction joints or cold joints were left at
the interface between the truss members and the slabs. Fig. 8 shows C ¼ f þ Qn ¼ 5,509 kN þ 3,109 kN ¼ 8,618 kN ð3Þ
the details of the cold joint at the northern end of the bridge. Mem-
bers 11 and 12 and the deck were connected via the construction The horizontal shear demand acting on the cold joint due to
joint (Fig. 8). The axial loading from Member 11 caused a shear gravity and prestressing was calculated to be 9,168 kN, which
force acting on the cold-joint plane, which was resisted through is larger than the calculated shear capacity [Eq. (4)]. In Eq. (4),
friction at the cold joint and dowel action of the steel rebars cross- PG is the axial loading in Member 11 from gravity, and PP is
ing the joint. Per ACI (2011), the coefficient of friction μ depends the axial loading from prestressing. The results of the hand calcu-
on the roughness of the interface across the joint. In FIU (2017b), lation match the conclusion from the NTSB report (NTSB 2018b)
the surface of the cold joint was intentionally roughened to an am- that the demand was underestimated for the cold joint at the
plitude of 6.35 mm. Therefore, to evaluate the shear capacity of the northern end

© ASCE 04019134-4 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 9. Punching shear in the cold-joint area (vertical Member 12 removed for clarity).

D ¼ ðPG þ PP Þ × cosðαÞ ¼ ð8,205 þ 2,491Þ × cosð31°Þ V ps ¼ ð1 − 0.18Þf ps Aps


¼ 9,168 kN > C ¼ f þ Qn ¼ 8,618 kN ð4Þ ¼ 0.82 × 1,303 MPa × 2 × 1,661 mm2 ¼ 3,550 kN ð7Þ
Per NTSB (2018c), workers were retensioning the tendons in
Member 11 when the bridge collapsed. The retensioning force ap- pffiffiffiffiffi
plied to Member 11 could increase the horizontal shear demand Vc ¼ 4 f c0 Ac
pffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
acting on the cold joint. For example, per Eq. (5), if the prestressing ¼ 4 58 × 145 × 0.0069 × ð1,159 × 625 þ 2 × 659 × 625Þ
force in Member 11 is increased by 25% of the designed value,
reaching the yield strength of the tendons, the demand will increase ¼ 3,918 kN ð8Þ
from 9,168 to 9,702 kN. In this scenario, per Eq. (6), the retension-
ing force also will increase the shear capacity from 8,618 to where V ps = prestressing force of tendons in deck; f ps = prestress-
8,939 kN. The overall demand:capacity ratio for the cold joint in- ing stress of tendon; Aps = area of tendon; V c = punching shear
creases from 1.06 to 1.09 due to retensioning, making the joint capacity of concrete; fc0 = compressive strength of concrete; and
more vulnerable to sliding. The concrete of the cold joint had been Ac = area of shear planes.
damaged before the retensioning per NTSB (2018a), which could The steel bar reinforcement also contributed to the punch-out
further degrade the assumed frictional capacity of the joint interface capacity
and aggravate the sliding capacity of the cold joint. The loads in
Eqs. (5) and (6) are the design loads without factors V s ¼ f y As ¼ 414 MPa × 3 × 4 × 2 × 129 mm2 ¼ 1,282 kN
D ¼ ð1.25 × Fp þ FG Þ × cosð31°Þ ð9Þ

¼ ð1.25 × 2,491 þ 8,205Þ × cosð31°Þ ¼ 9,702 kN ð5Þ

C ¼ f þ Qn ¼ μðFp þ FG Þ sin α þ Qn
¼ 1.0 × ð1.25 × 2,491 þ 8,205Þ × sinð31°Þ
þ 3,109 kN ¼ 8,939 kN ð6Þ

Punching Shear Capacity of Deck


Another possible failure mode of the cold-joint area is punching
shear. The north end of the concrete deck could punch out under
the effect of compressive axial loading from Member 11 (Fig. 9).
Two diagonal cracks radiating out at 45° (Fig. 9 inset, dashed lines)
could develop from the ends of Member 11 to form a wedge (Fig. 10).
The punch-out wedge geometry (based on 45° cracks) was inspired
by the punching shear design process for flat slabs (ACI 2011).
The two deck tendons adjacent to Member 12 were located
within the punch-out wedge (Fig. 10) and therefore could contrib-
ute to punch-out resistance [Eq. (7)]. An 18% prestress loss due to
time-dependent losses, such as creep and shrinkage of concrete and
steel relaxation (AASHTO 2017), was assumed. The punching
shear resistance due to concrete is computed in Eq. (8). As in
Fig. 10. Calculation diagram of punching shear.
Eq. (2), a strength-reduction factor was not used

© ASCE 04019134-5 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


where V s = capacity of regular steel bars; f y = yield strength of
steel bars; and As = area of steel bars.
Because it is not clear how much the prestressing tendons con-
tribute to the total punching shear strength, the capacity with and
without the tendons was computed (Cases 1 and 2, respectively) to
bracket the capacity.
Case 1: Punching shear capacity, V total , considering the effects
of tendons

V total ¼ V c þ V ps þ V s ¼ 3,918 þ 3,550 þ 1,282 ¼ 8,750 kN < D


¼ 9,168 kN ðdemandÞ ð10Þ

Case 2: Punching shear capacity, V total , without considering the


tendons
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

V total ¼ V c þ V s ¼ 3,918 þ 1,282 ¼ 5,200 kN


< 9,168 kN ðdemandÞ ð11Þ
Fig. 11. Concrete blowout failure mode of the anchorage area in the
Eqs. (10) and (11) show that the joint may have been defi- north end.
cient regarding this type of failure regardless of how much of
the tendons’ prestressing capacity had been engaged in preventing
punch out.
Blowout Damage from Prestressing Bars
Fig. 11 shows the possibility for blowout damage at the anchorage
Axial Loading Capacity of Member 11 points of the prestressing tendons (ACI 2011). The prestressing
Eqs. (12) and (13) compute the axial load capacity of and axial bars in Member 11 were anchored just inside the concrete joint area
demand on Member 11 per ACI (2011), in which Pn is the axial (Fig. 11). The anchor plates, which were embedded inside the joint
capacity, Ag is the gross area of the concrete section, Ast is the area region, had a relatively small size of 200 × 300 mm. Each of the
of the longitudinal steel rebars, f y is the yield strength of the rebars, anchor plates transferred a substantial anchoring force of 1,245 kN.
Aps is the area of the prestressing bars, and Dm11 is the axial de- Although concrete blowout would have been inhibited once the
mand on Member 11 due to gravity and prestressing. As noted pre- bridge was placed on its supports, it could have caused internal
viously, a strength-reduction factor was not used in Eq. (12). damage during transportation, weakening the joint region before
In Eq. (13), the axial loading due to the gravity is 8,205 kN and the bridge went into service.
the prestressing force applied to Member 11 is 2,491 kN per the
design drawings (FIU 2017a)
Finite-Element Modeling
Pn ¼ 0.85f c0 ðAg − Ast − Aps Þ þ Ast fy
¼ 0.85 × 58 MPa × 318,961 mm2 þ 3,096 mm2 × 414 MPa General Modeling Considerations
¼ 15,725 þ 1,282 ¼ 17,007 kN ð12Þ Fig. 12 shows the FE model of the main span of the bridge devel-
oped in LS-DYNA (Hallquist 2006). Nonlinear material models
were used to model the structural members in the northern end
Dm11 ¼ PG þ PP ¼ 8,205 kN þ 2,491 kN ¼ 10,696 kN < Pn of the bridge where the collapse started (Fig. 12, Nonlinear
¼ 17,007 kN ð13Þ material), as observed from the video evidence. To save on the mod-
eling effort, the rest of the bridge was modeled using linear elastic
materials (Fig. 12, Elastic material). The effect of the damage within
Based on the computed results in Eqs. (12) and (13), the axial the elastic regions on the northern end failure was considered to
capacity appears to be sufficient to resist the axial demand. In ad- be small and was ignored in this study. Prestressing was modeled
dition, the design capacity was found to be sufficient even when in Members 10 and 11, the deck, and the canopy of the bridge. The
considering accidental eccentricities (strength reduced by 20%) deck, canopy, and Truss members 10, 11, and 12 (Fig. 12, Nonlinear
per ACI (2011) [Eq. (14)], which also suggests that the design material) were modeled using reduced-integration eight-node solid
of Member 11 to support axial load was not flawed. The fact that elements with hourglass control. Other truss members, prestressing
Dm11 is close to the design capacity [Eq. (14)] has caused wide- tendons, and steel rebars were modeled using beam elements. The
spread speculation that the axial capacity of Member 11 was the steel plates for anchoring prestressing bars were modeled using
reason for the collapse. This argument has been bolstered by the fully integrated solid elements to eliminate hourglassing due to
observation that the collapse was sudden and that axial failure typ-
the highly concentrated nature of the applied forces.
ically occurs without warning. However, as discussed subsequently
The penalty method was used to model contact in LS-DYNA
in more detail and supported by the design computations discussed
(Hallquist 2006). When penetration was detected between two
previously, it is unlikely that the axial capacity of Member 11 was
surfaces, a contact force was applied between the surfaces to elimi-
the reason for the collapse
nate the penetration. More specifically, AUTOMATIC_SURFACE_
TO_SURFACE contact was defined between the anchor plates
ϕPn ¼ 0.8 × Pn ¼ 13,606 kN > Dm11 ¼ 10,696 kN ð14Þ and structural members with a 0.25 coefficient of friction.

© ASCE 04019134-6 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 12. FE setup of the bridge: (a) steel rebars detailing; (b) prestressing tendons detailing; (c) FE model of the bridge; and (d) close-up of
reinforcement at the joint.

Fig. 13. Utility conduits at the north end of the bridge. (Images reprinted from Ayub 2019.)

AUTOMATIC_SINGLE_SURFACE contact was defined between Material Models


the joint connecting Members 11 and 12 and the deck, as well as that
between Members 10 and 11 and the canopy to model the cold The concrete, steel rebars, and prestressing tendons in the Nonlin-
joints at those locations. As discussed subsequently, the static co- ear material in Fig. 12 were explicitly modeled based on the con-
efficient of friction for the contact condition was varied from 0.6 to struction plans (FIU 2017a). Some of the bars and tendons crossed
1.4 and the kinetic coefficient of friction was taken as 0.4. The two from Members 10, 11, and 12 into the canopy and deck per the
bridge piers were modeled as rigid and fixed at their bottom. The construction plans (e.g., Fig. 8). Concrete behavior was modeled
AUTOMATIC_SINGLE_SURFACE contact was defined between by the continuous surface cap model (CSCM MAT159) in
the superstructure and bridge piers. The utility conduits in Fig. 13 LS-DYNA (Hallquist 2006). The model can capture key aspects
and those located on either side of Member 12 also were modeled of inelastic concrete behavior, including postpeak softening and
using eight-node solid elements as discussed subsequently. Finite confinement effects. It is based on an elastoplastic damage formu-
strains were calculated and reported in the simulations. lation that accounts for rate effects. Default material parameters

© ASCE 04019134-7 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Table 1. Material model of bridge
Compressive/yielding Modulus of
Parts Material model strength (MPa) elasticity (MPa)
Concrete CSCM (159) 58 36,232
ELASTIC (1)
Steel bars PLASTIC_KINEMATIC (3) 414 200,000
Prestressing strands (deck) ELASTIC_PLASTIC_THERMAL (4) 1,675 196,500
Prestressing bars (truss) ELASTIC_PLASTIC_THERMAL (4) 896 200,000

were used in this study, which were generated based on the com- space, provide confidence in the authors’ nonlinear modeling ex-
pression strength and the maximum aggregate size of the concrete pertise. The NTSB reports (NTSB 2018a, c) included several pho-
(Murray et al. 2007). The compressive strength of the concrete was tos of concrete cracks in the joint area of diagonal Member 11 and
taken as 58 MPa and the maximum aggregate size was assumed to the deck. As discussed subsequently, these photos show damage
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

be 19 mm, as per the construction plans (FIU 2017a). To avoid that is consistent with the simulation results, providing additional
localization due to softening, the fracture energy was maintained evidence in support of the modeling scheme.
constant for the concrete model regardless of element size
(Murray et al. 2007). This regularization method has been validated
using existing drop hammer tests in the literature that were dis- Numerical Simulation Results
cussed in previous studies (Xu et al. 2019; Cao et al. 2019a). Be-
cause it was not clear how the utility conduits in Fig. 13 were Based on the FE model, four construction stages, i.e., prestressing,
constructed, they were modeled using eight-node solid elements transportation, relocation, and retensioning, were modeled. In these
with low-strength concrete (20 MPa). Steel rebars were modeled simulations, 18% of time-dependent prestress losses were assumed
using Hughes-Liu beam elements and were represented using for the tendons in the deck and trusses as per AASHTO (2017). As
material MAT 3, which accounts for yielding and kinematic hard- noted previously, because the interface of the joint was intention-
ening plasticity. Steel rebar elements were assumed to fracture and ally roughened, the coefficient of friction for the cold joint of diago-
were removed after the strain reached 0.20. The general mesh size nal Member 11 was assumed to be 1.0 (ACI 2011). However,
used was 38.1 mm (1.5 in.). A perfect bond was enforced between because the shear demand was calculated to be larger than the shear
the steel and concrete components by using the coupling method in capacity of the joint and could cause sliding and therefore damage
LS-DYNA, *CONSTRAINED_BEAM_IN_SOLID. Key informa- at the interface as per NTSB (2018a), the kinetic coefficient of fric-
tion about the material is listed in Table 1. tion was assumed to decrease to 0.4 after slip occurred at the joint.

Prestressing Stage (Before Transportation)


Prestressing Modeling
Fig. 14 shows cracking in the cold-joint area after applying the pre-
The tendons in the deck and truss members were unbonded. In the stressing force in the truss member and deck. The contour plots in
FE simulation, the *CONSTRAINED_BEAM_IN_SOLID com- Fig. 14 are of the principal tensile strain of the concrete, a number
mand was used to model the tendons and their interaction with that varies from 0.01% (no crack) to 0.02% (cracked). The heel of
the surrounding concrete. The selected model ensured kinematic Member 11 was damaged under the prestressing force (Fig. 14).
coupling (in displacement, velocity, and acceleration) between The simulation results captured reasonably well the concentration
the tendons and concrete only in the direction normal to the ten- of tensile strains in the heel of Member 11, especially where the
don’s axis, but permitted slip along the tendon’s axis. Prestressing computed strain of the concrete exceeded the cracking strain of
was achieved by cooling the tendons, which shrank in response and the concrete (0.01%).
applied a prestressing force. A similar approach was used in many
studies with reasonable simulation results (Nakalswamy 2010;
Jiang and Chorzepa 2015; Do et al. 2018). The prestressing tendons Transportation Stage
were modeled using the ELASTIC_PLASTIC_THERMAL mate- After being assembled on the ground, the main span was trans-
rial (MAT 4), which can simulate the thermal deformations of the ported onto the piers by two transporters (Fig. 15). After applying
material based on provided temperature time-history curves and a the prestress, gravity loading was applied to the structure and the
given coefficient of thermal expansion. nodes at the bottom of the deck were fixed at the transporters to
model the transportation stage. Fig. 16 shows the behavior of
Validation the bridge during the transportation stage. The north end joint did
not show much damage, although minor cracking was observed in
The concrete (Mat 159) and rebar (Mat 3) models have been va- the concrete under the anchor plates (recall the discussion of blow-
lidated for simulating the flexure/shear behavior of RC specimens out failure). The deflection at the northern end also was found to be
in multiple publications, including Moutoussamy et al. (2011), Liu small, less than 3 mm.
(2012), and Murray et al. (2007). These studies used multiple sets
of experimental data of RC beams subject to static or impact load-
Relocation and Retensioning
ing to prove the effectiveness of the RC modeling scheme. It has
been shown that the selected modeling scheme yielded reasonable After the main span was placed on the piers, the joint started sliding
comparisons with the test results. The authors used the same gen- along the interface at the northern end. The dowel action of the
eral modeling scheme described previously in a number of their stirrups caused internal damage in the joint of Member 11 and
publications where they conducted their own validation studies the concrete deck (Fig. 17). The contour plots in Fig. 17 are of
(Cao et al. 2019a, b, c; Xu et al. 2019). The validation efforts in the damage index of the concrete, a number that varies from 0
those papers, which are not repeated here in the interest of saving (no damage) to 1 (total damage), as defined by Hallquist (2006)

© ASCE 04019134-8 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Fig. 16. Simulated behavior of the main span at the transportation
stage.

apparently the effort was being conducted to reduce the cracking


symptoms observed after bridge placement. Fig. 19 shows a
simulation of the joint being damaged as the prestress level in
Member 11 approached the maximum jacking stress of the tendons,
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

i.e., 94% of yield strength as per ACI (2011). The horizontal com-
ponent of the retensioning force increased the shear demand in the
joint area, further aggravating the sliding situation [Fig. 19(a)]. As
sliding progressed, dowel action became fully mobilized, crushing
and damaging concrete locally within the joint and the deck
(Fig. 19). The evolving damage (to the cold joint and adjacent joint
and deck concrete) prompted more sliding and led to a vicious
Fig. 14. Comparison of cracks in the joint area of Member 11 after cycle that culminated in the collapse of the entire bridge.
prestressing. (Image from NTSB 2018c.) The simulated collapse mode of the structure is compared with
the actual video record in Fig. 20, in which the simulated failure
mode of the bridge matches the actual collapse reasonably well.
In both cases (simulation and actual collapse), severe structural
and Murray et al. (2007). The concrete elements eroded (were re- damage appeared to concentrate at three main locations (Fig. 20),
moved) after the damage index exceeded 0.99 and the maximum initiating the collapse process. Member 11 was damaged in flexure
principal strain was greater than 0.1. Fig. 17 compares the damage (especially at its upper portion) and did not show signs of buck-
mode of the actual joint with that from the simulation. On the east ling under compressive forces as was widely speculated after the
side of the joint, the heel of Member 11 was severely damaged and collapse.
the concrete cracks even reached the first anchorage of the tendon Fig. 21 also compares the simulated and actual bridge collapse
in the deck [Fig. 17(a)]. On the west side of the joint [Fig. 17(b)], a processes, in which the simulation results capture the progression
severe shear crack developed diagonally in the bridge deck, which of collapse well. Fig. 21 suggests that as the structure’s geometry
also was well captured in the simulations. The simulated damage changed drastically in response to sliding of the Member 11=12
mode in Fig. 17 matches the actual damage of the joint area rea- joint, the deck’s north end started sliding into the span under
sonably well and highlights the potential punching shear failure the influence of gravity loading. The relative motion between
mode that was discussed previously in the design calculations the joint and deck resulted in the deck falling off the support, leav-
section. ing behind a portion of the Member 11=12 joint wedged onto the
Based on our simulation results, Fig. 18(a) shows that the pre- pier. As the structure fell, continuing changes in its geometry
stress force in Member 11 decreased to 55% of the original level as caused Member 11 to pull out of its joint, which remained wedged
the slip of the cold joint reached 5 mm, which also caused concrete at the top of the pier (Fig. 22). Evidence of pullout is seen in the
damage in the anchorage zone. The slip behavior of the cold joint simulation results and physical evidence, in which the rebars at the
under gravity loading also was confirmed by a recent investigation end of Member 11 were mostly straight (Fig. 22, ovals). This is
by the Occupational Safety and Health Administration (OSHA) additional evidence that Member 11 did not fail in compression,
(Ayub 2019) [Fig. 18(b)]. because its rebars would have bulged outward if that had happened.
It was reported that, at the time when the bridge collapsed, a A comparison of videos of the collapse of the bridge based on
construction crew was retensioning Member 11 (NTSB 2018c). simulations and the actual collapse is available in Video S1 in the
It is not clear how much retensioning was being applied, but Supplemental Data.

Fig. 15. Transportation stage of the main span. (Base image reprinted from Ayub 2019.)

© ASCE 04019134-9 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 17. Cracks in the joint area of Member 11 after relocation: (a) east side; and (b) west side. (Images reprinted from NTSB 2018a.)

Parametric Study performance to gain further insight into the factors that led to the
collapse. The static coefficient of friction at the cold joint was var-
Based on the hand calculations and FE simulations discussed pre- ied from 0.6 to 1.4 to account for significant uncertainties that may
viously, the design of the cold joint at the north end is deemed have occurred in the friction conditions at the joint (Table 2). In all
flawed, and therefore was the primary reason for the failure of cases, the coefficient of friction was assumed to decrease to 0.4
the bridge. The three key factors that were recognized to most in- (kinetic) once slip occurred. Due to uncertainties regarding the pre-
fluence the behavior of the cold joint were (1) the coefficient of stress losses, the effects of losses that varied from 18% to 38% were
friction at the cold joint interface; (2) the prestress level in the deck; investigated. Retensioning at the time of collapse is not well doc-
and (3) the level of retensioning forces in Truss member 11. Para- umented because the collapse of the bridge occurred during this
metric simulations (Table 2) (10 cases in total) were carried out to process. Therefore, the retensioning stress in the tendons in
systematically investigate the effect of these parameters on system Member 11 was varied from 55% to 100% of the yield capacity.

© ASCE 04019134-10 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 18. Behavior of cold joint under gravity loading: (a) relationship between prestressing in Member 11 and cold-joint slip; and (b) damage mode of
the cold-joint of the deck and Member 11 (reprinted from Ayub 2019).

Fig. 19. Damage of the cold joint due to retensioning on Member 11: (a) before the retensioning; (b) during the retensioning; and (c) after the
retensioning.

Fig. 20. Failure mode of the north end from (a) FE simulation; and (b) accident video frame (image courtesy of Instagram/@o2webdev).

© ASCE 04019134-11 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 21. Collapse sequence between the simulation and accident. (Images courtesy of Instagram/@o2webdev.)

Fig. 22. Close-up of failure of Member 11 during the collapse: (a) simulation; and (b) accident photo (reprinted from NTSB 2019a).

Sensitivity Study of Coefficient of Friction between the smooth concrete surfaces of cold joints was 0.6 as per
ACI (2011), Eqs. (1) and (4) suggest that there was insufficient
According to OSHA (Ayub 2019), the designer did not specify in
the construction plans that the cold joints needed to be intention- shear friction capacity. Given the importance of this variable, a
ally roughened. This conflicts with assertions in FIU (2017b) that sensitivity study of the coefficient of friction was conducted.
the surface of the cold joints was indeed roughened to an ampli- Three values were considered, 0.6, 1.0, and 1.4. The first pertained
tude of 6.35 mm. Examination of pre-event photos was not con- to smooth surfaces, the second to roughened surfaces [the nominal
clusive, but appeared to agree with OSHA (Ayub 2019) that the design condition as per FIU (2017b)], and the last considered sit-
cold joint surfaces were smooth. If the static coefficient of friction uations in which the cold joint surfaces were prepared to be highly
slip resistant.
The damage levels at the cold joint for cases with different static
Table 2. Simulation matrix for parametric studies coefficients of friction are shown in Fig. 23. The damage caused by
the dowel action of the rebars mainly was localized around the
Static coefficient Retensioning
anchorage zone (Fig. 23) and was similar to the punching shear
of friction at Prestress losses stress/yield
Case the cold joint in the deck (%) strength (%) damage mode discussed previously and seen in the precollapse
photos. According to the simulation, slip of the joint still occurred
1 0.6 18 N=A even when the coefficient of friction increased to 1.4.
2 1.0 18 N=A
The damage levels in Fig. 23 show that relying on friction is
3 1.4 18 N=A
4 1.0 28 N=A risky for cold joints subject to shear forces in a concrete truss
5 1.0 38 N=A bridge. Shear keys or some other explicit shear-resisting mecha-
6 1.0 18 55 nism should have been placed in the cold joints, and would have
7 1.0 18 80 been more reliable and helpful in meeting the horizontal shear de-
8 1.0 18 90 mand in the joints. Furthermore, retensioning was not applied in
9 1.0 18 95 these three cases and the bridge did not appear to collapse under
10 1.0 18 100 gravity, although the cold joint area had severe cracks for the
Note: N=A = no retensioning applied. assumed conditions.

© ASCE 04019134-12 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 23. Damage mode of the cold-joint area with different static coefficients of friction: (a) μ ¼ 0.6; (b) μ ¼ 1.0; and (c) μ ¼ 1.4.

Prestressing Losses in Deck off the deck, starting the collapse process. The authors simulated
a scenario in which the joint was merged (i.e., there was no cold
To study the effect of prestressing losses on the behavior of the
joint), and the joint area was found to be almost intact under the
cold joint, losses of 18%, 28%, and 38% were considered for the
retensioning.
deck strands. The coefficient of friction in these series of simula-
The effect of retensioning on a cold joint could precipitate the
tions was assumed to be 1.0 before the sliding of the cold joint and
failure process, especially if the joint already was damaged in ear-
0.4 after sliding. Fig. 24 shows the damage mode of the north end
lier construction stages (Fig. 26). Even if Member 11 had not been
of the bridge with different levels of prestressing losses. The zone
retensioned, the bridge likely would have failed as creep exacer-
of punching shear damage expanded as the prestressing losses in-
bated sliding at the cold joint. However, because the process would
creased (Fig. 24). This observation also matched the previous
have been slow and entailed widening cracks that serve as an im-
design evaluation of the joint, which noted that the punching shear
portant warning sign of structural distress, action could have been
capacity could be insufficient when prestressing strands in the deck taken to address the situation. The simulation results suggest that
were not fully engaged in preventing punch out of the joint. retensioning Member 11 should not have been considered as an
appropriate solution to reduce the cracking symptoms observed
Retensioning of Diagonal Member 11 in the cold joint area, because it increased the sliding of the joint
and damaged the integrity of the structure in a catastrophic manner.
The joint of Member 11 was damaged under the effects of pre- “The restressing of member 11 was a manipulation of loads that
stressing and gravity, and retensioning the tendons in Member 11 constituted a change to the design plan, and, before being imple-
could have further aggravated the sliding of the cold joint mented, should have been independently peer reviewed and signed
[Fig. 19(a)]. In this study, five different retensioning forces were and sealed by a professional engineer” NTSB (2019b).
applied to the tendons in Member 11 to reach a stress level of
55%, 80%, 90%, 95%, and 100% of the yield strength. The coef-
ficient of friction at the cold joint was assumed to be 1.0 before Influence of Shear Capacity of Construction Joint
sliding and 0.4 after sliding, and 18% losses were assumed for the It was shown previously that the nominal shear capacity (as per
tendons in the deck. Fig. 25 shows the damage of the north-end design specifications) of the construction joint was less than the
joint of the bridge. Increasing the prestress levels in Member 11 applied demand. To meet the demand while conservatively ignor-
caused more damage in the joint area, specifically more heel ing the contribution of friction, the bar reinforcement crossing the
damage and widespread damage in the body of the joint itself construction joint was increased from 10,012 mm2 (mix of #6 and
(Fig. 25). Fig. 26 compares the sliding deformations of the cold #7 bars) to 30,645 mm2 (mix of #11 and #14 bars) to satisfy
joint under different retensioning forces, in which it is clear that Eq. (15), which is a modified version of Eq. (2). Fig. 27 shows the
joint slip increased significantly as the retensioning forces in- simulated damage mode of the northern end of the bridge with the
creased. After reaching 95% of the yield strength, the joint slid original joint design, the modified joint design, and a design in

© ASCE 04019134-13 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

Fig. 24. Damage mode of the cold-joint area with different prestress losses in the deck: (a) 18%; (b) 28%; and (c) 38%.

Fig. 25. Damage mode of the cold joint under different levels of retensioning: (a) 55% yield; (b) 80% yield; (c) 90% yield; and (d) 95% yield.

which the structure is made monolithic at the joint area (i.e., no punching-related cracking at the northern edge of the joint. Simu-
construction joint but with the original reinforcement). It is clear lation results showed that slip at the construction joint of the
from Fig. 27 that the modified design significantly decreased modified design decreased by two orders of magnitude to an insig-
sliding-induced damage at the heel of Member 11. The concrete nificant number compared with slip of the original design. These
deck also suffered less damage, although there still was evidence results indicate that although significantly increasing the shear con-
of cracking associated with the punching failure mode [Fig. 27(b)]. nectors at the construction joint was beneficial, the joint zone still
The monolithic joint [Fig. 27(c)] had the best performance in terms was vulnerable to localized cracking, although much less than the
of localized cracking, although that also showed evidence of cracking damage observed in the original design

© ASCE 04019134-14 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


of the bridge, with a specific focus on the behavior of Members
11 and 12’s cold joint with the deck during construction. The sim-
ulation results showed that the heel of the joint suffered severe
cracking, as observed in the bridge before the failure. The simula-
tion results also supported the punch-out design calculations and
showed that the computed damage locations coincided reasonably
well with the documented prefailure crack locations. The simula-
tion results suggest that the cold joint at the north end experienced
sliding behavior under the retensioning forces applied to diagonal
Member 11, which precipitated the collapse. The complete process
of the collapse also was simulated and shown to match actual foot-
age of the accident quite well, lending credence to the veracity of
the modeling effort.
To develop a better understanding of the joint behavior, para-
metric studies were carried out by varying the coefficient of fric-
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

tion at the cold joint, the prestressing forces in the deck, and the
Fig. 26. Sliding deformation of cold joint under different retensioning retensioning forces applied to the diagonal Member 11. It was
forces in Member 11. found that the punching shear damage of the joint was mildly
affected by the coefficient of friction and prestressing forces
applied in the deck.
D 9,168,000 N Based on the detailed analysis and simulations carried out in this
Asa ¼ 30,645 mm2 > ¼
Rg Rp Fu 1.0 × 0.75 × 414 MPa paper, several lessons can be drawn from this accident:
1. The collapsed bridge deck was supported by a concrete truss,
¼ 29,527 mm2 ð15Þ which required prestressing truss members undergoing tension,
because concrete is weak in tension. The use of a concrete truss
for aesthetic reasons unnecessarily introduced complications re-
Conclusions and Lessons Learned lated to prestressing and cold joints in the bridge, both of which
likely played key roles in the collapse of the bridge. Aesthetic
The factors affecting the collapse of the partially constructed 53-m- goals could have been achieved by using a steel truss (instead
long (174-foot) section of the FIU-Sweetwater UniversityCity of the concrete truss) encased in nonstructural concrete without
pedestrian bridge were investigated through a critical review of making the design and construction unnecessarily complex and
design calculations and high-fidelity computational simulation. risky.
Review of the calculations showed that the design was flawed 2. Simulation results showed that the cold joint between Members
because of underestimation of the horizontal shear demand on the 11 and 12 and the deck could have played a significant role in
cold joint in the northern failed end of the bridge. The joint, as built, the collapse of the bridge. This cold joint probably was intro-
had insufficient capacity to prevent sliding behavior of the joint duced in construction drawings for construction staging without
during retensioning. The computations also showed that the north accounting for its effect on the bridge behavior through detailed
end of the concrete deck could be vulnerable to punch out under the finite-element analysis. In fact, a review of design calculations
effect of compressive axial loading from Member 11, and that provided by the Florida International University showed that the
likely was a contributing factor for the severe deck cracking cold joint was not considered in the analysis model.
observed prior to failure. 3. Contrary to widespread speculation directly after the collapse,
High-fidelity computational simulation was conducted to sup- it appears that diagonal Member 11 did not suffer axial load
port the design calculations and investigate the failure mechanism failure. Although the hand calculations showed that the axial

Fig. 27. Damage mode of the northern end of the bridge with different shear design: (a) original shear connector design (cold joint); (b) revised shear
connector design (cold joint); and (c) monolithic joint design (with original reinforcement).

© ASCE 04019134-15 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


capacity was close to (i.e., just less than) the demand, the simu- Supplemental Data
lation results did not show crushing or buckling of Member 11
under compressive forces as the initiating event. Video S1 is available online in the ASCE Library (www
4. Relying on friction at the joint between Members 11 and 12 and .ascelibrary.org).
the deck was risky in a nonredundant system such as that used
in the bridge. Friction is unreliable by nature and can lead to
sudden failure when the demand exceeds capacity. Shear keys References
or some other explicit shear resisting mechanism placed in the AASHTO. 2017. AASHTO LRFD bridge design specifications. 8th ed.
cold joints would have been more reliable and helpful in Washington, DC: AASHTO.
meeting the horizontal shear demand in the joint. ACI (American Concrete Institute). 2011. Building code requirements for
5. Retensioning diagonal truss members should not be considered structural concrete (318-11) and commentary-(318R-11). ACI 318-11.
as an appropriate solution to remedy the cracks in the cold joint Detroit: ACI.
AISC. 2010. Specification for structural steel buildings. ANSI/AISC
area, because it increased the demand:capacity ratio making the
360-10. Chicago: AISC.
bridge more vulnerable to collapse. Cracks in the cold joint area Ayub, M. 2019. Investigation of March 15, 2018 pedestrian bridge
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

should be viewed as an important warning sign of impending collapse at Florida International University, Miami, FL. Washington,
collapse and immediate action should be taken to ensure the sta- DC: US Dept. of Labor, Occupational Safety and Health Administration.
bility of the structure after detailed calculations or modeling. Berman, J. W., B.-S. Wang, A. W. Olson, C. W. Roeder, and D. E. Lehman.
6. The collapse of the bridge does not necessarily imply that ac- 2012. “Rapid assessment of gusset plate safety in steel truss bridges.”
J. Bridge Eng. 17 (2): 221–231. https://doi.org/10.1061/(ASCE)BE
celerated bridge construction is risky, but certainly shows the
.1943-5592.0000246.
need for adequate analysis simulating construction aspects such Cao, R., A. K. Agrawal, S. El-Tawil, X. Xu, and W. Wong. 2019a. “Heavy
as the presence of cold joints or utility conduits to ensure the truck collision with bridge piers: A computational simulation study.”
safety of the bridge during and after construction. J. Bridge Eng. 24 (6): 04019052. https://doi.org/10.1061/(ASCE)BE
7. The peer-review of the bridge design plan was reported to be .1943-5592.0001398.
inadequate due to a limited budget and time frame. Some of Cao, R., A. K. Agrawal, S. El-Tawil, X. Xu, and W. Wong. 2019b.
the design flaws, particularly the lack of rebar detailing in “Performance-based design framework for bridge piers subjected to
truck collision.” J. Bridge Eng. 24 (7): 04019064. https://doi.org/10
the joint region, could have been identified during an adequate .1061/(ASCE)BE.1943-5592.0001423.
and more rigorous peer-review. Cao, R., S. El-Tawil, A. K. Agrawal, X. Xu, and W. Wong. 2019c. “Behav-
8. This accident re-emphasizes the lesson that public safety should ior and design of bridge piers subjected to heavy truck collision.”
never be compromised simply to showcase the application of a J. Bridge Eng. 24 (7): 04019057. https://doi.org/10.1061/(ASCE)BE
new construction technology, even though the technology itself .1943-5592.0001414.
may have been shown to be safe in prior applications. Any con- Do, T. V., T. M. Pham, and H. Hao. 2018. “Numerical investigation of
the behavior of precast concrete segmental columns subjected to ve-
struction area is by nature hazardous to the public. hicle collision.” Eng. Struct. 156 (Feb): 375–393. https://doi.org/10
.1016/j.engstruct.2017.11.033.
FIU (Florida International University). 2017a. “R.F.C. superstructure plan.”
Data Availability Statement Miami: FIU. Accessed January 22, 2019. http://facilities.fiu.edu
/projects/BT_904/PRR/PlanFiles.zip.
Some data, models, or code generated or used during the study FIU (Florida International University). 2017b. “UniversityCity pros-
are available from the corresponding author by request. Some perity project pedestrian bridge: Superstructure, final design calcula-
data, models, or code generated or used during the study are pro- tions.” Miami: FIU. Accessed January 22, 2019. http://facilities.fiu
prietary or confidential in nature and may only be provided with .edu/projects/BT_904/PRR/Calculations.zip.
FIU (Florida International University). 2018. “Time lapse videos.” BT-904
restrictions.
UniversityCity prosperity project PRR webpage (online archive).
Accessed January 22, 2019. http://facilities.fiu.edu/projects/BT_904
/PRR/time_lapse_videos.zip.
Acknowledgments FIU (Florida International University), Facilities Management. 2019.
“BT-904 records readily available.” BT-904 UniversityCity Prosperity
The authors thank Mohammad Ayub from the Occupational Safety Project PRR WebPage (online archive). Accessed January 22, 2019.
and Health Administration (OSHA) for his constructive comments https://facilities.fiu.edu/projects/BT-904-PRR.htm.
that improved this manuscript. This research was supported, in part, Hallquist, J. O. 2006. Vol. 3 of LS-DYNA theory manual, 25–31.
by National Science Foundation Grant Nos. CNS-0958379, CNS- Livermore, CA: Livermore Software Technology.
Hao, S. 2010. “I-35W bridge collapse.” J. Bridge Eng. 15 (5): 608–614.
0855217, and ACI-1126113 and by the City University of New
https://doi.org/10.1061/(ASCE)BE.1943-5592.0000090.
York High-Performance Computing Center at the College of Staten Jiang, H., and M. G. Chorzepa. 2015. “An effective numerical simulation
Island. This study also was partially supported by the INSPIRE methodology to predict the impact response of pre-stressed concrete
University Transportation Center (UTC). Financial support for members.” Eng. Fail. Anal. 55 (Sep): 63–78. https://doi.org/10.1016/j
INSPIRE UTC projects is provided by the US Department of .engfailanal.2015.05.006.
Transportation, Office of the Assistant Secretary for Research and Jung, K.-H., J.-W. Yi, and J.-H. J. Kim. 2010. “Structural safety and
Technology (USDOT/OST-R) under Grant No. 69A3551747126 serviceability evaluations of prestressed concrete hybrid bridge girders
through INSPIRE University Transportation Center (http://inspire with corrugated or steel truss web members.” Eng. Struct. 32 (12):
3866–3878. https://doi.org/10.1016/j.engstruct.2010.08.029.
-utc.mst.edu) at Missouri University of Science and Technology.
Liu, G. 2012. “Behavior of bridge piers during vehicular impacts.”
Any opinions, findings and conclusions or recommendations Ph.D. thesis, City College of New York, City Univ. of New York.
expressed in this publication are those of the authors and do not Moutoussamy, L., G. Herve, and F. Barbier. 2011. “Qualification of *Constrai-
necessarily reflect the views of the OSHA, the National Science ned_Lagrange_In_Solid command for steel/concrete interface modeling.”
Foundation, the USDOT/OST-R, or any State or other entity. In Proc., 8th European LS-Dyna Conf. San Francisco: LS-DYNA.

© ASCE 04019134-16 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134


Murray, Y. D., A. Y. Abu-Odeh, and R. P. Bligh. 2007. Evaluation of NTSB (National Transportation Safety Board). 2018c. “Preliminary report:
LS-DYNA concrete material model 159. Publication No. FHWA- Highway: Collapse of pedestrian bridge under construction Miami,
HRT-05-063. Washington, DC: Federal Highway Administration. Florida (HWY18MH009).” Accessed January 22, 2019. https://www
Nakalswamy, K. K. 2010. “Experimental and numerical analysis of struc- .ntsb.gov/investigations/AccidentReports/Reports/HWY18MH009-prelim
tures with bolted joints subjected to impact load.” Ph.D. thesis, Dept. of .pdf.
Mechanical Engineering, Univ. of Nevada, Las Vegas. NTSB (National Transportation Safety Board). 2019a. “NTSB B-roll of
NTSB (National Transportation Safety Board). 2008. Collapse of I-35W Miami, FL bridge collapse.” Accessed January 22, 2019. https://www
highway bridge, Minneapolis, Minnesota, August 1, 2007. Washington, .youtube.com/watch?v=aeJKqojmHgY.
DC: Createspace Independent Publishing. NTSB (National Transportation Safety Board). 2019b. “National Transpor-
NTSB (National Transportation Safety Board). 2018a. “Investigative tation Safety Board public meeting of October 22, 2019.” Accessed
update 1 (Aug. 09, 2018): Collapse of pedestrian bridge under con- October 28, 2019. https://www.ntsb.gov/news/events/Documents/2019
struction Miami, Florida (HWY18MH009).” Accessed January 22, -HWY18MH009-BMG-abstract.pdf.
2019. https://www.ntsb.gov/investigations/AccidentReports/Reports Xu, X., R. Cao, S. El-Tawil, A. K. Agrawal, and W. Wong. 2019. “Loading
/HWY18MH009-investigative-update.pdf. definition and design of bridge piers impacted by medium weight
NTSB (National Transportation Safety Board). 2018b. “Investigative trucks.” J. Bridge Eng. 24 (6): 04019042. https://doi.org/10.1061
update 2 (Nov. 15, 2018): Collapse of pedestrian bridge under /(ASCE)BE.1943-5592.0001397.
Xue, D., Y. Liu, J. He, and B. Ma. 2011. “Experimental study and numeri-
Downloaded from ascelibrary.org by 37.126.220.64 on 12/07/19. Copyright ASCE. For personal use only; all rights reserved.

construction Miami, Florida (HWY18MH009).” Accessed January


22, 2019. https://www.ntsb.gov/investigations/AccidentReports/Reports cal analysis of a composite truss joint.” J. Constr. Steel Res. 67 (6):
/HWY18MH009-investigative-update2.pdf. 957–964. https://doi.org/10.1016/j.jcsr.2011.01.013.

© ASCE 04019134-17 J. Bridge Eng.

J. Bridge Eng., 2020, 25(1): 04019134

Вам также может понравиться