Вы находитесь на странице: 1из 3

MOBILIZATION CONSTRUCTION SAFETY AND HEALTH PROGRAM

Start: 01/01/20 ID: 2 Start: 03/01/20 ID: 3


Finish: 02/01/20 Dur: 2 days Finish: 04/01/20 Dur: 2 days
Res: Res:

PROJECT PHOTOGRAPHS
Start: 03/01/20 ID: 4
Finish: 06/01/20 Dur: 4 days
Res:

PROJECT BILLBOARDS
Start: 03/01/20 ID: 5
Finish: 04/01/20 Dur: 2 days
Res:

TEMPORARY FACILITIES / FIELD OFFICE


Start: 03/01/20 ID: 6
Finish: 07/01/20 Dur: 5 days
Res:

Clearing and Grubbing Excavation Lean Concrete


Start: 03/01/20 ID: 9 Start: 18/01/20 ID: 10 Start: 20/01/20 ID: 12
Finish: 17/01/20 Dur: 15 days Finish: 19/01/20 Dur: 2 days Finish: 20/01/20 Dur: 1 day
Res: Res: Res:

Soil Poisoning and Termite Control Soil Poisoning Perforated Pipe Line system including
Polyethylene
installation
Sheet (Vapor Barrier) 6mils thick forGravel
slab Bedding for tie beam and slab on grade
Start: 20/01/20 ID: 15 Start: 22/01/20 ID: 16 Start: 27/01/20 ID: 14 Start: 30/01/20 ID: 13
Finish: 21/01/20 Dur: 2 days Finish: 26/01/20 Dur: 5 days Finish: 29/01/20 Dur: 3 days Finish: 01/02/20 Dur: 3 days
Res: Res: Res: Res:

Fdn - G Flr Reinforcing Steel Bars Fdn - G Flr Ready-Mix Concrete Earthfill , Backfill and Compaction G Flr - 2 Flr Reinforcing Steel Bars G Flr - 2 Flr Ready-Mix Concrete 2 Flr - 3 Flr Reinforcing Steel Bars 2 Flr - 3 Flr Ready-Mix Concrete 3 Flr - Upper Reinforcing Steel Bars 3 Flr - Upper Ready-Mix Concrete MASONRY WORKS PUMP HOUSE
Start: 21/01/20 ID: 19 Start: 10/02/20 ID: 20 Start: 14/02/20 ID: 11 Start: 20/02/20 ID: 21 Start: 09/03/20 ID: 22 Start: 11/03/20 ID: 23 Start: 29/03/20 ID: 24 Start: 31/03/20 ID: 25 Start: 10/04/20 ID: 26 Start: 11/04/20 ID: 27 Start: 12/05/20 ID: 32
Finish: 09/02/20 Dur: 20 days Finish: 13/02/20 Dur: 4 days Finish: 19/02/20 Dur: 6 days Finish: 08/03/20 Dur: 18 days Finish: 10/03/20 Dur: 2 days Finish: 28/03/20 Dur: 18 days Finish: 30/03/20 Dur: 2 days Finish: 09/04/20 Dur: 10 days Finish: 10/04/20 Dur: 1 day Finish: 11/05/20 Dur: 31 days Finish: 10/06/20 Dur: 30 days
Res: Res: Res: Res: Res: Res: Res: Res: Res: Res: Res:

PLASTERING WORKS THIRD FLOOR TILES


Start: 22/04/20 ID: 28 Start: 26/05/20 ID: 37
Finish: 15/05/20 Dur: 24 days Finish: 12/06/20 Dur: 18 days
Res: Res:

WATERPROOFING WORKS MALE RESTROOM FLOOR TILES (UPPER FLOOR)


Start: 16/05/20 ID: 30 Start: 26/05/20 ID: 38
Finish: 25/05/20 Dur: 10 days Finish: 28/05/20 Dur: 3 days
Res: Res:

FIRE PROTECTION WORKS


Start: 16/05/20 ID: 60
Finish: 14/06/20 Dur: 30 days
Res:

SECOND FLOOR TILES


Start: 21/05/20 ID: 36
Finish: 07/06/20 Dur: 18 days
Res:

GROUND FLOOR TILEWORKS COMMON AREAS


Start: 16/05/20 ID: 35 Start: 03/06/20 ID: 39
Finish: 02/06/20 Dur: 18 days Finish: 09/06/20 Dur: 7 days
Res: Res:

CEILING WORKS
Start: 03/06/20 ID: 41
Finish: 18/06/20 Dur: 16 days
Res:

ARCHITECTURAL DOORS, WINDOWS AND GLASS WORKS


Start: 03/06/20 ID: 33
Finish: 22/06/20 Dur: 20 days
Res:

Exterior
Start: 03/06/20 ID: 46
Finish: 17/06/20 Dur: 15 days
Res:

ELECTRONICS AND COMMUNICATION WORKS


Start: 03/06/20 ID: 62
Finish: 07/07/20 Dur: 35 days
Res:

METAL ROOFING WORKS STEEL WORKS


Start: 11/04/20 ID: 29 Start: 01/05/20 ID: 31
Finish: 30/04/20 Dur: 20 days Finish: 20/05/20 Dur: 20 days
Res: Res:

ELECTRICAL WORKS
Start: 20/02/20 ID: 61
Finish: 18/07/20 Dur: 150 days
Res:

PLUMBING WORKS
Start: 20/02/20 ID: 63
Finish: 18/07/20 Dur: 150 days
Res:

FORMS AND SCAFFOLDINGS


Start: 31/01/20 ID: 17
Finish: 10/03/20 Dur: 40 days
Res:

SEPTIC VAULTS AND CATCH BASINS


Start: 20/01/20 ID: 65
Finish: 24/01/20 Dur: 5 days
Res:

Dewatering
Start: 18/01/20 ID: 8
Finish: 18/01/20 Dur: 1 day?
Res:

STAINLESS STEEL RAILING WORKS


Start: 13/06/20 ID: 57
Finish: 22/06/20 Dur: 10 days
Res:

Page 1
MOVABLE PARTITION TABLES AND SHELVES
Start: 19/06/20 ID: 42 Start: 29/06/20 ID: 43
Finish: 28/06/20 Dur: 10 days Finish: 18/07/20 Dur: 20 days
Res: Res:

Exterior Exterior Interior AIR-CONDITIONING AND VENTILATION WORKS


Start: 18/06/20 ID: 49 Start: 06/07/20 ID: 52 Start: 21/07/20 ID: 53 Start: 10/08/20 ID: 59
Finish: 05/07/20 Dur: 18 days Finish: 20/07/20 Dur: 15 days Finish: 09/08/20 Dur: 20 days Finish: 19/08/20 Dur: 10 days
Res: Res: Res: Res:

PLUMBING FIXTURES AND ACCESSORIES HAULING OF DEMOLISHED MATERIALS DEMOBILIZATION


Start: 10/08/20 ID: 64 Start: 25/08/20 ID: 66 Start: 27/08/20 ID: 68
Finish: 24/08/20 Dur: 15 days Finish: 26/08/20 Dur: 2 days Finish: 27/08/20 Dur: 1 day
Res: Res: Res:

SUPPLY AND INSTALLATION OF FURNITURES


Start: 10/08/20 ID: 67
Finish: 19/08/20 Dur: 10 days
Res:

UPPER FLOOR (PAINT)


Start: 21/07/20 ID: 54
Finish: 23/07/20 Dur: 3 days
Res:

STAINLESS STEEL LOGO, LETTERS & SIGNAGES


Start: 21/07/20 ID: 56
Finish: 04/08/20 Dur: 15 days
Res:

CLADDING WORKS
Start: 21/07/20 ID: 58
Finish: 04/08/20 Dur: 15 days
Res:

Interior
Start: 06/07/20 ID: 50
Finish: 28/07/20 Dur: 23 days
Res:

Interior DOORS AND DOOR JAMB PAINTING


Start: 18/06/20 ID: 47 Start: 09/07/20 ID: 55
Finish: 08/07/20 Dur: 21 days Finish: 14/07/20 Dur: 6 days
Res: Res:

Page 2
Project: Schedule of Construction of T Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Date: Wed 31/07/19

Page 3

Вам также может понравиться