Вы находитесь на странице: 1из 15

Appendix “ A ”

H
Likelihood Descriptors
Consequence

Catastrophic Major Moderate Minor Negligible


(5) (4) (3) (2) (1)
Almost Certain 25 20 15 10 5
(5) VERY HIGH VERY HIGH HIGH HIGH MEDIUM
Likelihood

Highly Likely 20 16 12 8 4
(4) VERY HIGH VERY HIGH HIGH MEDIUM LOW
Likely 15 12 9 6 3
(3) HIGH HIGH MEDIUM MEDIUM LOW
Unlikely 10 8 6 4 2
(2) HIGH MEDIUM MEDIUM LOW LOW
Highly Unlikely 5 4 3 2 1
(1) MEDIUM LOW LOW LOW LOW

Risk Level Management Action


VERY HIGH Risks with a rating above 16 are totally unacceptable and the work will not be undertaken until the risk has been
reduced.

HIGH Where the risk rating is between 10 and 15, immediate action must be taken, including a stoppage of work if necessary,
to reduce the risk level.

MEDIUM If the rating is between 5 and 9, the risk is acceptable provided that everything reasonable practicable has been done
to reduce the risk.

LOW With a rating of 4 or less then the risk is acceptable, provided that the assessment is reviewed at regular intervals and
further reduced if possible.
Consequence Health and Safety Environmental Security

Catastrophic Fatality Major environmental damage with potential for litigation, Rioting in labour camp or worksite causing fatality or
media coverage or community outcry multiple major injury
Theft or vandalism causing company loss over QAR
1M
Major Injury or illness with potential for permanent disability Significant environmental damage with one or more Theft or vandalism causing company loss of over QAR
or long-term hospitalization (over 3 months) irreversible impact on the local environment or ecosystem 500,000 but less that QAR 1M
Physical assault causing major injury
Moderate Injury or illness requiring medical treatment but no Environmental impact requiring reasonable mitigation Theft or vandalism causing company loss of over QAR
potential for LTI measures but no adverse effect on the local environment 100,000 but less than QAR 500,000
or ecosystem Physical assault causing injury that would require
medical treatment
Minor Injury or illness requiring first aid Environmental impact requiring minor or no mitigation Theft or vandalism causing company loss of over QAR
measure and no adverse effect on the local environment 10, 000 but less than QAR 100,000
or ecosystem Assault without any injury
Workplace harassment and bullying
Negligible Injury or illness requiring no first aid or medical Negligible or untraceable impact requiring no mitigation Theft or vandalism causing company loss below QAR
treatment (e.g. muscle cramp, minor scratches, 10,000
abrasion, headache etc) Violation of site access and other security rules.

Likelihood Description
Almost Certain Often occurred within the company in similar situation or condition
Highly Likely Often occurred within the industry and sometimes occurred within the company in similar situation or condition

Likely Sometimes occurred within the industry in similar situation or condition


Unlikely Sometimes occurred in other industries but rarely occurred in the construction industry in similar situation or condition
Highly Unlikely Never occurred in the industry or within the company in similar situation or condition

Consequence
The nature and severity of the harm that can be caused by a hazard
Likelihood
The possibility or probability of the hazard to cause the harm
Risk
A combination of the consequence (C) and likelihood (L) (R = C x L)
Existing Control
Any risk control measure already in place at the time of hazard identification and risk
Assessment
Residual Risk
The level of risk exposure after the implementation of risk control measures
(R’ = C’ x L’)
Health and Safety Risk Assessment Worksheet

DESIGN AND BUILD OF LIGHT INDUSTRIAL & LOGISTICS UNITS LOCATED AT UM ALHOUL SPECIAL ECONOMIC
Project Title
ZONE

Client MANATEQ

Location UM ALHOUL QEZ-3 ECONOMIC ZONES

Scope INSTALLATION OF HVAC SUPPLY,RETURN & EXHAUST DUCTS

R/A Date 11th January 2020 Review date 10th July 2020

R/A Number EZ03-CW03-QBEC-MEC-RAS-000016-Rev02

R/A Undertaken by Aravindghosh K. ( Dy. HSE Manager )

Risk Assessment Residual Risk Level


S.I Who might be
Activity Task Hazards Identified Proposed Control Measures Action by
harmed and how?
No. Conseq Likeliho Risk Conseq Likelih Risk
uence od Score uence ood Score
1 Survey and  Working near edge Personal injury, collision,
Heat stress, eye irritation,
3 3 9  Carry out pre task inspection to assess area of 3 1 3 Project Manager
Setting out  Work in open area survey works. Site Engineer /
respiratory diseases.
under direct sun, in Supervisor
condition of High
Operatives and  Put adequate caution signs at required
(before the
other site distance and barricades the edges
heat Index personnel / activity)
 Working near edges  Site safety inspection prior to start. Eliminate
Workers
and floor openings or highlight all potential trips/ slip/ fall hazards.
  Tool box awareness on trip/ slip/ fall hazards
 No activity at the time of heavy wind, sand
storm. Use adequate eyes and respiratory
protection
 Implement heat stress prevention plan.
 Ensure availability of adequate potable
drinking water and resting areas.
 Stop work when heat index exceeds safe
exposure limit
 Follow summer working hours as per directive
of ministry.
 Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, hand gloves, Hi-Vi vest,etc
 Proper fall protection system should be in
place if working near edges.

 Trained and experienced person shall perform


the task.
 Appropriate Documents (RAMS) to be
obtained from concern parties in order to start
the activities.
 Project HSE induction should be attended all
the crew.
Hand Injury,  Maintain good housekeeping standards. Use
 Pinch point Cuts, safe handling techniques for the transportation
 Crush injury Crushing injury, of tools and equipment to the work place.
Personal injury Project Manager
 Lack of knowledge
Mobilization of Property Damage  TBT and JHA to be conducted prior to start of Site Engineer /
 Absent mindedness
2 men and Operatives and 3 4 12 the work 3 1 3 Supervisor
 Slip, Trip, Fall
materials other site  Proper supervision required. (before the
 Manual Handling
personnel / activity)
 Collision with
Workers
 Personnels should keep safe distance from
pedestrians vehicles equipments
 Banksman shall be provided for equipment
operation
 Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, hand gloves, Hi-Vi vest,etc
 All operative should undergo health screening
before deployed to work.

3 Use of Plant and  Unintentional Major injuries,


Fatality
5 4 20  A Plan must be produced that considers 5 1 5 Project Manager
Equipment release of load weight of load, radius of lift, overhead Site Engineer /
Impact
 Load or equipment Crushing clearance, ground conditions, positioning of Supervisor
striking person or Pinch point crane, and lifting equipment required. (before the
other vehicle Property Damage activity)
 Unplanned Operatives and  All plant and equipment should have valid
other site documents and operator should have valid
movement of load
personnel / documents ( License , 3rd party certification ,
 Fire
 Damage to Workers  Banks man should be available to guide and
equipment control the traffic.
 Equipment must be checked by operators
before use and secured afterwards
 Planned maintenance program for equipment
and plant
 All equipment shall be provided with fire
extinguishers
 Banksman should be trained personal.
 Vehicle movement should be allowed on
designated area.

 Palletized loads will not exceed two pallets in


height.
 No materials shall be stacked more than 1.5m
high if manually handled
 All materials shall be stored in clean and dry
storage area.
 Loads will be lifted in the correct manner,
avoiding the use of makeshift arrangements
 Manual handling training should be done to all
operative on correct lifting technique and TILE
Minor injuries
 rules.
Storage of  Falling Materials Material Damage  For hazardous materials, COSHH Project Manager
materials on site  Weather conditions Operatives and assessments and MSDS will be required Site Engineer /
4 ( Ducts, tread  Manual Handling other site 3 3 9 before delivery to site 3 1 3 Supervisor
rods, angles  Pinch points personnel /  Duct sealant and adhesive shall be stored on (before the
sealant )  Fall from height Workers a close container as per MSDS specification. activity)
 Chemicals shall be stored in a drip tray with
110% capacity.
 Verbal instructions and training will be given to
operatives as necessary to ensure good
housekeeping standards are maintained on
site. Stability and stacking instructions will be
given as needed to site operatives by
management.
 Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, appropriate hand gloves, Hi-Vi vest,etc

5 Installation of  Dust from cutting Lungs disease/Health


Effects
3 4 12  The duct should be assembled with respect to 3 1 3 Project Manager
( Horizontal and and drilling the assembly series to avoid additional Site Engineer /
Skin irritation
vertical ducts)  Ejected particles Eye Irritation manual handling. Supervisor
 Inhalation Personal Injury (before the
 Contact with skin Crush Injury  Ducts should be joint on ground to avoid
activity)
Cut injury working at height risk
 Contact with Eyes
 Entanglement Operatives and  If the weight of joint duct is heavy use
 Sharpe edges other site mechanical lifting jacks .
personnel /
 Manual handling  Before fixing the duct make sure that the
Working at height Workers
 fastening screw is secured properly.
 Electrical power
 All Power tools should be inspected and
colour coded as per the coding system
 Only competent and trained personal should
use the power tool
 Hand tools should be of suitable standard
 Homemade hand tools should not be used.
 Manual handling training needs to be done.
 Pinch point should be avoided.
 Sharp edges should be grinded off with file
 Proper working platform should be erected by
trained scaffolders.
 Scaffold should be inspected and tagged
before using.
tools  If mobile scaffold is used as working platform,
 Chemical handling harness should be hooked to the fastener
section of AC
 All operative working on scaffold should wear
full body harness.
 Working at height procedure should be
followed.
 Power tools should be inspected and colour
coded .
 All power tools should be used by competent
operative
 Operative should strictly not allowed to be on
the duct for any activity.
 No welding is allowed in the duct installed
area.

6 Use of  Improper setting of Slip, Trips,


Personal injury,
4 3 12  Carry out pre-task inspection to assess area of 4 1 4 Project Manager
Mechanical Mechanical jacks works. Site Engineer /
Hand injury
Jacks  Improper Supervisor
Arrangement
Collision, ,  Put adequate caution signs at required
(before the
distance and barricades.
 Adjacent Activities Operatives and activity)
 Damaged Jacks other site  Site safety inspection prior to start. Eliminate
 Unauthorized use personnel / or highlight all potential trips/ slip/ fall hazards.
Workers  TBT and JHA to be conducted prior to start of
the work
 All Jacks shall hold valid third Party certificate
 All personnel erecting and dismantling Jacks
shall be competent.
 Avoid any existing edge of potential fall.
 All Jacks shall be checked prior to use and
any damaged Jacks shall be removed from
use.
 Barricade around existing pits / trench if any.
 Tool box awareness on trip/ slip/ fall hazards
 Proper and timely maintenance of Jacks.
 Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, hand gloves, Hi-Vi vest,etc
 MSDS AND COSHH assessment shall be
followed
 Manufacturer instruction shall be followed
 COSHH material shall be stored in COSHH
room
 Required quantity of material only shall be
used or kept in the work area
 Waste material shall be dumped in hazardous
waste storage area.
 Put adequate caution signs at required
distance and barricades
Damage to organs
Infertifility
 Chemicals containers shall be labelled and
Lungs disease/Health provided with driptray.
 Inhalation
 Skin contact
Effects,  Eating and drinking should be prohibited in Project Manager
Soil containation
areas where this material is handled and Site Engineer /
Duct Sealant  Eye contact Operatives and
7 3 4 12 stored 3 1 3 Supervisor
Application  Ingestion other site
 Operatives should wash hands and face (before the
 Environment personnel /
before eating and drinking. activity)
impacts Workers
 Adequate eyewash and hand wash facilities
shall be provided on site
 TBT and JHA shall be conducted before start
of the task.
 Proper supervision required.
 Trained and experienced person shall perform
the task
 Medical Surveillance / medical fitness of
workers shall be checked periodically.
 Use appropriate PPEs(such as safety helmet,
dust mask, safety goggles, safety shoe, rubber
hand gloves, hi-vi vest)

8 Working at  Fall of person Major injuries,


Fracture
4 4 16  Work at height permit shall be obtained from 4 1 4 Project
height  Fall of material from the HSE department before performing the Manager
task.
 Working area shall be barricaded and
signage’s shall be posted
 Ensure that the operatives are medically and
physically fit for the task
 Work at height procedure shall be followed
 Proper tagging of the scaffolds shall be done.
 A competent scaffolding supervisor /
scaffolding inspector with valid third party
certification shall ensure inspection and
tagging of the scaffolds
 Three point contact shall be maintained while
accessing and descending from ladder
 Ensure that the foot of the ladder is free from
slip
 Ladders should be set, as near as possible, at
an angle of 75° (a ratio of 1 unit of length out
height to 4 units of length up) As per QCS section 11
Property Damage
 Slippage of foot Operatives and part 1.3.2.8)
 Physically unfit other site  Ladders must extend at least 1 meter Site Engineer /
(scaffolding,  Slippery foot while personnel / (approximately 5 rungs) above the landing Supervisor
ladders) climbing Workers place, unless an alternative, secure handhold (before the
 Absent mindedness is available. As per QCS section 11 part activity)
 Heavy wind 1.3.2.8)
 Ladders must extend at least 1 meter
(approximately 5 rungs) above the landing
place, unless an alternative, secure handhold
is available. (As per QCS section 11 part
1.3.2.8)
 TBT and JHA to be conducted prior to start of
work.
 Proper supervision required
 Trained and experienced person shall perform
the task
 Full body harness shall worn while performing
the task with 100% tie off
 Monitor wind speed and suspend activity
during heavy wind.
 Use adequate necessary PPEs such as safety
helmet, dust musk, safety goggles, safety
shoes, leather hand gloves, Hi-Vi vest,etc

9 Use of Hand  Pinch point Hand Injury,,cuts , 3 4 12  Use right tools for the task. 3 1 3 Project Manager
 Check the tools before performing the task.
 Don’t use damaged tools
 Follow the manufacture instruction.
 Defective tools should be identified and
 Crush injury crushing injury remove from the site.
 Cut injury
Operatives and  TBT and JHA to be conducted prior to start of Site Engineer /
 Lack of knowledge
other site the work Supervisor
tools  Absent mindedness
 Damaged hand tools
personnel /  Keep the cutting tools sharp. (before the
Workers activity)
 Flying particles  Don’t keep sharp hand tools on pockets.
 Proper supervision required.
 Trained and experienced person shall perform
the task.
 Use adequate PPEs. (Eye and Ear Protection)

 Only 110 V power tools to be used


 TBT and JHA to be conducted
 Cable joints shall be with industrial sockets
 Trailing cables should not be in path
 Electric tools should be earthed and double
insulated
Hand Injury,,cuts ,  Equipment should be repaired by competent
Use of Power  Electricity Entanglement, crushing person
injury, Electrocution Project Manager
tools  Moving parts  In case 220 V power tool needs to be used Site Engineer /
( Drilling  Sharp surfaces Operatives and
10 4 4 16 RCD of 30mA should be fixed in the system to 4 1 4 Supervisor
Machine,  Entanglement other site
avoid any electrical shock . (before the
Grinding  Damaged power personnel /
Machine) tools Workers  The power tools should be inspected quarterly activity)
and provided colour coding tag after
inspection.
 Equipment should be visually inspected before
use and checked for quarterly inspection
colour coding tag.
 Use of task specific / speed rated discs
 Use adequate PPEs. (Eye Protection)

11 Housekeeping  Slips, Trips and Falls Major minor injuries, back 3 3 9  Clear the area after the completion of the task. 3 1 3 Project Manager
 Minor / Major Injuries injury, Burns, Site Engineer /
 Fire Operatives and  Don’t leave any material on the work area Supervisor
other site after performing the task.
(before the
personnel /  Supervisor should ensure that every material activity)
Workers is kept in its designated place.
 Access / Egress should be always kept clear
and free from materials.
 Proper cable / hose management should be
ensured.
 Supervisor shall ensure all the time that the
work area shall be clear.
 Use appropriate PPEs
 Proper manual handling technique should be
followed
 Sharp edges should be covered
 Manual handling hazard awareness training
should be provided.
 Use mechanical aids for transporting the
material to work place
 Fall of material Back pain
Personal injury  If more than 20 kg use two person or
 Damage of material (strain/Sprain) mechanical means such as wheel barrow or Project Manager
Manual handling  Back pain herniated disc
other mechanical means (As per QCS section Site Engineer /
 Muscular disorder Operatives and
12 3 3 9 11 part 1.2.7.8) 3 1 3 Supervisor
 Hernia other site
 Cut injury personnel /  Don’t carry heavy material too long (before the
activity)
 Fracture Workers  TILE ( task, load , individual , environment )
shall be considered before manual handling of
any material
 Don’t carry overload
 Don’t twist the body
 Use adequate necessary PPEs such as safety
helmet , dust musk , safety goggles, safety
shoe , cotton gloves, hi-vi vest)

16  Before entering to the site attend the safety 4 1 4


 Unaware of the site
General induction training from the HSE office
safety rules
instructions :  Unaware of the Physical Injuries
 Sign in and out at the security gate
 Site induction emergency escape Major and Minor Injuries  Emergency escape route shall clear Project Manager
 Emergency routes and assembly Operatives and  Emergency contact number shall be clear Site Engineer /
13 point other site 4 4 Supervisor
response
 unaware of the personnel /  Report if found any incident , accident and
(before the
 Site traffic emergency Workers near miss
activity)
management procedures  Use mandatory PPEs while entering to the site
 Site welfare  unaware f the site ( safety helmet, safety shoe, handgloves,HI-
traffic plan VI vest)
 All work shall be stopped during the extreme
weather condition
 Regular interval to be provided for workers in
hot session
heat stroke,  Heat stress Index/ emergency plan to be
heat exhaustion, monitored and implemented during working in
heat cramps, extreme weather condition
heat rashes
Work Activities
Illness  Drink water more frequently and add ORS for
with exposure to skin burns lost minerals and salt.
high Project
vomiting,
14
temperature/ head ache, 4 4 16
 Supervisor need to Keep a sharp eye on heat
4 1 4 Manager/
collapse, related illness on fellow workers. Construction
high humidity  High heat stress
conditions (Heat Index
blood pressure, irritation  Proper meal and take proper rest during break Manager
Operatives and time. Summer factor awareness training shall
Stress) other site be conducted.
personnel /
Workers  First Aid responders should be available, and
an emergency response plan should be in
place.
 Trainings related to heat stress to make
awareness among workers.
 Provide adequate medical attention to anyone
reporting symptoms or uneasiness.
Collision, Major  Reversing of vehicles shall be done only with
injuries, fracture. banksman
Supervisor, Foreman
and site workers
 All vehicles shall be equipped with reverse
alarms and working head and tail lamps.
 Unauthorized area shall be barricaded with
appropriate signages
15 Night shift work  Adequate signages shall be provided
regarding speed limits, junction, sharp bends,
Vehicle movement vehicle crossing, etc.
 Separate, clearly marked pedestrian access
shall be provided for pedestrians Project Manager /
4 4 16  Traffic routes wide enough shall be provided 4 1 4 Site Engineer/
Supervision Team
for safety of the personnel where separation is
not practicable
 Pedestrian walkway provided with barriers at
site entrances and exits to prevent pedestrians
walking in front of vehicles
 Personnel shall use pedestrian access while
on site.
 Use adequate necessary PPEs such as safety
helmet, safety goggles, safety shoes, cotton
gloves, hi-vi vest)

Low visibility Supervisor, 4 4 16 To check the illumination level as per 4 1 4 Project Manager /
Foreman and site requirement by Lux meter from competent Site Engineer/
workers person Supervision Team
To provide the lighting meeting the QCS- 14,
Section 11, 1.5.3
Recommended levels for site lighting which
are given below
 Security 5/30Lux
 Movement and handling of peoples,
Machine and vehicles, Handling of
materials 20 LUX
 Store & stockyard 30 Lux
 Site entrance General access, vehicle and
pedestrian 30 LUX
 General work area 50LUX
 Reinforcing concreting, shattering erecting
100 LUX
 Fine craft work all work with Power tools
Painting Electrical 300 LUX
 Site hunts Rest room, Toilet 150 LUX
 Site office 500 LUX
 Emergency Lighting 5 to 70 LUX

Man Machine interface Supervisor, The Object of area lighting should be to


Foreman and site produce and overall level illumination,
workers Sufficient for workmen and vehicle to move
safely. Every part of the area should receive Project Manager /
4 4 16 light from the least two directions to avoid 4 1 4 Site Engineer/
dangerous, dense shadows Supervision Team
Pedestrian walkways should be kept clear
and illumination. High visibility

Open excavated area Supervisor, Excavation to be barrier off with warning


/edge Foreman and site signs and lighting to be arrange. Tower light Project Manager /
workers 4 4 16 to be increased and regular maintenance to 4 1 4 Site Engineer/
be ensure Supervision Team

Workers New to Night Supervisor, Site induction/ TBT to be performed regarding


works Foreman and site lighting and night works HSE
workers 4 4 16 4 1 4 Represent
ative/ Site
Supervisor
Pinch points Supervisor, All moving part of machinery need to be
Project
Foreman and site covered as per required guard Manager /
workers Site
3 4 12 3 1 3
Engineer/
Supervision
Team
Protruding nails Supervisor,  Unwanted projected objects must be Project
Foreman and site removed from the site or separate from the Manager /
workers movement area. Site
3 4 12 3 1 3
 De nailing to be done for all used and Engineer/
Supervision
waste plywood materials Team
Movement of works Supervisor,  Work area to be fenced off and secured
man outside the work Foreman and site
area in dark workers
 Continues supervision to be done by security
personal and supervisor Project
 Used emergency contact number in case of an Manager /
4 4 16 emergency (55219535) 4 1 4 Site
Engineer/
 Appropriate facilities should be provided Supervision
together with break periods to allow the worker Team
to rest, refresh themselves and regain
alertness.

15
Environment. Contamination n of soil Supervisor. 4 3 12  Always keep workplace and premise neat 4 1 4
that will harm Foreman and clean and tidy
environment if the workers  Arrange all materials in a proper manner
spillage is in big amounts
 Materials should be stored in a proper manner
 Inspection prior to commence of the activity to
be conduct by respective supervisor
 Notifying supervisor if there are dangerous
animals sighting.
 Evacuate the area immediately without Project
causing Panic Manager /
Site
 Never work alone Engineer/
 Ensure there is enough supervision to Supervision
facilitate communication between workers and Team
promote appropriate behavior and rational
decision making
 Adequate lighting should be install in the area
of work
 Avoid threatening the animals or insects as
these may aggravate the situation

Name: Amal Sarath Reviewed by: Name: Aravindghosh Kambaran Approved by: Name: Mohammed Ghallab
Prepared By: HSE Engineer Dy. HSE Manager Project Manager
Sign/ Date: Sign/ Date: Sign/ Date:

Fire and Emergency Evacuation Plan (FEEP)


 During the activity all staff must be aware of the FEEP for that activity. In the event of an injury during this task the HSE Officer shall ensure
that first aid treatment is available for the activity. The casualty shall be treated at the scene in the first instance. Should further treatment be required the
closest vehicle to the scene of the incident shall be deemed the FEEP vehicle to take the injured to the QBEC clinic for further treatment.
 In the unlikely event that somebody is struck by debris or the trencher itself the casualty shall not be moved at all unless there is an immediate threat
to life by the location they are in or by the nature of the injuries sustained. QBEC emergency no: 55219535 ambulance shall immediately be called to the
scene; in the meantime the Primary First Aider 70525485 shall ensure the stability of the casualty.
 In the event of a fire during the activity then the fire extinguishers at the scene should be used to tackle the blaze if possible, all un required staff
should be evacuated from the location to a pre agreed location at the start of the activity.
 Civil Defense fire service should be called immediately to assist. All engines and electrical sources should be switched off and isolated.
 During in any FEEP all other activities in the area shall immediately be stopped until advised otherwise by the Senior Staff at the scene.
 Once the FEEP has been activated and the immediate threat is controlled the Project Management must be informed of the incident or accident.
 The scene should be sealed, either by staff or barriers if possible to ensure that his area remains the same for photographs and other investigation
steps that may be required. Depending on the nature and severity of the incident the Police may be required to attend the scene and to carry out their own
investigation.
 For investigation purposes all people who were involved in the activity are to identify themselves to the HSE Officer to assist in the investigation.
 All staff involved in the activity must be aware of this FEEP prior to the start of work.

Вам также может понравиться