Вы находитесь на странице: 1из 133

PROJECT TITLE: PROPOSED 2 STOREY INPATIENT WARD BUILDING ESTIMATES

FLOOR AREA :

FORMULA L W A
A1 = L x W = 2.15 1.7 3.66 sq. m
A2 = L x W = 28 18.46 516.88 sq. m
A3 = L x W = 2.16 1.65 3.56 sq. m
A4 = L x W = 14.08 2.02 28.44 sq. m
A5 = L x W = 5.05 0.47 2.37 sq. m
A6 = L x W = 1.75 1.65 2.89 sq. m
AREA TOTAL = 557.80 sq. m

CONCRETING WORKS

BEAMS:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 31.24 P 3500.00
SUB TOTAL cu.m 31.24 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 1477.4 P 35.00
REBAR #12 (GRADE 60) kg 47.72 P 35.00
REBAR #16 (GRADE 60) kg 2932.34 P 35.00
REBAR #20 (GRADE 60) kg 842.9 P 35.00
REBAR #25 (GRADE 60) kg 297.88 P 35.00
SUB TOTAL kg 5598.24 P 175.00
MATERIALS UNIT QUANTITY PRICE
SHUTTERINGS sq.m 231.41 P 194.62
SUB TOTAL sq.m 231.41 P 194.62

GRAND TOTAL

ROOF BEAMS:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 26.09 P 3500.00
SUB TOTAL cu.m 26.09 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 1355.06 P 35.00
REBAR #16 (GRADE 60) kg 2393.34 P 35.00
SUB TOTAL kg 3748.4 P 70.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 220.31 P 194.62
SUB TOTAL sq.m 220.31 P 194.62

GRAND TOTAL

GRADE BEAMS:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 31.98 P 3500.00
SUB TOTAL cu.m 31.98 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 1335.71 P 35.00
REBAR #12 (GRADE 60) kg 47.16 P 35.00
REBAR #16 (GRADE 60) kg 3414.81 P 35.00
REBAR #20 (GRADE 60) kg 468.78 P 35.00
REBAR #25 (GRADE 60) kg 448.72 P 35.00
SUB TOTAL kg 5715.18 P 175.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 236.33 P 194.62
SUB TOTAL sq.m 236.33 P 194.62

GRAND TOTAL

COLUMNS:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 71.44 P 3500.00
SUB TOTAL cu.m 71.44 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 3427.12 P 35.00
REBAR #16 (GRADE 60) kg 11029 P 35.00
SUB TOTAL kg 14456.12 P 70.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 515.7 P 194.62
SUB TOTAL sq.m 515.7 P 194.62

GRAND TOTAL

SLAB ON GRADE:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 68.19 P 3500.00
SUB TOTAL cu.m 68.19 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 4608.65 P 35.00
SUB TOTAL kg 4608.65 P 35.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 454.59 P 194.62
SUB TOTAL sq.m 454.59 P 194.62

GRAND TOTAL

SUSPENDED SLAB:
FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 51.11 P 3500.00
SUB TOTAL cu.m 51.11 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 4608.65 P 35.00
SUB TOTAL kg 4608.65 P 35.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 454.59 P 194.62
SUB TOTAL sq.m 454.59 P 194.62

GRAND TOTAL

ROOF DECK SLAB:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 52.88 P 3500.00
SUB TOTAL cu.m 52.88 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 6092.79 P 35.00
SUB TOTAL kg 6092.79 P 35.00

MATERIALS UNIT QUANTITY PRICE


SHUTTERINGS sq.m 459.82 P 194.62
SUB TOTAL sq.m 459.82 P 194.62

GRAND TOTAL

COLUMN FOOTINGS:

FROM STAAD RCDC ANALYSIS

MATERIALS UNIT QUANTITY PRICE


CONCRETE C28 cu.m 21.2 P 3500.00
SUB TOTAL cu.m 21.2 P 3500.00

MATERIALS UNIT QUANTITY PRICE


REBAR #10 (GRADE 60) kg 780.45 P 35.00
REBAR #25 (GRADE 60) kg 488.89 P 35.00
SUB TOTAL kg 1269.34 P 70.00

MATERIALS UNIT QUANTITY PRICE


PCC cu.m 11.81 662
EXCAVATION cu.m 315 209
BACKFILLING cu.m 238.77 238.77
SHUTTERINGS sq.m 236.33 P 194.62
SUB TOTAL sq.m 236.33 P 194.62

GRAND TOTAL
ILDING ESTIMATES

A
3.66 sq. m
516.88 sq. m
3.56 sq. m
28.44 sq. m
2.37 sq. m
2.89 sq. m
557.80 sq. m

REBAR #10 (GRADE 60).616kg/m


REBAR #12 (GRADE 60).888kg/m
COST REBAR #16 (GRADE 60)1.578kg/m
P 109340.00
P 109340.00

COST
P 51709.00
P 1670.20 CONCRETE 354.13
P 102631.90 CEMENT 3187.17
P 29501.50 SAND 177.065
P 10425.80 GRAVEL 354.13
P 195938.40 REBAR #10 23685.83
REBAR #12 94.88
COST REBAR #16 19769.49
P 45037.01 REBAR #20 1311.68
P 45037.01 REBAR #25 1235.49
G.I. WIRE 599.26581
SHUTTERING 2809.08
P 350315.41 PCC 11.81
EXCAVATION 315
BACKFILLIN 238.77

COST
P 91315.00
P 91315.00

COST
P 47427.10
P 83766.90
P 131194.00

COST
P 42876.73
P 42876.73

P 265385.73

COST
P 111930.00
P 111930.00

COST
P 46749.85
P 1650.60
P 119518.35
P 16407.30
P 15705.20
P 200031.30

COST
P 45994.54
P 45994.54

P 357955.84

COST
P 250040.00
P 250040.00

COST
P 119949.20
P 386015.00
P 505964.20

COST
P 100365.53
P 100365.53

P 856369.73

COST
P 238665.00
P 238665.00

COST
P 161302.75
P 161302.75

COST
P 88472.31
P 88472.31

P 488440.06
COST
P 178885.00
P 178885.00

COST
P 161302.75
P 161302.75

COST
P 88472.31
P 88472.31

P 428660.06

COST
P 185080.00
P 185080.00

COST
P 213247.65
P 213247.65

COST
P 89490.17
P 89490.17

P 487817.82

COST
P 74200.00
P 74200.00

COST
P 27315.75
P 17111.15
P 44426.90

COST
P
7818.22
P 65835.00
P 57011.11
P 45994.54
P 176658.88

P 295285.78
Masonry Works
CHB Walls #5, Incl. Plastering
Ground Floor
CHB pcs = Area of walls x 12.50 Area of walls = Length x Height
Area of walls = 143.00 x 2.80
CHB pcs = 355.22 x 12.5 Area of walls = 400.40 m^2
CHB pcs = 4440.25 pcs
Area of holes = 45.18 m^2

A= 355.22

Ground Floor
CHB pcs = Area of walls x 12.50 Area of walls = Length x Height
Area of walls = 169.39 x 2.80
CHB pcs = 429.10 x 12.5 Area of walls = 474.28 m^2
CHB pcs = 5363.75 pcs
Area of holes = 45.18 m^2

Total CHB pcs = 9804.00 pcs A= 429.10

Total Area = 784.32 m^2

Finding the mortar for block laying by Area Method


Find the area of the wall Refering to class "B" mixture,

Area of the wall = 784.32 m^ Cement: 784.320184 x 0.522 = 409.42


Sand: 784.320184 x 0.0435 = 34.12

Determine the number of Vertical and Horizontal Reinforcement


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence Refering to Table 3-5.reinforced spaced at 60 cm
A= 784.32 Vertical = 784.320184 x 2.13 = 1670.60
Horizontal = 784.320184 x 2.15 = 1686.29

Total reinforcement = 3356.89 m. long

10 mm dia ba 0.616 kg/m


reinforcement kgs = 2,067.84 kgs

Tie Wire in kilograms


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence


A= 784.32 m^ Refering to Table 3-6.0.30 cm long tie wire
weight = 784.320184 x 0.032 = 25.10
#16 - G.I Wire
Plastering (16mm thick); Class B
Portland Cement (40 kg)
Sand
Area = 784.32 m^ Volume = 784.320184 x 0.016 = 12.549
Cement = 12.549 x 12.00 = 150.589
Sand = 12.549 x 1.00 = 12.549
Masonry Works
CHB Walls #4, Incl. Plastering
Ground Floor
CHB pcs = Area of walls x 12.50 Area of walls = Length x Height
Area of walls = 45.62 x 2.80
CHB pcs = 112.62 x 12.5 Area of walls = 127.74 m^2
CHB pcs = 1407.74 pcs
Area of holes = 15.12 m^2

A= 112.62

Total CHB pcs = 1408.00 pcs

Total Area = 112.62 m^2

Finding the mortar for block laying by Area Method


Find the area of the wall Refering to class "B" mixture,

Area of the wall = 112.62 m^ Cement: 112.6188 x 0.522 = 58.79


Sand: 112.6188 x 0.0435 = 4.90

Determine the number of Vertical and Horizontal Reinforcement


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence Refering to Table 3-5.reinforced spaced at 60 cm
A= 112.62 Vertical = 112.6188 x 2.13 = 239.88
Horizontal = 112.6188 x 2.15 = 242.13

Total reinforcement = 482.01 m. long

10 mm dia ba 0.616 kg/m


reinforcement kgs = 296.92 kgs

Tie Wire in kilograms


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence


A= 112.62 m^ Refering to Table 3-6.0.30 cm long tie wire
weight = 112.6188 x 0.032 = 3.60
#16 - G.I Wire
Plastering (16mm thick); Class B
Portland Cement (40 kg)
Sand
Area = 112.62 m^ Volume = 112.6188 x 0.016 = 1.802
Cement = 1.802 x 12.00 = 21.623
Sand = 1.802 x 1.00 = 1.802

Masonry Works
CHB Walls #6, Incl. Plastering
Ground Floor
CHB pcs = Area of walls x 12.50 Area of walls = Length x Height
Area of walls = 90.72 x 2.80
CHB pcs = 210.24 x 12.5 Area of walls = 254.03 m^2
CHB pcs = 2627.94 pcs
Area of holes = 43.79 m^2

A= 210.24

Second Floor
CHB pcs = Area of walls x 12.50 Area of walls = Length x Height
Area of walls = 90.72 x 2.80
CHB pcs = 211.48 x 12.5 Area of walls = 254.02 m^2
CHB pcs = 2643.45 pcs
Area of holes = 42.54 m^2

Total CHB pcs = 5272.00 pcs A= 211.48

Total Area = 421.71 m^2

Finding the mortar for block laying by Area Method


Find the area of the wall Refering to class "B" mixture,

Area of the wall = 421.71 m^ Cement: 421.71152 x 0.522 = 220.13


Sand: 421.71152 x 0.0435 = 18.34

Determine the number of Vertical and Horizontal Reinforcement


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence Refering to Table 3-5.reinforced spaced at 60 cm
A= 421.71 Vertical = 421.71152 x 2.13 = 898.25
Horizontal = 421.71152 x 2.15 = 906.68

Total reinforcement = 1804.93 m. long

10 mm dia ba 0.616 kg/m


reinforcement kgs = 1,111.83 kgs

Tie Wire in kilograms


Vertical reinforcement spaced at 60 cm
Horizontal reinforcement spaced at every 3 layers

1. Solve for the area of the fence


A= 421.71 m^ Refering to Table 3-6.0.30 cm long tie wire
weight = 421.71152 x 0.032 = 13.49
#16 - G.I Wire
Plastering (16mm thick); Class B
Portland Cement (40 kg)
Sand
Area = 421.71 m^ Volume = 421.71152 x 0.016 = 6.747
Cement = 6.747 x 12.00 = 80.969
Sand = 6.747 x 1.00 = 6.747
Length = 143.00 m. long
Height = 2.80 m. high

Length = 143.00 m. long


Height = 2.80 m. high

bags
cu.m

m. long
m. long

kgs
#16 - G.I Wire

m^3
bags
cu.m
Length = 45.62 m. long
Height = 2.80 m. high

bags
cu.m

m. long
m. long

kgs
#16 - G.I Wire

m^3
bags
cu.m
Length = 90.72 m. long
Height = 2.80 m. high

Length = 90.72 m. long


Height = 2.80 m. high

bags
cu.m

m. long
m. long

kgs
#16 - G.I Wire

m^3
bags
cu.m
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION General Requirements


ITEM NO.: __________ ITEM OF WORK: Informatory Signs
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Informatory Signs 1 lot 4,347.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER

DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION HOUR/S RATE/HOUR
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 4,347.00


E. VAT (5%) PhP 217.35
F. TOTAL COST (D+E) PhP 4,564.35
G. UNIT COST (F / Est. Qty.) PhP 4,564.35
SAY PhP 4,564.00

UNIT COST DERIVATION General Requirements


ITEM NO.: __________ ITEM OF WORK: Safety and Health
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Hard Hat, Safety Shoes, Gloves, Construction
1 lot 40,000.00
Signages, Caution Tape, Medicine, Cabinets, etc.
DIRECT COST : MATERIALS Php.

D. TOTAL DIRECT COST (A+B+C) PhP 40,000.00


E. VAT (5%) PhP 2,000.00
F. TOTAL COST (D+E) PhP 42,000.00
G. UNIT COST (F / Est. Qty.) PhP 42,000.00
SAY PhP 42,000.00

Page 17 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

(Note: Labor Cost is 30% of M

Page 18 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Clearing and Grubbing
ESTIMATED QUANTITIES: 100 UNIT: sq.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST

DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION DAYS DAILY RATE
MANPOWER
Foreman 1 0.63 648.29
Laborer 2 0.63 465.23
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT

DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 994.61


E. VAT (5%) PhP 49.73
F. TOTAL COST (D+E) PhP 1,044.34
G. UNIT COST (F / Est. Qty.) PhP 10.44
SAY PhP 10.00

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Subgrade Preparation
ESTIMATED QUANTITIES: 300 UNIT: sq.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST

DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Foreman 1 1 81.04
Laborer 2 1 58.15
DIRECT COST: LABOR PhP

Page 19 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT
Motorized Road Grader 1 1 2,173.00
Vibratory Roller 1 1 1,507.00
Water Truck 1 0.25 1,065.00
DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 4,143.59


E. VAT (5%) PhP 207.18
F. TOTAL COST (D+E) PhP 4,350.77
G. UNIT COST (F / Est. Qty.) PhP 14.50
SAY PhP 15.00

Page 20 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Aggregate Base Course
ESTIMATED QUANTITIES: 50 UNIT: cu.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST
Aggregate Base Course 57.5 cu.m. 400.00
(w/ 15% shringkage factor)
DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Foreman 1 1 81.04
Laborer 2 1 58.15
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT
Motorized Road Grader 1 1 2,173.00
Vibratory Roller 1 1 1,507.00
Water Truck 1 0.25 1,065.00
DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 27,143.59


E. VAT (5%) PhP 1,357.18
F. TOTAL COST (D+E) PhP 28,500.77
G. UNIT COST (F / Est. Qty.) PhP 570.02
SAY PhP 570.00

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Aggregate Sub-base Course
ESTIMATED QUANTITIES: 50 UNIT: cu.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST
Aggregate Sub-base Course 57.5 cu.m. 410.00
(w/ 15% shringkage factor)
DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Page 21 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
Foreman 1 1 81.04
Laborer 2 1 58.15
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT
Motorized Road Grader 1 1 2,173.00
Vibratory Roller 1 1 1,507.00
Water Truck 1 0.25 1,065.00
DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 27,718.59


E. VAT (5%) PhP 1,385.93
F. TOTAL COST (D+E) PhP 29,104.52
G. UNIT COST (F / Est. Qty.) PhP 582.09
SAY PhP 582.00

Page 22 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: PCC Pavement, 200mm thk.
ESTIMATED QUANTITIES: 80.50 UNIT: sq.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST
Reinforcing Steel Bars 31.395 kgs. 33.00
Curing Compound 23.345 ltr. 28.00
Asphalt Sealant 9.660 ltr. 44.00
Forms 37.03 l.m. 250.00
Ready Mix Concrete, 28Mpa @ 28 days 16.100 cu.m. 3,500.00
Diamond Blade 14" (Concrete Saw) 0.012075 pc 8,000.00
DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Foreman 1 1 81.04
Skilled Laborer 4 1 72.36
Laborer 12 1 58.15
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT
Concrete Vibrator 2 1 148.88
Payloader (1.50 cu.m.) 1 1 1,733.00
Concrete Screeder (5.5 Hp) 1 1 545.00
Water Truck (1,000 gal) 1 1 1,065.00
Concrete Saw, Blade 14" dia. 1 1 167.38
Bar Cutter, Single Phase, 25mm 1 0.1 219.75
DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 72,717.24


E. VAT (5%) PhP 3,635.86
F. TOTAL COST (D+E) PhP 76,353.10
G. UNIT COST (F / Est. Qty.) PhP 948.49
SAY PhP 948.00

Page 23 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Concrete Curb and Gutter
ESTIMATED QUANTITIES: 10.30 UNIT: l.m.

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST
Portland Cement 13.287 bags 205.00
Sand 0.721 cu.m. 700.00
Gravel 1.442 cu.m. 700.00
10mm dia. x 6m RSB 34.9 kgs. 33.00
2"x12"x1.2mm Channel 1 pc 1,600.00
#16 G.I. Tie Wire 1 kg 60.00
DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Foreman 1 1 81.04
Skilled Laborer 4 1 72.36
Laborer 8 1 58.15
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT
One Bagger Mixer 1 1 172.00
Concrete Vibrator 1 1 148.88
Water Truck (1,000 gal) 1 0.05 1,065.00
Minor Tools 5% of labor
DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 8,301.23


E. VAT (5%) PhP 415.06
F. TOTAL COST (D+E) PhP 8,716.29
G. UNIT COST (F / Est. Qty.) PhP 846.24
SAY PhP 846.00

UNIT COST DERIVATION Land Development


ITEM NO.: ITEM OF WORK: Drainage System
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS:
DESCRIPTION QUANTITY UNIT UNIT COST
Portland Cement 20 bags 205.00

Page 24 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
Sand 1.26 cu.m. 700.00
Gravel 1 cu.m. 700.00
10mm dia. x 6m RSB 46.84 kgs. 33.00
4" CHB 110 pcs. 8.00
#16 G.I. Tie Wire 0.63 kg 60.00
Miscellaneous 1 lot 2,500.00
DIRECT COST: MATERIALS PhP

B. LABOR:
NO. OF
DESCRIPTION HOURS HOURLY RATE
MANPOWER
Labor Cost
DIRECT COST: LABOR PhP

C. EQUIPMENT
NO. OF
DESCRIPTION HOURS RATE/HOUR
EQUIPMENT

DIRECT COST: EQUIPMENT PhP

D. TOTAL DIRECT COST (A+B+C) PhP 13,839.18


E. VAT (5%) PhP 691.96
F. TOTAL COST (D+E) PhP 14,531.13
G. UNIT COST (F / Est. Qty.) PhP 14,531.13
SAY PhP 14,531.00

Page 25 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Demolition/Removal of Existing


ITEM NO.: __________ ITEM OF WORK: Demolition of Existing Walls/C
Windows/Floor Tiles
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST

Demolition of existing walls/ceiling/windows/floor 1 lot 50,000.00


tiles
DIRECT COST : MATERIALS Php.

D. TOTAL DIRECT COST (A+B+C) PhP 50,000.00


E. VAT (5%) PhP 2,500.00
F. TOTAL COST (D+E) PhP 52,500.00
G. UNIT COST (F / Est. Qty.) PhP 52,500.00
SAY PhP 52,500.00

UNIT COST DERIVATION Masonry Works


ITEM NO.: __________ ITEM OF WORK: CHB Walls #5, Incl. Plastering
ESTIMATED QUANTITIES: 760.02 UNIT: sq.m.

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
4" CHB Ordinary 9804.00 pcs. 8.00
Cement 409.42 bags 205.00
Sand 34.12 cu.m 700.00
10mm dia. Bar 2,067.84 kgs. 33.00
G.I Tie Wire #16 25.10 kgs. 60.00
Plaster
Portland Cement (40 kg) 151 bags 225.00
Sand 12.549122944 cu.m. 650.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

Page 26 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 387,437.69


E. VAT (5%) PhP 19,371.88
F. TOTAL COST (D+E) PhP 406,809.58
G. UNIT COST (F / Est. Qty.) PhP 535.26
SAY PhP 535.00

Page 27 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Masonry Works


ITEM NO.: __________ ITEM OF WORK: CHB Walls #4, Incl. Plastering
ESTIMATED QUANTITIES: 112.62 UNIT: sq.m.

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
4" CHB Ordinary 1408.00 pcs. 8.50
Cement 58.79 bags 205.00
Sand 4.90 cu.m 700.00
10mm dia. Bar 296.92 kgs. 33.00
G.I Tie Wire #16 3.60 kgs. 60.00
Plaster
Portland Cement (40 kg) 22 bags 225.00
Sand 1.80 cu.m. 650.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 56,549.28


E. VAT (5%) PhP 2,827.46
F. TOTAL COST (D+E) PhP 59,376.74
G. UNIT COST (F / Est. Qty.) PhP 527.24
SAY PhP 527.00

UNIT COST DERIVATION Masonry Works


ITEM NO.: __________ ITEM OF WORK: CHB Walls #6, Incl. Plastering
ESTIMATED QUANTITIES: 421.71 UNIT: sq.m.

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
6" CHB Ordinary 5272.00 pcs. 9.00
Page 28 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
Cement 220.13 bags 205.00
Sand 18.34 cu.m 700.00
10mm dia. Bar 1,111.83 kgs. 33.00
G.I Tie Wire #16 13.49 kgs. 60.00
Plaster
Portland Cement (40 kg) 81 bags 225.00
Sand 6.75 cu.m. 650.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 215,176.53


E. VAT (5%) PhP 10,758.83
F. TOTAL COST (D+E) PhP 225,935.36
G. UNIT COST (F / Est. Qty.) PhP 535.76
SAY PhP 536.00

Page 29 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Doors
D-1 2.10m x 1.40m Double Sw
Flush Type Door
UNIT:
ESTIMATED QUANTITIES: 7 set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
2.10m x 1.40m Double Swing Door
20.58 sq.m. 850.00
Flush Type Door
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 5 578.84
Laborer 1 5 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 23,213.35


E. VAT (5%) PhP 1,160.67
F. TOTAL COST (D+E) PhP 24,374.02
G. UNIT COST (F / Est. Qty.) PhP 3,482.00
SAY PhP 3,482.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Doors
D-2 2.10m x 0.60m PVC Type

ESTIMATED QUANTITIES: 26 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
2.10m x 0.60m PVC Type Door
32.76 sq.m 980.00
Page 30 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
32.76 sq.m 980.00
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 9 578.84
Laborer 1 9 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 42,001.43


E. VAT (5%) PhP 2,100.07
F. TOTAL COST (D+E) PhP 44,101.50
G. UNIT COST (F / Est. Qty.) PhP 1,696.21
SAY PhP 1,696.00

Page 31 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: D-3 2.10m x 1.30m Double Sw
Flush Type Door

UNIT:
ESTIMATED QUANTITIES: 7 set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
2.10m x 1.0m Hollow Core Door with
19.11 sq.m. 850.00
Marine Plywood and Fixed Glass Panel
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 5 578.84
Laborer 1 5 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 21,963.85


E. VAT (5%) PhP 1,098.19
F. TOTAL COST (D+E) PhP 23,062.04
G. UNIT COST (F / Est. Qty.) PhP 3,294.58
SAY PhP 3,295.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Doors
D-4 2.10m x 0.80m Metal Doo
RESISTANCE
ESTIMATED QUANTITIES: 5 UNIT: set

A. MATERIALS
Page 32 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
DESCRIPTION QUANTITY UNIT UNIT COST
2.10m x 0.80m Metal Door w/ 1 HR FIR Resistance 8.4 sq.m. 5,500.00
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 13.5 578.84
Laborer 1 13.5 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 60,794.95


E. VAT (5%) PhP 3,039.75
F. TOTAL COST (D+E) PhP 63,834.69
G. UNIT COST (F / Est. Qty.) PhP 12,766.94
SAY PhP 12,767.00

Page 33 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Doors
D-5 2.10m x 1.60m Double Sw
Flush Type Door
ESTIMATED QUANTITIES: 4 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
2.10m x 1.60m Double Swing Door -
13.44 sq.m. 850.00
Flush Type Door
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 4 578.84
Laborer 1 4 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 16,100.28


E. VAT (5%) PhP 805.01
F. TOTAL COST (D+E) PhP 16,905.29
G. UNIT COST (F / Est. Qty.) PhP 4,226.32
SAY PhP 4,226.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Doors
D-6 2.10m x 0.80m Flush Type
ESTIMATED QUANTITIES: 5 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Page 34 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
2.10m x 1.2m Double Swing Door - Hollow Core
8.4 sq.m. 850.00
Door with Marine Plywood and Fixed Glass Panel
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 2.5 578.84
Laborer 1 2.5 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 10,250.18


E. VAT (5%) PhP 512.51
F. TOTAL COST (D+E) PhP 10,762.68
G. UNIT COST (F / Est. Qty.) PhP 2,152.54

SAY PhP 2,153.00

Page 35 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Windows
W-1 1.20m x 1.40m Steel Case
UNIT:
ESTIMATED QUANTITIES: 40 set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
1.20m x 1.40m Steel Casement Window
67.2 sq.m. 1,800.00
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 10 578.84
Laborer 1 10 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 131,900.70


E. VAT (5%) PhP 6,595.04
F. TOTAL COST (D+E) PhP 138,495.74
G. UNIT COST (F / Est. Qty.) PhP 3,462.39
SAY PhP 3,462.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Windows
W-2 1.20m x1.40m Fixed Glas
ESTIMATED QUANTITIES: 4 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
1.20m x1.40m Fixed Glass Window
6.72 sq.m. 440.00
Aluminum Frame
Miscellaneous 1 lot 500.00
Page 36 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 1 578.84
Laborer 1 1 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 4,500.87


E. VAT (5%) PhP 225.04
F. TOTAL COST (D+E) PhP 4,725.91
G. UNIT COST (F / Est. Qty.) PhP 1,181.48
SAY PhP 1,181.00

Page 37 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Windows
W-3 1.00m x 1.80m Steel Awn
ESTIMATED QUANTITIES: 1 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
1.00m x 1.80m Steel Awning Window
1.8 sq.m. 1,870.00
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 1 578.84
Laborer 1 1 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 4,910.07


E. VAT (5%) PhP 245.50
F. TOTAL COST (D+E) PhP 5,155.57
G. UNIT COST (F / Est. Qty.) PhP 5,155.57
SAY PhP 5,156.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Windows
W-4 0.60m x 0.60m Steel Awn
ESTIMATED QUANTITIES: 43 UNIT: set

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
1.20m x 1.20m Sliding Window with Glass
15.48 sq.m. 1,870.00
Page 38 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
15.48 sq.m. 1,870.00
on Aluminum Frame
Miscellaneous 1 lot 500.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Skilled 1 8.5 578.84
Laborer 1 8.5 465.23
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 38,322.20


E. VAT (5%) PhP 1,916.11
F. TOTAL COST (D+E) PhP 40,238.30
G. UNIT COST (F / Est. Qty.) PhP 935.77
SAY PhP 936.00

Page 39 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Painting Works
ESTIMATED QUANTITIES: 4991.44 UNIT: sq.m.

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
40 t.c. 1,845.00
Latex Paint Flat
Latex Paint Gloss 108 t.c. 2,200.00
Flatwall Enamel 104 t.c. 2,090.00
Quick Drying Enamel 104 t.c. 2,330.00
Acry-Color 20 ltr. 175.00
Paint Thinner 3 gals. 230.00
Paint Roller 2 pcs. 85.00
Paint Brush #3 2 pcs. 70.00
Paint Brush #4 2 pcs. 100.00
Sand Paper 2000 pcs. 20.00
Calsomine 50 kgs. 30.00
Concrete Neutralizer 15.14 ltr. 103.00
Glazing Putty 5 bags 550.00
Scaffolding Works 1 lot 40,000.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER

Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 1,120,066.25


E. VAT (5%) PhP 56,003.31
F. TOTAL COST (D+E) PhP 1,176,069.56
G. UNIT COST (F / Est. Qty.) PhP 235.62
SAY PhP 236.00

Page 40 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Tileworks and Finishes
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
24" x 24" Wall Tiles 127.16 sq.m. 740.00
12" x 12" Floor Tiles 74.44 sq.m. 800.00
24"x24" Floor Tiles 933.08 sq.m. 800.00
Portland Cement 98 bags 205.00
Tile Adhesive 125 bags 90.00
Tile Grout 568 bags 47.50
Water Proofing 75 gals. 1,700.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 1,411,714.72


E. VAT (5%) PhP 70,585.74
F. TOTAL COST (D+E) PhP 1,482,300.46
G. UNIT COST (F / Est. Qty.) PhP 1,482,300.46
SAY PhP 1,482,300.00

UNIT COST DERIVATION Architectural Works


ITEM NO.: __________ ITEM OF WORK: Stainless Steel Railings
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Stainless Steel Railings 1 lot 25,000.00

Page 41 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
DIRECT COST : MATERIALS Php.

D. TOTAL DIRECT COST (A+B+C) PhP 25,000.00

E. VAT (5%) PhP 1,250.00


F. TOTAL COST (D+E) PhP 26,250.00
G. UNIT COST (F / Est. Qty.) PhP 26,250.00
SAY PhP 26,250.00

Page 42 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Electrical Works


ITEM NO.: __________ ITEM OF WORK: Roughing-In and Wiring
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
3.5mm sq. THHN, Stranded Cu Wire 63 boxes 2,200.00
5.5mm sq. THHN, Stranded Cu Wire 3 boxes 2,500.00
8.0mm sq. THHN, Stranded Cu Wire (100m/box) 3 boxes 5,384.50
14.0mm sq. THHN, Stranded Cu Wire 30 l.m. 88.00
50.0mm sq. THHN, Stranded Cu Wire 30 l.m. 583.00
80.0mm sq. THHN, Stranded Cu Wire 111 l.m. 308.00
125.0mm sq. THHN, Stranded Cu Wire 36 l.m. 913.00
200.0mm sq. THHN, Stranded Cu Wire 459 l.m. 1,232.00
2.0mm sq. TWG, Stranded Cu Wire 29 boxes 2,420.00
3.5mm sq. TWG, Stranded Cu Wire 77 l.m. 22.00
5.5mm sq. TWG, Stranded Cu Wire 10 l.m. 38.50
14.0mm sq. TWG, Stranded Cu Wire 47 l.m. 96.80
22.0mm sq. TWG, Stranded Cu Wire 165 l.m. 115.50
3" PVC Conduit 50 lgt. 1,089.00
3" PVC Elbow 12 pcs. 682.00
3" PVC Clamp 18 pcs. 66.00
3" PVC Endbell 6 sets 115.50
17 lgt. 737.00
2 1/2" PVC Conduit
2 1/2" PVC Elbow 7 pcs. 363.00
2 1/2" PVC Clamp 20 pcs. 49.50
2 1/2" PVC Endbell 6 sets 115.50
2" PVC Conduit 5 lgt. 528.00
2" PVC Elbow 2 pcs. 165.00
2" PVC Clamp 6 pcs. 33.00
2 sets 49.50
2" PVC Endbell
1" PVC Conduit 5 lgt. 40.67
1" PVC Elbow 2 pcs. 55.00
1" PVC Clamp 6 pcs. 22.00
1" PVC Endbell 2 sets 27.50
3/4" PVC Conduit 95 lgt. 30.67
38 pcs. 27.50
3/4" PVC Elbow
3/4" PVC Adaptor and Nuts 80 sets 14.00
1/2" PVC Conduit 1000 lgt. 20.67
1/2" PVC Elbow 315 pcs. 22.00
Page 43 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
1/2" PVC Adaptor and Nuts 875 sets 9.00
1/2" Flexible Hose 350 l.m. 15.40
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 1,354,304.38


E. VAT (5%) PhP 67,715.22
F. TOTAL COST (D+E) PhP 1,422,019.60
G. UNIT COST (F / Est. Qty.) PhP 1,422,019.60
SAY PhP 1,422,020.00

Page 44 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Electrical Works


ITEM NO.: __________ ITEM OF WORK: Electrical Fixtures, Outlets, Sw
and Accessories
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
4" x 4" Junction Box 320 pcs. 21.00
2" x 4" Utility Box 330 pcs. 20.00
Splicing Box 1 pc. 550.00
Recessed Pinlight with Cover and Bulb 10 sets 561.00
Flourescent Light, 2x36W with Aluminum Reflector
172 sets 2,420.00
with Louver
Receptacle Socket with Bulb 50 sets 220.00
Emergency Light with Battery Back-Up 37 sets 1,815.00
Surface Mounted Exit Light 7 sets 968.00
Single Gang Switch 49 pcs. 110.00
Two Gang Switch 48 pcs. 214.50
Three Way Switch 4 pcs. 550.00
Simplex Convenience Outlet 37 pcs. 143.00
Duplex Convenience Outlet 145 pcs. 154.00
Air Conditioning Outlet 37 pcs. 236.50
Blank Cover Outlet 1 pc. 110.00
75 rolls 30.00
Electrical Tape
Guide Wire 8 kgs. 60.00
Cable Tie 10 packs 220.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER

Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

Page 45 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
D. TOTAL DIRECT COST (A+B+C) PhP 753,933.05
E. VAT (5%) PhP 37,696.65
F. TOTAL COST (D+E) PhP 791,629.70
G. UNIT COST (F / Est. Qty.) PhP 791,629.70
SAY PhP 791,630.00

Page 46 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Electrical Works


ITEM NO.: __________ ITEM OF WORK: Panel Board and Circuit Break
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
LPA 1 set/assy 76,670.00
Main: 250A 300AF 3P MCCB 22KAIC

Branches: 17 - 20AT 2P
1 - 200AT 3P
PPA 1 set/assy 46,310.00
Main: 200A 300AF 3P MCCB 22KAIC
Branches: 16 - 30AT 2P
4 - 40AT 2P
LPB 1 set/assy 31,680.00

Main: 70A 50AF 3P MCCB 22KAIC


Branches: 16 - 20AT 2P
PPB 1 set/assy 41,580.00
Main: 150A 200AF 3P MCCB 22KAIC
Branches: 14 - 30AT 2P
2 - 40AT 2P
1 set/assy 21,450.00
LPC
Main: 50A 50AF 3P MCCB 22KAIC
Branches: 6 - 20AT 2P
2 - 30AT 2P
LPD 1 set/assy 19,470.00
Main: 40A 50AF 3P MCCB 22KAIC
Branches: 2 - 22AT 2P
4 - 30AT 2P
MDP/ATS 1 set/assy 297,600.00
Main: 700A 3P MCCB 65KAIC
Branches: 1 - 250AT 3P
1 - 200AT 3P
1 - 150AT 3P
1 - 70AT 3P
1 - 50AT 3P
1 - 40AT 3P
DIRECT COST : MATERIALS Php.

B. LABOR

Page 47 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 695,188.00


E. VAT (5%) PhP 34,759.40
F. TOTAL COST (D+E) PhP 729,947.40

G. UNIT COST (F / Est. Qty.) PhP 729,947.40


SAY PhP 729,947.00

Page 48 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Electrical Works


ITEM NO.: __________ ITEM OF WORK: Overhead Service Entrance an
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
700A 3P ECB in NEMA 3R 1 set/assy 63,580.66
3" RSC Conduit 2 lgt. 1,870.00
3" Metal Clamp with Bolt and Nut 4 sets 88.00
3" Locknut and Bushing 2 sets 55.00
2 pcs. 275.00
3" RSC Entrance Cap
Ball Insulator 8 pcs. 33.00
Eyebolt 1 pc. 275.00
Eyenut 1 pc. 165.00
12mm Grounding Rod 1 pc. 660.00
Grounding Clamp 1 pc. 82.50
Grounding Strip 1 pc. 550.00
200mm sq. THHN, Stranded Cu Wire 24 l.m. 1,232.00
22mm sq. THHN, Stranded Cu Wire 8 l.m. 115.50
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 131,067.51


E. VAT (5%) PhP 6,553.38

F. TOTAL COST (D+E) PhP 137,620.88


G. UNIT COST (F / Est. Qty.) PhP 137,620.88
SAY PhP 137,621.00

Page 49 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Electrical Works


ITEM NO.: __________ ITEM OF WORK: Site Development
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Single Arm Lamp Post 4 sets 28,344.13
Double Arm Lamp Post 6 sets 37,509.76
1/2" RSC Conduit 50 lgt. 225.00
1/2" RSC Elbow 22 pcs. 22.00
22 sets 7.00
1/2" RSC Locknut and Bushing
4 x 4 Junction Box 12 pcs. 21.00
3.5mm sq. THHN, Stranded Cu Wire 2 boxes 2,200.00
2.0mm sq. THHN, Stranded Cu Wire 1 box 2,000.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 464,067.60


E. VAT (5%) PhP 23,203.38
F. TOTAL COST (D+E) PhP 487,270.98
G. UNIT COST (F / Est. Qty.) PhP 487,270.98

SAY PhP 487,271.00

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Cold Water Line
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Page 50 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
PVC Pipe 3/4 250 pcs. 70.00
3/4 Gate Valve 40 pcs. 250.00
Moldex Blue Elbow 3/4" 90d. 90 pcs. 17.00
Moldex Blue Tee 3/4" 90d. 124 pcs. 9.00
Moldex Blue Coupling 3/4" 135 pcs. 9.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 40,769.30


E. VAT (5%) PhP 2,038.47
F. TOTAL COST (D+E) PhP 42,807.77
G. UNIT COST (F / Est. Qty.) PhP 42,807.77
SAY PhP 42,808.00

Page 51 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Drainage Line
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
3" x 10' PVC Downspout 15 pcs. 447.00
3" PVC Elbow 15 pcs. 51.00
PVC Solvent Cement(100cc) 3 cans 80.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 10,023.00


E. VAT (5%) PhP 501.15
F. TOTAL COST (D+E) PhP 10,524.15
G. UNIT COST (F / Est. Qty.) PhP 10,524.15
SAY PhP 10,524.00

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Sewer Line
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
4" uPVC Sanitary Pipe 116 pcs. 770.00
2" uPVC Sanitary Pipe 64 pcs. 175.00
4" uPVC Clean Out 30 pcs. 60.00
2" P-Trap 76 pcs. 110.00
4" x 1/8 Bend uPVC Sanitary Elbow 88 pcs. 62.00
45 pcs. 21.00
2" x 1/8 Bend uPVC Sanitary Elbow
Page 52 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
4" x 4" uPVC Sanitary Wye 91 pcs. 130.00
2" x 4" uPVC Sanitary Wye 78 pcs. 103.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 178,028.50


E. VAT (5%) PhP 8,901.43
F. TOTAL COST (D+E) PhP 186,929.93
G. UNIT COST (F / Est. Qty.) PhP 186,929.93
SAY PhP 186,930.00

Page 53 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Plumbing Fixtures and Acces
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Water Closet 30 sets 7,055.00
Lavatory with Accessories 50 sets 6,695.00
4 x 4 Floor Drain Stainless 29 pcs. 85.00
Angle Valve 80 pcs. 420.00
Teflon Tape 25 rolls 12.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 757,594.50


E. VAT (5%) PhP 37,879.73
F. TOTAL COST (D+E) PhP 795,474.23
G. UNIT COST (F / Est. Qty.) PhP 795,474.23
SAY PhP 795,474.00

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Cistern Tank
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Aggregate Base Course 101.29 cu.m. 400.00
Portland Cement 103 bags 205.00
Washed Sand 6 cu.m. 700.00
Page 54 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
Crushed Gravel (3/4) 12 cu.m. 700.00
76 - 16mm dia. X 6.0m RSB Def. 719.72 kgs. 33.00
94 - 12mm dia. X 6.0m RSB Def. 500.73 kgs. 33.00
# 16 G.I. Tie Wire 13 kgs. 60.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 149,871.61


E. VAT (5%) PhP 7,493.58
F. TOTAL COST (D+E) PhP 157,365.19
G. UNIT COST (F / Est. Qty.) PhP 157,365.19
SAY PhP 157,365.00

Page 55 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Overhead Tank
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
3 x 3 x 1/4 Angle Bar 1310.44 kgs. 50.00
2 x 2 x 1/4 Angle Bar 3447.03 kgs. 50.00
9.10 - 16mm dia. X 6.0m RSB def. 86.18 kgs. 33.00
3.95 - 12mm dia. X 6.0m RSB def. 21.05 kgs. 33.00
Cutting Disk 4 kgs. 110.00
Welding Rod 1 box 3,200.00
Acetylene/Oxygen 11 sets 1,500.00
Epoxy Primer 12 t.c. 2,350.00
1000 gal. Stainless Water Tank/Fittings 1 pc. 87,000.00
P.E. Pipe 3/4 270 l.m. 35.00
2 pcs. 250.00
Gate Valve 3/4" dia.
G.I. Pipe 1" dia. Sch.40 4 pcs. 710.00
G.I. Coupling 1" dia. 4 pcs. 85.00
G.I. Elbow 1" dia. 4 pcs. 95.00
G.I. Tee 1" dia 4 pcs. 105.00
10 rolls 12.00
Teflon Tape
Gate Valve 1" 2 pcs. 250.00
Miscellaneous 1 lot 28,200.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 545,352.72


E. VAT (5%) PhP 27,267.64

F. TOTAL COST (D+E) PhP 572,620.35


G. UNIT COST (F / Est. Qty.) PhP 572,620.35
Page 56 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
SAY PhP 572,620.00

Page 57 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Plumbing Works


ITEM NO.: __________ ITEM OF WORK: Pump House
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Portland Cement 52 bags 205.00
Washed Sand 3 cu.m. 700.00
Crushed Gravel (3/4) 5 cu.m. 700.00
13-16mm dia. X 6.0m RSB def. 123.11 kgs. 33.00
71-12mm dia. X 6.0m RSB def. 378.21 kgs. 33.00
13 kgs. 60.00
#16 GI Tie Wire
CHB #6 340 pcs. 9.00
2 hp Water pump 1 set 28,000.00
P.E. Pipe 3/4 140 l.m. 35.00
G.I. Pipe 1" dia. Sch.40 4 pcs. 710.00
2 pcs. 85.00
G.I. Coupling 1" dia.
G.I. Elbow 1" dia. 2 pcs. 95.00
G.I. Tee 1" dia. 2 pcs. 105.00
Teflon Tape 6 rolls 12.00
Gate Valve 1" 1 pc. 250.00
Roofing and Accessories 1 lot 10,000.00
Steel Grill Door 1 set 3,000.00
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 112,158.23


E. VAT (5%) PhP 5,607.91
F. TOTAL COST (D+E) PhP 117,766.14
G. UNIT COST (F / Est. Qty.) PhP 117,766.14
SAY PhP 117,766.00
Page 58 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Fire Protection System


ITEM NO.: __________ ITEM OF WORK: Fire Detection and Alarm Sys
UNIT:
ESTIMATED QUANTITIES: 1 lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Boxes and Conduits
560 l.m. 930.46
EMT Pipe (20mm dia.)
FR Cable 4032 l.m. 119.63
Junction Box 142 pcs. 265.85
Square Box 20 pcs. 265.85
FMC (20mm dia.) 220 l.m. 332.31
DIA 210 pcs. 66.46
Ring Box 100 pcs. 664.61
Devices
Strobe Light with Horn 15 pcs. 7,551.49
Manual Pull Station 15 pcs. 7,551.49
Smoke Detector 90 pcs. 3,775.74
Monitor Module 26 pcs. 5,034.32
Fire Alarm Control 1 unit 352,402.75
Panel 1 set 50,343.25
Others
Miscellaneous 1 lot 41,411.28
Pipe Supports 1 lot 33,077.95
1 lot 41,661.28
Scaffolding Works
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 3,140,994.21

E. VAT (5%) PhP 157,049.71


Page 59 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
F. TOTAL COST (D+E) PhP 3,298,043.92
G. UNIT COST (F / Est. Qty.) PhP 3,298,043.92
SAY PhP 3,298,044.00

Page 60 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

UNIT COST DERIVATION Fire Protection System


ITEM NO.: __________ ITEM OF WORK: Fire Sprinkler System
ESTIMATED QUANTITIES: 1 UNIT: lot

A. MATERIALS
DESCRIPTION QUANTITY UNIT UNIT COST
Fire Protection System Equipments
Horizontal Spit Case Fire Pump 20HP 1 set 267,806.27
Jockey Pump 5HP 1 set 96,866.10
Concrete Pads 1 lot 13,675.21
1 lot 10,256.41
Electrical Loadside Works
Sensing Lines 1 lot 11,396.01
Fire Protection System Piping Works
B.I. Pipes, Sch.40
75mm dia. 12 pcs. 1,327.08
50mm dia. 140 pcs. 1,161.93
40mm dia. 20 pcs. 884.72
20 pcs. 759.39
32mm dia.
25mm dia. 440 pcs. 560.32
B.I. Elbow 90deg.
75mm dia. 5 pcs. 663.54
50mm dia. 16 pcs. 958.45
30 pcs. 611.93
40mm dia.
32mm dia. 30 pcs. 457.11
25mm dia. 350 pcs. 216.76
B.I. Tee
75mm dia. X 75mm dia. 10 pcs. 928.96
75mm dia. X 50mm dia. 5 pcs. 928.96
75mm dia. X 32mm dia. 5 pcs. 928.96
50mm dia. X 50mm dia. 120 pcs. 443.41
50mm dia. X 40mm dia. 50 pcs. 530.83
50mm dia. X 25mm dia. 50 pcs. 530.83
40mm dia. X 25mm dia. 50 pcs. 359.15
32mm dia. X 25mm dia. 50 pcs. 270.68
25mm dia. X 25mm dia. 250 pcs. 147.45
B.I. Reducer
75mm dia. X 50mm dia. 15 pcs. 486.60
75mm dia. X 40mm dia. 10 pcs. 486.60
50mm dia. X 40mm dia. 10 pcs. 253.62
50 pcs. 176.94
40mm dia. X 32mm dia.
32mm dia. X 25mm dia. 50 pcs. 132.71
Page 61 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
25mm dia. X 15mm dia. 120 pcs. 103.22
B.I. Union Patente 25mm dia 9 pcs. 589.81
B.I. Slip On Flanges 75mm dia. 20 pcs. 884.72
B.I. Slip On Flanges 50mm dia. 14 pcs. 589.81
B.I. Slip On Flanges 25mm dia. 24 pcs. 442.36
B.I. Blind Flanges 100mm dia. 6 pcs. 737.27
B.I. Cap Plug 40mm dia. 6 pcs. 589.81
O.S.Y. Valve 75mm dia. 3 pcs. 31,597.21
Alarm Check Valve 75mm dia. 1 set 49,502.30
Floor Control Bulb 50mm dia. 2 sets 12,638.89
1 set 25,277.77
Check Valve 75mm dia.
Check Valve 40mm dia. 1 set 12,638.89
Supervisory Switch 50mm dia. 2 pcs. 5,266.20
Water Flow Switch 50mm dia. 2 pcs. 10,532.40
I.T.C. Valves 25mm dia. 2 pcs. 2,633.10
4 pcs. 2,633.10
Sight Glass 25mm dia.
Drain Valve 25mm dia. 4 pcs. 1,895.83
Upright Sprinkler Heads 113 sets 521.35
Pendent Heads 10 sets 521.35
Grooved Coupling (Victaulic) 65mm dia. 2 pcs. 1,579.86
Others
Painting Works 1 lot 26,756.11
Pipe Supports 1 lot 33,221.62
Scaffolding Works 1 lot 29,342.31

Page 62 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN
Miscellaneous 1 lot 30,635.42
DIRECT COST : MATERIALS Php.

B. LABOR
NO. OF
DESCRIPTION DAY/S DAILY RATE
MANPOWER
Labor Cost
DIRECT COST : LABOR Php.

C. EQUIPMENT
NO OF
DESCRIPTION DAY/S RATE/DAY
EQUIPMENT

DIRECT COST : EQUIPMENT Php.

D. TOTAL DIRECT COST (A+B+C) PhP 2,235,937.12


E. VAT (5%) PhP 111,796.86
F. TOTAL COST (D+E) PhP 2,347,733.97
G. UNIT COST (F / Est. Qty.) PhP 2,347,733.97

SAY PhP 2,347,734.00

Prepared & Submitted by: Checked & R

WILHELMINO M. SY-ALVARADO RAMON S


Provincial Governor Manager,

Recommending Approval:

Page 63 of 133
AMOUNT
4,347.00
4,347.00

AMOUNT

AMOUNT

4,347.00

AMOUNT

40,000.00
40,000.00

40,000.00

Page 64 of 133
(Note: Labor Cost is 30% of Materials Cost)

Page 65 of 133
AMOUNT

AMOUNT
408.42
586.19
994.61

AMOUNT

9.95

AMOUNT

AMOUNT
81.04
116.30
197.34

Page 66 of 133
AMOUNT
2,173.00
1,507.00
266.25
3,946.25

13.81

Page 67 of 133
AMOUNT
23,000.00

23,000.00

AMOUNT
81.04
116.30
197.34

AMOUNT
2,173.00
1,507.00
266.25
3,946.25

542.87

Aggregate Sub-base Course

AMOUNT
23,575.00

23,575.00

AMOUNT
Page 68 of 133
81.04
116.30
197.34

AMOUNT
2,173.00
1,507.00
266.25
3,946.25

554.37

Page 69 of 133
PCC Pavement, 200mm thk.

AMOUNT
1,036.04
653.66
425.04
9,257.50
56,350.00
96.60
67,818.84

AMOUNT
81.04
289.44
697.80
1,068.28

AMOUNT
297.76
1,733.00
545.00
1,065.00
167.38
21.98
3,830.12

903.32

Page 70 of 133
AMOUNT
2,723.84
504.70
1,009.40
1,151.70
1,600.00
60.00
7,049.64

AMOUNT
81.04
289.44
465.20
835.68

AMOUNT
172.00
148.88
53.25
41.78
415.91

805.94

AMOUNT
4,100.00

Page 71 of 133
882.00
700.00
1,545.72
880.00
37.80
2,500.00
10,645.52

AMOUNT
3,193.66
3,193.66

AMOUNT

13,839.18

Page 72 of 133
Demolition/Removal of Existing Structures
Demolition of Existing Walls/Ceiling/

AMOUNT

50,000.00
50,000.00

50,000.00

CHB Walls #5, Incl. Plastering

AMOUNT
78,432.02
83,930.10
23,882.55
68,238.87
1,505.89

33,882.63
8,156.93
298,029.00

AMOUNT
89,408.70
89,408.70

AMOUNT

Page 73 of 133
509.77

Page 74 of 133
CHB Walls #4, Incl. Plastering

AMOUNT
11,968.00
12,051.34
3,429.24
9,798.27
216.23

4,865.13
1,171.24
43,499.44

AMOUNT
13,049.83
13,049.83

AMOUNT

502.13

CHB Walls #6, Incl. Plastering

AMOUNT
47,448.00
Page 75 of 133
45,127.35
12,841.12
36,690.52
809.69

18,217.94
4,385.80
165,520.41

AMOUNT
49,656.12
49,656.12

AMOUNT

510.25

Page 76 of 133
D-1 2.10m x 1.40m Double Swing Door -

AMOUNT
17,493.00
500.00
17,993.00

AMOUNT
2,894.20
2,326.15
5,220.35

AMOUNT

3,316.19

D-2 2.10m x 0.60m PVC Type Door

AMOUNT
32,104.80
Page 77 of 133
32,104.80
500.00
32,604.80

AMOUNT
5,209.56
4,187.07
9,396.63

AMOUNT

1,615.44

Page 78 of 133
D-3 2.10m x 1.30m Double Swing Door -

AMOUNT
16,243.50
500.00
16,743.50

AMOUNT
2,894.20
2,326.15
5,220.35

AMOUNT

3,137.69

D-4 2.10m x 0.80m Metal Door w/ 1 HR FIR

Page 79 of 133
AMOUNT
46,200.00
500.00
46,700.00

AMOUNT
7,814.34
6,280.61
14,094.95

AMOUNT

12,158.99

Page 80 of 133
D-5 2.10m x 1.60m Double Swing Door -

AMOUNT
11,424.00
500.00
11,924.00

AMOUNT
2,315.36
1,860.92
4,176.28

AMOUNT

4,025.07

D-6 2.10m x 0.80m Flush Type Door

AMOUNT
Page 81 of 133
7,140.00
500.00
7,640.00

AMOUNT
1,447.10
1,163.08
2,610.18

AMOUNT

2,050.04

Page 82 of 133
W-1 1.20m x 1.40m Steel Casement Window

AMOUNT
120,960.00
500.00
121,460.00

AMOUNT
5,788.40
4,652.30
10,440.70

AMOUNT

3,297.52

W-2 1.20m x1.40m Fixed Glass Window

AMOUNT
2,956.80
500.00
Page 83 of 133
3,456.80

AMOUNT
578.84
465.23
1,044.07

AMOUNT

1,125.22

Page 84 of 133
W-3 1.00m x 1.80m Steel Awning Window

AMOUNT
3,366.00
500.00
3,866.00

AMOUNT
578.84
465.23
1,044.07

AMOUNT

4,910.07

W-4 0.60m x 0.60m Steel Awning Window

AMOUNT
28,947.60
Page 85 of 133
28,947.60
500.00
29,447.60

AMOUNT
4,920.14
3,954.46
8,874.60

AMOUNT

891.21

Page 86 of 133
AMOUNT
73,800.00
237,600.00
217,360.00
242,320.00
3,500.00
690.00
170.00
140.00
200.00
40,000.00
1,500.00
1,559.42
2,750.00
40,000.00
861,589.42

AMOUNT

258,476.83
258,476.83

AMOUNT

224.40

Page 87 of 133
AMOUNT
94,098.40
59,552.00
746,464.00
20,090.00
11,250.00
26,980.00
127,500.00
1,085,934.40

AMOUNT
325,780.32
325,780.32

AMOUNT

1,411,714.72

AMOUNT
25,000.00

Page 88 of 133
25,000.00

25,000.00

Page 89 of 133
AMOUNT
138,600.00
7,500.00
16,153.50
2,640.00
17,490.00
34,188.00
32,868.00
565,488.00
70,180.00
1,694.00
385.00
4,549.60
19,057.50
54,450.00
8,184.00
1,188.00
693.00
12,529.00
2,541.00
990.00
693.00
2,640.00
330.00
198.00
99.00
203.35
110.00
132.00
55.00
2,913.65
1,045.00
1,120.00
20,670.00
6,930.00
Page 90 of 133
7,875.00
5,390.00
1,041,772.60

AMOUNT
312,531.78
312,531.78

AMOUNT

1,354,304.38

Page 91 of 133
Electrical Fixtures, Outlets, Switches

AMOUNT
6,720.00
6,600.00
550.00
5,610.00
416,240.00
11,000.00
67,155.00
6,776.00
5,390.00
10,296.00
2,200.00
5,291.00
22,330.00
8,750.50
110.00
2,250.00
480.00
2,200.00
579,948.50

AMOUNT

173,984.55
173,984.55

AMOUNT

Page 92 of 133
753,933.05

Page 93 of 133
Panel Board and Circuit Breaker

AMOUNT
76,670.00

46,310.00

31,680.00

41,580.00

21,450.00

19,470.00

297,600.00

534,760.00

Page 94 of 133
AMOUNT
160,428.00
160,428.00

AMOUNT

695,188.00

Page 95 of 133
Overhead Service Entrance and Accessories

AMOUNT
63,580.66
3,740.00
352.00
110.00
550.00
264.00
275.00
165.00
660.00
82.50
550.00
29,568.00
924.00
100,821.16

AMOUNT
30,246.35
30,246.35

AMOUNT

131,067.51

Page 96 of 133
AMOUNT
113,376.52
225,058.56
11,250.00
484.00
154.00
252.00
4,400.00
2,000.00
356,975.08

AMOUNT
107,092.52
107,092.52

AMOUNT

464,067.60

AMOUNT
Page 97 of 133
17,500.00
10,000.00
1,530.00
1,116.00
1,215.00
31,361.00

AMOUNT
9,408.30
9,408.30

AMOUNT

40,769.30

Page 98 of 133
AMOUNT
6,705.00
765.00
240.00
7,710.00

AMOUNT
2,313.00
2,313.00

AMOUNT

10,023.00

AMOUNT
89,320.00
11,200.00
1,800.00
8,360.00
5,456.00
945.00
Page 99 of 133
11,830.00
8,034.00
136,945.00

AMOUNT
41,083.50
41,083.50

AMOUNT

178,028.50

Page 100 of 133


Plumbing Fixtures and Accessories

AMOUNT
211,650.00
334,750.00
2,465.00
33,600.00
300.00
582,765.00

AMOUNT
174,829.50
174,829.50

AMOUNT

757,594.50

AMOUNT
40,516.00
21,115.00
4,200.00
Page 101 of 133
8,400.00
23,750.76
16,524.09
780.00
115,285.85

AMOUNT
34,585.76
34,585.76

AMOUNT

149,871.61

Page 102 of 133


AMOUNT
65,522.00
172,351.50
2,843.94
694.65
440.00
3,200.00
16,500.00
28,200.00
87,000.00
9,450.00
500.00
2,840.00
340.00
380.00
420.00
120.00
500.00
28,200.00
419,502.09

AMOUNT
125,850.63
125,850.63

AMOUNT

545,352.72

Page 103 of 133


AMOUNT
10,660.00
2,100.00
3,500.00
4,062.63
12,480.93
780.00
3,060.00
28,000.00
4,900.00
2,840.00
170.00
190.00
210.00
72.00
250.00
10,000.00
3,000.00
86,275.56

AMOUNT
25,882.67
25,882.67

AMOUNT

112,158.23

Page 104 of 133


Fire Detection and Alarm System

AMOUNT

521,057.60
482,348.16
37,750.70
5,317.00
73,108.20
13,956.60
66,461.00

113,272.35
113,272.35
339,816.60
130,892.32
352,402.75
50,343.25

41,411.28
33,077.95
41,661.28
2,416,149.39

AMOUNT
724,844.82
724,844.82

AMOUNT

3,140,994.21

Page 105 of 133


AMOUNT

267,806.27
96,866.10
13,675.21
10,256.41
11,396.01

15,924.96
162,670.20
17,694.40
15,187.80
246,540.80

3,317.70
15,335.20
18,357.90
13,713.30
75,866.00

9,289.60
4,644.80
4,644.80
53,209.20
26,541.50
26,541.50
17,957.50
13,534.00
36,862.50

7,299.00
4,866.00
2,536.20
8,847.00
6,635.50
Page 106 of 133
12,386.40
5,308.29
17,694.40
8,257.34
10,616.64
4,423.62
3,538.86
94,791.63
49,502.30
25,277.78
25,277.77
12,638.89
10,532.40
21,064.80
5,266.20
10,532.40
7,583.32
58,912.55
5,213.50
3,159.72

26,756.11
33,221.62
29,342.31

Page 107 of 133


30,635.42
1,719,951.63

AMOUNT
515,985.49
515,985.49

AMOUNT

2,235,937.12

Checked & Reviewed by:

RAMON S. PARAGAS
Manager, Region III-A

Page 108 of 133


24"x24" WALL TILES
DETERMINE THE FLOOR AREA
LENGTH
HEIGHT 1
AREA 0

PCS 0
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.

I GENERAL REQUIREMENTS
A Mobilization and Demobilization lot 1.00 24,803.00
B Informatory Signs lot 1.00 4,564.00
C Safety and Health lot 1.00 42,000.00

SUB-TOTAL I - General Requirements

II LAND DEVELOPMENT
A Clearing and Grubbing sq.m. 1,375.54 10.00
B Subgrade Preparation sq.m. 1,375.54 15.00
C Aggregate Base Course cu.m. 137.55 570.00
D Aggregate Sub-base Course cu.m. 137.55 582.00
E PCC Pavement, 200mm thk. sq.m. 1,375.54 948.00
F Concrete Curb and Gutter l.m. 60.00 846.00
G Drainage System lot 1.00 14,531.00

SUB-TOTAL II - Land Development

III DEMOLITION/REMOVAL OF EXISTING STRUCTURES


A Demolition of Existing Walls/Ceiling/Windows/Floor Tiles lot 1.00 52,500.00

SUB-TOTAL III - Demolition/Removal

IV MASONRY WORKS
A CHB Walls #4, Incl. Plastering sq.m. 40.96 527.00
B CHB Walls #5, Incl. Plastering sq.m. 212.24 664.00
C CHB Walls #6, Incl. Plastering sq.m. 324.64 795.00

SUB-TOTAL IV - Masonry Works

V CARPENTRY WORKS
A Ceiling sq.m. 939.89 249.00
B Cabinets & Shelves/Front Desk lot 1.00 210,000.00

SUB-TOTAL V - Carpentry Works

VI ARCHITECTURAL WORKS
A Doors
1 D-1 2.50m x 2.0m Double Swing Door set 21.00 29,299.00
2 D-2 2.50m x 1.2m Aluminum Casement Door set 5.00 17,827.00

Page 110 of 133


PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
3 D-3 2.10m x 1.0m Hollow Core Door set 11.00 4,192.00
4 D-4 2.10m x 0.9m Solid K.D. Panel Door set 29.00 6,336.00
5 D-5 2.10m x 0.8m Hollow Core Door set 50.00 3,398.00
6 D-6 2.10m x 1.2m Double Swing Door - Hollow Core Door set 2.00 5,365.00
7 D-7 2.10m x 1.6m Double Swing Door - Hollow Core Door set 2.00 6,884.00
B Windows
1 W-1 4.0m x 2.1m Fixed Glass Window set 1.00 32,934.00
2 W-2 5.40m x 2.1m Fixed Glass Window set 1.00 43,894.00
3 W-3 2.40m x 1.2m Sliding Window set 14.00 12,876.00
4 W-4 1.20m x 1.20m Sliding Window set 14.00 6,457.00
5 W-5 1.80m x 1.20m Sliding Window set 13.00 9,603.00
6 W-6 0.60m x 0.60m Awning Window set 29.00 1,921.00
7 W-7 1.8m x 1.4m Fixed Glass Window set 4.00 9,936.00
8 CW-1 4.0m x 2.10m Fixed Glass Window set 1.00 32,934.00
9 CW-1.1 0.95m x 2.45m Fixed Glass Window set 1.00 10,298.00
10 CW-1.2 1.60m x 2.45m Fixed Glass Window set 1.00 16,233.00

Page 111 of 133


PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
C Painting Works sq.m. 4,991.44 236.00
D Tileworks and Finishes lot 1.00 2,652,152.00
E Stainless Steel Railings lot 1.00 52,501.00

SUB-TOTAL VI - Architectural Works

VII ELECTRICAL WORKS


A Roughing-In and Wiring lot 1.00 1,422,020.00
B Electrical Fixtures, Outlets, Switches and Accessories lot 1.00 791,630.00
C Panel Board and Circuit Breaker lot 1.00 729,947.00
D Overhead Service Entrance and Accessories lot 1.00 137,621.00
E Site Development lot 1.00 487,271.00

SUB-TOTAL VII - Electrical Works

VIII PLUMBING WORKS


A Cold Water Line lot 1.00 42,808.00
B Drainage Line lot 1.00 10,524.00
C Sewer Line lot 1.00 186,930.00
D Plumbing Fixtures and Accessories lot 1.00 795,474.00
E Cistern Tank lot 1.00 157,365.00
F Overhead Tank lot 1.00 572,620.00
G Pump House lot 1.00 117,766.00

SUB-TOTAL VIII - Plumbing Works

IX FIRE PROTECTION SYSTEM


A Fire Detection and Alarm System lot 1.00 3,298,044.00
B Fire Sprinkler System lot 1.00 2,347,734.00

SUB-TOTAL IX - Fire Protection System

TOTAL - I to IX

X FURNITURES AND FIXTURES


A Administrative Service/Kitchen
1 Fire Extinguisher unit 5.00 7,000.00
2 Standby Generator 100KVA unit 1.00 2,100,000.00
3 Food Conveyor (closed type) unit 1.00 50,000.00
4 Refrigerator/Freezer unit 1.00 20,000.00
5 Stove unit 1.00 25,000.00
6 Computer Set set 10.00 60,000.00

Page 112 of 133


PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
Sub-Total A

B Clinical Services
1 Emergency Room/Out-patient
1.1 Ambu Bag
a. Adult unit 2.00 7,500.00
b. Pediatric unit 2.00 7,500.00
1.2 Clinical Weighing Scale unit 2.00 25,000.00
1.3 EENT Diagnostic Set set 1.00 12,000.00
1.4 Emergency Chart unit 1.00 50,000.00
1.5 Examining Table (OPD) unit 4.00 10,000.00
1.6 ER Stretcher Bed unit 6.00 85,000.00
1.7 Gooseneck Lamp/Examining Light unit 4.00 20,000.00
1.8 Instrument Table unit 4.00 5,000.00
1.9 Medicine Cabinet unit 2.00 10,000.00
1.10 Minor Surgery Instrument Set set 10.00 25,000.00

Page 113 of 133


PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
1.11 Nebulizer unit 4.00 7,000.00
1.12 Neurological Hammer unit 5.00 500.00
1.13 Oxygen Gauges unit 30.00 3,000.00
1.14 Sphygmomanometer
a. Adult Cuff set 4.00 15,000.00
b. Pediatric Cuff Set set 4.00 15,000.00
1.15 Stethoscope unit 10.00 3,500.00
1.16 Sunction Apparatus unit 4.00 15,000.00
1.17 Vaginal Speculum Set set 20.00 1,500.00
1.18 Wheelchair unit 10.00 5,000.00
1.19 Wheeled Stretcher unit 4.00 7,500.00

2 Surgical and Obstetrical Service


2.1 Anaesthesia Machine unit 1.00 1,500,000.00
2.2 Bassinet unit 15.00 10,000.00
2.3 C/S Set set 10.00 60,000.00
2.4 D/C Set set 5.00 30,000.00
2.5 Delivery Set set 10.00 15,000.00
2.6 DR Light unit 1.00 100,000.00
2.7 DR Table with Stirrup unit 1.00 150,000.00
2.8 Infant Weighing Scale unit 3.00 10,000.00
2.9 Instrument Table unit 4.00 5,000.00
2.10 Kelly Pad unit 10.00 1,000.00
2.11 Laparotomy set 10.00 75,000.00
2.12 Laryngoscope with blades unit 4.00 100,000.00
2.13 OR Light unit 1.00 1,200,000.00
2.14 OR Table unit 1.00 700,000.00
2.15 Sphygmomanometer
a. Adult Cuff set 4.00 15,000.00
b. Pediatric Cuff Set set 4.00 15,000.00
2.16 Spinal Set set 10.00 2,000.00
2.17 Stethoscope unit 4.00 3,500.00
2.18 Sunction Apparatus (heavy duty) unit 2.00 60,000.00
2.19 Wheeled Stretcher unit 4.00 7,500.00

3 Nursing Unit
3.1 Ambu Bag
a. Adult unit 3.00 7,500.00
b. Pediatric unit 3.00 7,500.00
3.2 Clinical Weighing Scale unit 3.00 25,000.00
3.3 Emergency Chart unit 3.00 50,000.00
3.4 Patient Bed with bedside table IV stand, over-bed, foot stool unit 25.00 65,000.00
3.5 Nebulizer unit 3.00 7,000.00
3.6 Sphygmomanometer
a. Adult Cuff set 3.00 15,000.00
b. Pediatric Cuff Set set 3.00 15,000.00
Page 114 of 133
PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
3.7 Stethoscope unit 3.00 3,500.00
3.8 Sunction Apparatus unit 3.00 15,000.00

4 Central Sterelizing and Supply Room


4.1 Autoclave (heavy duty big) unit 1.00 1,400,000.00

5 ER/OR/RR
5.1 Cardiac Monitors unit 5.00 200,000.00
5.2 X-Ray 300 MA unit 1.00 1,500,000.00
5.3 Ultrasound Machine unit 1.00 2,400,000.00
5.4 ECG Machine unit 4.00 100,000.00

6 Additional
6.1 Defibrillator (ER/Ward) unit 2.00 200,000.00
6.2 Electrocautery Machine unit 1.00 600,000.00

Page 115 of 133


PROJECT : COMPLETION OF PANDI DISTRICT HOSPITAL
LOCATION : BRGY. BUNSURAN 1ST, PANDI, BULACAN

APPROVED BUDGET FOR THE CONTRACT

ITEM
DESCRIPTION UNIT QUANTITY UNIT COST
NO.
6.3 Infusion Pumps unit 2.00 50,000.00
6.4 Bio Refrigerator unit 1.00 100,000.00
6.5 Blood Refrigerator unit 1.00 200,000.00

Sub-Total B
SUB-TOTAL X - Furnitures and Fixtures

GRAND TOTAL (ITEMS I - X)

SAY PhP

Prepared & Submitted by: Checked & Reviewed by:

WILHELMINO M. SY-ALVARADO RAMON S. PARAGAS


Provincial Governor Manager, Region III-A

Recommending Approval: Approved by:

ROMUEL P. ALIMBOYAO MARCELINO P. ESCALADA


Department Manager, General Manager
NCL-Central Luzon

Page 116 of 133


ET FOR THE CONTRACT

TOTAL COST

24,803.00
4,564.00
42,000.00

71,367.00

13,755.40
20,633.10
78,403.50
80,054.10
1,304,011.92
50,760.00
14,531.00

1,562,149.02

52,500.00

52,500.00

21,585.92
140,927.36
258,088.80

420,602.08

234,032.61
210,000.00

444,032.61

615,279.00
89,135.00

Page 117 of 133


ET FOR THE CONTRACT

TOTAL COST
46,112.00
183,744.00
169,900.00
10,730.00
13,768.00

32,934.00
43,894.00
180,264.00
90,398.00
124,839.00
55,709.00
39,744.00
32,934.00
10,298.00
16,233.00

Page 118 of 133


ET FOR THE CONTRACT

TOTAL COST
1,177,979.84
2,652,152.00
52,501.00

5,638,547.84

1,422,020.00
791,630.00
729,947.00
137,621.00
487,271.00

3,568,489.00

42,808.00
10,524.00
186,930.00
795,474.00
157,365.00
572,620.00
117,766.00

1,883,487.00

3,298,044.00
2,347,734.00

5,645,778.00

19,286,952.55

35,000.00
2,100,000.00
50,000.00
20,000.00
25,000.00
600,000.00

Page 119 of 133


ET FOR THE CONTRACT

TOTAL COST
2,830,000.00

15,000.00
15,000.00
50,000.00
12,000.00
50,000.00
40,000.00
510,000.00
80,000.00
20,000.00
20,000.00
250,000.00

Page 120 of 133


ET FOR THE CONTRACT

TOTAL COST
28,000.00
2,500.00
90,000.00

60,000.00
60,000.00
35,000.00
60,000.00
30,000.00
50,000.00
30,000.00

1,500,000.00
150,000.00
600,000.00
150,000.00
150,000.00
100,000.00
150,000.00
30,000.00
20,000.00
10,000.00
750,000.00
400,000.00
1,200,000.00
700,000.00

60,000.00
60,000.00
20,000.00
14,000.00
120,000.00
30,000.00

22,500.00
22,500.00
75,000.00
150,000.00
1,625,000.00
21,000.00

45,000.00
45,000.00
Page 121 of 133
ET FOR THE CONTRACT

TOTAL COST
10,500.00
45,000.00

1,400,000.00

1,000,000.00
1,500,000.00
2,400,000.00
400,000.00

400,000.00
600,000.00

Page 122 of 133


ET FOR THE CONTRACT

TOTAL COST
100,000.00
100,000.00
200,000.00

17,883,000.00
20,713,000.00

39,999,952.55

40,000,000.00

Checked & Reviewed by:

RAMON S. PARAGAS
Manager, Region III-A

Approved by:

MARCELINO P. ESCALADA JR.


General Manager

Page 123 of 133


OFFICE OF THE PRESIDENT
NATIONAL HOUSING AUTHORITY

PROJECT : TWO - STOREY WARDS FACILITY BUILDING


LOCATION : 15 C DE JESUS STREET, POBLACION, STA. MARIA, BULACAN
MARK-UPS
DIRECT UNIT ESTIMATED
ITEM NO. DESCRIPTION QUANTITY UNIT OCM PROFIT
COST DIRECT COST
(%) (%)
I GENERAL REQUIREMENTS
A Mobilization and Demobilization 1.00 lot 9,737.99 9,737.99 0% 0%
B Informatory Signs 1.00 lot 4,347.00 4,347.00 0% 0%
C Safety and Health 1.00 lot 40,000.00 40,000.00 0% 0%
sub-total ₱54,084.99
II DEMOLITION/REMOVAL
A Demolition of Multipurpose Chapel and Dormitory facility 1.00 lot 50,000.00 50,000.00 0% 0%
sub-total ₱50,000.00
III SITE WORKS
A Clearing and Grubbing 557.80 sq.m. 81.75 45,597.36 0% 0%
B Excavation 557.80 cu.m 51.08 28,492.42 0% 0%
C Back filling and Compaction 557.80 cu.m 44.38 24,755.16 0% 0%
D Batter board installation 137.55 l.m. 41.59 5,721.25 0% 0%
E Soil Poisoning 11.81 cu.m 4,500.00 53,145.00 0% 0%
F Disposal 557.80 cu.m 51.08 28,492.42 0% 0%
G General cleaning and Lot leveling 557.80 l.m. 81.75 45,597.36 0% 0%
sub-total ₱231,800.99
IV CONCRETING WORKS
A Portland Cement 3187.17 bag 205 653,369.85 0% 0%
B Sand 177.065 cu.m. 700 123,945.50 0% 0%
C Gravel (3/4) 354.13 cu.m. 700 247,891.00 0% 0%
D ᴓ 10 mm RSB 23685.83 kgs 35 829,004.05 0% 0%
E ᴓ 12 mm RSB 94.88 kgs 35 3,320.80 0% 0%
F ᴓ 16 mm RSB 19769.49 kgs 35 691,932.15 0% 0%
Page 124 of 133
MARK-UPS
DIRECT UNIT ESTIMATED
ITEM NO. DESCRIPTION QUANTITY UNIT OCM PROFIT
COST DIRECT COST
(%) (%)
G ᴓ 20 mm RSB 1311.68 kgs 35 45,908.80 0% 0%
H ᴓ 25 mm RSB 1235.49 kgs 35 43,242.15 0% 0%
I G.I. Wire 599.26581 kgs 60 35,955.95 0% 0%
J Shutterings 2809.08 sq.m. 194.62 546,703.15 0% 0%
K PCC 11.81 cu.m. 662 7,818.22 0% 0%
0L Excavation 315 cu.m. 209 65,835.00 0% 0%
M Backfiling 238.77 cu.m. 238.77 57,011.11 0% 0%
sub-total ₱3,351,937.73
V MASONRY WORKS
A CHB Walls #4, Incl. Plastering 112.62 sq.m. 527.00 59,350.11 0% 0%
B CHB Walls #5, Incl. Plastering 760.02 sq.m. 535.00 406,610.70 0% 0%
C CHB Walls #6, Incl. Plastering 421.71 sq.m. 536.00 226,037.37 0% 0%
sub-total ₱691,998.18
VI ARCHITECTURAL WORKS
A Doors

1 D-1 2.10m x 1.40m Double Swing Door - Flush Type Door 7.00 set 3,316.19 23,213.33 0% 0%

2 D-2 2.10m x 0.60m PVC Type Door 26.00 set 1,615.44 42,001.44 0% 0%
3 D-3 2.10m x 1.30m Double Swing Door - Flush Type Door 7.00 set 3,137.69 21,963.83 0% 0%
4 D-4 2.10m x 0.80m Metal Door 5.00 set 12,158.99 60,794.95 0% 0%
5 D-5 2.10m x 1.60m Double Swing Door - Flush Type Door 4.00 set 4,025.07 16,100.28 0% 0%
6 D-6 2.10m x 0.80m Flush Type Door 5.00 set 2,050.04 10,250.20 0% 0%
B Windows
1 W-1 1.20m x 1.40m Steel Casement Window 40.00 set 3,297.52 131,900.80 0% 0%
2 W-2 1.20m x1.40m Fixed Glass Window 4.00 set 1,125.22 4,500.88 0% 0%
3 W-3 1.00m x 1.80m Steel Awning Window 1.00 set 4,910.07 4,910.07 0% 0%
4 W-4 0.60m x 0.60m Steel Awning Window 43.00 set 891.21 38,322.03 0% 0%
C Painting Works 4,991.44 sq.m. 224.40 1,120,079.14 0% 0%
Page 125 of 133
MARK-UPS
DIRECT UNIT ESTIMATED
ITEM NO. DESCRIPTION QUANTITY UNIT OCM PROFIT
COST DIRECT COST
(%) (%)
D Tileworks and Finishes 1.00 lot 1,411,714.72 1,411,714.72 0% 0%
E Stainless Steel Railings 1.00 lot 25,000.00 25,000.00 0% 0%
sub-total ₱2,910,751.67

Page 126 of 133


MARK-UPS
DIRECT UNIT ESTIMATED
ITEM NO. DESCRIPTION QUANTITY UNIT OCM PROFIT
COST DIRECT COST
(%) (%)
VII ELECTRICAL WORKS
A Roughing-In and Wiring 1.00 lot 1,354,304.38 1,354,304.38 0% 0%
B Electrical Fixtures, Outlets, Switches and Accessories 1.00 lot 1,055,506.27 1,055,506.27 0% 0%
C Panel Board and Circuit Breaker 1.00 lot 695,188.00 695,188.00 0% 0%
D Overhead Service Entrance and Accessories 1.00 lot 131,067.51 131,067.51 0% 0%
E Site Development 1.00 lot 464,067.60 464,067.60 0% 0%
sub-total ₱3,700,133.76
VIII PLUMBING WORKS
A Cold Water Line 1.00 lot 40,769.30 40,769.30 0% 0%
B Drainage Line 1.00 lot 10,023.00 10,023.00 0% 0%
C Sewer Line 1.00 lot 178,028.50 178,028.50 0% 0%
D Plumbing Fixtures and Accessories 1.00 lot 757,594.50 757,594.50 0% 0%
E Cistern Tank 1.00 lot 149,871.61 149,871.61 0% 0%
F Overhead Tank 1.00 lot 545,352.72 545,352.72 0% 0%
G Pump House 1.00 lot 112,158.23 112,158.23 0% 0%
sub-total ₱1,793,797.86
IX FIRE PROTECTION SYSTEM
A Fire Detection and Alarm System 1.00 lot 3,140,994.21 3,140,994.21 0% 0%
B Fire Sprinkler System 1.00 lot 2,235,937.12 2,235,937.12 0% 0%
sub-total ₱5,376,931.33
TOTAL PROJECT COST ₱18,161,436.51

Submitted by: Checked & Reviewed by: Recommendi

WILHELMINO M. SY-ALVARADO RAMON S. PARAGAS ROMUEL P. A


Provincial Governor Manager, Region III-A Department M
Page 127 of 133
THE PRESIDENT
OUSING AUTHORITY

TOTAL MARK-UP
TOTAL
VAT (5%) TOTAL COST UNIT COST TOTAL ABC
(%) AMOUNT INDIRECT

0% 0.00 486.90 486.90 10,224.89 10,225.00 10,225.00


0% 0.00 217.35 217.35 4,564.35 4,564.00 4,564.00
0% 0.00 2,000.00 2,000.00 42,000.00 42,000.00 42,000.00
₱56,789.24 ₱68,146.80

0% 0.00 2,500.00 2,500.00 52,500.00 52,500.00 52,500.00


₱52,500.00 ₱63,000.00

0% 0.00 2,279.87 2,279.87 47,877.23 86.00 47,970.80


0% 0.00 1,424.62 1,424.62 29,917.05 54.00 30,121.20
0% 0.00 1,237.76 1,237.76 25,992.92 47.00 26,216.60
0% 0.00 286.06 286.06 6,007.32 44.00 6,052.20
0% 0.00 2,657.25 2,657.25 55,802.25 4,725.00 55,802.25
0% 0.00 1,424.62 1,424.62 29,917.05 54.00 30,121.20
0% 0.00 2,279.87 2,279.87 47,877.23 86.00 47,970.80
₱243,391.04 ₱293,106.06

0% 0.00 32,668.49 32,668.49 686,038.34 215.00 685,241.55


0% 0.00 6,197.28 6,197.28 130,142.78 735.00 130,142.78
0% 0.00 12,394.55 12,394.55 260,285.55 735.00 260,285.55
0% 0.00 41,450.20 41,450.20 870,454.25 37.00 876,375.71
0% 0.00 166.04 166.04 3,486.84 37.00 3,510.56
0% 0.00 34,596.61 34,596.61 726,528.76 37.00 731,471.13
Page 128 of 133
TOTAL MARK-UP
TOTAL
VAT (5%) TOTAL COST UNIT COST TOTAL ABC
(%) AMOUNT INDIRECT
0% 0.00 2,295.44 2,295.44 48,204.24 37.00 48,532.16
0% 0.00 2,162.11 2,162.11 45,404.26 37.00 45,713.13
0% 0.00 1,797.80 1,797.80 37,753.75 63.00 37,753.75
0% 0.00 27,335.16 27,335.16 574,038.31 204.00 573,052.32
0% 0.00 390.91 390.91 8,209.13 695.00 8,207.95
0% 0.00 3,291.75 3,291.75 69,126.75 219.00 68,985.00
0% 0.00 2,850.56 2,850.56 59,861.67 251.00 59,931.27
167,596.89 ₱3,519,534.62 ₱4,235,043.42

0% 0.00 2,967.51 2,967.51 62,317.61 553.00 62,278.20


0% 0.00 20,330.54 20,330.54 426,941.24 562.00 427,131.24
0% 0.00 11,301.87 11,301.87 237,339.24 563.00 237,423.59
₱726,598.09 ₱726,833.02

0% 0.00 1,160.67 1,160.67 24,374.00 3,482.00 24,374.00

0% 0.00 2,100.07 2,100.07 44,101.51 1,696.00 44,096.00


0% 0.00 1,098.19 1,098.19 23,062.02 3,295.00 23,065.00
0% 0.00 3,039.75 3,039.75 63,834.70 12,767.00 63,835.00
0% 0.00 805.01 805.01 16,905.29 4,226.00 16,904.00
0% 0.00 512.51 512.51 10,762.71 2,153.00 10,765.00

0% 0.00 6,595.04 6,595.04 138,495.84 3,462.00 138,480.00


0% 0.00 225.04 225.04 4,725.92 1,181.00 4,724.00
0% 0.00 245.50 245.50 5,155.57 5,156.00 5,156.00
0% 0.00 1,916.10 1,916.10 40,238.13 936.00 40,248.00
0% 0.00 56,003.96 56,003.96 1,176,083.09 236.00 1,177,979.84
Page 129 of 133
TOTAL MARK-UP
TOTAL
VAT (5%) TOTAL COST UNIT COST TOTAL ABC
(%) AMOUNT INDIRECT
0% 0.00 70,585.74 70,585.74 1,482,300.46 1,482,300.00 1,482,300.00
0% 1.00 1,250.00 1,251.00 26,251.00 26,251.00 26,251.00
₱3,056,290.25 ₱3,669,813.41

Page 130 of 133


TOTAL MARK-UP
TOTAL
VAT (5%) TOTAL COST UNIT COST TOTAL ABC
(%) AMOUNT INDIRECT

0% 0.00 67,715.22 67,715.22 1,422,019.60 1,422,020.00 1,422,020.00


0% 0.00 52,775.31 52,775.31 1,108,281.58 1,108,282.00 1,108,282.00
0% 0.00 34,759.40 34,759.40 729,947.40 729,947.00 729,947.00
0% 0.00 6,553.38 6,553.38 137,620.89 137,621.00 137,621.00
0% 0.00 23,203.38 23,203.38 487,270.98 487,271.00 487,271.00
₱3,885,140.45 ₱4,662,169.20

0% 0.00 2,038.47 2,038.47 42,807.77 42,808.00 42,808.00


0% 0.00 501.15 501.15 10,524.15 10,524.00 10,524.00
0% 0.00 8,901.43 8,901.43 186,929.93 186,930.00 186,930.00
0% 0.00 37,879.73 37,879.73 795,474.23 795,474.00 795,474.00
0% 0.00 7,493.58 7,493.58 157,365.19 157,365.00 157,365.00
0% 0.00 27,267.64 27,267.64 572,620.36 572,620.00 572,620.00
0% 0.00 5,607.91 5,607.91 117,766.14 117,766.00 117,766.00
₱1,883,487.75 ₱2,260,184.40

0% 0.00 157,049.71 157,049.71 3,298,043.92 3,298,044.00 3,298,044.00


0% 0.00 111,796.86 111,796.86 2,347,733.98 2,347,734.00 2,347,734.00
₱5,645,777.90 ₱6,774,933.60
₱19,069,509.34 ₱22,753,229.91

Recommending Approval: Approved by:

ROMUEL P. ALIMBOYAO MARCELINO P. ESCALADA JR.


Department Manager, NCL-Central Luzon General Manager
Page 131 of 133
ITEM NO. ITEM/ DESCRIPTION
1 GENERAL REQUIREMENTS
2 DEMOLITION/REMOVAL
3 SITE WORKS
4 CONCRETING WORKS
5 MASONRY WORKS
6 ARCHITECTURAL WORKS
7 ELECTRICAL WORKS
8 PLUMBING WORKS
9 FIRE PROTECTION SYSTEM

TOTAL DIRECT COST


CONTIGENCY (CONT.)
CONTRACTORS OVERHEAD & PROFIT (O&P)
Evat
Wtax
SUB TOTAL (P)
68,146.80
63,000.00
293,106.06
4,235,043.42
726,833.02
3,669,813.41
4,662,169.20
2,260,184.40
6,774,933.60

22,753,229.91
568,830.75
1,865,764.85
3,022,539.06
503,756.51
28,714,121.08

Вам также может понравиться