Вы находитесь на странице: 1из 297

To : TARLAC SATE UNIVERSITY Date: 01 October 2019

Re : INVITATION TO BID NO. INFRA 024-08-2019A

DETAILED ESTIMATES

Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

(1) (2) (3) (4) (5) (6) (7)


1.0 GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization 1.00 lot 50,000.00 50,000.00 5,000.00 5,000.00 55,000.00 0 0
1.2 Temporary Facilities 1.00 lot 100,000.00 100,000.00 10,000.00 10,000.00 110,000.00 0 0
1.2.1 Temporary Barracks & Storage

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

1.2.2 Temporary Fence/Board-up


1.2.3 Temporary Water and Power Consumption
1.3 Permits and Licenses 1.00 lot 150,000.00 150,000.00 15,000.00 15,000.00 165,000.00 0 0
1.3.1 Building Permit Processing, fire clearance, occupancy
1.3.2 Licenses and certifications - operations
1.4 Safety and Health 1.00 lot 50,000.00 50,000.00 5,000.00 5,000.00 55,000.00 0 0
1.4.1 Pre-cautionary Signages, Safety nets & Scaffolds
1.4.2 Personal Protective Equipment for personnel

Sub-Total 350,000.00 35,000.00 385,000.00 0 0

SUNSHADING, STAIRCASE, ELEVATOR, PUMP RM,


2.0
CISTERN
2.1 EARTHWORKS
2.1.1 Site Clearing (including cutting & bases) 1,120.00 m² 0 0 150.00 168,000.00 168,000.00 1,680.00 10,080.00
2.1.2 Demolition (selected windows and plantboxes) see dwgs 160.00 m ²
0 0 100.00 16,000.00 16,000.00 160.00 960.00
2.1.3 Layout and Staking 1,120.00 m² 0 0 100.00 112,000.00 112,000.00 1,120.00 6,720.00
2.1.4 Excavation 575.00 m³ 0 0 450.00 258,750.00 258,750.00 2,587.50 15,525.00
2.1.5 Backfill / Compaction 412.00 m³ 650.00 267,800.00 195.00 80,340.00 348,140.00 3,481.40 20,888.40
2.1.6 Gravelbase Coarse 20.00 m³ 900.00 18,000.00 270.00 5,400.00 23,400.00 234.00 1,404.00
2.1.7 Soil Poisoning 280.00 m ²
100.00 28,000.00 30.00 8,400.00 36,400.00 364.00 2,184.00
Sub-Total 313,800.00 648,890.00 962,690.00 9,626.90 57,761.40

2.2 CONCRETING
2.2.1 Footing 100.00 m³ 4,500.00 450,000.00 900.00 90,000.00 540,000.00 5,400.00 32,400.00
2.2.2 Shear Wall of Elevator Shaft & Cistern Tank 47.00 m³ 4,500.00 211,500.00 900.00 42,300.00 253,800.00 2,538.00 15,228.00
2.2.3 Pedestal, Encasement & Pull Box (Service Entrance) 20.00 m³ 4,500.00 90,000.00 900.00 18,000.00 108,000.00 1,080.00 6,480.00
2.2.4 Columns 86.00 m³ 4,500.00 387,000.00 900.00 77,400.00 464,400.00 4,644.00 27,864.00
2.2.5 Beams 148.00 m³ 4,500.00 666,000.00 900.00 133,200.00 799,200.00 7,992.00 47,952.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2.2.6 Roof Beams 58.00 m³ 4,500.00 261,000.00 900.00 52,200.00 313,200.00 3,132.00 18,792.00
2.2.7 Suspended Slab. Ledges, Staircase 157.00 m³ 4,500.00 706,500.00 900.00 141,300.00 847,800.00 8,478.00 50,868.00
2.2.8 Slab on fill 14.00 m³ 4,200.00 58,800.00 840.00 11,760.00 70,560.00 705.60 4,233.60
2.2.9 Concrete Trellis (Sunshading) 10.00 m³ 4,500.00 45,000.00 900.00 9,000.00 54,000.00 540.00 3,240.00
2.2.10 Vertical Fins (Sunshading) 155.00 m³ 4,500.00 697,500.00 900.00 139,500.00 837,000.00 8,370.00 50,220.00
2.2.11 Stiffener Columns 19.00 m³ 4,500.00 85,500.00 900.00 17,100.00 102,600.00 1,026.00 6,156.00

Sub-Total ### 731,760.00 ### 43,905.60 263,433.60

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg 44.00 265,980.00 13.20 79,794.00 345,774.00 3,457.74 20,746.44
HIDE 20mm Dia Rebar @6m 408 pcs 598.00 244,006.43 - -
2.3.1.2 16mm Dia Rebar 615.00 kg 44.00 27,060.00 13.20 8,118.00 35,178.00 351.78 2,110.68
HIDE 16mm Dia Rebar @6m 65 pcs 390.00 25,296.68
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg 44.00 211,420.00 13.20 63,426.00 274,846.00 2,748.46 16,490.76
HIDE 16mm Dia Rebar @6m 507 pcs 390.00 197,643.16 - -
2.3.2.2 12mm Dia Rebar 1,780.00 kg 42.00 74,760.00 12.60 22,428.00 97,188.00 971.88 5,831.28
HIDE 12mm Dia Rebar @6mm 334 pcs 225.00 75,093.75
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg 44.00 55,440.00 13.20 16,632.00 72,072.00 720.72 4,324.32
HIDE 16mm Dia Rebar @6m 133 pcs 390.00 51,827.34 - -
2.3.3.2 10mm Dia Rebar 920.00 kg 42.00 38,640.00 12.60 11,592.00 50,232.00 502.32 3,013.92
HIDE 10mm Dia Rebar @6m 248 pcs 160.00 39,744.00 - -
2.3.3.3 12mm dia rebar 19.00 kg 42.00 798.00 12.60 239.40 1,037.40 10.37 62.24
HIDE 12mm dia rebar @6m 4 pcs 225.00 801.56
2.3.4 Beam Rebars

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2.3.4.1 20mm Dia Rebar 20,404.00 kg 44.00 897,776.00 13.20 269,332.80 1,167,108.80 11,671.09 70,026.53
HIDE 20mm Dia Rebar @6m 1,377 pcs 600.00 826,362.00 - -
2.3.4.2 10mm Dia Rebar 7,230.00 kg 42.00 303,660.00 12.60 91,098.00 394,758.00 3,947.58 23,685.48
HIDE 10mm Dia Rebar @6m 1,952 pcs 160.00 312,336.00
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg 44.00 526,372.00 13.20 157,911.60 684,283.60 6,842.84 41,057.02
HIDE 20mm Dia Rebar @6m 808 pcs 600.00 484,501.50 - -
2.3.5.2 10mm Dia Rebar 2,930.00 kg 42.00 123,060.00 12.60 36,918.00 159,978.00 1,599.78 9,598.68
HIDE 10mm Dia Rebar @6m 791 pcs 160.00 126,576.00
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m 190.00 5,700.00 57.00 1,710.00 7,410.00 74.10 444.60
HIDE 2 x 6 x 1.5mm C Channel Rafter (GI) 6.00 pcs 950.00 5,700.00 - -
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m 131.25 26,250.00 39.38 7,875.00 34,125.00 341.25 2,047.50
HIDE 2 x 4 x 1.5mm C Purlins (GI) 35.00 pcs 750.00 26,250.00 - -
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot 4,020.00 4,020.00 1,206.00 1,206.00 5,226.00 52.26 313.56
Welding Rods 10.00 kgs 150.00 1,500.00
Cutting Disk 3.00 pcs 95.00 285.00
Grinding Disk 3.00 pcs 95.00 285.00
Red oxide primer 4.00 gals 400.00 1,600.00
Paint thinner 1.00 gal 250.00 250.00
Baby roller 2.00 pcs 50.00 100.00
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg 42.00 512,946.00 12.60 153,883.80 666,829.80 6,668.30 40,009.79
HIDE 12mm Dia Rebar @6mm 2,290 pcs 225.00 515,235.94 - -
2.3.7.2 10mm dia rebar 2,834.00 kg 42.00 119,028.00 12.60 35,708.40 154,736.40 1,547.36 9,284.18
HIDE 10mm Dia Rebar @6m 765 pcs 160.00 122,428.80
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg 42.00 63,840.00 12.60 19,152.00 82,992.00 829.92 4,979.52

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

HIDE 10mm Dia Rebar @6m 410 pcs 160.00 65,664.00


2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg 42.00 60,900.00 12.60 18,270.00 79,170.00 791.70 4,750.20
HIDE 10mm Dia Rebar @6m 392 pcs 160.00 62,640.00
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m² 550.00 103,950.00 165.00 31,185.00 135,135.00 1,351.35 8,108.10
2.3.10.2 12mm dia Rebar 9,720.00 kg 42.00 408,240.00 12.60 122,472.00 530,712.00 5,307.12 31,842.72
HIDE 12mm Dia Rebar @6mm 1,823 pcs 225.00 410,062.50
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg 42.00 63,000.00 12.60 18,900.00 81,900.00 819.00 4,914.00
HIDE 12mm Dia Rebar @6mm 281 pcs 225.00 63,281.25 - -
2.3.11.2 10mm Dia Rebar 1,150.00 kg 42.00 48,300.00 12.60 14,490.00 62,790.00 627.90 3,767.40
HIDE 10mm Dia Rebar @6m 311 pcs 160.00 49,680.00 - -
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg 70.00 301,000.00 21.00 90,300.00 391,300.00 3,913.00 23,478.00
HIDE #16 GI Tie Wire @25kg per roll 154.00 rolls 1,700.00 261,800.00

Sub-Total ### ### ### 55,147.82 330,886.92

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m² 211.08 15,198.00 63.33 4,559.40 19,757.40 197.57 1,185.44
12mm formply 13.00 pcs 690.00 8,970.00
2"x2"x10' good lumber 106.56 bd.ft. 50.00 5,328.00
CWN 6.00 kgs 80.00 480.00
GI tie wire #16 6.00 kgs 70.00 420.00
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m ²
353.27 69,946.50 105.98 20,983.95 90,930.45 909.30 5,455.83
12mm formply 49.00 pcs 690.00 33,810.00
2"x2"x10' good lumber 269.73 bd.ft. 50.00 13,486.50
2"x3"x10' good lumber 405.00 bd.ft. 50.00 20,250.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

CWN 16.00 kgs 80.00 1,280.00


GI tie wire #16 16.00 kgs 70.00 1,120.00
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m² 386.04 5,559.00 115.81 1,667.70 7,226.70 72.27 433.60
12mm formply 4.00 pcs 690.00 2,760.00
2"x2"x10' good lumber 19.98 bd.ft. 50.00 999.00
2"x3"x10' good lumber 30.00 bd.ft. 50.00 1,500.00
CWN 2.00 kgs 80.00 160.00
GI tie wire #16 2.00 kgs 70.00 140.00
2.4.4 Columns 61.92 m ²
365.29 22,619.00 109.59 6,785.70 29,404.70 294.05 1,764.28
12mm formply 16.00 pcs 690.00 11,040.00
2"x2"x10' good lumber 86.58 bd.ft. 50.00 4,329.00
2"x3"x10' good lumber 130.00 bd.ft. 50.00 6,500.00
CWN 5.00 kgs 80.00 400.00
GI tie wire #16 5.00 kgs 70.00 350.00
2.4.5 Beams 106.56 m ²
318.63 33,953.00 95.59 10,185.90 44,138.90 441.39 2,648.33
12mm formply 26.00 pcs 690.00 17,940.00
2"x2"x10' good lumber 73.26 bd.ft. 50.00 3,663.00
2"x3"x10' good lumber 220.00 bd.ft. 50.00 11,000.00
CWN 9.00 kgs 80.00 720.00
GI tie wire #16 9.00 kgs 70.00 630.00
2.4.6 Roof Beams 41.76 m² 342.60 14,307.00 102.78 4,292.10 18,599.10 185.99 1,115.95
12mm formply 9.00 pcs 690.00 6,210.00
2"x2"x10' good lumber 59.94 bd.ft. 50.00 2,997.00
2"x3"x10' good lumber 90.00 bd.ft. 50.00 4,500.00
CWN 4.00 kgs 80.00 320.00
GI tie wire #16 4.00 kgs 70.00 280.00
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m² 498.06 56,300.50 149.42 16,890.15 73,190.65 731.91 4,391.44
12mm formply 49.00 pcs 690.00 33,810.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2"x2"x10' good lumber 189.81 bd.ft. 50.00 9,490.50


2"x3"x10' good lumber 230.00 bd.ft. 50.00 11,500.00
CWN 10.00 kgs 80.00 800.00
GI tie wire #16 10.00 kgs 70.00 700.00
2.4.8 Slab on fill 10.08 m² 408.73 4,120.00 122.62 1,236.00 5,356.00 53.56 321.36
12mm formply 3.00 pcs 690.00 2,070.00
2"x2"x10' good lumber 15.00 bd.ft. 50.00 750.00
2"x3"x10' good lumber 23.00 bd.ft. 50.00 1,150.00
CWN 1.00 kgs 80.00 80.00
GI tie wire #16 1.00 kgs 70.00 70.00
2.4.9 Concrete Trellis (Sunshading) 72.00 m² 368.13 26,505.00 110.44 7,951.50 34,456.50 344.57 2,067.39
12mm formply 19.00 pcs 690.00 13,110.00
2"x2"x10' good lumber 99.90 bd.ft. 50.00 4,995.00
2"x3"x10' good lumber 150.00 bd.ft. 50.00 7,500.00
CWN 6.00 kgs 80.00 480.00
GI tie wire #16 6.00 kgs 70.00 420.00
2.4.10 Vertical Fins (Sunshading) 486.00 m ²
351.02 170,593.50 105.30 51,178.05 221,771.55 2,217.72 13,306.29
12mm formply 119.00 pcs 690.00 82,110.00
2"x2"x10' good lumber 662.67 bd.ft. 50.00 33,133.50
2"x3"x10' good lumber 990.00 bd.ft. 50.00 49,500.00
CWN 39.00 kgs 80.00 3,120.00
GI tie wire #16 39.00 kgs 70.00 2,730.00
2.4.11 Stiffener Columns 120.00 m ²
355.07 42,608.50 106.52 12,782.55 55,391.05 553.91 3,323.46
12mm formply 30.00 pcs 690.00 20,700.00
2"x2"x10' good lumber 163.17 bd.ft. 50.00 8,158.50
2"x3"x10' good lumber 245.00 bd.ft. 50.00 12,250.00
CWN 10.00 kgs 80.00 800.00
GI tie wire #16 10.00 kgs 70.00 700.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Sub-Total 461,710.00 138,513.00 600,223.00 6,002.23 36,013.38

2.5 MASONRY & WATERPROOFING


2.5.1 Integral Waterproofing (decks, cistern & elevator pit) 1,600.00 kg 301.30 482,080.00 90.39 144,624.00 626,704.00 6,267.04 37,602.24
Admixture 1,600.00 kg 280.00 448,000.00 -
HIDE
Cement (40 kg) 142.00 bags 240.00 34,080.00 -

2.5.2 Cementitious waterproofing lining (decks, plantbox & cistern) 1,100.00 m² 436.55 480,200.00 130.96 144,060.00 624,260.00 6,242.60 37,455.60

DAVCO K-11Superflex 90.00 sets 4,000.00 360,000.00 -


HIDE Bituminous primer 37.00 tins 3,200.00 118,400.00 -
Heavy duty paint roller 12.00 pcs 150.00 1,800.00 -
2.5.3 6" thk CHB parapet Walls 1,144.00 pc 15.00 17,160.00 4.50 5,148.00 22,308.00 223.08 1,338.48
2.5.4 mortar and Plastering
2.5.4.1 Cement 210.00 bag 240.00 50,400.00 72.00 15,120.00 65,520.00 655.20 3,931.20
2.5.4.2 Sand 20.00 m³ 650.00 13,000.00 195.00 3,900.00 16,900.00 169.00 1,014.00

2.5.5 10mm dia horiz and Vertical rebars for CHB and Deco Blocks 1,820.00 kg 42.00 76,440.00 12.60 22,932.00 99,372.00 993.72 5,962.32

HIDE 10mm dia rebars @6m 491 pcs 160.00 78,624.00 - -


2.5.6 #16 Gi Tie Wire 182.00 kg 70.00 12,740.00 21.00 3,822.00 16,562.00 165.62 993.72
HIDE #16 Gi Tie Wire @25kg per roll 8.00 rolls 1,700.00 13,600.00 - -

2.5.7 Heavy Duty Cement-based Adhesive for Decorative Blocks 450.00 bag 500.00 225,000.00 150.00 67,500.00 292,500.00 2,925.00 17,550.00

2.5.8 Decorative Blocks (Sunshading) 250 x 250 x 88 9,300.00 pc 40.00 372,000.00 12.00 111,600.00 483,600.00 4,836.00 29,016.00

Sub-Total ### 518,706.00 ### 22,477.26 134,863.56

2.6 EQUIPMENT

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Machine roomless elevator Equipment 1500 kg, 3 stops (3


front openings) 1m/s, steel hoist Silver brushed car Walls, w/
gray Black Granite Car Floor, Silver brushed skirting, mirror on
2.6.1 1.00 set 2,700,000.00 2,700,000.00 540,000.00 540,000.00 3,240,000.00 32,400.00 194,400.00
walls, LED direct light 7.6kW, 31A-43A, 3P, 230V 60Hz incl
reqd electrical outlets, breakers and exhaust fans, incl I-Beams
or any strucl steel reqd for installation

2.6.2 Electric Water Heater (complete with telephone Shower) 6.00 set 7,000.00 42,000.00 2,100.00 12,600.00 54,600.00 546.00 3,276.00
2.6.3 2HP Electric Submersible Pump (at Elevator pit) 1.00 set 48,000.00 48,000.00 14,400.00 14,400.00 62,400.00 624.00 3,744.00
Booster Pump (1HP) (40PSI) (65% efficiency) w/ foot valve w/
2.6.4 1.00 set 36,700.00 36,700.00 11,010.00 11,010.00 47,710.00 477.10 2,862.60
Bladder Tank (30gal) w/ complete accessories

Sub-Total ### 578,010.00 ### 34,047.10 204,282.60

2.7 FINISHING WORKS


Engineer weatherproof wood planks (25mm thk)- 150mm x
2.7.1 880.00 m² 3,272.73 2,880,000.00 981.82 864,000.00 3,744,000.00 37,440.00 224,640.00
900mm
HIDE Wood Planks Weatherproof 150 x 3660mm 1,600.00 pcs 1,800.00 2,880,000.00 - -
2.7.1.1 Cement Glue for Floor Plank 880.00 m² 21.82 19,200.00 6.55 5,760.00 24,960.00 249.60 1,497.60
Cement Glue 22.00 gals 850.00 18,700.00 - -
HIDE
Comb trowel 5.00 pcs 100.00 500.00 - -
2.7.2 Non-Skid Rubberized Painted Finish (Hallways) 232.00 m² 209.48 48,600.00 62.84 14,580.00 63,180.00 631.80 3,790.80
Non-skid Rubberized Paint 24.00 gal 1,450.00 34,800.00 - -
HIDE Epoxy Primer 11.00 gal 1,200.00 13,200.00 - -
Paint roller #7 4.00 pcs 150.00 600.00 - -
Built-up Acrylic LED Lighted Signage with 9mm thk Acrylic
2.7.3 1.00 set 65,000.00 65,000.00 19,500.00 19,500.00 84,500.00 845.00 5,070.00
built-up letters, LED lighting, mounting and installation

Elevator & Pump Room Roof, Rib Type G.I. (0.5mm), prepainted
2.7.4 120.00 m² 738.33 88,600.00 221.50 26,580.00 115,180.00 1,151.80 6,910.80
Longspan incl flushings; w/ insulation

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Rib type GI(0.5mm), pre painted long span 120.00 ln.m 600.00 72,000.00 - -
HIDE Flashings 28.00 ln.m 450.00 12,600.00 - -
Insulation (1m x 50m)-double sided 1.00 roll 4,000.00 4,000.00 - -
2.7.5 Roof Works Miscellaneous (Tuxscrews, Silicon, blind rivets) 1.00 lot 8,800.00 8,800.00 2,640.00 2,640.00 11,440.00 114.40 686.40
Texscrews 400.00 pcs 2.00 800.00 - -
HIDE Silicon 50.00 gals 150.00 7,500.00 - -
Blind Rivets 1,000.00 pcs 0.50 500.00 - -

2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m² 554.43 38,810.00 166.33 11,643.00 50,453.00 504.53 3,027.18

4.5mm thk Ficem board 34.00 pcs 400.00 13,600.00


Wall Angle 33.00 pcs 55.00 1,815.00
Carrying Channel 24.00 pcs 120.00 2,880.00
Double Furring 36.00 pcs 130.00 4,680.00
W-clip 148.00 pcs 3.50 518.00
Suspension clip 119.00 pcs 5.50 654.50
Threaded Rod 3/8" 39.00 pcs 130.00 5,070.00
Expansion Shield 3/8" 119.00 pcs 8.00 952.00
Nut and Washer 3/8" 119.00 pcs 4.50 535.50
Blind Rivets 1/8x1/2 5.00 boxes 350.00 1,750.00
Blind Rivets 1/8x3/4 5.00 boxes 350.00 1,750.00
Drill Bit 1/8 5.00 pcs 95.00 475.00
Drive Pin and Gas 118.00 sets 35.00 4,130.00
2.7.7 Balcony & Stair Handrails & railing (painted Finish)
2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m² 295.57 18,030.00 88.67 5,409.00 23,439.00 234.39 1,406.34
2 1/2" x 2 1/2" x 3/16" Angle bar 11.00 pcs 1,350.00 14,850.00 -
Grinding disc 2.00 pc 95.00 190.00 -
HIDE Cutting disc 2.00 pc 95.00 190.00 -
Welding Rod 2.00 kg 150.00 300.00 -
Painting Works 1.00 lot 2,500.00 2,500.00 -

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2.7.7.2 12mm Square Bar 28.00 m 78.00 2,184.00 23.40 655.20 2,839.20 28.39 170.35
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m 238.64 3,730.00 71.59 1,119.00 4,849.00 48.49 290.94
75 x 75 x 1.2mm tubular (GI) 3.00 pcs 1,130.00 3,390.00 - -
Grinding disc 1.00 pc 95.00 95.00 - -
HIDE
Cutting disc 1.00 pc 95.00 95.00 - -
Welding Rod 1.00 kg 150.00 150.00 - -
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m² 60.75 11,300.00 18.23 3,390.00 14,690.00 146.90 881.40
Rubber Type Stair Nosings(2mm thk) @3m 32.00 pcs 300.00 9,600.00
HIDE
Adhesive 2.00 gal 850.00 1,700.00
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal 550.00 159,500.00 165.00 47,850.00 207,350.00 2,073.50 12,441.00
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal 695.00 55,600.00 208.50 16,680.00 72,280.00 722.80 4,336.80
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal 810.00 3,240.00 243.00 972.00 4,212.00 42.12 252.72
Epoxy primer 4.00 gals 650.00 2,600.00 - -
Baby roller 3.00 pcs 50.00 150.00 - -
HIDE
Paint brush 3.00 pcs 80.00 240.00 - -
Paint thinner 1.00 gals 250.00 250.00 - -
2.7.9.4 Flat Latex Paint 185.00 gal 480.00 88,800.00 144.00 26,640.00 115,440.00 1,154.40 6,926.40
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot 108,580.00 108,580.00 32,574.00 32,574.00 141,154.00 1,411.54 8,469.24
Boral Compound 35.00 bags 600.00 21,000.00
Patching Compound 50.00 bags 550.00 27,500.00
Skim coat 45.00 bags 490.00 22,050.00
Mesh Tape 28.00 rolls 180.00 5,040.00
Paint Roller 23.00 pcs 50.00 1,150.00
Baby Roller 20.00 pcs 70.00 1,400.00
Sand Paper 8.00 rolls 3,500.00 28,000.00
Paint Brush 17.00 pcs 70.00 1,190.00
Rugs 25.00 kgs 50.00 1,250.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2.7.10 uPVC Clear Transparent Rib Type Roof + misc. 250.00 m² 606.20 151,550.00 181.86 45,465.00 197,015.00 1,970.15 11,820.90
uPVC Clear Transparent Rib Type Roof (1.2 x 2.4) 87.00 pcs 1,650.00 143,550.00 - -
HIDE
Accessories 1.00 lot 8,000.00 8,000.00 - -
2.7.11 Paver blocks 250.00 m² 400.00 100,000.00 120.00 30,000.00 130,000.00 1,300.00 7,800.00
HIDE Y-shaped interlocking paver blocks(16pcs/sq.m) 4,000.00 pcs 25.00 100,000.00

Sub-Total ### ### ### 50,069.81 300,418.87

TOTAL ITEM 2 ### ### ### 221,276.72 ###

3.0 GENERAL REPAIR & IMPROVEMENTS ON CAFA BUILDING


3.1 ROOFING AND EAVES SOFFIT
Replacement of delapidated roofing, (pre-painted longspan,
3.1.1 1,100.00 m 668.18 735,000.00 290.45 319,500.00 1,054,500.00 10,545.00 63,270.00
ribtype, G.I. 0.5mm thk)

Long span pre-painted White G.I rib type Roofing including


1,100.00 sq.m 650.00 715,000.00 195.00 214,500.00
accessories (0.5mm thk)
Miscellaneous and Consumables 1.00 lot 20,000.00 20,000.00 6,000.00 6,000.00
Dismantling of existing roofing 1,100.00 sq.m 0 0 90.00 99,000.00
3.1.2 Insulation (double sided aluminum) (w/ chicken wire) 1,100.00 m² 129.09 142,000.00 38.73 42,600.00 184,600.00 1,846.00 11,076.00

Double sided embossed aluminum Foil XPE Foam(9mm thk) 23.00 rolls 4,000.00 92,000.00 -
HIDE
Chicken wire mesh1.2 x 40mtrs 20.00 rolls 2,500.00 50,000.00 -
Replacement of Eaves Soffit - Spandrel (110mm wide), (pre-
3.1.3 2,000.00 m 120.00 240,000.00 36.00 72,000.00 312,000.00 3,120.00 18,720.00
painted G.I., 0.5mm thk) complete w/ misc.

Spandrel Mouldings/Edging Wall Angles, complete w/


3.1.4 450.00 m 124.00 55,800.00 37.20 16,740.00 72,540.00 725.40 4,352.40
misc./silicon
H profile 39.00 pcs 200.00 7,800.00
End moulding 185.00 pcs 200.00 37,000.00
HIDE
Carrying channel 60.00 pcs 100.00 6,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
HIDE Unit Cost Total

Accessories 1.00 lot 5,000.00 5,000.00

Sub-Total ### 450,840.00 ### 16,236.40 97,418.40

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal 550.00 118,250.00 165.00 35,475.00 153,725.00 1,537.25 9,223.50

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal 695.00 111,200.00 208.50 33,360.00 144,560.00 1,445.60 8,673.60
3.2.3 Flat Latex for Existing Ceiling 90.00 gal 480.00 43,200.00 144.00 12,960.00 56,160.00 561.60 3,369.60
3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal 600.00 6,000.00 180.00 1,800.00 7,800.00 78.00 468.00
3.2.5 Flat Latex Primer 150.00 gal 480.00 72,000.00 144.00 21,600.00 93,600.00 936.00 5,616.00
3.2.6 Metal Primer, rust Converters 5.00 gal 350.00 1,750.00 105.00 525.00 2,275.00 22.75 136.50
3.2.7 Paint Thinner 2.00 gal 300.00 600.00 90.00 180.00 780.00 7.80 46.80

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot 66,700.00 66,700.00 20,010.00 20,010.00 86,710.00 867.10 5,202.60

Boral Compound 30.00 bags 600.00 18,000.00


Patching Compound 45.00 bags 550.00 24,750.00
Paint Roller 100.00 pcs 50.00 5,000.00
Baby Roller 100.00 pcs 70.00 7,000.00
Sand Paper 500.00 pcs 15.00 7,500.00
Paint Brush 40.00 pcs 80.00 3,200.00
Rugs 25.00 kgs 50.00 1,250.00

Sub-Total 419,700.00 125,910.00 545,610.00 5,456.10 32,736.60

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m 520.00 32,240.00 156.00 9,672.00 41,912.00 419.12 2,514.72

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.3.1.2 100mm Ø 29.00 m 230.00 6,670.00 69.00 2,001.00 8,671.00 86.71 520.26
3.3.1.3 50mm Ø 29.00 m 80.00 2,320.00 24.00 696.00 3,016.00 30.16 180.96
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc 950.00 3,800.00 285.00 1,140.00 4,940.00 49.40 296.40
3.3.2.2 Wye 100 x 100 4.00 pc 145.00 580.00 43.50 174.00 754.00 7.54 45.24
3.3.2.3 Elbow 90" x 100 44.00 pc 435.00 19,140.00 130.50 5,742.00 24,882.00 248.82 1,492.92
3.3.2.4 Elbow 45" x 200 3.00 pc 715.00 2,145.00 214.50 643.50 2,788.50 27.89 167.31
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc 515.00 7,725.00 154.50 2,317.50 10,042.50 100.43 602.55
3.3.2.6 Sanitary Tee 100 x 50 25.00 pc 110.00 2,750.00 33.00 825.00 3,575.00 35.75 214.50
3.3.2.7 P-Trap 100 22.00 pc 215.00 4,730.00 64.50 1,419.00 6,149.00 61.49 368.94
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc 1,284.36 35,962.00 385.31 10,788.60 46,750.60 467.51 2,805.04
10mm dia bar 46.00 kg 42.00 1,932.00 -
HIDE
concrete catch basin 8.30 cu.m. 4,100.00 34,030.00 -
3.3.3.2 Solvent / Adhesive 20.00 qt 190.00 3,800.00 57.00 1,140.00 4,940.00 49.40 296.40
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc 1,142.86 32,000.00 342.86 9,600.00 41,600.00 416.00 2,496.00
Floor Drain 12.00 pcs 800.00 9,600.00
hide
Roof Drain, dome type 16.00 pcs 1,400.00 22,400.00
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56.00 m 130.00 7,280.00 39.00 2,184.00 9,464.00 94.64 567.84
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57.00 pc 25.00 1,425.00 7.50 427.50 1,852.50 18.53 111.15
3.3.4.2.2 25mm Tee 30.00 pc 30.00 900.00 9.00 270.00 1,170.00 11.70 70.20
3.3.4.2.3 25mm Coupling 9.00 pc 22.00 198.00 6.60 59.40 257.40 2.57 15.44
3.3.4.2.4 25mm Reducer 10.00 pc 30.00 300.00 9.00 90.00 390.00 3.90 23.40
3.3.4.2.5 25mm Gate Valve 6.00 pc 750.00 4,500.00 225.00 1,350.00 5,850.00 58.50 351.00
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4.00 set 7,500.00 30,000.00 2,250.00 9,000.00 39,000.00 390.00 2,340.00
3.3.4.5 1000L Polyethylene Water Tank 1.00 pc 13,000.00 13,000.00 3,900.00 3,900.00 16,900.00 169.00 1,014.00
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1.00 set 45,000.00 45,000.00 13,500.00 13,500.00 58,500.00 585.00 3,510.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Sub-Total 256,465.00 76,939.50 333,404.50 3,334.05 20,004.27

3.4 ELECTRICAL WORKS & FIXTURES


3.4.1 Conduits
3.4.1.1 1/2" Ø PVC 214.00 pc 75.00 16,050.00 22.50 4,815.00 20,865.00 208.65 1,251.90
3.4.1.2 3/4" Ø PVC 527.00 pc 120.00 63,240.00 36.00 18,972.00 82,212.00 822.12 4,932.72
3.4.1.3 2 1/2" Ø PVC 63.00 pc 435.00 27,405.00 130.50 8,221.50 35,626.50 356.27 2,137.59
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set 203.00 1,624.00 60.90 487.20 2,111.20 21.11 126.67
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set 165.00 660.00 49.50 198.00 858.00 8.58 51.48
3.4.1.6 3/4" Ø EMT 10.00 pc 185.00 1,850.00 55.50 555.00 2,405.00 24.05 144.30
3.4.1.7 1" Ø EMT 75.00 pc 260.00 19,500.00 78.00 5,850.00 25,350.00 253.50 1,521.00
3.4.1.8 1 1/4" Ø EMT 14.00 pc 395.00 5,530.00 118.50 1,659.00 7,189.00 71.89 431.34
3.4.1.9 1 1/2" Ø EMT 12.00 pc 445.00 5,340.00 133.50 1,602.00 6,942.00 69.42 416.52
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc 19.00 190.00 5.70 57.00 247.00 2.47 14.82
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set 25.00 50.00 7.50 15.00 65.00 0.65 3.90
3.4.1.12 1" Ø EMT Coupling 72.00 pc 30.00 2,160.00 9.00 648.00 2,808.00 28.08 168.48
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set 45.00 585.00 13.50 175.50 760.50 7.61 45.63
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc 48.00 672.00 14.40 201.60 873.60 8.74 52.42
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set 63.00 63.00 18.90 18.90 81.90 0.82 4.91
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc 58.00 174.00 17.40 52.20 226.20 2.26 13.57
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set 85.00 1,020.00 25.50 306.00 1,326.00 13.26 79.56
3.4.1.18 2 1/2" Ø RSC 29.00 pc 2,130.00 61,770.00 639.00 18,531.00 80,301.00 803.01 4,818.06
3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc 175.00 2,100.00 52.50 630.00 2,730.00 27.30 163.80
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set 125.00 250.00 37.50 75.00 325.00 3.25 19.50
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc 950.00 3,800.00 285.00 1,140.00 4,940.00 49.40 296.40
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m 28.00 203,980.00 8.40 61,194.00 265,174.00 2,651.74 15,910.44

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.4.2.2 5.5mm2 THHN Cu 483.00 m 38.00 18,354.00 11.40 5,506.20 23,860.20 238.60 1,431.61
3.4.2.3 8.0mm2 THHN Cu 118.00 m 65.00 7,670.00 19.50 2,301.00 9,971.00 99.71 598.26
3.4.2.4 14mm2 THHN Cu 106.00 m 98.00 10,388.00 29.40 3,116.40 13,504.40 135.04 810.26
3.4.2.5 22mm2 THHN Cu 39.00 m 165.00 6,435.00 49.50 1,930.50 8,365.50 83.66 501.93
3.4.2.6 30mm2 THHN Cu 12.00 m 225.00 2,700.00 67.50 810.00 3,510.00 35.10 210.60
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m 510.00 74,460.00 153.00 22,338.00 96,798.00 967.98 5,807.88
3.4.2.8 125mm2 THHN Cu 853.00 m 780.00 665,340.00 234.00 199,602.00 864,942.00 8,649.42 51,896.52
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m 28.00 26,124.00 8.40 7,837.20 33,961.20 339.61 2,037.67
3.4.3.2 5.5mm2 Cu Grounding 257.00 m 38.00 9,766.00 11.40 2,929.80 12,695.80 126.96 761.75
3.4.3.3 8.0mm2 Cu Grounding 104.00 m 65.00 6,760.00 19.50 2,028.00 8,788.00 87.88 527.28
3.4.3.4 30mm2 Cu Grounding 73.00 m 165.00 12,045.00 49.50 3,613.50 15,658.50 156.59 939.51
3.4.3.5 60mm2 Cu Grounding 5.00 m 415.00 2,075.00 124.50 622.50 2,697.50 26.98 161.85
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc 750.00 1,500.00 225.00 450.00 1,950.00 19.50 117.00
3.4.4 Others
3.4.4.1 Junction and Utility Boxes 800.00 pc 33.00 26,400.00 9.90 7,920.00 34,320.00 343.20 2,059.20
Junction Boxes w/ cover 480.00 pcs 35.00 16,800.00
HIDE
Utility Box 320.00 pcs 30.00 9,600.00
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set 12,500.00 12,500.00 3,750.00 3,750.00 16,250.00 162.50 975.00
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set 8,500.00 8,500.00 2,550.00 2,550.00 11,050.00 110.50 663.00
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P
3.4.5.3 1.00 set 12,500.00 12,500.00 3,750.00 3,750.00 16,250.00 162.50 975.00
+ 2 Spare

3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00 12,500.00 3,750.00 3,750.00 16,250.00 162.50 975.00

3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00 12,500.00 3,750.00 3,750.00 16,250.00 162.50 975.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set 12,500.00 12,500.00 3,750.00 3,750.00 16,250.00 162.50 975.00

3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set 16,750.00 16,750.00 5,025.00 5,025.00 21,775.00 217.75 1,306.50

90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.8 1.00 set 16,750.00 16,750.00 5,025.00 5,025.00 21,775.00 217.75 1,306.50
+ 2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.9 1.00 set 16,750.00 16,750.00 5,025.00 5,025.00 21,775.00 217.75 1,306.50
+ 2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-


3.4.5.10 1.00 set 19,500.00 19,500.00 5,850.00 5,850.00 25,350.00 253.50 1,521.00
40AT, 2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set 110,000.00 110,000.00 33,000.00 33,000.00 143,000.00 1,430.00 8,580.00
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P +
3.4.5.12 1.00 set 225,000.00 225,000.00 67,500.00 67,500.00 292,500.00 2,925.00 17,550.00
100AT, 3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set 115,000.00 115,000.00 34,500.00 34,500.00 149,500.00 1,495.00 8,970.00
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set 850.00 40,800.00 255.00 12,240.00 53,040.00 530.40 3,182.40
3.4.6.2 Emergency Light 24.00 set 2,000.00 48,000.00 600.00 14,400.00 62,400.00 624.00 3,744.00
3.4.6.3 Strip Light (Cove Light) 500.00 m 500.00 250,000.00 150.00 75,000.00 325,000.00 3,250.00 19,500.00
3.4.6.4 36 W Up Light Garden Light 70.00 pc 2,400.00 168,000.00 720.00 50,400.00 218,400.00 2,184.00 13,104.00

3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc 850.00 42,500.00 255.00 12,750.00 55,250.00 552.50 3,315.00

3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc 1,200.00 2,400.00 360.00 720.00 3,120.00 31.20 187.20
3.4.6.7 One Gang Switch 30.00 pc 105.00 3,150.00 31.50 945.00 4,095.00 40.95 245.70
3.4.6.8 Two gang Switch 30.00 pc 165.00 4,950.00 49.50 1,485.00 6,435.00 64.35 386.10

Sub-Total ### 731,574.00 ### 31,701.54 190,209.24

3.5 FIRE ALARM WORKS & FIXTURES

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes


3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m 25.00 8,550.00 7.50 2,565.00 11,115.00 111.15 666.90
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc 8.00 1,200.00 2.40 360.00 1,560.00 15.60 93.60
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc 3.50 525.00 1.05 157.50 682.50 6.83 40.95
3.5.1.4 15mm Ø St. Connector 100.00 pc 18.00 1,800.00 5.40 540.00 2,340.00 23.40 140.40
3.5.1.5 Utility Box 100.00 pc 30.00 3,000.00 9.00 900.00 3,900.00 39.00 234.00
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc 65.00 16,250.00 19.50 4,875.00 21,125.00 211.25 1,267.50
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc 90.00 6,300.00 27.00 1,890.00 8,190.00 81.90 491.40
3.5.1.8 Fire Alarm Pull Box 25.00 pc 870.00 21,750.00 261.00 6,525.00 28,275.00 282.75 1,696.50
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m 55.00 37,620.00 16.50 11,286.00 48,906.00 489.06 2,934.36
3.5.3 Smoke Detectors 141.00 set 870.00 122,670.00 261.00 36,801.00 159,471.00 1,594.71 9,568.26
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set 18,500.00 18,500.00 5,550.00 5,550.00 24,050.00 240.50 1,443.00
3.5.5 Monitoring Switches (6 zones) 1.00 set 17,500.00 17,500.00 5,250.00 5,250.00 22,750.00 227.50 1,365.00
3.5.6 Fire Alarm Check Valve 1.00 set 65,000.00 65,000.00 19,500.00 19,500.00 84,500.00 845.00 5,070.00
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot 18,900.00 18,900.00 5,670.00 5,670.00 24,570.00 245.70 1,474.20
Accessories, Solvents)
Hangers 220.00 pcs 25.00 5,500.00
Wiring Accessories 1.00 lot 10,000.00 10,000.00
Electrical tape 50.00 rolls 30.00 1,500.00
Solvents @400cc 10.00 pcs 190.00 1,900.00

Sub-Total 339,565.00 101,869.50 441,434.50 4,414.35 26,486.07

3.6 FIRE PROTECTION/SPRINKLER SYSTEM


3.6.1 BI Pipe and Fittings
3.6.1.1 150mm Ø S40 BI Pipes 29.00 m 1,830.00 53,070.00 549.00 15,921.00 68,991.00 689.91 4,139.46
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m 963.00 61,632.00 288.90 18,489.60 80,121.60 801.22 4,807.30

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.6.1.3 80mm Ø S40 BI Pipes 60.00 m 963.00 57,780.00 288.90 17,334.00 75,114.00 751.14 4,506.84
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m 640.00 42,880.00 192.00 12,864.00 55,744.00 557.44 3,344.64
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m 505.00 16,160.00 151.50 4,848.00 21,008.00 210.08 1,260.48
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m 305.00 8,540.00 91.50 2,562.00 11,102.00 111.02 666.12
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m 226.00 1,808.00 67.80 542.40 2,350.40 23.50 141.02
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m 195.00 1,560.00 58.50 468.00 2,028.00 20.28 121.68
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m 145.00 47,125.00 43.50 14,137.50 61,262.50 612.63 3,675.75
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc 820.00 2,460.00 246.00 738.00 3,198.00 31.98 191.88
3.6.2.2 BI Tee welded type 100mm 3.00 pc 435.00 1,305.00 130.50 391.50 1,696.50 16.97 101.79
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc 165.00 165.00 49.50 49.50 214.50 2.15 12.87
3.6.2.4 BI Tee threaded type 50mm 3.00 pc 220.00 660.00 66.00 198.00 858.00 8.58 51.48
3.6.2.5 BI Tee threaded type 25mm 50.00 pc 75.00 3,750.00 22.50 1,125.00 4,875.00 48.75 292.50
3.6.2.6 BI Elbow welded type 150mm 2.00 pc 335.00 670.00 100.50 201.00 871.00 8.71 52.26
3.6.2.7 BI Elbow welded type 100mm 9.00 pc 325.00 2,925.00 97.50 877.50 3,802.50 38.03 228.15
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc 115.00 2,990.00 34.50 897.00 3,887.00 38.87 233.22
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc 85.00 10,030.00 25.50 3,009.00 13,039.00 130.39 782.34
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc 60.00 18,480.00 18.00 5,544.00 24,024.00 240.24 1,441.44
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc 810.00 1,620.00 243.00 486.00 2,106.00 21.06 126.36
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc 435.00 435.00 130.50 130.50 565.50 5.66 33.93
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc 435.00 4,350.00 130.50 1,305.00 5,655.00 56.55 339.30
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc 435.00 1,305.00 130.50 391.50 1,696.50 16.97 101.79
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc 435.00 15,660.00 130.50 4,698.00 20,358.00 203.58 1,221.48
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc 385.00 1,155.00 115.50 346.50 1,501.50 15.02 90.09
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc 385.00 6,160.00 115.50 1,848.00 8,008.00 80.08 480.48
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc 385.00 1,155.00 115.50 346.50 1,501.50 15.02 90.09
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc 385.00 9,240.00 115.50 2,772.00 12,012.00 120.12 720.72
3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc 285.00 570.00 85.50 171.00 741.00 7.41 44.46

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc 330.00 330.00 99.00 99.00 429.00 4.29 25.74
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc 350.00 5,250.00 105.00 1,575.00 6,825.00 68.25 409.50
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc 245.00 4,410.00 73.50 1,323.00 5,733.00 57.33 343.98
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc 175.00 1,050.00 52.50 315.00 1,365.00 13.65 81.90
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc 125.00 375.00 37.50 112.50 487.50 4.88 29.25
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc 1,330.00 1,330.00 399.00 399.00 1,729.00 17.29 103.74
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc 490.00 2,450.00 147.00 735.00 3,185.00 31.85 191.10
3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc 550.00 550.00 165.00 165.00 715.00 7.15 42.90
3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc 185.00 555.00 55.50 166.50 721.50 7.22 43.29
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc 185.00 555.00 55.50 166.50 721.50 7.22 43.29
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc 135.00 135.00 40.50 40.50 175.50 1.76 10.53
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc 115.00 345.00 34.50 103.50 448.50 4.49 26.91
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc 95.00 285.00 28.50 85.50 370.50 3.71 22.23
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc 120.00 240.00 36.00 72.00 312.00 3.12 18.72
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc 80.00 9,200.00 24.00 2,760.00 11,960.00 119.60 717.60
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc 55.00 8,140.00 16.50 2,442.00 10,582.00 105.82 634.92
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc 75.00 1,125.00 22.50 337.50 1,462.50 14.63 87.75
3.6.2.38 BI Union Patente 25mm 3.00 pc 115.00 345.00 34.50 103.50 448.50 4.49 26.91
3.6.2.39 Slip on flange 150mm 36.00 pc 550.00 19,800.00 165.00 5,940.00 25,740.00 257.40 1,544.40
3.6.2.40 Slip on flange 100mm 84.00 pc 350.00 29,400.00 105.00 8,820.00 38,220.00 382.20 2,293.20
3.6.2.41 Slip on flange 80mm 12.00 pc 235.00 2,820.00 70.50 846.00 3,666.00 36.66 219.96
3.6.2.42 Slip on flange 75mm 6.00 pc 235.00 1,410.00 70.50 423.00 1,833.00 18.33 109.98
3.6.2.43 Slip on flange 65mm 18.00 pc 195.00 3,510.00 58.50 1,053.00 4,563.00 45.63 273.78
3.6.2.44 Rubber Gasket 150mm 18.00 pc 145.00 2,610.00 43.50 783.00 3,393.00 33.93 203.58
3.6.2.45 Rubber Gasket 100mm 42.00 pc 115.00 4,830.00 34.50 1,449.00 6,279.00 62.79 376.74
3.6.2.46 Rubber Gasket 80mm 6.00 pc 90.00 540.00 27.00 162.00 702.00 7.02 42.12
3.6.2.47 Rubber Gasket 75mm 3.00 pc 90.00 270.00 27.00 81.00 351.00 3.51 21.06
3.6.2.48 Rubber Gasket 65mm 9.00 pc 85.00 765.00 25.50 229.50 994.50 9.95 59.67

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

3.6.3 Valve, Sprinkler, FHC and Accessories

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc 220.00 20,680.00 66.00 6,204.00 26,884.00 268.84 1,613.04
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc 345.00 16,560.00 103.50 4,968.00 21,528.00 215.28 1,291.68
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc 15,700.00 15,700.00 4,710.00 4,710.00 20,410.00 204.10 1,224.60
3.6.3.4 Fire Hose Valve 65mm 7.00 pc 7,350.00 51,450.00 2,205.00 15,435.00 66,885.00 668.85 4,013.10
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc 1,050.00 3,150.00 315.00 945.00 4,095.00 40.95 245.70
3.6.3.6 Inspector Test valve 25mm 7.00 pc 750.00 5,250.00 225.00 1,575.00 6,825.00 68.25 409.50
3.6.3.7 Sight Glass 25mm 7.00 pc 790.00 5,530.00 237.00 1,659.00 7,189.00 71.89 431.34
3.6.3.8 Water Flow Switch 7.00 pc 4,720.00 33,040.00 1,416.00 9,912.00 42,952.00 429.52 2,577.12
3.6.3.9 Supervisory Switch 7.00 pc 6,500.00 45,500.00 1,950.00 13,650.00 59,150.00 591.50 3,549.00

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc 15,000.00 210,000.00 4,500.00 63,000.00 273,000.00 2,730.00 16,380.00
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc 7,300.00 21,900.00 2,190.00 6,570.00 28,470.00 284.70 1,708.20
3.6.4 Hanger and Brackets 1.00 lot 99,775.00 99,775.00 29,932.50 29,932.50 129,707.50 1,297.08 7,782.45
3.6.4.1 Bolt and Nut and Washer 5/8 x 4" 150.00 pc 35.00 5,250.00
3.6.4.2 Angle Bar 2" x 2" x 1/4" 25.00 pc 1,280.00 32,000.00
3.6.4.3 Full threaded 3/8 374.00 pc 115.00 43,010.00
3.6.4.4 Loop Hanger 75mm 70.00 pc 70.00 4,900.00
3.6.4.5 Loop Hanger 25mm 152.00 pc 25.00 3,800.00
3.6.4.6 U-Bolt 75mm x 1/2 70.00 pc 95.00 6,650.00
3.6.4.7 U-Bolt 150mm x 5/8 17.00 pc 245.00 4,165.00
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot 9,676.00 9,676.00 2,902.80 2,902.80 12,578.80 125.79 754.73
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe) 1.00 lot 7,876.00 7,876.00
2" DIA 8.00 pcs 245.00 1,960.00
HIDE

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

HIDE 4" DIA 4.00 pcs 714.00 2,856.00


6" DIA 2.00 pcs 1,530.00 3,060.00
3.6.5.1 Clear Silicon Sealant 15.00 tubes 120.00 1,800.00
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m² 62.33 7,480.00 18.70 2,244.00 9,724.00 97.24 583.44
Red Oxide Primer 8.00 gals 400.00 3,200.00
QDE international Red 6.00 gals 650.00 3,900.00
HIDE
Paint Brush 4.00 pcs 70.00 280.00
Paint Roller 2.00 pcs 50.00 100.00
3.6.7 Fire Fighting Equipment & Installation

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set 2,050,000.00 2,050,000.00 307,500.00 307,500.00 2,357,500.00 23,575.00 141,450.00
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set 85,000.00 85,000.00 12,750.00 12,750.00 97,750.00 977.50 5,865.00
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot 36,396.00 36,396.00 10,918.80 10,918.80 47,314.80 473.15 2,838.89
3.6.8.1 teflon tape 5.00 pc 12.00 60.00
3.6.8.2 red Oxide 2.00 gal 390.00 780.00
3.6.8.3 grip anchor 3/8 12.00 pc 8.00 96.00
3.6.8.4 expansion Shield 3/8 x 2 20.00 pc 15.00 300.00
3.6.8.5 grinding stone 4" 8.00 pc 95.00 760.00
3.6.8.6 cut off disks 14" 12.00 pc 450.00 5,400.00
3.6.8.7 weldingrRod 6011 4.00 box 2,400.00 9,600.00
3.6.8.8 welding rod 6013 4.00 box 2,100.00 8,400.00
3.6.8.9 Abaca sacks 10.00 pc 100.00 1,000.00
3.6.8.10 Flinknote 1.00 lot 10,000.00 10,000.00

Sub-Total ### 638,355.60 ### 38,337.08 230,022.46

TOTAL ITEM 3 ### ### ### 99,479.51 596,877.04

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

4.0 TOILETS (2 @Ground, 1 @ Third Flr)


4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot 0 0 10,045.00 10,045.00 10,045.00 100.45 602.70

Demolition of Existing tiles, fixtures, hauling of debris, etc. 100.45 m² 0 0 100.00 10,045.00

4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m² 380.77 49,500.00 114.23 14,850.00 64,350.00 643.50 3,861.00
HIDE 300 x 300 Vitrified Floor and Wall Tiles 1,500.00 pcs 33.00 49,500.00 -
4.1.3 Tile Adhesive 86.67 bag 250.00 21,667.50 75.00 6,500.25 28,167.75 281.68 1,690.07
4.1.4 Tile Grout 8.67 kg 70.00 606.90 21.00 182.07 788.97 7.89 47.34

Sub-Total 71,774.40 31,577.32 103,351.72 1,033.52 6,201.10

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set 15,250.00 228,750.00 4,575.00 68,625.00 297,375.00 2,973.75 17,842.50
Male & Female entry/interior door 12.00 pcs 12,500.00 150,000.00 -
PWD entry door 3.00 pcs 15,500.00 46,500.00 -
HIDE
Door Knob 15.00 pcs 1,500.00 22,500.00 -
Door Stoppers 15.00 pcs 650.00 9,750.00 -
4.2.2 Powder Coated Window (see schedule) 12.00 set 4,500.00 54,000.00 1,350.00 16,200.00 70,200.00 702.00 4,212.00
4.2.3 Laminated Modular partitions with SS accessories 15.00 set 18,500.00 277,500.00 5,550.00 83,250.00 360,750.00 3,607.50 21,645.00
4.2.4 Semi Gloss Latex 15.00 gal 695.00 10,425.00 208.50 3,127.50 13,552.50 135.53 813.15
4.2.5 Flat Latex Paint 15.00 gal 480.00 7,200.00 144.00 2,160.00 9,360.00 93.60 561.60

4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 10,605.00 10,605.00 3,181.50 3,181.50 13,786.50 137.87 827.19

Boral Compound 6.00 bags 600.00 3,600.00


Patching Compound 6.00 bags 550.00 3,300.00
Mesh Tape 9.00 rolls 180.00 1,620.00
Paint Roller 9.00 pcs 50.00 450.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Baby Roller 9.00 pcs 70.00 630.00


Sand Paper 41.00 pcs 15.00 615.00
Paint Brush 3.00 pcs 80.00 240.00
Rugs 3.00 kgs 50.00 150.00

Sub-Total 588,480.00 176,544.00 765,024.00 7,650.24 45,901.44

4.3 PLUMBING WORKS


4.3.1 PVC Pipes Series 1000
4.3.1.1 150mm Ø 77.00 m 520.00 40,040.00 156.00 12,012.00 52,052.00 520.52 3,123.12
4.3.1.2 100mm Ø 188.00 m 230.00 43,240.00 69.00 12,972.00 56,212.00 562.12 3,372.72
4.3.2 PVC Fittings Series 1000
4.3.2.1 Wye 150 x 150 21.00 pc 950.00 19,950.00 285.00 5,985.00 25,935.00 259.35 1,556.10
4.3.2.2 Wye 100 x 100 24.00 pc 145.00 3,480.00 43.50 1,044.00 4,524.00 45.24 271.44
4.3.2.3 Elbow 90" x 100 66.00 pc 435.00 28,710.00 130.50 8,613.00 37,323.00 373.23 2,239.38
4.3.2.4 Elbow 45" x 200 6.00 pc 715.00 4,290.00 214.50 1,287.00 5,577.00 55.77 334.62
4.3.2.5 Sanitary Tee 150 x 100 24.00 pc 515.00 12,360.00 154.50 3,708.00 16,068.00 160.68 964.08
4.3.2.6 Sanitary Tee 100 x 50 39.00 pc 110.00 4,290.00 33.00 1,287.00 5,577.00 55.77 334.62
4.3.2.7 P-Trap 100 39.00 pc 215.00 8,385.00 64.50 2,515.50 10,900.50 109.01 654.03
4.3.3 19mm Ø PPR Pipes (PN20) 100.00 m 135.00 13,500.00 40.50 4,050.00 17,550.00 175.50 1,053.00
4.3.4 PPR Fittings
4.3.4.1 Elbow 90 x 19 85.50 pc 25.00 2,137.50 7.50 641.25 2,778.75 27.79 166.73
4.3.4.2 Tee 19 x 19 45.00 pc 25.00 1,125.00 7.50 337.50 1,462.50 14.63 87.75
4.3.4.3 Coupling 25 x 25 13.50 pc 25.00 337.50 7.50 101.25 438.75 4.39 26.33
4.3.4.4 Coupling 25 x 19 15.00 pc 25.00 375.00 7.50 112.50 487.50 4.88 29.25
4.3.4.5 Gate Valve 19 6.00 pc 750.00 4,500.00 225.00 1,350.00 5,850.00 58.50 351.00
4.3.5 Sanitary Fixtures
4.3.5.1 Shower Head and Shower Valves 6.00 set 2,500.00 15,000.00 750.00 4,500.00 19,500.00 195.00 1,170.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

4.3.5.2 Telephone Water Heater 6.00 set 7,000.00 42,000.00 2,100.00 12,600.00 54,600.00 546.00 3,276.00
4.3.5.3 Lavatory Sink 15.00 set 5,000.00 75,000.00 1,500.00 22,500.00 97,500.00 975.00 5,850.00
4.3.5.4 Water Closet dual flush 12.00 set 8,200.00 98,400.00 2,460.00 29,520.00 127,920.00 1,279.20 7,675.20
Water closet 12.00 set 7,000.00 84,000.00 -
Bidet 12.00 set 1,200.00 14,400.00 -
4.3.5.5 Waterless Urinal 7.00 set 14,000.00 98,000.00 4,200.00 29,400.00 127,400.00 1,274.00 7,644.00
4.3.6 Miscellaneous/Consumables 1.00 lot 10,880.00 10,880.00 3,264.00 3,264.00 14,144.00 141.44 848.64
4.3.6.1 Pipe Sleeves 1.00 lot 4,490.00 4,490.00
5" dia PVC 2.00 pcs 715.00 1,430.00
HIDE
6" dia PVC 2.00 pcs 1,530.00 3,060.00
4.3.6.2 Pipe Hangers & Support 1.00 lot 5,140.00 5,140.00
Pipe Hangers 100.00 pcs 25.00 2,500.00
HIDE
Supports 120.00 pcs 22.00 2,640.00
4.3.6.3 Teflon, Solvent etc. 1.00 lot 1,250.00 1,250.00
Teflon tape 25.00 pcs 12.00 300.00
HIDE
Solvent Cement 400cc 5.00 pcs 190.00 950.00

Sub-Total 526,000.00 157,800.00 683,800.00 6,838.00 41,028.00

4.4 ELECTRICAL WORKS & FIXTURES


4.4.1 Conduits
4.4.1.1 15mm dia PVC (Lighting) 270.00 m 30.56 8,250.00 9.17 2,475.00 10,725.00 107.25 643.50
15mm PVC pipe 270.00 ln.m 25.00 6,750.00 - -
HIDE 15mm adaptor 100.00 pcs 7.00 700.00 - -
15mm locknut and bushing 100.00 pcs 8.00 800.00 - -
4.4.1.2 15mm dia PVC (power lines) 270.00 m 30.56 8,250.00 9.17 2,475.00 10,725.00 107.25 643.50
15mm PVC pipe 270.00 ln.m 25.00 6,750.00
HIDE 15mm adaptor 100.00 pcs 7.00 700.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total
HIDE
15mm locknut and bushing 100.00 pcs 8.00 800.00
4.4.2 Wires and Cables (Ground Floor Toilet Only)
4.4.2.1 2-3.5mm THHN cu. Stranded Wires 540.00 m 28.00 15,120.00 8.40 4,536.00 19,656.00 196.56 1,179.36
4.4.3 Junction and utility Boxes 120.00 pc 33.33 4,000.00 10.00 1,200.00 5,200.00 52.00 312.00
Junction boxes w/ cover 80.00 pcs 35.00 2,800.00
HIDE
Utility Boxes 40.00 pcs 30.00 1,200.00
4.4.4 Electrical Fixtures
4.4.4.1 100mm dia Cylindrical Downlight Fixture with LED 13W 33.00 pc 850.00 28,050.00 255.00 8,415.00 36,465.00 364.65 2,187.90
4.4.4.2 Emergency Light 6.00 pc 2,000.00 12,000.00 600.00 3,600.00 15,600.00 156.00 936.00
4.4.4.3 Ceiling Exhaust Fan & Switch (heavy duty) 6.00 pc 4,000.00 24,000.00 1,200.00 7,200.00 31,200.00 312.00 1,872.00
4.4.4.4 Two Gang Switch 9.00 pc 165.00 1,485.00 49.50 445.50 1,930.50 19.31 115.83

Sub-Total 101,155.00 30,346.50 131,501.50 1,315.02 7,890.09

TOTAL ITEM 4 ### 396,267.82 ### 16,836.77 101,020.63

5.0 LECTURE ROOM A-1 (GROUND FLOOR)


5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m² 1,028.00 68,773.20 308.40 20,631.96 89,405.16 894.05 5,364.31
600 X 600 Homogenous Granite Tiles 204.00 pcs 280.00 57,120.00 -
HIDE
Cement 48.00 bags 240.00 11,520.00 -
5.1.2 Tile Adhesive 46.46 bag 250.00 11,615.00 75.00 3,484.50 15,099.50 151.00 905.97
5.1.3 Tile Grout 4.65 kg 70.00 325.50 21.00 97.65 423.15 4.23 25.39
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m² 891.00 8,910.00 267.30 2,673.00 11,583.00 115.83 694.98
HIDE 150 x 900 Vinyl Tiles 81.00 pcs 110.00 8,910.00 - -
5.1.5 Vinyl Adhesive 1.00 gal 650.00 650.00 195.00 195.00 845.00 8.45 50.70

Sub-Total 90,273.70 27,082.11 117,355.81 1,173.56 7,041.35

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal 695.00 9,035.00 208.50 2,710.50 11,745.50 117.46 704.73
5.2.2 Flat Latex Primer 7.00 gal 480.00 3,360.00 144.00 1,008.00 4,368.00 43.68 262.08

5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot 3,180.00 3,180.00 954.00 954.00 4,134.00 41.34 248.04

Boral Compound 2.00 bags 600.00 1,200.00


Patching Compound 2.00 bags 550.00 1,100.00
Mesh Tape 2.00 rolls 180.00 360.00
Paint Roller 2.00 pcs 50.00 100.00
Baby Roller 2.00 pcs 70.00 140.00
Sand Paper 10.00 pcs 15.00 150.00
Paint Brush 1.00 pcs 80.00 80.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 15,575.00 4,672.50 20,247.50 202.48 1,214.85

5.3 CEILING WORKS


5.3.1 9mm thk Gypsum Board 58.33 m² 124.46 7,260.00 37.34 2,178.00 9,438.00 94.38 566.28
HIDE 9mm thk Gypsum Board 22.00 pcs 330.00 7,260.00 - -
5.3.2 Metal Double Furring 286.87 m 39.30 11,275.00 11.79 3,382.50 14,657.50 146.58 879.45
Double furring 60.00 pcs 140.00 8,400.00 - -
HIDE
Threaded rod 25.00 pcs 115.00 2,875.00 - -
5.3.3 Wall Angle 30.55 m 35.02 1,070.00 10.51 321.00 1,391.00 13.91 83.46
Wall angle 11.00 pcs 50.00 550.00 - -
HIDE
Expansion shield 65.00 pcs 8.00 520.00 - -
5.3.4 600 x 600 acoustic boards 44.93 m² 417.32 18,750.00 125.19 5,625.00 24,375.00 243.75 1,462.50
HIDE 600 x 600 acoustic boards 125.00 pcs 150.00 18,750.00 - -
5.3.5 T-runners (white) 292.05 m 11.64 3,400.00 3.49 1,020.00 4,420.00 44.20 265.20

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Main tee 12" 20.00 pcs 110.00 2,200.00 - -


HIDE Cross tee 4' 20.00 pcs 40.00 800.00 - -
Cross tee 2' 20.00 pcs 20.00 400.00 - -
5.3.6 Wall Angle (White) 26.81 m 10.50 281.51 3.15 84.45 365.96 3.66 21.96
5.3.7 Carrying Channel 103.26 m 23.00 2,374.98 6.90 712.49 3,087.47 30.87 185.25
5.3.8 W-Clamps/Clips 206.52 pc 3.50 722.82 1.05 216.85 939.67 9.40 56.38
5.3.9 Blind Rivets 1/8 20.65 box 350.00 7,227.50 105.00 2,168.25 9,395.75 93.96 563.75
5.3.10 Black Screws 1,749.90 pc 0.75 1,312.43 0.23 393.73 1,706.15 17.06 102.37

Sub-Total 53,674.23 16,102.27 69,776.50 697.76 4,186.59

5.4 ELECTRICAL WORKS AND FIXTURES


5.4.1 Conduits
5.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67 4,280.00 10.70 1,284.00 5,564.00 55.64 333.84
15mm PVC pipe 120.00 ln.m 25.00 3,000.00 - -
HIDE 15mm adaptor 80.00 pcs 7.00 560.00 - -
15mm locknut and bushing 80.00 pcs 9.00 720.00 - -
5.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67 4,280.00 10.70 1,284.00 5,564.00 55.64 333.84
15mm PVC pipe 120.00 ln.m 25.00 3,000.00
HIDE 15mm adaptor 80.00 pcs 7.00 560.00
15mm locknut and bushing 80.00 pcs 9.00 720.00
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m 28.00 6,720.00 8.40 2,016.00 8,736.00 87.36 524.16
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m 38.00 9,120.00 11.40 2,736.00 11,856.00 118.56 711.36
5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc 33.00 1,980.00 9.90 594.00 2,574.00 25.74 154.44
Junction boxes w/ cover 36.00 pcs 35.00 1,260.00
HIDE
Utility Boxes 24.00 pcs 30.00 720.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

5.4.4 Electrical fixtures


5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc 850.00 11,050.00 255.00 3,315.00 14,365.00 143.65 861.90
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00 12,000.00 600.00 3,600.00 15,600.00 156.00 936.00
5.4.4.3 Emergency Light 1.00 set 2,000.00 2,000.00 600.00 600.00 2,600.00 26.00 156.00
5.4.4.4 Ceiling Fans 6.00 set 2,500.00 15,000.00 750.00 4,500.00 19,500.00 195.00 1,170.00
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 3,400.00 255.00 1,020.00 4,420.00 44.20 265.20
5.4.4.6 Aircon Outlet 2.00 pc 270.00 540.00 81.00 162.00 702.00 7.02 42.12
5.4.4.7 Three Gang Switch 1.00 pc 215.00 215.00 64.50 64.50 279.50 2.80 16.77
5.4.4.8 Ceiling Fan Switch 2.00 pc 250.00 500.00 75.00 150.00 650.00 6.50 39.00

Sub-Total 71,085.00 21,325.50 92,410.50 924.11 5,544.63

5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 0 10,035.00 10,035.00 10,035.00 100.35 602.10

hide Demolition of Existing tiles, fixtures, hauling of debris, etc 66.90 m² 0 0 150.00 10,035.00

Whiteboard Screen with Integrated Smart TV Enclosure


5.5.2 1.00 set 50,275.00 50,275.00 15,082.50 15,082.50 65,357.50 653.58 3,921.45
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit 35,000.00 35,000.00
Sliding laminated White board (1.2m x 2.4m) 1.00 pcs 5,000.00 5,000.00
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs 3,000.00 6,000.00
3/4" thk Class A Plyboard 3.00 pcs 1,400.00 4,200.00
Screws 100.00 pcs 0.75 75.00
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 15,000.00 2,250.00 2,250.00 17,250.00 172.50 1,035.00
Professor's desk 1.00 pc 7,500.00 7,500.00 - -
HIDE Ergonomic chair 1.00 pc 2,500.00 2,500.00 - -
Podium 1.00 pc 5,000.00 5,000.00 - -
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 102,000.00 15,300.00 30,600.00 132,600.00 1,326.00 7,956.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

2 HP Inverter Window type Aircon Unit 2.00 units 49,000.00 98,000.00 - -


HIDE
Angle Bar Frame 2.00 sets 2,000.00 4,000.00 - -
5.5.3.3 PVC Student Armchair 45.00 set 950.00 42,750.00 142.50 6,412.50 49,162.50 491.63 2,949.75

Sub-Total 210,025.00 64,380.00 274,405.00 2,744.05 16,464.30

DOORS AND WINDOWS (WITH COMPLETE


5.6
ACCESSORIES)

5.6.1 D-1: Metal Door Jams and Panel (w/ knobs & hinges) 2.00 set 18,140.00 36,280.00 5,442.00 10,884.00 47,164.00 471.64 2,829.84
1.00m x 2.10m Steel Door w/ viewing glass 2.00 pcs 15,500.00 31,000.00 - -
Door knob 2.00 set 1,500.00 3,000.00 - -
Flat wall enamel 1.00 gals 580.00 580.00 - -
QDE 1.00 gals 560.00 560.00 - -
HIDE Paint thinner 1.00 gals 250.00 250.00 - -
SPot putty 1.00 gals 630.00 630.00 - -
Sand paper 10.00 pcs 15.00 150.00 - -
Baby roller 1.00 pcs 60.00 60.00 - -
Cotton rugs 1.00 kgs 50.00 50.00 - -
5.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 48,000.00 3,600.00 14,400.00 62,400.00 624.00 3,744.00
5.6.3 W-2: Clear glass powder coated white pivot window 4.00 set 5,600.00 22,400.00 1,680.00 6,720.00 29,120.00 291.20 1,747.20

Sub-Total 106,680.00 32,004.00 138,684.00 1,386.84 8,321.04

TOTAL ITEM 5 547,312.93 165,566.38 712,879.31 7,128.79 42,772.76

6.0 STUDENT ORG ROOMS (GROUND FLOOR)


6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m² 895.40 44,770.00 268.62 13,431.00 58,201.00 582.01 3,492.06

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

HIDE 150 X 900 Vinyl Tiles 407.00 pcs 110.00 44,770.00 - -


6.1.2 Vinyl Adhesive 5.00 gal 650.00 3,250.00 195.00 975.00 4,225.00 42.25 253.50

Sub-Total 48,020.00 14,406.00 62,426.00 624.26 3,745.56

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal 695.00 15,985.00 208.50 4,795.50 20,780.50 207.81 1,246.83
6.2.2 Flat Latex 10.00 gal 480.00 4,800.00 144.00 1,440.00 6,240.00 62.40 374.40

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot 4,730.00 4,730.00 1,419.00 1,419.00 6,149.00 61.49 368.94

Boral Compound 2.00 bags 600.00 1,200.00


Patching Compound 2.00 bags 550.00 1,100.00
Mesh Tape 6.00 rolls 180.00 1,080.00
Paint Roller 6.00 pcs 50.00 300.00
Baby Roller 6.00 pcs 70.00 420.00
Sand Paper 28.00 pcs 15.00 420.00
Paint Brush 2.00 pcs 80.00 160.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 25,515.00 7,654.50 33,169.50 331.70 1,990.17

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m² 125.92 9,570.00 37.78 2,871.00 12,441.00 124.41 746.46
HIDE 9mm thk Gypsum Board 29.00 pcs 330.00 9,570.00 -
6.3.2 Metal Double Furring 373.77 m 30.17 11,275.00 9.05 3,382.50 14,657.50 146.58 879.45
Double furring 60.00 pcs 140.00 8,400.00 -
HIDE
Threaded rod 25.00 pcs 115.00 2,875.00 -
6.3.3 Wall Angle 34.87 m 37.57 1,310.00 11.27 393.00 1,703.00 17.03 102.18
Wall angle 15.00 pcs 50.00 750.00 -
HIDE

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total
HIDE
Expansion shield 70.00 pcs 8.00 560.00 -
6.3.4 Carrying Channel 76.00 m 23.00 1,748.00 6.90 524.40 2,272.40 22.72 136.34
6.3.5 W-clamps/Clips 152.00 pc 3.50 532.00 1.05 159.60 691.60 6.92 41.50
6.3.6 Blind rivets(1/8) 15.00 box 350.00 5,250.00 105.00 1,575.00 6,825.00 68.25 409.50
6.3.7 Black Screws 2,280.00 pc 0.75 1,710.00 0.23 513.00 2,223.00 22.23 133.38

Sub-Total 31,395.00 9,418.50 40,813.50 408.14 2,448.81

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67 4,280.00 10.70 1,284.00 5,564.00 55.64 333.84
15mm PVC pipe 120.00 ln.m 25.00 3,000.00 - -
HIDE 15mm adaptor 80.00 pcs 7.00 560.00 - -
15mm locknut and bushing 80.00 pcs 9.00 720.00 - -
6.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67 4,280.00 10.70 1,284.00 5,564.00 55.64 333.84
15mm PVC pipe 120.00 ln.m 25.00 3,000.00
HIDE 15mm adaptor 80.00 pcs 7.00 560.00
15mm locknut and bushing 80.00 pcs 9.00 720.00
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00 6,720.00 8.40 2,016.00 8,736.00 87.36 524.16
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00 9,120.00 11.40 2,736.00 11,856.00 118.56 711.36
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc 33.75 2,025.00 10.13 607.50 2,632.50 26.33 157.95
Junction boxes w/ cover 45.00 pcs 35.00 1,575.00
hide
Utility Boxes 15.00 pcs 30.00 450.00
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set 850.00 13,600.00 255.00 4,080.00 17,680.00 176.80 1,060.80
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00 16,000.00 600.00 4,800.00 20,800.00 208.00 1,248.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

6.4.4.3 Emergency Light 4.00 set 2,000.00 8,000.00 600.00 2,400.00 10,400.00 104.00 624.00
6.4.4.4 Ceiling Fan 4.00 set 2,500.00 10,000.00 750.00 3,000.00 13,000.00 130.00 780.00
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc 850.00 6,800.00 255.00 2,040.00 8,840.00 88.40 530.40
6.4.4.6 One Gang Switch 4.00 pc 105.00 420.00 31.50 126.00 546.00 5.46 32.76
6.4.4.7 Ceiling Fan Switch 4.00 pc 250.00 1,000.00 75.00 300.00 1,300.00 13.00 78.00

Sub-Total 82,245.00 24,673.50 106,918.50 1,069.19 6,415.11

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc 750.00 13,500.00 225.00 4,050.00 17,550.00 175.50 1,053.00
6.5.1.2 2 x 3 Metal Stud 250.82 m 55.58 13,940.00 16.67 4,182.00 18,122.00 181.22 1,087.32
Metal stud 84.00 pcs 135.00 11,340.00 - -
HIDE
Metal tracks 20.00 pcs 130.00 2,600.00 - -
6.5.1.3 Blind rivets (1/8) 4.00 box 350.00 1,400.00 105.00 420.00 1,820.00 18.20 109.20
6.5.1.4 Black Screws 1,530.00 pc 0.75 1,147.50 0.23 344.25 1,491.75 14.92 89.51
Demolition of existing tiles, fixtures, hauling of debris,
6.5.2 1.00 lot 0 0 7,500.00 7,500.00 7,500.00 75.00 450.00
etc.
Demolition of existing tiles, fixtures, hauling of debris, etc. 50.00 sq.m 0 0 150.00 7,500.00

6.5.3 Furniture & Appliances


6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set 33,000.00 132,000.00 4,950.00 19,800.00 151,800.00 1,518.00 9,108.00
Working Table 4.00 pc 13,000.00 52,000.00 - -
hide
Ergonomic chair 32.00 pcs 2,500.00 80,000.00 - -
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc 1,200.00 360,000.00 180.00 54,000.00 414,000.00 4,140.00 24,840.00
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set 12,000.00 72,000.00 3,600.00 21,600.00 93,600.00 936.00 5,616.00
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc 4,000.00 16,000.00 1,200.00 4,800.00 20,800.00 208.00 1,248.00

Sub-Total 609,987.50 116,696.25 726,683.75 7,266.84 43,601.03

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

DOORS AND WINDOWS (WITH COMPLETE


6.6
ACCESSORIES)
6.6.1 D-1: White Steel Door / view panel on Metal Jamb 4.00 set 18,147.50 72,590.00 5,444.25 21,777.00 94,367.00 943.67 5,662.02
1.00m x 2.10m Steel Door w/ viewing glass 4.00 pcs 15,500.00 62,000.00 - -
Door knob 4.00 set 1,500.00 6,000.00 - -
Flat wall enamel 2.00 gals 580.00 1,160.00 - -
QDE 2.00 gals 600.00 1,200.00 - -
HIDE Paint thinner 2.00 gals 250.00 500.00 - -
SPot putty 2.00 gals 630.00 1,260.00 - -
Sand paper 20.00 pcs 15.00 300.00 - -
Baby roller 2.00 pcs 60.00 120.00 - -
Cotton rugs 1.00 kgs 50.00 50.00 - -
6.6.2 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 22,400.00 1,680.00 6,720.00 29,120.00 291.20 1,747.20

94,990.00 28,497.00 123,487.00 1,234.87 7,409.22

TOTAL ITEM 6 892,152.50 201,345.75 ### 10,934.98 65,609.90

7.0 LECTURE ROOM A-4 (GROUND FLOOR)


7.1 FLOOR FINISHES
7.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00 129,528.00 308.40 38,858.40 168,386.40 1,683.86 10,103.18
HIDE 600 x 600 Homogenous Granite Tiles 385.00 pcs 280.00 107,800.00 -
HIDE Cement 91.00 bgas 240.00 21,840.00 -
7.1.2 Tile Adhesive 87.50 bag 250.00 21,875.00 75.00 6,562.50 28,437.50 284.38 1,706.25
7.1.3 Tile Grout 8.75 kg 70.00 612.50 21.00 183.75 796.25 7.96 47.78
7.1.4 Vinyl Adhesive 2.00 gal 650.00 1,300.00 195.00 390.00 1,690.00 16.90 101.40
7.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00 17,820.00 267.30 5,346.00 23,166.00 231.66 1,389.96
HIDE 150 x 900 Vinyl tiles 162.00 pcs 110.00 17,820.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Sub-Total 171,135.50 51,340.65 222,476.15 2,224.76 13,348.57

7.2 PAINTING
7.2.1 Semi Gloss Latex 4.00 gal 695.00 2,780.00 208.50 834.00 3,614.00 36.14 216.84
7.2.2 Flat Latex 7.00 gal 480.00 3,360.00 144.00 1,008.00 4,368.00 43.68 262.08

7.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,395.00 2,395.00 718.50 718.50 3,113.50 31.14 186.81

Boral Compound 1.00 bags 600.00 600.00


Patching Compound 1.00 bags 550.00 550.00
Mesh Tape 4.00 rolls 180.00 720.00
Paint Roller 2.00 pcs 50.00 100.00
Baby Roller 2.00 pcs 70.00 140.00
Sand Paper 5.00 pcs 15.00 75.00
Paint Brush 2.00 pcs 80.00 160.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 8,535.00 2,560.50 11,095.50 110.96 665.73

7.3 CEILING WORKS


7.3.1 9mm thk Gypsum bd on Metal Furring 51.00 m² 129.41 6,600.00 38.82 1,980.00 8,580.00 85.80 514.80
HIDE 9mm thk Gypsum Board 20.00 pcs 330.00 6,600.00 - -
7.3.2 Metal Double Furring 250.82 m 29.66 7,440.00 8.90 2,232.00 9,672.00 96.72 580.32
Double furring 40.00 pcs 140.00 5,600.00 - -
HIDE
Threaded rod 16.00 pcs 115.00 1,840.00 - -
7.3.3 Wall Angle 28.57 m 32.90 940.00 9.87 282.00 1,222.00 12.22 73.32
Wall angle 10.00 pcs 50.00 500.00 - -
HIDE
Expansion shield 55.00 pcs 8.00 440.00 - -
7.3.4 Carrying Channel 125.00 m 23.00 2,875.00 6.90 862.50 3,737.50 37.38 224.25

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

7.3.5 W-clamps/clips 250.00 pc 3.50 875.00 1.05 262.50 1,137.50 11.38 68.25
7.3.6 Blind rivets(1/8) 25.00 box 350.00 8,750.00 105.00 2,625.00 11,375.00 113.75 682.50
7.3.7 Black Screws 1,530.00 pc 0.75 1,147.50 0.23 344.25 1,491.75 14.92 89.51
7.3.8 T-Runner (White) 481.00 m 12.37 5,950.00 3.71 1,785.00 7,735.00 77.35 464.10
Main tee 12" 35.00 pcs 110.00 3,850.00 - -
HIDE Cross tee 4' 35.00 pcs 40.00 1,400.00 - -
Cross tee 2' 35.00 pcs 20.00 700.00 - -
7.3.9 Wall Angle (White) 34.41 m 10.50 361.31 3.15 108.39 469.70 4.70 28.18
7.3.10 600 x 600 acoustic board 74.00 m² 458.11 33,900.00 137.43 10,170.00 44,070.00 440.70 2,644.20
HIDE 600 x 600 Acoustic Boards 226.00 pcs 150.00 33,900.00

Sub-Total 68,838.81 20,651.64 89,490.45 894.90 5,369.43

7.4 ELECTRICAL WORKS AND FIXTURES


7.4.1 Conduits
7.4.1.1 15mm dia PVC (Lighting) 100.00 m 35.56 3,556.00 10.67 1,066.80 4,622.80 46.23 277.37
15mm PVC pipe 100.00 ln.m 25.00 2,500.00 - -
HIDE 15mm adaptor 66.00 pcs 7.00 462.00 - -
15mm locknut and bushing 66.00 pcs 9.00 594.00 - -
7.4.1.2 15mm dia PVC (Power Lines) 100.00 m 35.56 3,556.00 10.67 1,066.80 4,622.80 46.23 277.37
15mm PVC pipe 100.00 ln.m 25.00 2,500.00
HIDE 15mm adaptor 66.00 pcs 7.00 462.00
15mm locknut and bushing 66.00 pcs 9.00 594.00
7.4.2 Wires and Cables (Ground Floor Toilet Only)
7.4.2.1 2-3.5mm THHN CU, Stranded Wires 200.00 m 28.00 5,600.00 8.40 1,680.00 7,280.00 72.80 436.80
7.4.2.2 2-5.5mm THHN CU, Stranded Wires 200.00 m 38.00 7,600.00 11.40 2,280.00 9,880.00 98.80 592.80
7.4.3 Others
7.4.3.1 Junction and Utility Box 60.00 pc 33.00 1,980.00 9.90 594.00 2,574.00 25.74 154.44

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Junction boxes w/ cover 36.00 pcs 35.00 1,260.00


HIDE
Utility Boxes 24.00 pcs 30.00 720.00
7.4.4 Electrical fixtures
7.4.4.1 Pinlight (100mm dia) with 7W LED 22.00 pc 850.00 18,700.00 255.00 5,610.00 24,310.00 243.10 1,458.60
7.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00 16,000.00 600.00 4,800.00 20,800.00 208.00 1,248.00
7.4.4.3 Emergency Light 1.00 set 2,000.00 2,000.00 600.00 600.00 2,600.00 26.00 156.00
7.4.4.4 Ceiling Fan 8.00 set 2,500.00 20,000.00 750.00 6,000.00 26,000.00 260.00 1,560.00
7.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 3,400.00 255.00 1,020.00 4,420.00 44.20 265.20
7.4.4.6 Aircon Outlet 2.00 pc 270.00 540.00 81.00 162.00 702.00 7.02 42.12
7.4.4.7 Three Gang Switch 2.00 pc 105.00 210.00 31.50 63.00 273.00 2.73 16.38
7.4.4.8 Ceiling Fan Switch 4.00 pc 250.00 1,000.00 75.00 300.00 1,300.00 13.00 78.00

Sub-Total 84,142.00 25,242.60 109,384.60 1,093.85 6,563.08

7.5 OTHERS
7.5.1 Demolition of existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 0 18,900.00 18,900.00 18,900.00 189.00 1,134.00

Demolition of existing tiles, fixtures, hauling of debris, etc 126.00 sq.m 0 0 150.00 18,900.00

Whiteboard Screen with Integrated Smart TV Enclosure,


7.5.2 1.00 set 50,275.00 50,275.00 15,082.50 15,082.50 65,357.50 653.58 3,921.45
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit 35,000.00 35,000.00
Sliding laminated White board (1.2m x 2.4m) 1.00 pcs 5,000.00 5,000.00
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs 3,000.00 6,000.00
3/4" thk Class A Plyboard 3.00 pcs 1,400.00 4,200.00
Screws 100.00 pcs 0.75 75.00
7.5.3 Furniture & Appliances
7.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 15,000.00 2,250.00 2,250.00 17,250.00 172.50 1,035.00
Professor's desk 1.00 pc 7,500.00 7,500.00 - -
hide Ergonomic chair 1.00 pc 2,500.00 2,500.00 - -

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total
hide
Podium 1.00 pc 5,000.00 5,000.00 - -
7.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 102,000.00 15,300.00 30,600.00 132,600.00 1,326.00 7,956.00
2 HP Inverter Window type Aircon Unit 2.00 units 49,000.00 98,000.00 - -
hide
Angle Bar Frame 2.00 sets 2,000.00 4,000.00 - -
7.5.3.3 Working Table fit with 8 Ergonomic Chairs 9.00 set 33,000.00 297,000.00 4,950.00 44,550.00 341,550.00 3,415.50 20,493.00
Working Table 9.00 pc 13,000.00 117,000.00
hide
Ergonomic chair 72.00 pcs 2,500.00 180,000.00
Sub-Total 464,275.00 111,382.50 575,657.50 5,756.58 34,539.45

DOORS AND WINDOWS (WITH COMPLETE


7.6
ACCESSORIES)
7.6.1 D-1: White Steel Door / view pane on Metal Jamb 2.00 set 18,160.00 36,320.00 5,448.00 10,896.00 47,216.00 472.16 2,832.96
1.00m x 2.10m Steel Door w/ viewing glass 2.00 pcs 15,500.00 31,000.00 - -
Door knob 2.00 set 1,500.00 3,000.00 - -
Flat wall enamel 1.00 gals 580.00 580.00 - -
QDE 1.00 gals 600.00 600.00 - -
hide Paint thinner 1.00 gals 250.00 250.00 - -
SPot putty 1.00 gals 630.00 630.00 - -
Sand paper 10.00 pcs 15.00 150.00 - -
Baby roller 1.00 pcs 60.00 60.00 - -
Cotton rugs 1.00 kgs 50.00 50.00 - -
7.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 48,000.00 3,600.00 14,400.00 62,400.00 624.00 3,744.00
7.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 22,400.00 1,680.00 6,720.00 29,120.00 291.20 1,747.20

Sub-Total 106,720.00 32,016.00 138,736.00 1,387.36 8,324.16

TOTAL ITEM 7 903,646.31 243,193.89 ### 11,468.40 68,810.41

8.0 THEATER TYPE LECTURE RM (A-5) (SECOND FLR)

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

8.1 FLOOR FINISHES


8.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00 129,528.00 308.40 38,858.40 168,386.40 1,683.86 10,103.18
HIDE 600 x 600 Homogenous Granite Tiles 385.00 pcs 280.00 107,800.00 -
HIDE Cement 91.00 bags 240.00 21,840.00 -
8.1.2 Tile Adhesive 87.50 bag 250.00 21,875.00 75.00 6,562.50 28,437.50 284.38 1,706.25
8.1.3 Tile Grout 8.75 kg 70.00 612.50 21.00 183.75 796.25 7.96 47.78
8.1.4 Vinyl Adhesive 2.00 gal 650.00 1,300.00 195.00 390.00 1,690.00 16.90 101.40
8.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00 17,820.00 267.30 5,346.00 23,166.00 231.66 1,389.96
HIDE 150 x 900 Vinyl tiles 162.00 pcs 110.00 17,820.00

Sub-Total 171,135.50 51,340.65 222,476.15 2,224.76 13,348.57

8.2 PAINTING
8.2.1 Semi Gloss Latex 28.00 gal 695.00 19,460.00 208.50 5,838.00 25,298.00 252.98 1,517.88
8.2.2 Flat Latex 6.00 gal 480.00 2,880.00 144.00 864.00 3,744.00 37.44 224.64

8.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,800.00 2,800.00 840.00 840.00 3,640.00 36.40 218.40

Boral Compound 1.00 bags 600.00 600.00


Patching Compound 1.00 bags 550.00 550.00
Mesh Tape 4.00 rolls 180.00 720.00
Paint Roller 4.00 pcs 50.00 200.00
Baby Roller 4.00 pcs 70.00 280.00
Sand Paper 16.00 pcs 15.00 240.00
Paint Brush 2.00 pcs 80.00 160.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 25,140.00 7,542.00 32,682.00 326.82 1,960.92

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

8.3 CEILING WORKS


8.3.1 9mm thk Gypsum bd on Metal Furring 50.00 m² 125.40 6,270.00 37.62 1,881.00 8,151.00 81.51 489.06
HIDE 9mm thk Gypsum Board 19.00 pcs 330.00 6,270.00 - -
8.3.2 Metal Double Furring 245.90 m 32.33 7,950.00 9.70 2,385.00 10,335.00 103.35 620.10
Double furring 42.00 pcs 140.00 5,880.00 - -
HIDE
Threaded rod 18.00 pcs 115.00 2,070.00 - -
8.3.3 Wall Angle 28.28 m 30.62 866.00 9.19 259.80 1,125.80 11.26 67.55
Wall angle 9.00 pcs 50.00 450.00 - -
HIDE
Expansion shield 52.00 pcs 8.00 416.00 - -
8.3.4 Carrying Channel 150.00 m 23.00 3,450.00 6.90 1,035.00 4,485.00 44.85 269.10
8.3.5 W-Clamps/Clips 300.00 m 3.50 1,050.00 1.05 315.00 1,365.00 13.65 81.90
8.3.6 Blind rivets(1/8) 75.00 box 350.00 26,250.00 105.00 7,875.00 34,125.00 341.25 2,047.50
8.3.7 Black Screws 1,500.00 pc 0.75 1,125.00 0.23 337.50 1,462.50 14.63 87.75
8.3.8 T-Runner (White) 650.00 m 11.77 7,650.00 3.53 2,295.00 9,945.00 99.45 596.70
Main tee 12" 45.00 pcs 110.00 4,950.00 - -
HIDE Cross tee 4' 45.00 pcs 40.00 1,800.00 - -
Cross tee 2' 45.00 pcs 20.00 900.00 - -
8.3.9 Wall Angle (White) 40.00 m 10.50 420.00 3.15 126.00 546.00 5.46 32.76
8.3.10 600 x 600 acoustic board on T-Runner 100.00 m² 457.50 45,750.00 137.25 13,725.00 59,475.00 594.75 3,568.50
HIDE 600 x 600 Acooustic Board Tile 305.00 pcs 150.00 45,750.00

Sub-Total 100,781.00 30,234.30 131,015.30 1,310.15 7,860.92

8.4 ELECTRICAL WORKS AND FIXTURES


8.4.1 Conduits
8.4.1.1 15mm dia PVC (Lighting) 200.00 m 25.00 5,000.00 7.50 1,500.00 6,500.00 65.00 390.00
8.4.1.2 15mm dia PVC (power lines) 200.00 m 25.00 5,000.00 7.50 1,500.00 6,500.00 65.00 390.00
8.4.2 Wires and Cables (Ground Floor Toilet Only)

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

8.4.2.1 2-3.5mm THHN CU, Stranded Wires 400.00 m 28.00 11,200.00 8.40 3,360.00 14,560.00 145.60 873.60
8.4.2.2 2-5.5mm THHN CU, Stranded Wires 400.00 m 38.00 15,200.00 11.40 4,560.00 19,760.00 197.60 1,185.60
8.4.3 Others
8.4.3.1 Junction and Utility Box 90.00 pc 33.06 2,975.00 9.92 892.50 3,867.50 38.68 232.05
Junction boxes w/ cover 55.00 pcs 35.00 1,925.00
hide
Utility Boxes 35.00 pcs 30.00 1,050.00
8.4.4 Electrical fixtures
8.4.4.1 Pinlight (100mm dia) with 7W LED 24.00 set 850.00 20,400.00 255.00 6,120.00 26,520.00 265.20 1,591.20
8.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 12.00 set 2,000.00 24,000.00 600.00 7,200.00 31,200.00 312.00 1,872.00
8.4.4.3 Emergency Light 2.00 set 2,000.00 4,000.00 600.00 1,200.00 5,200.00 52.00 312.00
8.4.4.4 Ceiling Fan 12.00 set 2,500.00 30,000.00 750.00 9,000.00 39,000.00 390.00 2,340.00
8.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 3,400.00 255.00 1,020.00 4,420.00 44.20 265.20
8.4.4.6 Aircon Outlet 3.00 pc 270.00 810.00 81.00 243.00 1,053.00 10.53 63.18
8.4.4.7 Three Gang Switch 2.00 pc 215.00 430.00 64.50 129.00 559.00 5.59 33.54
8.4.4.8 Two Gang Switch 1.00 pc 165.00 165.00 49.50 49.50 214.50 2.15 12.87
8.4.4.9 Ceiling Fan Switch 5.00 pc 250.00 1,250.00 75.00 375.00 1,625.00 16.25 97.50

Sub-Total 123,830.00 37,149.00 160,979.00 1,609.79 9,658.74

8.5 OTHERS
8.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 0 18,900.00 18,900.00 18,900.00 189.00 1,134.00

Demolition of Existing tiles, fixtures, hauling of debris, etc 126.00 sq.m 0 0 150.00 18,900.00

Whiteboard Screen with Integrated Smart TV Enclosure,


8.5.2 1.00 set 50,275.00 50,275.00 15,082.50 15,082.50 65,357.50 653.58 3,921.45
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit 35,000.00 35,000.00
Sliding laminated White board (1.2m x 2.4m) 1.00 pcs 5,000.00 5,000.00
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs 3,000.00 6,000.00
3/4" thk Class A Plyboard 3.00 pcs 1,400.00 4,200.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
HIDE Unit Cost
Unit Cost Total

Screws 100.00 pcs 0.75 75.00


8.5.3 Furniture & Appliances
8.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 15,000.00 2,250.00 2,250.00 17,250.00 172.50 1,035.00
Professor's Desk 1.00 pc 7,500.00 7,500.00 - -
hide Ergonomic chair 1.00 pc 2,500.00 2,500.00 - -
Podium 1.00 pc 5,000.00 5,000.00 - -
8.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00 153,000.00 15,300.00 45,900.00 198,900.00 1,989.00 11,934.00
2 HP Inverter Window type Aircon Unit 3.00 units 49,000.00 147,000.00 - -
hide
Angle Bar Frame 3.00 sets 2,000.00 6,000.00 - -
8.5.3.3 Fixed Retractable Theatre Arm Chair 111.00 pc 8,000.00 888,000.00 1,600.00 177,600.00 1,065,600.00 10,656.00 63,936.00

Sub-Total ### 259,732.50 ### 13,660.08 81,960.45

DOORS AND WINDOWS (WITH COMPLETE


8.6
ACCESSORIES)
8.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,295.00 38,590.00 5,788.50 11,577.00 50,167.00 501.67 3,010.02
1.00m x 2.10m Steel Door w/ viewing glass 2.00 pcs 15,500.00 31,000.00 - -
Door knob 2.00 set 1,500.00 3,000.00 - -
Flat wall enamel 2.00 gals 580.00 1,160.00 - -
QDE 2.00 gals 600.00 1,200.00 - -
HIDE Paint thinner 2.00 gals 250.00 500.00 - -
SPot putty 2.00 gals 630.00 1,260.00 - -
Sand paper 20.00 pcs 15.00 300.00 - -
Baby roller 2.00 pcs 60.00 120.00 - -
Cotton rugs 1.00 kgs 50.00 50.00 - -
8.6.2 W-1: Clear Glass powder coated white awning window 6.00 set 12,000.00 72,000.00 3,600.00 21,600.00 93,600.00 936.00 5,616.00
8.6.3 W-2: Clear Glass powder coated white pivot window 6.00 set 5,600.00 33,600.00 1,680.00 10,080.00 43,680.00 436.80 2,620.80

Sub-Total 144,190.00 43,257.00 187,447.00 1,874.47 11,246.82

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

TOTAL ITEM 8 ### 429,255.45 ### 21,006.07 126,036.42

9.0 LECTURE ROOM (A-7) (SECOND FLOOR)


9.1 FLOOR FINISHES
9.1.1 600 x 600 Homogenous Granite Tiles 68.00 m² 1,028.00 69,904.00 308.40 20,971.20 90,875.20 908.75 5,452.51
HIDE 600 x 600 Homogenous Granite Tiles 207.00 pcs 280.00 57,960.00 -
HIDE Cement 49.00 bags 240.00 11,760.00 -
9.1.2 Tile Adhesive 47.22 bag 250.00 11,805.00 75.00 3,541.50 15,346.50 153.47 920.79
9.1.3 Tile Grout 4.72 kg 70.00 330.40 21.00 99.12 429.52 4.30 25.77
9.1.4 Vinyl Adhesive 0.90 gal 650.00 585.00 195.00 175.50 760.50 7.61 45.63
9.1.5 150 x 900 Vinyl tiles 9.00 m² 892.22 8,030.00 267.67 2,409.00 10,439.00 104.39 626.34
HIDE 150 x 900 Vinyl tiles 73.00 pcs 110.00 8,030.00

Sub-Total 90,654.40 27,196.32 117,850.72 1,178.51 7,071.04

9.2 PAINTING
9.2.1 Semi Gloss Latex 15.00 gal 695.00 10,425.00 208.50 3,127.50 13,552.50 135.53 813.15
9.2.2 Flat Latex 10.00 gal 480.00 4,800.00 144.00 1,440.00 6,240.00 62.40 374.40

9.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,365.00 2,365.00 709.50 709.50 3,074.50 30.75 184.47

Boral Compound 1.00 bags 600.00 600.00


Patching Compound 1.00 bags 550.00 550.00
Mesh Tape 3.00 rolls 180.00 540.00
Paint Roller 2.00 pcs 50.00 100.00
Baby Roller 2.00 pcs 70.00 140.00
Sand Paper 15.00 pcs 15.00 225.00
Paint Brush 2.00 pcs 80.00 160.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Rugs 1.00 kgs 50.00 50.00

Sub-Total 17,590.00 5,277.00 22,867.00 228.67 1,372.02

9.3 CEILING WORKS


9.3.1 9mm thk Gypsum Board on Metal Furring 30.00 m² 121.00 3,630.00 36.30 1,089.00 4,719.00 47.19 283.14
HIDE 9mm thk Gypsum Board 11.00 pcs 330.00 3,630.00 - -
9.3.2 Metal Double Furring 147.54 m 38.26 5,645.00 11.48 1,693.50 7,338.50 73.39 440.31
Double furring 28.00 pcs 140.00 3,920.00 - -
HIDE
Threaded rod 15.00 pcs 115.00 1,725.00 - -
9.3.3 Wall Angle 21.91 m 34.69 760.00 10.41 228.00 988.00 9.88 59.28
Wall angle 8.00 pcs 50.00 400.00 - -
HIDE
Expansion shield 45.00 pcs 8.00 360.00 - -
9.3.4 Carrying Channel 76.00 m 23.00 1,748.00 6.90 524.40 2,272.40 22.72 136.34
9.3.5 W-clamps/clips 152.00 pc 3.50 532.00 1.05 159.60 691.60 6.92 41.50
9.3.6 Blind rivets(1/8) 38.00 box 350.00 13,300.00 105.00 3,990.00 17,290.00 172.90 1,037.40
9.3.7 Black Screws 900.00 pc 0.75 675.00 0.23 202.50 877.50 8.78 52.65
9.3.8 T-Runner (White) 299.00 m 11.94 3,570.00 3.58 1,071.00 4,641.00 46.41 278.46
Main tee 12" 21.00 pcs 110.00 2,310.00 - -
HIDE Cross tee 4' 21.00 pcs 40.00 840.00 - -
Cross tee 2' 21.00 pcs 20.00 420.00 - -
9.3.9 Wall Angle (White) 27.13 m 10.50 284.87 3.15 85.46 370.32 3.70 22.22
9.3.10 600 x 600 acoustic board on T-Runner 46.00 m² 456.52 21,000.00 136.96 6,300.00 27,300.00 273.00 1,638.00
HIDE 600 x 600 Acooustic Board Tile 140.00 pcs 150.00 21,000.00

Sub-Total 51,144.87 15,343.46 66,488.32 664.88 3,989.30

9.4 ELECTRICAL WORKS AND FIXTURES

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

9.4.1 Conduits
9.4.1.1 15mm dia PVC (Lighting) 88.00 m 25.00 2,200.00 7.50 660.00 2,860.00 28.60 171.60
9.4.1.2 15mm dia PVC (Power Lines) 88.00 m 25.00 2,200.00 7.50 660.00 2,860.00 28.60 171.60
9.4.2 Wires and Cables (Ground Floor Toilet Only)
9.4.2.1 2-3.5mm THHN cu. Stranded Wires 176.00 m 28.00 4,928.00 8.40 1,478.40 6,406.40 64.06 384.38
9.4.2.2 2-5.5mm THHN cu. Stranded Wires 176.00 m 38.00 6,688.00 11.40 2,006.40 8,694.40 86.94 521.66
9.4.3 Others
9.4.3.1 Junction and Utility Box 60.00 pc 33.00 1,980.00 9.90 594.00 2,574.00 25.74 154.44
Junction boxes w/ cover 36.00 pcs 35.00 1,260.00
hide
Utility Boxes 24.00 pcs 30.00 720.00
9.4.4 Electrical fixtures
9.4.4.1 Pinlight (100mm dia) with 7W LED 9.00 pc 850.00 7,650.00 255.00 2,295.00 9,945.00 99.45 596.70
9.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00 12,000.00 600.00 3,600.00 15,600.00 156.00 936.00
9.4.4.3 Emergency Light 1.00 set 2,000.00 2,000.00 600.00 600.00 2,600.00 26.00 156.00
9.4.4.4 Ceiling Fan 6.00 set 2,500.00 15,000.00 750.00 4,500.00 19,500.00 195.00 1,170.00
9.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 3,400.00 255.00 1,020.00 4,420.00 44.20 265.20
9.4.4.6 Aircon Outlet 2.00 pc 270.00 540.00 81.00 162.00 702.00 7.02 42.12
9.4.4.7 Three Gang Switch 1.00 pc 215.00 215.00 64.50 64.50 279.50 2.80 16.77
9.4.4.8 Ceiling Fan Switch 2.00 pc 250.00 500.00 75.00 150.00 650.00 6.50 39.00

Sub-Total 59,301.00 17,790.30 77,091.30 770.91 4,625.48

9.5 OTHERS
9.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 0 10,200.00 10,200.00 10,200.00 102.00 612.00

Demolition of Existing tiles, fixtures, hauling of debris, etc 68.00 sq.m 0 0 150.00 10,200.00

Whiteboard Screen with Integrated Smart TV Enclosure,


9.5.2 1.00 set 50,275.00 50,275.00 15,082.50 15,082.50 65,357.50 653.58 3,921.45
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit 35,000.00 35,000.00

HIDE
RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Sliding laminated White board (1.2m x 2.4m) 1.00 pcs 5,000.00 5,000.00
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs 3,000.00 6,000.00
3/4" thk Class A Plyboard 3.00 pcs 1,400.00 4,200.00
Screws 100.00 pcs 0.75 75.00
9.5.3 Furniture & Appliances
9.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00 15,000.00 2,250.00 2,250.00 17,250.00 172.50 1,035.00
Professor's Desk 1.00 pc 7,500.00 7,500.00 -
hide Ergonomic chair 1.00 pc 2,500.00 2,500.00 -
Podium 1.00 pc 5,000.00 5,000.00 -
9.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 102,000.00 15,300.00 30,600.00 132,600.00 1,326.00 7,956.00
2 HP Inverter Window type Aircon Unit 2.00 units 49,000.00 98,000.00 -
hide
Angle Bar Frame 2.00 sets 2,000.00 4,000.00 -
9.5.3.3 PVC Student Armchair 50.00 pc 950.00 47,500.00 142.50 7,125.00 54,625.00 546.25 3,277.50

Sub-Total 214,775.00 65,257.50 280,032.50 2,800.33 16,801.95

DOORS AND WINDOWS (WITH COMPLETE


9.6
ACCESSORIES)
9.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00 38,440.00 5,766.00 11,532.00 49,972.00 499.72 2,998.32
1.00m x 2.10m Steel Door w/ viewing glass 2.00 pcs 15,500.00 31,000.00 -
Door knob 2.00 set 1,500.00 3,000.00 -
Flat wall enamel 2.00 gals 580.00 1,160.00 -
QDE 2.00 gals 600.00 1,200.00 -
HIDE Paint thinner 2.00 gals 250.00 500.00 -
SPot putty 2.00 gals 630.00 1,260.00 -
Sand paper 10.00 pcs 15.00 150.00 -
Baby roller 2.00 pcs 60.00 120.00 -
Cotton rugs 1.00 kgs 50.00 50.00 -
9.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 48,000.00 3,600.00 14,400.00 62,400.00 624.00 3,744.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

9.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 22,400.00 1,680.00 6,720.00 29,120.00 291.20 1,747.20

Sub-Total 108,840.00 32,652.00 141,492.00 1,414.92 8,489.52

TOTAL ITEM 9 542,305.27 163,516.58 705,821.84 7,058.22 42,349.31

10.0 LECTURE ROOM (THIRD FLOOR)


10.1 FLOOR FINISHES
10.1.1 600 x 600 Homogenous Granite Tiles 63.00 m² 1,028.00 64,764.00 308.40 19,429.20 84,193.20 841.93 5,051.59
HIDE 600 x 600 Homogenous Granite Tiles 192.00 pcs 280.00 53,760.00 -
HIDE Cement 46.00 bag 240.00 11,040.00 -
10.1.2 Tile Adhesive 43.75 bag 250.00 10,937.50 75.00 3,281.25 14,218.75 142.19 853.13
10.1.3 Tile Grout 4.38 kg 70.00 306.60 21.00 91.98 398.58 3.99 23.91
10.1.4 Vinyl Adhesive 1.00 gal 650.00 650.00 195.00 195.00 845.00 8.45 50.70
10.1.5 150 x 900 Vinyl tiles 10.00 m² 891.00 8,910.00 267.30 2,673.00 11,583.00 115.83 694.98
HIDE 150 x 900 Vinyl tiles 81.00 pcs 110.00 8,910.00

Sub-Total 85,568.10 25,670.43 111,238.53 1,112.39 6,674.31

10.2 PAINTING
10.2.1 Semi Gloss Latex 14.00 gal 695.00 9,730.00 208.50 2,919.00 12,649.00 126.49 758.94
10.2.2 Flat Latex 5.00 gal 480.00 2,400.00 144.00 720.00 3,120.00 31.20 187.20

10.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 1,730.00 1,730.00 519.00 519.00 2,249.00 22.49 134.94

Boral Compound 1.00 bags 600.00 600.00


Patching Compound 1.00 bags 550.00 550.00
Mesh Tape 1.00 rolls 180.00 180.00
Paint Roller 1.00 pcs 50.00 50.00
HIDE

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total
HIDE
Baby Roller 1.00 pcs 70.00 70.00
Sand Paper 10.00 pcs 15.00 150.00
Paint Brush 1.00 pcs 80.00 80.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 13,860.00 4,158.00 18,018.00 180.18 1,081.08

10.3 CEILING WORKS


10.3.1 9mm thk Gypsum Board on Metal Furring 21.00 m² 125.71 2,640.00 37.71 792.00 3,432.00 34.32 205.92
HIDE 9mm thk Gypsum Board 8.00 pcs 330.00 2,640.00 -
10.3.2 Metal Double Furring 103.28 m 33.31 3,440.00 9.99 1,032.00 4,472.00 44.72 268.32
Double furring 18.00 pcs 140.00 2,520.00 -
HIDE
Threaded rod 8.00 pcs 115.00 920.00 -
10.3.3 Wall Angle 18.33 m 36.55 670.00 10.97 201.00 871.00 8.71 52.26
Wall angle 7.00 pcs 50.00 350.00 -
HIDE
Expansion shield 40.00 pcs 8.00 320.00 -
10.3.4 Carrying Channel 71.00 m 23.00 1,633.00 6.90 489.90 2,122.90 21.23 127.37
10.3.5 W-Clamps/Clips 142.00 pc 3.50 497.00 1.05 149.10 646.10 6.46 38.77
10.3.6 Blind rivets(1/8) 35.50 box 350.00 12,425.00 105.00 3,727.50 16,152.50 161.53 969.15
10.3.7 Black Screws 630.00 pc 0.75 472.50 0.23 141.75 614.25 6.14 36.86
10.3.8 T-Runner (White) 325.00 m 13.08 4,250.00 3.92 1,275.00 5,525.00 55.25 331.50
Main tee 12" 25.00 pcs 110.00 2,750.00 -
HIDE Cross tee 4' 25.00 pcs 40.00 1,000.00 -
Cross tee 2' 25.00 pcs 20.00 500.00 -
10.3.9 Wall Angle (White) 28.28 m 10.50 296.94 3.15 89.08 386.02 3.86 23.16
10.3.10 600 x 600 acoustic board on T-Runner 50.00 m² 456.00 22,800.00 136.80 6,840.00 29,640.00 296.40 1,778.40
HIDE 600 x 600 acoustic board on T-Runner 152.00 pcs 150.00 22,800.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Sub-Total 49,124.44 14,737.33 63,861.77 638.62 3,831.71

10.4 ELECTRICAL WORKS AND FIXTURES


10.4.1 Conduits
10.4.1.1 15mm dia PVC (Lighting) 120.00 m 25.00 3,000.00 7.50 900.00 3,900.00 39.00 234.00
10.4.1.2 15mm dia PVC (Power Lines) 120.00 m 25.00 3,000.00 7.50 900.00 3,900.00 39.00 234.00
10.4.2 Wires and Cables (Ground Floor Toilet Only)
10.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00 6,720.00 8.40 2,016.00 8,736.00 87.36 524.16
10.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00 9,120.00 11.40 2,736.00 11,856.00 118.56 711.36
10.4.3 Others
10.4.3.1 Junction and Utility Box 60.00 pc 33.00 1,980.00 9.90 594.00 2,574.00 25.74 154.44
Junction boxes w/ cover 36.00 pcs 35.00 1,260.00
hide
Utility Boxes 24.00 pcs 30.00 720.00
10.4.4 Electrical fixtures
10.4.4.1 Pinlight (100mm dia) with 7W LED 6.00 set 850.00 5,100.00 255.00 1,530.00 6,630.00 66.30 397.80
10.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 4.00 set 2,000.00 8,000.00 600.00 2,400.00 10,400.00 104.00 624.00
10.4.4.3 Emergency Light 1.00 set 2,000.00 2,000.00 600.00 600.00 2,600.00 26.00 156.00
10.4.4.4 Ceiling Fans 3.00 set 2,500.00 7,500.00 750.00 2,250.00 9,750.00 97.50 585.00
10.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 3,400.00 255.00 1,020.00 4,420.00 44.20 265.20
10.4.4.6 Aircon Outlet 2.00 pc 270.00 540.00 81.00 162.00 702.00 7.02 42.12
10.4.4.7 Three Gang Switch 1.00 pc 215.00 215.00 64.50 64.50 279.50 2.80 16.77
10.4.4.8 Ceiling Fan Switch 3.00 pc 250.00 750.00 75.00 225.00 975.00 9.75 58.50

Sub-Total 51,325.00 15,397.50 66,722.50 667.23 4,003.35

10.5 OTHERS
10.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 0 9,450.00 9,450.00 9,450.00 94.50 567.00

Demolition of Existing tiles, fixtures, hauling of debris, etc 63.00 sq.m 0 0 150.00 9,450.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Whiteboard Screen with Integrated Smart TV Enclosure


10.5.2 1.00 set 50,275.00 50,275.00 15,082.50 15,082.50 65,357.50 653.58 3,921.45
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit 35,000.00 35,000.00
Sliding laminated White board (1.2m x 2.4m) 1.00 pcs 5,000.00 5,000.00
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs 3,000.00 6,000.00
3/4" thk Class A Plyboard 3.00 pcs 1,400.00 4,200.00
Screws 100.00 pcs 0.75 75.00
10.5.3 Furniture & Appliances
10.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00 15,000.00 2,250.00 2,250.00 17,250.00 172.50 1,035.00
Professor's Desk 1.00 pc 7,500.00 7,500.00 -
hide Ergonomic chair 1.00 pc 2,500.00 2,500.00 -
Podium 1.00 pc 5,000.00 5,000.00 -
10.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00 153,000.00 15,300.00 45,900.00 198,900.00 1,989.00 11,934.00
2 HP Inverter Window type Aircon Unit 3.00 sets 49,000.00 147,000.00 -
hide
Angle Bar Frame 3.00 sets 2,000.00 6,000.00 -
10.5.3.3 Student Armchair 30.00 pc 950.00 28,500.00 142.50 4,275.00 32,775.00 327.75 1,966.50

Sub-Total 246,775.00 76,957.50 323,732.50 3,237.33 19,423.95

DOORS AND WINDOWS (WITH COMPLETE


10.6
ACCESSORIES)

10.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00 38,440.00 5,766.00 11,532.00 49,972.00 499.72 2,998.32
1.00m x 2.10m Steel Door w/ viewing glass 2.00 pcs 15,500.00 31,000.00 -
Door knob 2.00 set 1,500.00 3,000.00 -
Flat wall enamel 2.00 gals 580.00 1,160.00 -
QDE 2.00 gals 600.00 1,200.00 -
HIDE Paint thinner 2.00 gals 250.00 500.00 -
SPot putty 2.00 gals 630.00 1,260.00 -

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
HIDE Unit Cost
Unit Cost Total

Sand paper 10.00 pcs 15.00 150.00 -


Baby roller 2.00 pcs 60.00 120.00 -
Cotton rugs 1.00 kgs 50.00 50.00 -
10.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 48,000.00 3,600.00 14,400.00 62,400.00 624.00 3,744.00
10.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 22,400.00 1,680.00 6,720.00 29,120.00 291.20 1,747.20

Sub-Total 108,840.00 32,652.00 141,492.00 1,414.92 8,489.52

TOTAL ITEM 10 555,492.54 169,572.76 725,065.30 7,250.65 43,503.92

11.0 OPENINGS & PATHWAY TO ADJACENT BUILDINGS


11.1 ACCESS PATHWAY (to Library)
11.1.1 Demolition Works of existing including hauling 1.00 lot 0 0 5,785.50 5,785.50 5,785.50 57.86 347.13

Demolition Works of existing including hauling(existing walls) 38.57 sq.m 0 0 150.00 5,785.50

11.1.2 Site clearing, Soil preparation 60.00 m² 0 0 600.00 36,000.00 36,000.00 360.00 2,160.00
11.1.3 Burrow Fill & compaction 15.00 m³ 0 0 600.00 9,000.00 9,000.00 90.00 540.00
11.1.4 Concreting 15.00 m³ 4,100.00 61,500.00 1,230.00 18,450.00 79,950.00 799.50 4,797.00
11.1.5 10mm dia Reinforcing Bars 1,200.00 kg 42.00 50,400.00 12.60 15,120.00 65,520.00 655.20 3,931.20
11.1.6 Formworks 60.00 m² 221.42 13,285.05 66.43 3,985.52 17,270.57 172.71 1,036.23
12mm formply 11.00 pcs 690.00 7,590.00
2"x2"x10' good lumber 98.90 bd.ft. 50.00 4,945.05
CWN 5.00 kgs 80.00 400.00
GI tie wire #16 5.00 kgs 70.00 350.00
11.1.7 Railings and Balusters 26.00 m² 1,560.00 40,560.00 468.00 12,168.00 52,728.00 527.28 3,163.68
11.1.8 Roll-up Door 1.00 set 85,000.00 85,000.00 25,500.00 25,500.00 110,500.00 1,105.00 6,630.00
11.1.9 Paver blocks 250.00 m² 400.00 100,000.00 120.00 30,000.00 130,000.00 1,300.00 7,800.00
hide Y-shaped Paver Blocks (16 pcs/sq.m) 4,000.00 pcs 25.00 100,000.00 -
11.1.10 Wall & Slab Soffit Painting Works 200.00 m² 118.23 23,645.00 35.47 7,093.50 30,738.50 307.39 1,844.31

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

Flat Latex Paint 10.00 gals 480.00 4,800.00


Semi-gloss Latex Paint 21.00 gals 695.00 14,595.00
Boral Compound 2.00 bags 600.00 1,200.00
Patching Compound 2.00 bags 550.00 1,100.00
Mesh Tape 6.00 rolls 180.00 1,080.00
Paint Roller 3.00 pcs 50.00 150.00
Baby Roller 3.00 pcs 70.00 210.00
Sand Paper 20.00 pcs 15.00 300.00
Paint Brush 2.00 pcs 80.00 160.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 374,390.05 163,102.52 537,492.57 5,374.93 32,249.55

11.2 ACCESS PATHWAY (to Pond)


11.2.1 Demolition Works of existing including hauling 1.00 lot 0 0 2,250.00 2,250.00 2,250.00 22.50 135.00
Demolition Works of existing including hauling 15.00 sq.m 0 0 150.00 2,250.00
11.2.2 Site clearing, Soil preparation 60.00 m² 0 0 600.00 36,000.00 36,000.00 360.00 2,160.00
11.2.3 Burrow Fill & Compaction 15.00 m³ 0 0 600.00 9,000.00 9,000.00 90.00 540.00
11.2.4 Concreting 12.00 m³ 4,100.00 49,200.00 1,230.00 14,760.00 63,960.00 639.60 3,837.60
11.2.5 10mm dia Reinforcing Bars 960.00 kg 42.00 40,320.00 12.60 12,096.00 52,416.00 524.16 3,144.96
11.2.6 Formworks 50.00 m² 223.26 11,163.00 66.98 3,348.90 14,511.90 145.12 870.71
12mm formply 10.00 pcs 690.00 6,900.00
2"x2"x10' good lumber 73.26 bd.ft. 50.00 3,663.00
CWN 4.00 kgs 80.00 320.00
GI tie wire #16 4.00 kgs 70.00 280.00
11.2.7 Railings and Balusters 26.00 m² 1,560.00 40,560.00 468.00 12,168.00 52,728.00 527.28 3,163.68
11.2.8 Roll-up Door 1.00 set 85,000.00 85,000.00 25,500.00 25,500.00 110,500.00 1,105.00 6,630.00
11.2.9 Paver blocks 250.00 m² 400.00 100,000.00 120.00 30,000.00 130,000.00 1,300.00 7,800.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

HIDE Y-shaped Paver Blocks (16 pcs/sq.m) 4,000.00 pcs 25.00 100,000.00 -
11.2.10 Wall & Slab Soffit Painting Works 200.00 m² 107.50 21,500.00 32.25 6,450.00 27,950.00 279.50 1,677.00
Flat Latex Paint 10.00 gals 480.00 4,800.00
Semi-gloss Latex Paint 20.00 gals 695.00 13,900.00
Boral Compound 2.00 bags 600.00 1,200.00
Patching Compound 1.00 bags 550.00 550.00
Mesh Tape 1.00 rolls 180.00 180.00
Paint Roller 3.00 pcs 50.00 150.00
Baby Roller 3.00 pcs 70.00 210.00
Sand Paper 20.00 pcs 15.00 300.00
Paint Brush 2.00 pcs 80.00 160.00
Rugs 1.00 kgs 50.00 50.00

Sub-Total 347,743.00 151,572.90 499,315.90 4,993.16 29,958.95

TOTAL ITEM 11 722,133.05 314,675.42 ### 10,368.08 62,208.51

AMOUNT IN FIGURES ### ### ### 412,808.20 ###

AMOUNT IN WORDS FORTY-SEVEN MILLION SIX HUNDRED SEVENTY-FOUR THOUSAND THREE HUNDRED SIXTY-ONE PESOS AND

Submitted By:

RICHARD B. SORIANO

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Material Cost
Item No. Work Description Quantity Unit Labor and
Labor &
Equipment Total OCM PROFIT
Equipment
Unit Cost
Unit Cost Total

General Manager
R.B. SORIANO CONSTRUCTION
Date: 01 October 2019

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1 October 2019

Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

(8) (9) (10) (11) (12)

0 55,000.00 3,850.00 58,850.00 58,850.00


0 110,000.00 7,700.00 117,700.00 117,700.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

0 165,000.00 11,550.00 176,550.00 176,550.00

0 55,000.00 3,850.00 58,850.00 58,850.00

0 385,000.00 26,950.00 411,950.00

11,760.00 179,760.00 12,583.20 192,343.20 171.74


1,120.00 17,120.00 1,198.40 18,318.40 114.49
7,840.00 119,840.00 8,388.80 128,228.80 114.49
18,112.50 276,862.50 19,380.38 296,242.88 515.21
24,369.80 372,509.80 26,075.69 398,585.49 967.44
1,638.00 25,038.00 1,752.66 26,790.66 1,339.53
2,548.00 38,948.00 2,726.36 41,674.36 148.84
67,388.30 ### 72,105.48 ###

37,800.00 577,800.00 40,446.00 618,246.00 6,182.46


17,766.00 271,566.00 19,009.62 290,575.62 6,182.46
7,560.00 115,560.00 8,089.20 123,649.20 6,182.46
32,508.00 496,908.00 34,783.56 531,691.56 6,182.46
55,944.00 855,144.00 59,860.08 915,004.08 6,182.46

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

21,924.00 335,124.00 23,458.68 358,582.68 6,182.46


59,346.00 907,146.00 63,500.22 970,646.22 6,182.46
4,939.20 75,499.20 5,284.94 80,784.14 5,770.30
3,780.00 57,780.00 4,044.60 61,824.60 6,182.46
58,590.00 895,590.00 62,691.30 958,281.30 6,182.46
7,182.00 109,782.00 7,684.74 117,466.74 6,182.46

307,339.20 ### 328,852.94 ###

24,204.18 369,978.18 25,898.47 395,876.65 65.49

2,462.46 37,640.46 2,634.83 40,275.29 65.49

19,239.22 294,085.22 20,585.97 314,671.19 65.49

6,803.16 103,991.16 7,279.38 111,270.54 62.51

5,045.04 77,117.04 5,398.19 82,515.23 65.49

3,516.24 53,748.24 3,762.38 57,510.62 62.51

72.62 1,110.02 77.70 1,187.72 62.51

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

81,697.62 1,248,806.42 87,416.45 1,336,222.87 65.49

27,633.06 422,391.06 29,567.37 451,958.43 62.51

47,899.85 732,183.45 51,252.84 783,436.29 65.49

11,198.46 171,176.46 11,982.35 183,158.81 62.51

518.70 7,928.70 555.01 8,483.71 282.79

2,388.75 36,513.75 2,555.96 39,069.71 195.35

365.82 5,591.82 391.43 5,983.25 5,983.25

46,678.09 713,507.89 49,945.55 763,453.44 62.51

10,831.55 165,567.95 11,589.76 177,157.70 62.51

5,809.44 88,801.44 6,216.10 95,017.54 62.51

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

5,541.90 84,711.90 5,929.83 90,641.73 62.51

9,459.45 144,594.45 10,121.61 154,716.06 818.60


37,149.84 567,861.84 39,750.33 607,612.17 62.51

5,733.00 87,633.00 6,134.31 93,767.31 62.51

4,395.30 67,185.30 4,702.97 71,888.27 62.51

27,391.00 418,691.00 29,308.37 447,999.37 104.19

386,034.74 ### 413,057.17 ###

1,383.02 21,140.42 1,479.83 22,620.25 314.17

6,365.13 97,295.58 6,810.69 104,106.27 525.79

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

505.87 7,732.57 541.28 8,273.85 574.57

2,058.33 31,463.03 2,202.41 33,665.44 543.69

3,089.72 47,228.62 3,306.00 50,534.63 474.24

1,301.94 19,901.04 1,393.07 21,294.11 509.92

5,123.35 78,314.00 5,481.98 83,795.98 741.29

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

374.92 5,730.92 401.16 6,132.08 608.34

2,411.96 36,868.46 2,580.79 39,449.25 547.91

15,524.01 237,295.56 16,610.69 253,906.25 522.44

3,877.37 59,268.42 4,148.79 63,417.21 528.48

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

42,015.61 642,238.61 44,956.70 687,195.31

43,869.28 670,573.28 46,940.13 717,513.41 448.45

43,698.20 667,958.20 46,757.07 714,715.27 649.74

1,561.56 23,869.56 1,670.87 25,540.43 22.33

4,586.40 70,106.40 4,907.45 75,013.85 357.21


1,183.00 18,083.00 1,265.81 19,348.81 967.44

6,956.04 106,328.04 7,442.96 113,771.00 62.51

1,159.34 17,721.34 1,240.49 18,961.83 104.19

20,475.00 312,975.00 21,908.25 334,883.25 744.19

33,852.00 517,452.00 36,221.64 553,673.64 59.53

157,340.82 ### 168,354.68 ###

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

226,800.00 3,466,800.00 242,676.00 3,709,476.00 3,709,476.00

3,822.00 58,422.00 4,089.54 62,511.54 10,418.59


4,368.00 66,768.00 4,673.76 71,441.76 71,441.76

3,339.70 51,049.70 3,573.48 54,623.18 54,623.18

238,329.70 ### 255,012.78 ###

262,080.00 4,006,080.00 280,425.60 4,286,505.60 4,871.03

1,747.20 26,707.20 1,869.50 28,576.70 32.47

4,422.60 67,602.60 4,732.18 72,334.78 311.79

5,915.00 90,415.00 6,329.05 96,744.05 96,744.05

8,062.60 123,242.60 8,626.98 131,869.58 1,098.91

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

800.80 12,240.80 856.86 13,097.66 13,097.66

3,531.71 53,984.71 3,778.93 57,763.64 825.19

1,640.73 25,079.73 1,755.58 26,835.31 439.92

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

198.74 3,037.94 212.66 3,250.60 116.09


339.43 5,188.43 363.19 5,551.62 355.19

1,028.30 15,718.30 1,100.28 16,818.58 90.42

14,514.50 221,864.50 15,530.52 237,395.02 818.60


5,059.60 77,339.60 5,413.77 82,753.37 1,034.42
294.84 4,506.84 315.48 4,822.32 1,205.58

8,080.80 123,520.80 8,646.46 132,167.26 714.42


9,880.78 151,034.78 10,572.43 161,607.21 161,607.21

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

13,791.05 210,806.05 14,756.42 225,562.47 902.25

9,100.00 139,100.00 9,737.00 148,837.00 595.35

350,488.68 ### 375,022.89 ###

1,548,937.05 ### ### ###

73,815.00 1,128,315.00 78,982.05 1,207,297.05 1,097.54

12,922.00 197,522.00 13,826.54 211,348.54 192.14

21,840.00 333,840.00 23,368.80 357,208.80 178.60

5,077.80 77,617.80 5,433.25 83,051.05 184.56

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

113,654.80 ### 121,610.64 ###

10,760.75 164,485.75 11,514.00 175,999.75 818.60

10,119.20 154,679.20 10,827.54 165,506.74 1,034.42


3,931.20 60,091.20 4,206.38 64,297.58 714.42
546.00 8,346.00 584.22 8,930.22 893.02
6,552.00 100,152.00 7,010.64 107,162.64 714.42
159.25 2,434.25 170.40 2,604.65 520.93
54.60 834.60 58.42 893.02 446.51

6,069.70 92,779.70 6,494.58 99,274.28 99,274.28

38,192.70 583,802.70 40,866.19 624,668.89

2,933.84 44,845.84 3,139.21 47,985.05 773.95

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

606.97 9,277.97 649.46 9,927.43 342.33


211.12 3,227.12 225.90 3,453.02 119.07

345.80 5,285.80 370.01 5,655.81 1,413.95


52.78 806.78 56.47 863.25 215.81
1,741.74 26,623.74 1,863.66 28,487.40 647.44
195.20 2,983.70 208.86 3,192.55 1,064.18
702.98 10,745.48 752.18 11,497.66 766.51
250.25 3,825.25 267.77 4,093.02 163.72
430.43 6,579.43 460.56 7,039.99 320.00

3,272.54 50,023.14 3,501.62 53,524.76 1,911.60

345.80 5,285.80 370.01 5,655.81 282.79


2,912.00 44,512.00 3,115.84 47,627.84 1,700.99

662.48 10,126.48 708.85 10,835.33 193.49

129.68 1,982.18 138.75 2,120.93 37.21


81.90 1,251.90 87.63 1,339.53 44.65
18.02 275.42 19.28 294.70 32.74
27.30 417.30 29.21 446.51 44.65
409.50 6,259.50 438.17 6,697.67 1,116.28
2,730.00 41,730.00 2,921.10 44,651.10 11,162.78
1,183.00 18,083.00 1,265.81 19,348.81 19,348.81
4,095.00 62,595.00 4,381.65 66,976.65 66,976.65

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

23,338.32 356,742.82 24,972.00 381,714.81

1,460.55 22,325.55 1,562.79 23,888.34 111.63


5,754.84 87,966.84 6,157.68 94,124.52 178.60
2,493.86 38,120.36 2,668.42 40,788.78 647.44
147.78 2,258.98 158.13 2,417.11 302.14
60.06 918.06 64.26 982.32 245.58
168.35 2,573.35 180.13 2,753.48 275.35
1,774.50 27,124.50 1,898.72 29,023.22 386.98
503.23 7,692.23 538.46 8,230.69 587.91
485.94 7,427.94 519.96 7,947.90 662.32
17.29 264.29 18.50 282.79 28.28
4.55 69.55 4.87 74.42 37.21
196.56 3,004.56 210.32 3,214.88 44.65
53.24 813.74 56.96 870.70 66.98
61.15 934.75 65.43 1,000.18 71.44
5.73 87.63 6.13 93.77 93.77
15.83 242.03 16.94 258.98 86.33
92.82 1,418.82 99.32 1,518.14 126.51
5,621.07 85,922.07 6,014.54 91,936.61 3,170.23
191.10 2,921.10 204.48 3,125.58 260.46
22.75 347.75 24.34 372.09 186.05
345.80 5,285.80 370.01 5,655.81 1,413.95

18,562.18 283,736.18 19,861.53 303,597.71 41.67

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,670.21 25,530.41 1,787.13 27,317.54 56.56


697.97 10,668.97 746.83 11,415.80 96.74
945.31 14,449.71 1,011.48 15,461.19 145.86
585.59 8,951.09 626.58 9,577.66 245.58
245.70 3,755.70 262.90 4,018.60 334.88
6,775.86 103,573.86 7,250.17 110,824.03 759.07
60,545.94 925,487.94 64,784.16 990,272.10 1,160.93

2,377.28 36,338.48 2,543.69 38,882.18 41.67


888.71 13,584.51 950.92 14,535.42 56.56
615.16 9,403.16 658.22 10,061.38 96.74
1,096.10 16,754.60 1,172.82 17,927.42 245.58
188.83 2,886.33 202.04 3,088.37 617.67
136.50 2,086.50 146.06 2,232.56 1,116.28

2,402.40 36,722.40 2,570.57 39,292.97 49.12

1,137.50 17,387.50 1,217.13 18,604.63 18,604.63


773.50 11,823.50 827.65 12,651.15 12,651.15

1,137.50 17,387.50 1,217.13 18,604.63 18,604.63

1,137.50 17,387.50 1,217.13 18,604.63 18,604.63

1,137.50 17,387.50 1,217.13 18,604.63 18,604.63

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,137.50 17,387.50 1,217.13 18,604.63 18,604.63

1,524.25 23,299.25 1,630.95 24,930.20 24,930.20

1,524.25 23,299.25 1,630.95 24,930.20 24,930.20

1,524.25 23,299.25 1,630.95 24,930.20 24,930.20

1,774.50 27,124.50 1,898.72 29,023.22 29,023.22

10,010.00 153,010.00 10,710.70 163,720.70 163,720.70

20,475.00 312,975.00 21,908.25 334,883.25 334,883.25

10,465.00 159,965.00 11,197.55 171,162.55 171,162.55

3,712.80 56,752.80 3,972.70 60,725.50 1,265.11


4,368.00 66,768.00 4,673.76 71,441.76 2,976.74
22,750.00 347,750.00 24,342.50 372,092.50 744.19
15,288.00 233,688.00 16,358.16 250,046.16 3,572.09

3,867.50 59,117.50 4,138.23 63,255.73 1,265.11

218.40 3,338.40 233.69 3,572.09 1,786.04


286.65 4,381.65 306.72 4,688.37 156.28
450.45 6,885.45 481.98 7,367.43 245.58

221,910.78 ### 237,444.53 ###

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

778.05 11,893.05 832.51 12,725.56 37.21


109.20 1,669.20 116.84 1,786.04 11.91
47.78 730.28 51.12 781.39 5.21
163.80 2,503.80 175.27 2,679.07 26.79
273.00 4,173.00 292.11 4,465.11 44.65
1,478.75 22,603.75 1,582.26 24,186.01 96.74
573.30 8,763.30 613.43 9,376.73 133.95
1,979.25 30,254.25 2,117.80 32,372.05 1,294.88

3,423.42 52,329.42 3,663.06 55,992.48 81.86


11,162.97 170,633.97 11,944.38 182,578.35 1,294.88
1,683.50 25,733.50 1,801.35 27,534.85 27,534.85
1,592.50 24,342.50 1,703.98 26,046.48 26,046.48
5,915.00 90,415.00 6,329.05 96,744.05 96,744.05

1,719.90 26,289.90 1,840.29 28,130.19 28,130.19

30,900.42 472,334.92 33,063.44 505,398.36

4,829.37 73,820.37 5,167.43 78,987.80 2,723.72


5,608.51 85,730.11 6,001.11 91,731.22 1,433.30

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

5,257.98 80,371.98 5,626.04 85,998.02 1,433.30


3,902.08 59,646.08 4,175.23 63,821.31 952.56
1,470.56 22,478.56 1,573.50 24,052.06 751.63
777.14 11,879.14 831.54 12,710.68 453.95
164.53 2,514.93 176.04 2,690.97 336.37
141.96 2,169.96 151.90 2,321.86 290.23
4,288.38 65,550.88 4,588.56 70,139.44 215.81

223.86 3,421.86 239.53 3,661.39 1,220.46


118.76 1,815.26 127.07 1,942.32 647.44
15.02 229.52 16.07 245.58 245.58
60.06 918.06 64.26 982.32 327.44
341.25 5,216.25 365.14 5,581.39 111.63
60.97 931.97 65.24 997.21 498.60
266.18 4,068.68 284.81 4,353.48 483.72
272.09 4,159.09 291.14 4,450.23 171.16
912.73 13,951.73 976.62 14,928.35 126.51
1,681.68 25,705.68 1,799.40 27,505.08 89.30
147.42 2,253.42 157.74 2,411.16 1,205.58
39.59 605.09 42.36 647.44 647.44
395.85 6,050.85 423.56 6,474.41 647.44
118.76 1,815.26 127.07 1,942.32 647.44
1,425.06 21,783.06 1,524.81 23,307.87 647.44
105.11 1,606.61 112.46 1,719.07 573.02
560.56 8,568.56 599.80 9,168.36 573.02
105.11 1,606.61 112.46 1,719.07 573.02
840.84 12,852.84 899.70 13,752.54 573.02
51.87 792.87 55.50 848.37 424.19

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

30.03 459.03 32.13 491.16 491.16


477.75 7,302.75 511.19 7,813.94 520.93
401.31 6,134.31 429.40 6,563.71 364.65
95.55 1,460.55 102.24 1,562.79 260.46
34.13 521.63 36.51 558.14 186.05
121.03 1,850.03 129.50 1,979.53 1,979.53
222.95 3,407.95 238.56 3,646.51 729.30
50.05 765.05 53.55 818.60 818.60
50.51 772.01 54.04 826.05 275.35
50.51 772.01 54.04 826.05 275.35
12.29 187.79 13.14 200.93 200.93
31.40 479.90 33.59 513.49 171.16
25.94 396.44 27.75 424.19 141.40
21.84 333.84 23.37 357.21 178.60
837.20 12,797.20 895.80 13,693.00 119.07
740.74 11,322.74 792.59 12,115.33 81.86
102.38 1,564.88 109.54 1,674.42 111.63
31.40 479.90 33.59 513.49 171.16
1,801.80 27,541.80 1,927.93 29,469.73 818.60
2,675.40 40,895.40 2,862.68 43,758.08 520.93
256.62 3,922.62 274.58 4,197.20 349.77
128.31 1,961.31 137.29 2,098.60 349.77
319.41 4,882.41 341.77 5,224.18 290.23
237.51 3,630.51 254.14 3,884.65 215.81
439.53 6,718.53 470.30 7,188.83 171.16
49.14 751.14 52.58 803.72 133.95
24.57 375.57 26.29 401.86 133.95
69.62 1,064.12 74.49 1,138.60 126.51

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,881.88 28,765.88 2,013.61 30,779.49 327.44

1,506.96 23,034.96 1,612.45 24,647.41 513.49

1,428.70 21,838.70 1,528.71 23,367.41 23,367.41


4,681.95 71,566.95 5,009.69 76,576.64 10,939.52
286.65 4,381.65 306.72 4,688.37 1,562.79
477.75 7,302.75 511.19 7,813.94 1,116.28
503.23 7,692.23 538.46 8,230.69 1,175.81
3,006.64 45,958.64 3,217.10 49,175.74 7,025.11
4,140.50 63,290.50 4,430.34 67,720.84 9,674.41

19,110.00 292,110.00 20,447.70 312,557.70 22,325.55

1,992.90 30,462.90 2,132.40 32,595.30 10,865.10


9,079.53 138,787.03 9,715.09 148,502.12 148,502.12

880.52 13,459.32 942.15 14,401.47 14,401.47

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

680.68 10,404.68 728.33 11,133.01 92.78

165,025.00 2,522,525.00 176,576.75 2,699,101.75 2,699,101.75

6,842.50 104,592.50 7,321.48 111,913.98 111,913.98

3,312.04 50,626.84 3,543.88 54,170.71 54,170.71

268,359.53 ### 287,144.70 ###

696,356.54 ### 745,101.50 ###

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

703.15 10,748.15 752.37 11,500.52 11,500.52

4,504.50 68,854.50 4,819.82 73,674.32 566.73

1,971.74 30,139.49 2,109.76 32,249.26 372.09


55.23 844.20 59.09 903.29 104.19

7,234.62 110,586.34 7,741.04 118,327.38

20,816.25 318,191.25 22,273.39 340,464.64 22,697.64

4,914.00 75,114.00 5,257.98 80,371.98 6,697.67


25,252.50 386,002.50 27,020.18 413,022.68 27,534.85
948.68 14,501.18 1,015.08 15,516.26 1,034.42
655.20 10,015.20 701.06 10,716.26 714.42

965.06 14,751.56 1,032.61 15,784.16 15,784.16

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

53,551.68 818,575.68 57,300.30 875,875.98

3,643.64 55,695.64 3,898.69 59,594.33 773.95


3,934.84 60,146.84 4,210.28 64,357.12 342.33

1,815.45 27,750.45 1,942.53 29,692.98 1,413.95


316.68 4,840.68 338.85 5,179.53 215.81
2,612.61 39,935.61 2,795.49 42,731.10 647.44
390.39 5,967.39 417.72 6,385.11 1,064.18
1,124.76 17,192.76 1,203.49 18,396.25 766.51
390.39 5,967.39 417.72 6,385.11 163.72
763.04 11,663.54 816.45 12,479.98 320.00
1,228.50 18,778.50 1,314.50 20,093.00 200.93

194.51 2,973.26 208.13 3,181.39 37.21


102.38 1,564.88 109.54 1,674.42 37.21
30.71 469.46 32.86 502.32 37.21
34.13 521.63 36.51 558.14 37.21
409.50 6,259.50 438.17 6,697.67 1,116.28

1,365.00 20,865.00 1,460.55 22,325.55 3,720.93

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

3,822.00 58,422.00 4,089.54 62,511.54 10,418.59


6,825.00 104,325.00 7,302.75 111,627.75 7,441.85
8,954.40 136,874.40 9,581.21 146,455.61 12,204.63

8,918.00 136,318.00 9,542.26 145,860.26 20,837.18


990.08 15,134.08 1,059.39 16,193.47 16,193.47

47,866.00 731,666.00 51,216.62 782,882.62

750.75 11,475.75 803.30 12,279.05 45.48

750.75 11,475.75 803.30 12,279.05 45.48

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,375.92 21,031.92 1,472.23 22,504.15 41.67


364.00 5,564.00 389.48 5,953.48 49.61

2,552.55 39,017.55 2,731.23 41,748.78 1,265.11


1,092.00 16,692.00 1,168.44 17,860.44 2,976.74
2,184.00 33,384.00 2,336.88 35,720.88 5,953.48
135.14 2,065.64 144.59 2,210.23 245.58

9,205.11 140,706.61 9,849.46 150,556.07

117,857.41 ### 126,107.42 ###

6,258.36 95,663.52 6,696.45 102,359.97 1,530.04

1,056.97 16,156.47 1,130.95 17,287.42 372.09


29.62 452.77 31.69 484.46 104.19
810.81 12,393.81 867.57 13,261.38 1,326.14

59.15 904.15 63.29 967.44 967.44

8,214.91 125,570.72 8,789.95 134,360.67

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

822.19 12,567.69 879.74 13,447.42 1,034.42


305.76 4,673.76 327.16 5,000.92 714.42

289.38 4,423.38 309.64 4,733.02 4,733.02

1,417.33 21,664.83 1,516.54 23,181.36

660.66 10,098.66 706.91 10,805.57 185.25

1,026.03 15,683.53 1,097.85 16,781.37 58.50

97.37 1,488.37 104.19 1,592.56 52.13

1,706.25 26,081.25 1,825.69 27,906.94 621.12

309.40 4,729.40 331.06 5,060.46 17.33

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

25.62 391.57 27.41 418.98 15.63


216.12 3,303.60 231.25 3,534.85 34.23
65.78 1,005.44 70.38 1,075.82 5.21
657.70 10,053.45 703.74 10,757.19 520.93
119.43 1,825.58 127.79 1,953.37 1.12

4,884.35 74,660.85 5,226.26 79,887.11

389.48 5,953.48 416.74 6,370.22 53.09

389.48 5,953.48 416.74 6,370.22 53.09

611.52 9,347.52 654.33 10,001.85 41.67


829.92 12,685.92 888.01 13,573.93 56.56

180.18 2,754.18 192.79 2,946.97 49.12

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,005.55 15,370.55 1,075.94 16,446.49 1,265.11


1,092.00 16,692.00 1,168.44 17,860.44 2,976.74
182.00 2,782.00 194.74 2,976.74 2,976.74
1,365.00 20,865.00 1,460.55 22,325.55 3,720.93
309.40 4,729.40 331.06 5,060.46 1,265.11
49.14 751.14 52.58 803.72 401.86
19.57 299.07 20.93 320.00 320.00
45.50 695.50 48.69 744.19 372.09

6,468.74 98,879.24 6,921.55 105,800.78

702.45 10,737.45 751.62 11,489.07 11,489.07

4,575.03 69,932.53 4,895.28 74,827.80 74,827.80

1,207.50 18,457.50 1,292.03 19,749.53 19,749.53

9,282.00 141,882.00 9,931.74 151,813.74 75,906.87

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

3,441.38 52,603.88 3,682.27 56,286.15 1,250.80

19,208.35 293,613.35 20,552.93 314,166.28

3,301.48 50,465.48 3,532.58 53,998.06 26,999.03

4,368.00 66,768.00 4,673.76 71,441.76 17,860.44


2,038.40 31,158.40 2,181.09 33,339.49 8,334.87

9,707.88 148,391.88 10,387.43 158,779.31

49,901.55 762,780.86 53,394.66 816,175.52

4,074.07 62,275.07 4,359.25 66,634.32 1,332.69

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

295.75 4,520.75 316.45 4,837.20 967.44

4,369.82 66,795.82 4,675.71 71,471.53

1,454.64 22,235.14 1,556.46 23,791.59 1,034.42


436.80 6,676.80 467.38 7,144.18 714.42

430.43 6,579.43 460.56 7,039.99 7,039.99

2,321.87 35,491.37 2,484.40 37,975.76

870.87 13,311.87 931.83 14,243.70 187.42

1,026.03 15,683.53 1,097.85 16,781.37 44.90

119.21 1,822.21 127.55 1,949.76 55.92

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

159.07 2,431.47 170.20 2,601.67 34.23


48.41 740.01 51.80 791.81 5.21
477.75 7,302.75 511.19 7,813.94 520.93
155.61 2,378.61 166.50 2,545.11 1.12

2,856.95 43,670.45 3,056.93 46,727.38

389.48 5,953.48 416.74 6,370.22 53.09

389.48 5,953.48 416.74 6,370.22 53.09

611.52 9,347.52 654.33 10,001.85 41.67


829.92 12,685.92 888.01 13,573.93 56.56

184.28 2,816.78 197.17 3,013.95 50.23

1,237.60 18,917.60 1,324.23 20,241.83 1,265.11


1,456.00 22,256.00 1,557.92 23,813.92 2,976.74

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

728.00 11,128.00 778.96 11,906.96 2,976.74


910.00 13,910.00 973.70 14,883.70 3,720.93
618.80 9,458.80 662.12 10,120.92 1,265.11
38.22 584.22 40.90 625.12 156.28
91.00 1,391.00 97.37 1,488.37 372.09

7,484.30 114,402.80 8,008.20 122,410.99

1,228.50 18,778.50 1,314.50 20,093.00 1,116.28


1,268.54 19,390.54 1,357.34 20,747.88 82.72

127.40 1,947.40 136.32 2,083.72 520.93


104.42 1,596.17 111.73 1,707.90 1.12
525.00 8,025.00 561.75 8,586.75 8,586.75

10,626.00 162,426.00 11,369.82 173,795.82 43,448.96

28,980.00 442,980.00 31,008.60 473,988.60 1,579.96


6,552.00 100,152.00 7,010.64 107,162.64 17,860.44
1,456.00 22,256.00 1,557.92 23,813.92 5,953.48

50,867.86 777,551.61 54,428.61 831,980.23

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

6,605.69 100,972.69 7,068.09 108,040.78 27,010.19

2,038.40 31,158.40 2,181.09 33,339.49 8,334.87

8,644.09 132,131.09 9,249.18 141,380.27

76,544.88 ### 81,903.02 ###

11,787.05 180,173.45 12,612.14 192,785.59 1,530.04

1,990.63 30,428.13 2,129.97 32,558.09 372.09


55.74 851.99 59.64 911.63 104.19
118.30 1,808.30 126.58 1,934.88 967.44
1,621.62 24,787.62 1,735.13 26,522.75 1,326.14

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

15,573.33 238,049.48 16,663.46 254,712.94

252.98 3,866.98 270.69 4,137.67 1,034.42


305.76 4,673.76 327.16 5,000.92 714.42

217.95 3,331.45 233.20 3,564.65 3,564.65

776.69 11,872.19 831.05 12,703.24

600.60 9,180.60 642.64 9,823.24 192.61

677.04 10,349.04 724.43 11,073.47 44.15

85.54 1,307.54 91.53 1,399.07 48.97

261.63 3,999.13 279.94 4,279.06 34.23

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

79.63 1,217.13 85.20 1,302.32 5.21


796.25 12,171.25 851.99 13,023.24 520.93
104.42 1,596.17 111.73 1,707.90 1.12
541.45 8,276.45 579.35 8,855.80 18.41

32.88 502.58 35.18 537.76 15.63


3,084.90 47,154.90 3,300.84 50,455.74 681.83

6,264.33 95,754.78 6,702.83 102,457.61

323.60 4,946.40 346.25 5,292.64 52.93

323.60 4,946.40 346.25 5,292.64 52.93

509.60 7,789.60 545.27 8,334.87 41.67


691.60 10,571.60 740.01 11,311.61 56.56

180.18 2,754.18 192.79 2,946.97 49.12

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,701.70 26,011.70 1,820.82 27,832.52 1,265.11


1,456.00 22,256.00 1,557.92 23,813.92 2,976.74
182.00 2,782.00 194.74 2,976.74 2,976.74
1,820.00 27,820.00 1,947.40 29,767.40 3,720.93
309.40 4,729.40 331.06 5,060.46 1,265.11
49.14 751.14 52.58 803.72 401.86
19.11 292.11 20.45 312.56 156.28
91.00 1,391.00 97.37 1,488.37 372.09

7,656.92 117,041.52 8,192.91 125,234.43

1,323.00 20,223.00 1,415.61 21,638.61 21,638.61

4,575.03 69,932.53 4,895.28 74,827.80 74,827.80

1,207.50 18,457.50 1,292.03 19,749.53 19,749.53

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

9,282.00 141,882.00 9,931.74 151,813.74 75,906.87

23,908.50 365,458.50 25,582.10 391,040.60 43,448.96

40,296.03 615,953.53 43,116.75 659,070.27

3,305.12 50,521.12 3,536.48 54,057.60 27,028.80

4,368.00 66,768.00 4,673.76 71,441.76 17,860.44


2,038.40 31,158.40 2,181.09 33,339.49 8,334.87

9,711.52 148,447.52 10,391.33 158,838.85

80,278.81 ### 85,898.33 ###

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

11,787.05 180,173.45 12,612.14 192,785.59 1,530.04

1,990.63 30,428.13 2,129.97 32,558.09 372.09


55.74 851.99 59.64 911.63 104.19
118.30 1,808.30 126.58 1,934.88 967.44
1,621.62 24,787.62 1,735.13 26,522.75 1,326.14

15,573.33 238,049.48 16,663.46 254,712.94

1,770.86 27,068.86 1,894.82 28,963.68 1,034.42


262.08 4,006.08 280.43 4,286.51 714.42

254.80 3,894.80 272.64 4,167.44 4,167.44

2,287.74 34,969.74 2,447.88 37,417.62

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

570.57 8,721.57 610.51 9,332.08 186.64

723.45 11,058.45 774.09 11,832.54 48.12

78.81 1,204.61 84.32 1,288.93 45.58

313.95 4,798.95 335.93 5,134.88 34.23


95.55 1,460.55 102.24 1,562.79 5.21
2,388.75 36,513.75 2,555.96 39,069.71 520.93
102.38 1,564.88 109.54 1,674.42 1.12
696.15 10,641.15 744.88 11,386.03 17.52

38.22 584.22 40.90 625.12 15.63


4,163.25 63,638.25 4,454.68 68,092.93 680.93

9,171.07 140,186.37 9,813.05 149,999.42

455.00 6,955.00 486.85 7,441.85 37.21


455.00 6,955.00 486.85 7,441.85 37.21

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,019.20 15,579.20 1,090.54 16,669.74 41.67


1,383.20 21,143.20 1,480.02 22,623.22 56.56

270.73 4,138.23 289.68 4,427.90 49.20

1,856.40 28,376.40 1,986.35 30,362.75 1,265.11


2,184.00 33,384.00 2,336.88 35,720.88 2,976.74
364.00 5,564.00 389.48 5,953.48 2,976.74
2,730.00 41,730.00 2,921.10 44,651.10 3,720.93
309.40 4,729.40 331.06 5,060.46 1,265.11
73.71 1,126.71 78.87 1,205.58 401.86
39.13 598.13 41.87 640.00 320.00
15.02 229.52 16.07 245.58 245.58
113.75 1,738.75 121.71 1,860.46 372.09

11,268.53 172,247.53 12,057.33 184,304.86

1,323.00 20,223.00 1,415.61 21,638.61 21,638.61

4,575.03 69,932.53 4,895.28 74,827.80 74,827.80

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,207.50 18,457.50 1,292.03 19,749.53 19,749.53

13,923.00 212,823.00 14,897.61 227,720.61 75,906.87

74,592.00 1,140,192.00 79,813.44 1,220,005.44 10,991.04

95,620.53 ### 102,313.96 ###

3,511.69 53,678.69 3,757.51 57,436.20 28,718.10

6,552.00 100,152.00 7,010.64 107,162.64 17,860.44


3,057.60 46,737.60 3,271.63 50,009.23 8,334.87

13,121.29 200,568.29 14,039.78 214,608.07

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

147,042.49 ### 157,335.46 ###

6,361.26 97,236.46 6,806.55 104,043.02 1,530.04

1,074.26 16,420.76 1,149.45 17,570.21 372.09


30.07 459.59 32.17 491.76 104.19
53.24 813.74 56.96 870.70 967.44
730.73 11,169.73 781.88 11,951.61 1,327.96

8,249.55 126,100.27 8,827.02 134,927.29

948.68 14,501.18 1,015.08 15,516.26 1,034.42


436.80 6,676.80 467.38 7,144.18 714.42

215.22 3,289.72 230.28 3,520.00 3,520.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,600.69 24,467.69 1,712.74 26,180.43

330.33 5,049.33 353.45 5,402.78 180.09

513.70 7,852.20 549.65 8,401.85 56.95

69.16 1,057.16 74.00 1,131.16 51.63

159.07 2,431.47 170.20 2,601.67 34.23


48.41 740.01 51.80 791.81 5.21
1,210.30 18,500.30 1,295.02 19,795.32 520.93
61.43 938.93 65.72 1,004.65 1.12
324.87 4,965.87 347.61 5,313.48 17.77

25.92 396.25 27.74 423.98 15.63


1,911.00 29,211.00 2,044.77 31,255.77 679.47

4,654.18 71,142.51 4,979.98 76,122.48

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

200.20 3,060.20 214.21 3,274.41 37.21


200.20 3,060.20 214.21 3,274.41 37.21

448.45 6,854.85 479.84 7,334.69 41.67


608.61 9,303.01 651.21 9,954.22 56.56

180.18 2,754.18 192.79 2,946.97 49.12

696.15 10,641.15 744.88 11,386.03 1,265.11


1,092.00 16,692.00 1,168.44 17,860.44 2,976.74
182.00 2,782.00 194.74 2,976.74 2,976.74
1,365.00 20,865.00 1,460.55 22,325.55 3,720.93
309.40 4,729.40 331.06 5,060.46 1,265.11
49.14 751.14 52.58 803.72 401.86
19.57 299.07 20.93 320.00 320.00
45.50 695.50 48.69 744.19 372.09

5,396.39 82,487.69 5,774.14 88,261.83

714.00 10,914.00 763.98 11,677.98 11,677.98

4,575.03 69,932.53 4,895.28 74,827.80 74,827.80

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,207.50 18,457.50 1,292.03 19,749.53 19,749.53

9,282.00 141,882.00 9,931.74 151,813.74 75,906.87

3,823.75 58,448.75 4,091.41 62,540.16 1,250.80

19,602.28 299,634.78 20,974.43 320,609.21

3,498.04 53,470.04 3,742.90 57,212.94 28,606.47

4,368.00 66,768.00 4,673.76 71,441.76 17,860.44

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

2,038.40 31,158.40 2,181.09 33,339.49 8,334.87

9,904.44 151,396.44 10,597.75 161,994.19

49,407.53 755,229.37 52,866.06 808,095.43

5,893.52 90,086.72 6,306.07 96,392.79 1,530.04

995.31 15,214.06 1,064.98 16,279.05 372.09


27.90 426.48 29.85 456.33 104.19
59.15 904.15 63.29 967.44 967.44
810.81 12,393.81 867.57 13,261.38 1,326.14

7,786.70 119,025.23 8,331.77 127,356.99

885.43 13,534.43 947.41 14,481.84 1,034.42


218.40 3,338.40 233.69 3,572.09 714.42

157.43 2,406.43 168.45 2,574.88 2,574.88

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

1,261.26 19,279.26 1,349.55 20,628.81

240.24 3,672.24 257.06 3,929.30 187.11

313.04 4,785.04 334.95 5,119.99 49.57

60.97 931.97 65.24 997.21 54.40

148.60 2,271.50 159.01 2,430.51 34.23


45.23 691.33 48.39 739.72 5.21
1,130.68 17,283.18 1,209.82 18,493.00 520.93
43.00 657.25 46.01 703.25 1.12
386.75 5,911.75 413.82 6,325.57 19.46

27.02 413.04 28.91 441.96 15.63


2,074.80 31,714.80 2,220.04 33,934.84 678.70

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

4,470.32 68,332.10 4,783.25 73,115.34

273.00 4,173.00 292.11 4,465.11 37.21


273.00 4,173.00 292.11 4,465.11 37.21

611.52 9,347.52 654.33 10,001.85 41.67


829.92 12,685.92 888.01 13,573.93 56.56

180.18 2,754.18 192.79 2,946.97 49.12

464.10 7,094.10 496.59 7,590.69 1,265.11


728.00 11,128.00 778.96 11,906.96 2,976.74
182.00 2,782.00 194.74 2,976.74 2,976.74
682.50 10,432.50 730.28 11,162.78 3,720.93
309.40 4,729.40 331.06 5,060.46 1,265.11
49.14 751.14 52.58 803.72 401.86
19.57 299.07 20.93 320.00 320.00
68.25 1,043.25 73.03 1,116.28 372.09

4,670.58 71,393.08 4,997.52 76,390.59

661.50 10,111.50 707.81 10,819.31 10,819.31

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

4,575.03 69,932.53 4,895.28 74,827.80 74,827.80

1,207.50 18,457.50 1,292.03 19,749.53 19,749.53

13,923.00 212,823.00 14,897.61 227,720.61 75,906.87

2,294.25 35,069.25 2,454.85 37,524.10 1,250.80

22,661.28 346,393.78 24,247.56 370,641.34

3,498.04 53,470.04 3,742.90 57,212.94 28,606.47

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

4,368.00 66,768.00 4,673.76 71,441.76 17,860.44


2,038.40 31,158.40 2,181.09 33,339.49 8,334.87

9,904.44 151,396.44 10,597.75 161,994.19

50,754.57 775,819.87 54,307.39 830,127.26

404.99 6,190.49 433.33 6,623.82 6,623.82

2,520.00 38,520.00 2,696.40 41,216.40 686.94


630.00 9,630.00 674.10 10,304.10 686.94
5,596.50 85,546.50 5,988.26 91,534.76 6,102.32
4,586.40 70,106.40 4,907.45 75,013.85 62.51
1,208.94 18,479.50 1,293.57 19,773.07 329.55

3,690.96 56,418.96 3,949.33 60,368.29 2,321.86


7,735.00 118,235.00 8,276.45 126,511.45 126,511.45
9,100.00 139,100.00 9,737.00 148,837.00 595.35

2,151.70 32,890.20 2,302.31 35,192.51 175.96

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost

Overhead, Total Direct Cost per


Contingencies Value
& Indirect Total Cost Unit of Work
, Added Tax
Cost Item
Miscellaneous
& Profit

37,624.48 575,117.04 40,258.19 615,375.24

157.50 2,407.50 168.53 2,576.03 2,576.03

2,520.00 38,520.00 2,696.40 41,216.40 686.94


630.00 9,630.00 674.10 10,304.10 686.94
4,477.20 68,437.20 4,790.60 73,227.80 6,102.32
3,669.12 56,085.12 3,925.96 60,011.08 62.51
1,015.83 15,527.73 1,086.94 16,614.67 332.29

3,690.96 56,418.96 3,949.33 60,368.29 2,321.86


7,735.00 118,235.00 8,276.45 126,511.45 126,511.45
9,100.00 139,100.00 9,737.00 148,837.00 595.35

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
To : TARLAC SATE UNIVERSITY Date: 01 October 2019
Re : INVITATION TO BID NO. INFRA 024-08-2019A

BILL OF QUANTITIES

Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

(1) (2) (3) (4) (5) (7) (8) (9) (10) (11)
1.0 GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization 1.00 lot 50,000.00 5,000.00 55,000.00 0 55,000.00 3,850.00 58,850.00
1.2 Temporary Facilities 1.00 lot 100,000.00 10,000.00 110,000.00 0 110,000.00 7,700.00 117,700.00
1.2.1 Temporary Barracks & Storage
1.2.2 Temporary Fence/Board-up
1.2.3 Temporary Water and Power Consumption
1.3 Permits and Licenses 1.00 lot 150,000.00 15,000.00 165,000.00 0 165,000.00 11,550.00 176,550.00
1.3.1 Building Permit Processing, fire clearance, occupancy
1.3.2 Licenses and certifications - operations
1.4 Safety and Health 1.00 lot 50,000.00 5,000.00 55,000.00 0 55,000.00 3,850.00 58,850.00
1.4.1 Pre-cautionary Signages, Safety nets & Scaffolds

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

1.4.2 Personal Protective Equipment for personnel

Sub-Total 385,000.00 0 385,000.00 26,950.00 411,950.00

SUNSHADING, STAIRCASE, ELEVATOR, PUMP RM,


2.0
CISTERN
2.1 EARTHWORKS
2.1.1 Site Clearing (including cutting & bases) 1,120.00 m² 0 150.00 168,000.00 11,760.00 179,760.00 12,583.20 192,343.20
2.1.2 Demolition (selected windows and plantboxes) see dwgs 160.00 m² 0 100.00 16,000.00 1,120.00 17,120.00 1,198.40 18,318.40
2.1.3 Layout and Staking 1,120.00 m² 0 100.00 112,000.00 7,840.00 119,840.00 8,388.80 128,228.80
2.1.4 Excavation 575.00 m³ 0 450.00 258,750.00 18,112.50 276,862.50 19,380.38 296,242.88
2.1.5 Backfill / Compaction 412.00 m³ 650.00 195.00 348,140.00 24,369.80 372,509.80 26,075.69 398,585.49
2.1.6 Gravelbase Coarse 20.00 m³ 900.00 270.00 23,400.00 1,638.00 25,038.00 1,752.66 26,790.66
2.1.7 Soil Poisoning 280.00 m² 100.00 30.00 36,400.00 2,548.00 38,948.00 2,726.36 41,674.36
Sub-Total 962,690.00 67,388.30 1,030,078.30 72,105.48 1,102,183.78

2.2 CONCRETING
2.2.1 Footing 100.00 m³ 4,500.00 900.00 540,000.00 37,800.00 577,800.00 40,446.00 618,246.00
2.2.2 Shear Wall of Elevator Shaft & Cistern Tank 47.00 m³ 4,500.00 900.00 253,800.00 17,766.00 271,566.00 19,009.62 290,575.62
2.2.3 Pedestal, Encasement & Pull Box (Service Entrance) 20.00 m³ 4,500.00 900.00 108,000.00 7,560.00 115,560.00 8,089.20 123,649.20
2.2.4 Columns 86.00 m³ 4,500.00 900.00 464,400.00 32,508.00 496,908.00 34,783.56 531,691.56
2.2.5 Beams 148.00 m³ 4,500.00 900.00 799,200.00 55,944.00 855,144.00 59,860.08 915,004.08
2.2.6 Roof Beams 58.00 m³ 4,500.00 900.00 313,200.00 21,924.00 335,124.00 23,458.68 358,582.68
2.2.7 Suspended Slab. Ledges, Staircase 157.00 m³ 4,500.00 900.00 847,800.00 59,346.00 907,146.00 63,500.22 970,646.22
2.2.8 Slab on fill 14.00 m³ 4,200.00 840.00 70,560.00 4,939.20 75,499.20 5,284.94 80,784.14
2.2.9 Concrete Trellis (Sunshading) 10.00 m³ 4,500.00 900.00 54,000.00 3,780.00 57,780.00 4,044.60 61,824.60
2.2.10 Vertical Fins (Sunshading) 155.00 m³ 4,500.00 900.00 837,000.00 58,590.00 895,590.00 62,691.30 958,281.30
2.2.11 Stiffener Columns 19.00 m³ 4,500.00 900.00 102,600.00 7,182.00 109,782.00 7,684.74 117,466.74

Sub-Total 4,390,560.00 307,339.20 4,697,899.20 328,852.94 5,026,752.14

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg 44.00 13.20 345,774.00 24,204.18 369,978.18 25,898.47 395,876.65
2.3.1.2 16mm Dia Rebar 615.00 kg 44.00 13.20 35,178.00 2,462.46 37,640.46 2,634.83 40,275.29
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg 44.00 13.20 274,846.00 19,239.22 294,085.22 20,585.97 314,671.19
2.3.2.2 12mm Dia Rebar 1,780.00 kg 42.00 12.60 97,188.00 6,803.16 103,991.16 7,279.38 111,270.54
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg 44.00 13.20 72,072.00 5,045.04 77,117.04 5,398.19 82,515.23
2.3.3.2 10mm Dia Rebar 920.00 kg 42.00 12.60 50,232.00 3,516.24 53,748.24 3,762.38 57,510.62
2.3.3.3 12mm dia rebar 19.00 kg 42.00 12.60 1,037.40 72.62 1,110.02 77.70 1,187.72
2.3.4 Beam Rebars
2.3.4.1 20mm Dia Rebar 20,404.00 kg 44.00 13.20 1,167,108.80 81,697.62 1,248,806.42 87,416.45 1,336,222.87
2.3.4.2 10mm Dia Rebar 7,230.00 kg 42.00 12.60 394,758.00 27,633.06 422,391.06 29,567.37 451,958.43
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg 44.00 13.20 684,283.60 47,899.85 732,183.45 51,252.84 783,436.29
2.3.5.2 10mm Dia Rebar 2,930.00 kg 42.00 12.60 159,978.00 11,198.46 171,176.46 11,982.35 183,158.81
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m 190.00 57.00 7,410.00 518.70 7,928.70 555.01 8,483.71
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m 131.25 39.38 34,125.00 2,388.75 36,513.75 2,555.96 39,069.71
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot 4,020.00 1,206.00 5,226.00 365.82 5,591.82 391.43 5,983.25
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg 42.00 12.60 666,829.80 46,678.09 713,507.89 49,945.55 763,453.44
2.3.7.2 10mm dia rebar 2,834.00 kg 42.00 12.60 154,736.40 10,831.55 165,567.95 11,589.76 177,157.70
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg 42.00 12.60 82,992.00 5,809.44 88,801.44 6,216.10 95,017.54
2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg 42.00 12.60 79,170.00 5,541.90 84,711.90 5,929.83 90,641.73
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m² 550.00 165.00 135,135.00 9,459.45 144,594.45 10,121.61 154,716.06

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

2.3.10.2 12mm dia Rebar 9,720.00 kg 42.00 12.60 530,712.00 37,149.84 567,861.84 39,750.33 607,612.17
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg 42.00 12.60 81,900.00 5,733.00 87,633.00 6,134.31 93,767.31
2.3.11.2 10mm Dia Rebar 1,150.00 kg 42.00 12.60 62,790.00 4,395.30 67,185.30 4,702.97 71,888.27
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg 70.00 21.00 391,300.00 27,391.00 418,691.00 29,308.37 447,999.37

Sub-Total 5,514,782.00 386,034.74 5,900,816.74 413,057.17 6,313,873.91

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m² 211.08 63.33 19,757.40 1,383.02 21,140.42 1,479.83 22,620.25
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m² 353.27 105.98 90,930.45 6,365.13 97,295.58 6,810.69 104,106.27
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m² 386.04 115.81 7,226.70 505.87 7,732.57 541.28 8,273.85
2.4.4 Columns 61.92 m² 365.29 109.59 29,404.70 2,058.33 31,463.03 2,202.41 33,665.44
2.4.5 Beams 106.56 m² 318.63 95.59 44,138.90 3,089.72 47,228.62 3,306.00 50,534.63
2.4.6 Roof Beams 41.76 m² 342.60 102.78 18,599.10 1,301.94 19,901.04 1,393.07 21,294.11
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m² 498.06 149.42 73,190.65 5,123.35 78,314.00 5,481.98 83,795.98
2.4.8 Slab on fill 10.08 m² 408.73 122.62 5,356.00 374.92 5,730.92 401.16 6,132.08
2.4.9 Concrete Trellis (Sunshading) 72.00 m² 368.13 110.44 34,456.50 2,411.96 36,868.46 2,580.79 39,449.25
2.4.10 Vertical Fins (Sunshading) 486.00 m² 351.02 105.30 221,771.55 15,524.01 237,295.56 16,610.69 253,906.25
2.4.11 Stiffener Columns 120.00 m² 355.07 106.52 55,391.05 3,877.37 59,268.42 4,148.79 63,417.21

Sub-Total 600,223.00 42,015.61 642,238.61 44,956.70 687,195.31

2.5 MASONRY & WATERPROOFING


2.5.1 Integral Waterproofing (decks, cistern & elevator pit) 1,600.00 kg 301.30 90.39 626,704.00 43,869.28 670,573.28 46,940.13 717,513.41

2.5.2 Cementitious waterproofing lining (decks, plantbox & cistern) 1,100.00 m² 436.55 130.96 624,260.00 43,698.20 667,958.20 46,757.07 714,715.27

2.5.3 6" thk CHB parapet Walls 1,144.00 pc 15.00 4.50 22,308.00 1,561.56 23,869.56 1,670.87 25,540.43
2.5.4 mortar and Plastering
2.5.4.1 Cement 210.00 bag 240.00 72.00 65,520.00 4,586.40 70,106.40 4,907.45 75,013.85

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

2.5.4.2 Sand 20.00 m³ 650.00 195.00 16,900.00 1,183.00 18,083.00 1,265.81 19,348.81

2.5.5 10mm dia horiz and Vertical rebars for CHB and Deco Blocks 1,820.00 kg 42.00 12.60 99,372.00 6,956.04 106,328.04 7,442.96 113,771.00

2.5.6 #16 Gi Tie Wire 182.00 kg 70.00 21.00 16,562.00 1,159.34 17,721.34 1,240.49 18,961.83

2.5.7 Heavy Duty Cement-based Adhesive for Decorative Blocks 450.00 bag 500.00 150.00 292,500.00 20,475.00 312,975.00 21,908.25 334,883.25

2.5.8 Decorative Blocks (Sunshading) 250 x 250 x 88 9,300.00 pc 40.00 12.00 483,600.00 33,852.00 517,452.00 36,221.64 553,673.64

Sub-Total 2,247,726.00 157,340.82 2,405,066.82 168,354.68 2,573,421.50

2.6 EQUIPMENT

Machine roomless elevator Equipment 1500 kg, 3 stops (3 front


openings) 1m/s, steel hoist Silver brushed car Walls, w/ gray
Black Granite Car Floor, Silver brushed skirting, mirror on walls,
2.6.1 1.00 set 2,700,000.00 540,000.00 3,240,000.00 226,800.00 3,466,800.00 242,676.00 3,709,476.00
LED direct light 7.6kW, 31A-43A, 3P, 230V 60Hz incl reqd
electrical outlets, breakers and exhaust fans, incl I-Beams or
any strucl steel reqd for installation

2.6.2 Electric Water Heater (complete with telephone Shower) 6.00 set 7,000.00 2,100.00 54,600.00 3,822.00 58,422.00 4,089.54 62,511.54
2.6.3 2HP Electric Submersible Pump (at Elevator pit) 1.00 set 48,000.00 14,400.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
Booster Pump (1HP) (40PSI) (65% efficiency) w/ foot valve w/
2.6.4 1.00 set 36,700.00 11,010.00 47,710.00 3,339.70 51,049.70 3,573.48 54,623.18
Bladder Tank (30gal) w/ complete accessories

Sub-Total 3,404,710.00 238,329.70 3,643,039.70 255,012.78 3,898,052.48

2.7 FINISHING WORKS


Engineer weatherproof wood planks (25mm thk)- 150mm x
2.7.1 880.00 m² 3,272.73 981.82 3,744,000.00 262,080.00 4,006,080.00 280,425.60 4,286,505.60
900mm
2.7.1.1 Cement Glue for Floor Plank 880.00 m² 21.82 6.55 24,960.00 1,747.20 26,707.20 1,869.50 28,576.70
2.7.2 Non-Skid Rubberized Painted Finish (Hallways) 232.00 m² 209.48 62.84 63,180.00 4,422.60 67,602.60 4,732.18 72,334.78

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Built-up Acrylic LED Lighted Signage with 9mm thk Acrylic


2.7.3 1.00 set 65,000.00 19,500.00 84,500.00 5,915.00 90,415.00 6,329.05 96,744.05
built-up letters, LED lighting, mounting and installation

Elevator & Pump Room Roof, Rib Type G.I. (0.5mm), prepainted
2.7.4 120.00 m² 738.33 221.50 115,180.00 8,062.60 123,242.60 8,626.98 131,869.58
Longspan incl flushings; w/ insulation
2.7.5 Roof Works Miscellaneous (Tuxscrews, Silicon, blind rivets) 1.00 lot 8,800.00 2,640.00 11,440.00 800.80 12,240.80 856.86 13,097.66

2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m² 554.43 166.33 50,453.00 3,531.71 53,984.71 3,778.93 57,763.64

2.7.7 Balcony & Stair Handrails & railing (painted Finish)


2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m² 295.57 88.67 23,439.00 1,640.73 25,079.73 1,755.58 26,835.31
2.7.7.2 12mm Square Bar 28.00 m 78.00 23.40 2,839.20 198.74 3,037.94 212.66 3,250.60
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m 238.64 71.59 4,849.00 339.43 5,188.43 363.19 5,551.62
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m² 60.75 18.23 14,690.00 1,028.30 15,718.30 1,100.28 16,818.58
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal 550.00 165.00 207,350.00 14,514.50 221,864.50 15,530.52 237,395.02
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal 695.00 208.50 72,280.00 5,059.60 77,339.60 5,413.77 82,753.37
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal 810.00 243.00 4,212.00 294.84 4,506.84 315.48 4,822.32
2.7.9.4 Flat Latex Paint 185.00 gal 480.00 144.00 115,440.00 8,080.80 123,520.80 8,646.46 132,167.26
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot 108,580.00 32,574.00 141,154.00 9,880.78 151,034.78 10,572.43 161,607.21
2.7.10 uPVC Clear Transparent Rib Type Roof + misc. 250.00 m² 606.20 181.86 197,015.00 13,791.05 210,806.05 14,756.42 225,562.47
2.7.11 Paver blocks 250.00 m² 400.00 120.00 130,000.00 9,100.00 139,100.00 9,737.00 148,837.00

Sub-Total 5,006,981.20 350,488.68 5,357,469.88 375,022.89 5,732,492.78

3.0 GENERAL REPAIR & IMPROVEMENTS ON CAFA BUILDING


3.1 ROOFING AND EAVES SOFFIT
Replacement of delapidated roofing, (pre-painted longspan,
3.1.1 1,100.00 m 668.18 290.45 1,054,500.00 73,815.00 1,128,315.00 78,982.05 1,207,297.05
ribtype, G.I. 0.5mm thk)
3.1.2 Insulation (double sided aluminum) (w/ chicken wire) 1,100.00 m² 129.09 38.73 184,600.00 12,922.00 197,522.00 13,826.54 211,348.54
Replacement of Eaves Soffit - Spandrel (110mm wide), (pre-
3.1.3 2,000.00 m 120.00 36.00 312,000.00 21,840.00 333,840.00 23,368.80 357,208.80
painted G.I., 0.5mm thk) complete w/ misc.

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Spandrel Mouldings/Edging Wall Angles, complete w/


3.1.4 450.00 m 124.00 37.20 72,540.00 5,077.80 77,617.80 5,433.25 83,051.05
misc./silicon

Sub-Total 1,623,640.00 113,654.80 1,737,294.80 121,610.64 1,858,905.44

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal 550.00 165.00 153,725.00 10,760.75 164,485.75 11,514.00 175,999.75

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal 695.00 208.50 144,560.00 10,119.20 154,679.20 10,827.54 165,506.74
3.2.3 Flat Latex for Existing Ceiling 90.00 gal 480.00 144.00 56,160.00 3,931.20 60,091.20 4,206.38 64,297.58
3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal 600.00 180.00 7,800.00 546.00 8,346.00 584.22 8,930.22
3.2.5 Flat Latex Primer 150.00 gal 480.00 144.00 93,600.00 6,552.00 100,152.00 7,010.64 107,162.64
3.2.6 Metal Primer, rust Converters 5.00 gal 350.00 105.00 2,275.00 159.25 2,434.25 170.40 2,604.65
3.2.7 Paint Thinner 2.00 gal 300.00 90.00 780.00 54.60 834.60 58.42 893.02

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot 66,700.00 20,010.00 86,710.00 6,069.70 92,779.70 6,494.58 99,274.28

Sub-Total 545,610.00 38,192.70 583,802.70 40,866.19 624,668.89

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m 520.00 156.00 41,912.00 2,933.84 44,845.84 3,139.21 47,985.05
3.3.1.2 100mm Ø 29.00 m 230.00 69.00 8,671.00 606.97 9,277.97 649.46 9,927.43
3.3.1.3 50mm Ø 29.00 m 80.00 24.00 3,016.00 211.12 3,227.12 225.90 3,453.02
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc 950.00 285.00 4,940.00 345.80 5,285.80 370.01 5,655.81
3.3.2.2 Wye 100 x 100 4.00 pc 145.00 43.50 754.00 52.78 806.78 56.47 863.25
3.3.2.3 Elbow 90" x 100 44.00 pc 435.00 130.50 24,882.00 1,741.74 26,623.74 1,863.66 28,487.40
3.3.2.4 Elbow 45" x 200 3.00 pc 715.00 214.50 2,788.50 195.20 2,983.70 208.86 3,192.55
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc 515.00 154.50 10,042.50 702.98 10,745.48 752.18 11,497.66

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.3.2.6 Sanitary Tee 100 x 50 25.00 pc 110.00 33.00 3,575.00 250.25 3,825.25 267.77 4,093.02
3.3.2.7 P-Trap 100 22.00 pc 215.00 64.50 6,149.00 430.43 6,579.43 460.56 7,039.99
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc 1,284.36 385.31 46,750.60 3,272.54 50,023.14 3,501.62 53,524.76
3.3.3.2 Solvent / Adhesive 20.00 qt 190.00 57.00 4,940.00 345.80 5,285.80 370.01 5,655.81
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc 1,142.86 342.86 41,600.00 2,912.00 44,512.00 3,115.84 47,627.84
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56 m 130.00 39.00 9,464.00 662.48 10,126.48 708.85 10,835.33
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57 pc 25.00 7.50 1,852.50 129.68 1,982.18 138.75 2,120.93
3.3.4.2.2 25mm Tee 30 pc 30.00 9.00 1,170.00 81.90 1,251.90 87.63 1,339.53
3.3.4.2.3 25mm Coupling 9 pc 22.00 6.60 257.40 18.02 275.42 19.28 294.70
3.3.4.2.4 25mm Reducer 10 pc 30.00 9.00 390.00 27.30 417.30 29.21 446.51
3.3.4.2.5 25mm Gate Valve 6 pc 750.00 225.00 5,850.00 409.50 6,259.50 438.17 6,697.67
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4 set 7,500.00 2,250.00 39,000.00 2,730.00 41,730.00 2,921.10 44,651.10
3.3.4.5 1000L Polyethylene Water Tank 1 pc 13,000.00 3,900.00 16,900.00 1,183.00 18,083.00 1,265.81 19,348.81
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1 set 45,000.00 13,500.00 58,500.00 4,095.00 62,595.00 4,381.65 66,976.65

Sub-Total 333,404.50 23,338.32 356,742.82 24,972.00 381,714.81

3.4 ELECTRICAL WORKS & FIXTURES


3.4.1 Conduits
3.4.1.1 1/2" Ø PVC 214.00 pc 75.00 22.50 20,865.00 1,460.55 22,325.55 1,562.79 23,888.34
3.4.1.2 3/4" Ø PVC 527.00 pc 120.00 36.00 82,212.00 5,754.84 87,966.84 6,157.68 94,124.52
3.4.1.3 2 1/2" Ø PVC 63.00 pc 435.00 130.50 35,626.50 2,493.86 38,120.36 2,668.42 40,788.78
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set 203.00 60.90 2,111.20 147.78 2,258.98 158.13 2,417.11
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set 165.00 49.50 858.00 60.06 918.06 64.26 982.32
3.4.1.6 3/4" Ø EMT 10.00 pc 185.00 55.50 2,405.00 168.35 2,573.35 180.13 2,753.48
3.4.1.7 1" Ø EMT 75.00 pc 260.00 78.00 25,350.00 1,774.50 27,124.50 1,898.72 29,023.22
3.4.1.8 1 1/4" Ø EMT 14.00 pc 395.00 118.50 7,189.00 503.23 7,692.23 538.46 8,230.69

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.4.1.9 1 1/2" Ø EMT 12.00 pc 445.00 133.50 6,942.00 485.94 7,427.94 519.96 7,947.90
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc 19.00 5.70 247.00 17.29 264.29 18.50 282.79
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set 25.00 7.50 65.00 4.55 69.55 4.87 74.42
3.4.1.12 1" Ø EMT Coupling 72.00 pc 30.00 9.00 2,808.00 196.56 3,004.56 210.32 3,214.88
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set 45.00 13.50 760.50 53.24 813.74 56.96 870.70
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc 48.00 14.40 873.60 61.15 934.75 65.43 1,000.18
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set 63.00 18.90 81.90 5.73 87.63 6.13 93.77
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc 58.00 17.40 226.20 15.83 242.03 16.94 258.98
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set 85.00 25.50 1,326.00 92.82 1,418.82 99.32 1,518.14
3.4.1.18 2 1/2" Ø RSC 29.00 pc 2,130.00 639.00 80,301.00 5,621.07 85,922.07 6,014.54 91,936.61
3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc 175.00 52.50 2,730.00 191.10 2,921.10 204.48 3,125.58
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set 125.00 37.50 325.00 22.75 347.75 24.34 372.09
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc 950.00 285.00 4,940.00 345.80 5,285.80 370.01 5,655.81
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m 28.00 8.40 265,174.00 18,562.18 283,736.18 19,861.53 303,597.71
3.4.2.2 5.5mm2 THHN Cu 483.00 m 38.00 11.40 23,860.20 1,670.21 25,530.41 1,787.13 27,317.54
3.4.2.3 8.0mm2 THHN Cu 118.00 m 65.00 19.50 9,971.00 697.97 10,668.97 746.83 11,415.80
3.4.2.4 14mm2 THHN Cu 106.00 m 98.00 29.40 13,504.40 945.31 14,449.71 1,011.48 15,461.19
3.4.2.5 22mm2 THHN Cu 39.00 m 165.00 49.50 8,365.50 585.59 8,951.09 626.58 9,577.66
3.4.2.6 30mm2 THHN Cu 12.00 m 225.00 67.50 3,510.00 245.70 3,755.70 262.90 4,018.60
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m 510.00 153.00 96,798.00 6,775.86 103,573.86 7,250.17 110,824.03
3.4.2.8 125mm2 THHN Cu 853.00 m 780.00 234.00 864,942.00 60,545.94 925,487.94 64,784.16 990,272.10
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m 28.00 8.40 33,961.20 2,377.28 36,338.48 2,543.69 38,882.18
3.4.3.2 5.5mm2 Cu Grounding 257.00 m 38.00 11.40 12,695.80 888.71 13,584.51 950.92 14,535.42
3.4.3.3 8.0mm2 Cu Grounding 104.00 m 65.00 19.50 8,788.00 615.16 9,403.16 658.22 10,061.38
3.4.3.4 30mm2 Cu Grounding 73.00 m 165.00 49.50 15,658.50 1,096.10 16,754.60 1,172.82 17,927.42
3.4.3.5 60mm2 Cu Grounding 5.00 m 415.00 124.50 2,697.50 188.83 2,886.33 202.04 3,088.37
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc 750.00 225.00 1,950.00 136.50 2,086.50 146.06 2,232.56
3.4.4 Others

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.4.4.1 Junction and Utility Boxes 800.00 pc 33.00 9.90 34,320.00 2,402.40 36,722.40 2,570.57 39,292.97
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set 12,500.00 3,750.00 16,250.00 1,137.50 17,387.50 1,217.13 18,604.63
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set 8,500.00 2,550.00 11,050.00 773.50 11,823.50 827.65 12,651.15
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P
3.4.5.3 1.00 set 12,500.00 3,750.00 16,250.00 1,137.50 17,387.50 1,217.13 18,604.63
+ 2 Spare

3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00 3,750.00 16,250.00 1,137.50 17,387.50 1,217.13 18,604.63

3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00 3,750.00 16,250.00 1,137.50 17,387.50 1,217.13 18,604.63

3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set 12,500.00 3,750.00 16,250.00 1,137.50 17,387.50 1,217.13 18,604.63

3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set 16,750.00 5,025.00 21,775.00 1,524.25 23,299.25 1,630.95 24,930.20

90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.8 1.00 set 16,750.00 5,025.00 21,775.00 1,524.25 23,299.25 1,630.95 24,930.20
+ 2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.9 1.00 set 16,750.00 5,025.00 21,775.00 1,524.25 23,299.25 1,630.95 24,930.20
+ 2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-40AT,


3.4.5.10 1.00 set 19,500.00 5,850.00 25,350.00 1,774.50 27,124.50 1,898.72 29,023.22
2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set 110,000.00 33,000.00 143,000.00 10,010.00 153,010.00 10,710.70 163,720.70
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P + 100AT,
3.4.5.12 1.00 set 225,000.00 67,500.00 292,500.00 20,475.00 312,975.00 21,908.25 334,883.25
3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set 115,000.00 34,500.00 149,500.00 10,465.00 159,965.00 11,197.55 171,162.55
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set 850.00 255.00 53,040.00 3,712.80 56,752.80 3,972.70 60,725.50
3.4.6.2 Emergency Light 24.00 set 2,000.00 600.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
3.4.6.3 Strip Light (Cove Light) 500.00 m 500.00 150.00 325,000.00 22,750.00 347,750.00 24,342.50 372,092.50
3.4.6.4 36 W Up Light Garden Light 70.00 pc 2,400.00 720.00 218,400.00 15,288.00 233,688.00 16,358.16 250,046.16

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc 850.00 255.00 55,250.00 3,867.50 59,117.50 4,138.23 63,255.73

3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc 1,200.00 360.00 3,120.00 218.40 3,338.40 233.69 3,572.09
3.4.6.7 One Gang Switch 30.00 pc 105.00 31.50 4,095.00 286.65 4,381.65 306.72 4,688.37
3.4.6.8 Two gang Switch 30.00 pc 165.00 49.50 6,435.00 450.45 6,885.45 481.98 7,367.43

Sub-Total 3,170,154.00 221,910.78 3,392,064.78 237,444.53 3,629,509.31

3.5 FIRE ALARM WORKS & FIXTURES


3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes
3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m 25.00 7.50 11,115.00 778.05 11,893.05 832.51 12,725.56
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc 8.00 2.40 1,560.00 109.20 1,669.20 116.84 1,786.04
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc 3.50 1.05 682.50 47.78 730.28 51.12 781.39
3.5.1.4 15mm Ø St. Connector 100.00 pc 18.00 5.40 2,340.00 163.80 2,503.80 175.27 2,679.07
3.5.1.5 Utility Box 100.00 pc 30.00 9.00 3,900.00 273.00 4,173.00 292.11 4,465.11
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc 65.00 19.50 21,125.00 1,478.75 22,603.75 1,582.26 24,186.01
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc 90.00 27.00 8,190.00 573.30 8,763.30 613.43 9,376.73
3.5.1.8 Fire Alarm Pull Box 25.00 pc 870.00 261.00 28,275.00 1,979.25 30,254.25 2,117.80 32,372.05
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m 55.00 16.50 48,906.00 3,423.42 52,329.42 3,663.06 55,992.48
3.5.3 Smoke Detectors 141.00 set 870.00 261.00 159,471.00 11,162.97 170,633.97 11,944.38 182,578.35
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set 18,500.00 5,550.00 24,050.00 1,683.50 25,733.50 1,801.35 27,534.85
3.5.5 Monitoring Switches (6 zones) 1.00 set 17,500.00 5,250.00 22,750.00 1,592.50 24,342.50 1,703.98 26,046.48
3.5.6 Fire Alarm Check Valve 1.00 set 65,000.00 19,500.00 84,500.00 5,915.00 90,415.00 6,329.05 96,744.05
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot 18,900.00 5,670.00 24,570.00 1,719.90 26,289.90 1,840.29 28,130.19
Accessories, Solvents)

Sub-Total 441,434.50 30,900.42 472,334.92 33,063.44 505,398.36

3.6 FIRE PROTECTION/SPRINKLER SYSTEM

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.6.1 BI Pipe and Fittings


3.6.1.1 150mm Ø S40 BI Pipes 29.00 m 1,830.00 549.00 68,991.00 4,829.37 73,820.37 5,167.43 78,987.80
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m 963.00 288.90 80,121.60 5,608.51 85,730.11 6,001.11 91,731.22
3.6.1.3 80mm Ø S40 BI Pipes 60.00 m 963.00 288.90 75,114.00 5,257.98 80,371.98 5,626.04 85,998.02
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m 640.00 192.00 55,744.00 3,902.08 59,646.08 4,175.23 63,821.31
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m 505.00 151.50 21,008.00 1,470.56 22,478.56 1,573.50 24,052.06
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m 305.00 91.50 11,102.00 777.14 11,879.14 831.54 12,710.68
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m 226.00 67.80 2,350.40 164.53 2,514.93 176.04 2,690.97
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m 195.00 58.50 2,028.00 141.96 2,169.96 151.90 2,321.86
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m 145.00 43.50 61,262.50 4,288.38 65,550.88 4,588.56 70,139.44
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc 820.00 246.00 3,198.00 223.86 3,421.86 239.53 3,661.39
3.6.2.2 BI Tee welded type 100mm 3.00 pc 435.00 130.50 1,696.50 118.76 1,815.26 127.07 1,942.32
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc 165.00 49.50 214.50 15.02 229.52 16.07 245.58
3.6.2.4 BI Tee threaded type 50mm 3.00 pc 220.00 66.00 858.00 60.06 918.06 64.26 982.32
3.6.2.5 BI Tee threaded type 25mm 50.00 pc 75.00 22.50 4,875.00 341.25 5,216.25 365.14 5,581.39
3.6.2.6 BI Elbow welded type 150mm 2.00 pc 335.00 100.50 871.00 60.97 931.97 65.24 997.21
3.6.2.7 BI Elbow welded type 100mm 9.00 pc 325.00 97.50 3,802.50 266.18 4,068.68 284.81 4,353.48
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc 115.00 34.50 3,887.00 272.09 4,159.09 291.14 4,450.23
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc 85.00 25.50 13,039.00 912.73 13,951.73 976.62 14,928.35
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc 60.00 18.00 24,024.00 1,681.68 25,705.68 1,799.40 27,505.08
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc 810.00 243.00 2,106.00 147.42 2,253.42 157.74 2,411.16
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc 435.00 130.50 565.50 39.59 605.09 42.36 647.44
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc 435.00 130.50 5,655.00 395.85 6,050.85 423.56 6,474.41
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc 435.00 130.50 1,696.50 118.76 1,815.26 127.07 1,942.32
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc 435.00 130.50 20,358.00 1,425.06 21,783.06 1,524.81 23,307.87
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc 385.00 115.50 1,501.50 105.11 1,606.61 112.46 1,719.07
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc 385.00 115.50 8,008.00 560.56 8,568.56 599.80 9,168.36
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc 385.00 115.50 1,501.50 105.11 1,606.61 112.46 1,719.07
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc 385.00 115.50 12,012.00 840.84 12,852.84 899.70 13,752.54

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc 285.00 85.50 741.00 51.87 792.87 55.50 848.37
3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc 330.00 99.00 429.00 30.03 459.03 32.13 491.16
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc 350.00 105.00 6,825.00 477.75 7,302.75 511.19 7,813.94
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc 245.00 73.50 5,733.00 401.31 6,134.31 429.40 6,563.71
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc 175.00 52.50 1,365.00 95.55 1,460.55 102.24 1,562.79
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc 125.00 37.50 487.50 34.13 521.63 36.51 558.14
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc 1,330.00 399.00 1,729.00 121.03 1,850.03 129.50 1,979.53
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc 490.00 147.00 3,185.00 222.95 3,407.95 238.56 3,646.51
3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc 550.00 165.00 715.00 50.05 765.05 53.55 818.60
3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc 185.00 55.50 721.50 50.51 772.01 54.04 826.05
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc 185.00 55.50 721.50 50.51 772.01 54.04 826.05
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc 135.00 40.50 175.50 12.29 187.79 13.14 200.93
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc 115.00 34.50 448.50 31.40 479.90 33.59 513.49
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc 95.00 28.50 370.50 25.94 396.44 27.75 424.19
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc 120.00 36.00 312.00 21.84 333.84 23.37 357.21
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc 80.00 24.00 11,960.00 837.20 12,797.20 895.80 13,693.00
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc 55.00 16.50 10,582.00 740.74 11,322.74 792.59 12,115.33
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc 75.00 22.50 1,462.50 102.38 1,564.88 109.54 1,674.42
3.6.2.38 BI Union Patente 25mm 3.00 pc 115.00 34.50 448.50 31.40 479.90 33.59 513.49
3.6.2.39 Slip on flange 150mm 36.00 pc 550.00 165.00 25,740.00 1,801.80 27,541.80 1,927.93 29,469.73
3.6.2.40 Slip on flange 100mm 84.00 pc 350.00 105.00 38,220.00 2,675.40 40,895.40 2,862.68 43,758.08
3.6.2.41 Slip on flange 80mm 12.00 pc 235.00 70.50 3,666.00 256.62 3,922.62 274.58 4,197.20
3.6.2.42 Slip on flange 75mm 6.00 pc 235.00 70.50 1,833.00 128.31 1,961.31 137.29 2,098.60
3.6.2.43 Slip on flange 65mm 18.00 pc 195.00 58.50 4,563.00 319.41 4,882.41 341.77 5,224.18
3.6.2.44 Rubber Gasket 150mm 18.00 pc 145.00 43.50 3,393.00 237.51 3,630.51 254.14 3,884.65
3.6.2.45 Rubber Gasket 100mm 42.00 pc 115.00 34.50 6,279.00 439.53 6,718.53 470.30 7,188.83
3.6.2.46 Rubber Gasket 80mm 6.00 pc 90.00 27.00 702.00 49.14 751.14 52.58 803.72
3.6.2.47 Rubber Gasket 75mm 3.00 pc 90.00 27.00 351.00 24.57 375.57 26.29 401.86
3.6.2.48 Rubber Gasket 65mm 9.00 pc 85.00 25.50 994.50 69.62 1,064.12 74.49 1,138.60
3.6.3 Valve, Sprinkler, FHC and Accessories

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc 220.00 66.00 26,884.00 1,881.88 28,765.88 2,013.61 30,779.49
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc 345.00 103.50 21,528.00 1,506.96 23,034.96 1,612.45 24,647.41
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc 15,700.00 4,710.00 20,410.00 1,428.70 21,838.70 1,528.71 23,367.41
3.6.3.4 Fire Hose Valve 65mm 7.00 pc 7,350.00 2,205.00 66,885.00 4,681.95 71,566.95 5,009.69 76,576.64
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc 1,050.00 315.00 4,095.00 286.65 4,381.65 306.72 4,688.37
3.6.3.6 Inspector Test valve 25mm 7.00 pc 750.00 225.00 6,825.00 477.75 7,302.75 511.19 7,813.94
3.6.3.7 Sight Glass 25mm 7.00 pc 790.00 237.00 7,189.00 503.23 7,692.23 538.46 8,230.69
3.6.3.8 Water Flow Switch 7.00 pc 4,720.00 1,416.00 42,952.00 3,006.64 45,958.64 3,217.10 49,175.74
3.6.3.9 Supervisory Switch 7.00 pc 6,500.00 1,950.00 59,150.00 4,140.50 63,290.50 4,430.34 67,720.84

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc 15,000.00 4,500.00 273,000.00 19,110.00 292,110.00 20,447.70 312,557.70
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc 7,300.00 2,190.00 28,470.00 1,992.90 30,462.90 2,132.40 32,595.30
3.6.4 Hanger and Brackets 1.00 lot 99,775.00 29,932.50 129,707.50 9,079.53 138,787.03 9,715.09 148,502.12
3.6.4.1 Bolt and Nut and Washer 5/8 x 4"
3.6.4.2 Angle Bar 2" x 2" x 1/4"
3.6.4.3 Full threaded 3/8
3.6.4.4 Loop Hanger 75mm
3.6.4.5 Loop Hanger 25mm
3.6.4.6 U-Bolt 75mm x 1/2
3.6.4.7 U-Bolt 150mm x 5/8
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot 9,676.00 2,902.80 12,578.80 880.52 13,459.32 942.15 14,401.47
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe)
3.6.5.1 Clear Silicon Sealant
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m² 62.33 18.70 9,724.00 680.68 10,404.68 728.33 11,133.01
3.6.7 Fire Fighting Equipment & Installation

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set 2,050,000.00 307,500.00 2,357,500.00 165,025.00 2,522,525.00 176,576.75 2,699,101.75
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set 85,000.00 12,750.00 97,750.00 6,842.50 104,592.50 7,321.48 111,913.98
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot 36,396.00 10,918.80 47,314.80 3,312.04 50,626.84 3,543.88 54,170.71
3.6.8.1 teflon tape
3.6.8.2 red Oxide
3.6.8.3 grip anchor 3/8
3.6.8.4 expansion Shield 3/8 x 2
3.6.8.5 grinding stone 4"
3.6.8.6 cut off disks 14"
3.6.8.7 weldingrRod 6011
3.6.8.8 welding rod 6013
3.6.8.9 Abaca sacks
3.6.8.10 Flinknote

Sub-Total 3,833,707.60 268,359.53 4,102,067.13 287,144.70 4,389,211.83

4.0 TOILETS (2 @Ground, 1 @ Third Flr)


4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot 0 10,045.00 10,045.00 703.15 10,748.15 752.37 11,500.52
4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m² 380.77 114.23 64,350.00 4,504.50 68,854.50 4,819.82 73,674.32
4.1.3 Tile Adhesive 86.67 bag 250.00 75.00 28,167.75 1,971.74 30,139.49 2,109.76 32,249.26
4.1.4 Tile Grout 8.67 kg 70.00 21.00 788.97 55.23 844.20 59.09 903.29

Sub-Total 103,351.72 7,234.62 110,586.34 7,741.04 118,327.38

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set 15,250.00 4,575.00 297,375.00 20,816.25 318,191.25 22,273.39 340,464.64

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

4.2.2 Powder Coated Window (see schedule) 12.00 set 4,500.00 1,350.00 70,200.00 4,914.00 75,114.00 5,257.98 80,371.98
4.2.3 Laminated Modular partitions with SS accessories 15.00 set 18,500.00 5,550.00 360,750.00 25,252.50 386,002.50 27,020.18 413,022.68
4.2.4 Semi Gloss Latex 15.00 gal 695.00 208.50 13,552.50 948.68 14,501.18 1,015.08 15,516.26
4.2.5 Flat Latex Paint 15.00 gal 480.00 144.00 9,360.00 655.20 10,015.20 701.06 10,716.26

4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 10,605.00 3,181.50 13,786.50 965.06 14,751.56 1,032.61 15,784.16

Sub-Total 765,024.00 53,551.68 818,575.68 57,300.30 875,875.98

4.3 PLUMBING WORKS


4.3.1 PVC Pipes Series 1000
4.3.1.1 150mm Ø 77.00 m 520.00 156.00 52,052.00 3,643.64 55,695.64 3,898.69 59,594.33
4.3.1.2 100mm Ø 188.00 m 230.00 69.00 56,212.00 3,934.84 60,146.84 4,210.28 64,357.12
4.3.2 PVC Fittings Series 1000
4.3.2.1 Wye 150 x 150 21.00 pc 950.00 285.00 25,935.00 1,815.45 27,750.45 1,942.53 29,692.98
4.3.2.2 Wye 100 x 100 24.00 pc 145.00 43.50 4,524.00 316.68 4,840.68 338.85 5,179.53
4.3.2.3 Elbow 90" x 100 66.00 pc 435.00 130.50 37,323.00 2,612.61 39,935.61 2,795.49 42,731.10
4.3.2.4 Elbow 45" x 200 6.00 pc 715.00 214.50 5,577.00 390.39 5,967.39 417.72 6,385.11
4.3.2.5 Sanitary Tee 150 x 100 24.00 pc 515.00 154.50 16,068.00 1,124.76 17,192.76 1,203.49 18,396.25
4.3.2.6 Sanitary Tee 100 x 50 39.00 pc 110.00 33.00 5,577.00 390.39 5,967.39 417.72 6,385.11
4.3.2.7 P-Trap 100 39.00 pc 215.00 64.50 10,900.50 763.04 11,663.54 816.45 12,479.98
4.3.3 19mm Ø PPR Pipes (PN20) 100.00 m 135.00 40.50 17,550.00 1,228.50 18,778.50 1,314.50 20,093.00
4.3.4 PPR Fittings
4.3.4.1 Elbow 90 x 19 85.50 pc 25.00 7.50 2,778.75 194.51 2,973.26 208.13 3,181.39
4.3.4.2 Tee 19 x 19 45.00 pc 25.00 7.50 1,462.50 102.38 1,564.88 109.54 1,674.42
4.3.4.3 Coupling 25 x 25 13.50 pc 25.00 7.50 438.75 30.71 469.46 32.86 502.32
4.3.4.4 Coupling 25 x 19 15.00 pc 25.00 7.50 487.50 34.13 521.63 36.51 558.14
4.3.4.5 Gate Valve 19 6.00 pc 750.00 225.00 5,850.00 409.50 6,259.50 438.17 6,697.67
4.3.5 Sanitary Fixtures
4.3.5.1 Shower Head and Shower Valves 6.00 set 2,500.00 750.00 19,500.00 1,365.00 20,865.00 1,460.55 22,325.55

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

4.3.5.2 Telephone Water Heater 6.00 set 7,000.00 2,100.00 54,600.00 3,822.00 58,422.00 4,089.54 62,511.54
4.3.5.3 Lavatory Sink 15.00 set 5,000.00 1,500.00 97,500.00 6,825.00 104,325.00 7,302.75 111,627.75
4.3.5.4 Water Closet dual flush 12.00 set 8,200.00 2,460.00 127,920.00 8,954.40 136,874.40 9,581.21 146,455.61
4.3.5.5 Waterless Urinal 7.00 set 14,000.00 4,200.00 127,400.00 8,918.00 136,318.00 9,542.26 145,860.26
4.3.6 Miscellaneous/Consumables 1.00 lot 10,880.00 3,264.00 14,144.00 990.08 15,134.08 1,059.39 16,193.47
4.3.6.1 Pipe Sleeves
4.3.6.2 Pipe Hangers & Support
4.3.6.3 Teflon, Solvent etc.

Sub-Total 683,800.00 47,866.00 731,666.00 51,216.62 782,882.62

4.4 ELECTRICAL WORKS & FIXTURES


4.4.1 Conduits
4.4.1.1 15mm dia PVC (Lighting) 270.00 m 30.56 9.17 10,725.00 750.75 11,475.75 803.30 12,279.05
4.4.1.2 15mm dia PVC (power lines) 270.00 m 30.56 9.17 10,725.00 750.75 11,475.75 803.30 12,279.05
4.4.2 Wires and Cables (Ground Floor Toilet Only)
4.4.2.1 2-3.5mm THHN cu. Stranded Wires 540.00 m 28.00 8.40 19,656.00 1,375.92 21,031.92 1,472.23 22,504.15
4.4.3 Junction and utility Boxes 120.00 pc 33.33 10.00 5,200.00 364.00 5,564.00 389.48 5,953.48
4.4.4 Electrical Fixtures
4.4.4.1 100mm dia Cylindrical Downlight Fixture with LED 13W 33.00 pc 850.00 255.00 36,465.00 2,552.55 39,017.55 2,731.23 41,748.78
4.4.4.2 Emergency Light 6.00 pc 2,000.00 600.00 15,600.00 1,092.00 16,692.00 1,168.44 17,860.44
4.4.4.3 Ceiling Exhaust Fan & Switch (heavy duty) 6.00 pc 4,000.00 1,200.00 31,200.00 2,184.00 33,384.00 2,336.88 35,720.88
4.4.4.4 Two Gang Switch 9.00 pc 165.00 49.50 1,930.50 135.14 2,065.64 144.59 2,210.23

Sub-Total 131,501.50 9,205.11 140,706.61 9,849.46 150,556.07

5.0 LECTURE ROOM A-1 (GROUND FLOOR)


5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m² 1,028.00 308.40 89,405.16 6,258.36 95,663.52 6,696.45 102,359.97
5.1.2 Tile Adhesive 46.46 bag 250.00 75.00 15,099.50 1,056.97 16,156.47 1,130.95 17,287.42

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

5.1.3 Tile Grout 4.65 kg 70.00 21.00 423.15 29.62 452.77 31.69 484.46
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m² 891.00 267.30 11,583.00 810.81 12,393.81 867.57 13,261.38
5.1.5 Vinyl Adhesive 1.00 gal 650.00 195.00 845.00 59.15 904.15 63.29 967.44

Sub-Total 117,355.81 8,214.91 125,570.72 8,789.95 134,360.67

5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal 695.00 208.50 11,745.50 822.19 12,567.69 879.74 13,447.42
5.2.2 Flat Latex Primer 7.00 gal 480.00 144.00 4,368.00 305.76 4,673.76 327.16 5,000.92

5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot 3,180.00 954.00 4,134.00 289.38 4,423.38 309.64 4,733.02

Sub-Total 20,247.50 1,417.33 21,664.83 1,516.54 23,181.36

5.3 CEILING WORKS


5.3.1 9mm thk Gypsum Board 58.33 m² 124.46 37.34 9,438.00 660.66 10,098.66 706.91 10,805.57
5.3.2 Metal Double Furring 286.87 m 39.30 11.79 14,657.50 1,026.03 15,683.53 1,097.85 16,781.37
5.3.3 Wall Angle 30.55 m 35.02 10.51 1,391.00 97.37 1,488.37 104.19 1,592.56
5.3.4 600 x 600 acoustic boards 44.93 m² 417.32 125.19 24,375.00 1,706.25 26,081.25 1,825.69 27,906.94
5.3.5 T-runners (white) 292.05 m 11.64 3.49 4,420.00 309.40 4,729.40 331.06 5,060.46
5.3.6 Wall Angle (White) 26.81 m 10.50 3.15 365.96 25.62 391.57 27.41 418.98
5.3.7 Carrying Channel 103.26 m 23.00 6.90 3,087.47 216.12 3,303.60 231.25 3,534.85
5.3.8 W-Clamps/Clips 206.52 pc 3.50 1.05 939.67 65.78 1,005.44 70.38 1,075.82
5.3.9 Blind Rivets 1/8 20.65 box 350.00 105.00 9,395.75 657.70 10,053.45 703.74 10,757.19
5.3.10 Black Screws 1,749.90 pc 0.75 0.23 1,706.15 119.43 1,825.58 127.79 1,953.37

Sub-Total 69,776.50 4,884.35 74,660.85 5,226.26 79,887.11

5.4 ELECTRICAL WORKS AND FIXTURES


5.4.1 Conduits

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

5.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67 10.70 5,564.00 389.48 5,953.48 416.74 6,370.22
5.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67 10.70 5,564.00 389.48 5,953.48 416.74 6,370.22
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m 28.00 8.40 8,736.00 611.52 9,347.52 654.33 10,001.85
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m 38.00 11.40 11,856.00 829.92 12,685.92 888.01 13,573.93
5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc 33.00 9.90 2,574.00 180.18 2,754.18 192.79 2,946.97
5.4.4 Electrical fixtures
5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc 850.00 255.00 14,365.00 1,005.55 15,370.55 1,075.94 16,446.49
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00 600.00 15,600.00 1,092.00 16,692.00 1,168.44 17,860.44
5.4.4.3 Emergency Light 1.00 set 2,000.00 600.00 2,600.00 182.00 2,782.00 194.74 2,976.74
5.4.4.4 Ceiling Fans 6.00 set 2,500.00 750.00 19,500.00 1,365.00 20,865.00 1,460.55 22,325.55
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 255.00 4,420.00 309.40 4,729.40 331.06 5,060.46
5.4.4.6 Aircon Outlet 2.00 pc 270.00 81.00 702.00 49.14 751.14 52.58 803.72
5.4.4.7 Three Gang Switch 1.00 pc 215.00 64.50 279.50 19.57 299.07 20.93 320.00
5.4.4.8 Ceiling Fan Switch 2.00 pc 250.00 75.00 650.00 45.50 695.50 48.69 744.19

Sub-Total 92,410.50 6,468.74 98,879.24 6,921.55 105,800.78

5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 10,035.00 10,035.00 702.45 10,737.45 751.62 11,489.07
Whiteboard Screen with Integrated Smart TV Enclosure
5.5.2 1.00 set 50,275.00 15,082.50 65,357.50 4,575.03 69,932.53 4,895.28 74,827.80
laminate mounted on plywood on sliding rollers
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 2,250.00 17,250.00 1,207.50 18,457.50 1,292.03 19,749.53
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 15,300.00 132,600.00 9,282.00 141,882.00 9,931.74 151,813.74
5.5.3.3 PVC Student Armchair 45.00 set 950.00 142.50 49,162.50 3,441.38 52,603.88 3,682.27 56,286.15

Sub-Total 274,405.00 19,208.35 293,613.35 20,552.93 314,166.28

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

5.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)

5.6.1 D-1: Metal Door Jams and Panel (w/ knobs & hinges) 2.00 set 18,140.00 5,442.00 47,164.00 3,301.48 50,465.48 3,532.58 53,998.06
5.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 3,600.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
5.6.3 W-2: Clear glass powder coated white pivot window 4.00 set 5,600.00 1,680.00 29,120.00 2,038.40 31,158.40 2,181.09 33,339.49

Sub-Total 138,684.00 9,707.88 148,391.88 10,387.43 158,779.31

6.0 STUDENT ORG ROOMS (GROUND FLOOR)


6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m² 895.40 268.62 58,201.00 4,074.07 62,275.07 4,359.25 66,634.32
6.1.2 Vinyl Adhesive 5.00 gal 650.00 195.00 4,225.00 295.75 4,520.75 316.45 4,837.20

Sub-Total 62,426.00 4,369.82 66,795.82 4,675.71 71,471.53

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal 695.00 208.50 20,780.50 1,454.64 22,235.14 1,556.46 23,791.59
6.2.2 Flat Latex 10.00 gal 480.00 144.00 6,240.00 436.80 6,676.80 467.38 7,144.18

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot 4,730.00 1,419.00 6,149.00 430.43 6,579.43 460.56 7,039.99

Sub-Total 33,169.50 2,321.87 35,491.37 2,484.40 37,975.76

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m² 125.92 37.78 12,441.00 870.87 13,311.87 931.83 14,243.70
6.3.2 Metal Double Furring 373.77 m 30.17 9.05 14,657.50 1,026.03 15,683.53 1,097.85 16,781.37
6.3.3 Wall Angle 34.87 m 37.57 11.27 1,703.00 119.21 1,822.21 127.55 1,949.76
6.3.4 Carrying Channel 76.00 m 23.00 6.90 2,272.40 159.07 2,431.47 170.20 2,601.67
6.3.5 W-clamps/Clips 152.00 pc 3.50 1.05 691.60 48.41 740.01 51.80 791.81

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

6.3.6 Blind rivets(1/8) 15.00 box 350.00 105.00 6,825.00 477.75 7,302.75 511.19 7,813.94
6.3.7 Black Screws 2,280.00 pc 0.75 0.23 2,223.00 155.61 2,378.61 166.50 2,545.11

Sub-Total 40,813.50 2,856.95 43,670.45 3,056.93 46,727.38

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67 10.70 5,564.00 389.48 5,953.48 416.74 6,370.22
6.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67 10.70 5,564.00 389.48 5,953.48 416.74 6,370.22
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00 8.40 8,736.00 611.52 9,347.52 654.33 10,001.85
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00 11.40 11,856.00 829.92 12,685.92 888.01 13,573.93
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc 33.75 10.13 2,632.50 184.28 2,816.78 197.17 3,013.95
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set 850.00 255.00 17,680.00 1,237.60 18,917.60 1,324.23 20,241.83
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00 600.00 20,800.00 1,456.00 22,256.00 1,557.92 23,813.92
6.4.4.3 Emergency Light 4.00 set 2,000.00 600.00 10,400.00 728.00 11,128.00 778.96 11,906.96
6.4.4.4 Ceiling Fan 4.00 set 2,500.00 750.00 13,000.00 910.00 13,910.00 973.70 14,883.70
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc 850.00 255.00 8,840.00 618.80 9,458.80 662.12 10,120.92
6.4.4.6 One Gang Switch 4.00 pc 105.00 31.50 546.00 38.22 584.22 40.90 625.12
6.4.4.7 Ceiling Fan Switch 4.00 pc 250.00 75.00 1,300.00 91.00 1,391.00 97.37 1,488.37

Sub-Total 106,918.50 7,484.30 114,402.80 8,008.20 122,410.99

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc 750.00 225.00 17,550.00 1,228.50 18,778.50 1,314.50 20,093.00
6.5.1.2 2 x 3 Metal Stud 250.82 m 55.58 16.67 18,122.00 1,268.54 19,390.54 1,357.34 20,747.88
6.5.1.3 Blind rivets (1/8) 4.00 box 350.00 105.00 1,820.00 127.40 1,947.40 136.32 2,083.72

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

6.5.1.4 Black Screws 1,530.00 pc 0.75 0.23 1,491.75 104.42 1,596.17 111.73 1,707.90
6.5.2 Demolition of existing tiles, fixtures, hauling of debris, etc. 1.00 lot 0 7,500.00 7,500.00 525.00 8,025.00 561.75 8,586.75
6.5.3 Furniture & Appliances
6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set 33,000.00 4,950.00 151,800.00 10,626.00 162,426.00 11,369.82 173,795.82
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc 1,200.00 180.00 414,000.00 28,980.00 442,980.00 31,008.60 473,988.60
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set 12,000.00 3,600.00 93,600.00 6,552.00 100,152.00 7,010.64 107,162.64
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc 4,000.00 1,200.00 20,800.00 1,456.00 22,256.00 1,557.92 23,813.92

Sub-Total 726,683.75 50,867.86 777,551.61 54,428.61 831,980.23

6.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


6.6.1 D-1: White Steel Door / view panel on Metal Jamb 4.00 set 18,147.50 5,444.25 94,367.00 6,605.69 100,972.69 7,068.09 108,040.78
6.6.2 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 1,680.00 29,120.00 2,038.40 31,158.40 2,181.09 33,339.49

123,487.00 8,644.09 132,131.09 9,249.18 141,380.27

7.0 LECTURE ROOM A-4 (GROUND FLOOR)


7.1 FLOOR FINISHES
7.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00 308.40 168,386.40 11,787.05 180,173.45 12,612.14 192,785.59
7.1.2 Tile Adhesive 87.50 bag 250.00 75.00 28,437.50 1,990.63 30,428.13 2,129.97 32,558.09
7.1.3 Tile Grout 8.75 kg 70.00 21.00 796.25 55.74 851.99 59.64 911.63
7.1.4 Vinyl Adhesive 2.00 gal 650.00 195.00 1,690.00 118.30 1,808.30 126.58 1,934.88
7.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00 267.30 23,166.00 1,621.62 24,787.62 1,735.13 26,522.75

Sub-Total 866.70 222,476.15 15,573.33 238,049.48 16,663.46 254,712.94

7.2 PAINTING
7.2.1 Semi Gloss Latex 4.00 gal 695.00 208.50 3,614.00 252.98 3,866.98 270.69 4,137.67
7.2.2 Flat Latex 7.00 gal 480.00 144.00 4,368.00 305.76 4,673.76 327.16 5,000.92

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

7.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,395.00 718.50 3,113.50 217.95 3,331.45 233.20 3,564.65

Sub-Total 11,095.50 776.69 11,872.19 831.05 12,703.24

7.3 CEILING WORKS


7.3.1 9mm thk Gypsum bd on Metal Furring 51.00 m² 129.41 38.82 8,580.00 600.60 9,180.60 642.64 9,823.24
7.3.2 Metal Double Furring 250.82 m 29.66 8.90 9,672.00 677.04 10,349.04 724.43 11,073.47
7.3.3 Wall Angle 28.57 m 32.90 9.87 1,222.00 85.54 1,307.54 91.53 1,399.07
7.3.4 Carrying Channel 125.00 m 23.00 6.90 3,737.50 261.63 3,999.13 279.94 4,279.06
7.3.5 W-clamps/clips 250.00 pc 3.50 1.05 1,137.50 79.63 1,217.13 85.20 1,302.32
7.3.6 Blind rivets(1/8) 25.00 box 350.00 105.00 11,375.00 796.25 12,171.25 851.99 13,023.24
7.3.7 Black Screws 1,530.00 pc 0.75 0.23 1,491.75 104.42 1,596.17 111.73 1,707.90
7.3.8 T-Runner (White) 481.00 m 12.37 3.71 7,735.00 541.45 8,276.45 579.35 8,855.80
7.3.9 Wall Angle (White) 34.41 m 10.50 3.15 469.70 32.88 502.58 35.18 537.76
7.3.10 600 x 600 acoustic board 74.00 m² 458.11 137.43 44,070.00 3,084.90 47,154.90 3,300.84 50,455.74

Sub-Total 89,490.45 6,264.33 95,754.78 6,702.83 102,457.61

7.4 ELECTRICAL WORKS AND FIXTURES


7.4.1 Conduits
7.4.1.1 15mm dia PVC (Lighting) 100.00 m 35.56 10.67 4,622.80 323.60 4,946.40 346.25 5,292.64
7.4.1.2 15mm dia PVC (Power Lines) 100.00 m 35.56 10.67 4,622.80 323.60 4,946.40 346.25 5,292.64
7.4.2 Wires and Cables (Ground Floor Toilet Only)
7.4.2.1 2-3.5mm THHN CU, Stranded Wires 200.00 m 28.00 8.40 7,280.00 509.60 7,789.60 545.27 8,334.87
7.4.2.2 2-5.5mm THHN CU, Stranded Wires 200.00 m 38.00 11.40 9,880.00 691.60 10,571.60 740.01 11,311.61
7.4.3 Others
7.4.3.1 Junction and Utility Box 60.00 pc 33.00 9.90 2,574.00 180.18 2,754.18 192.79 2,946.97
7.4.4 Electrical fixtures
7.4.4.1 Pinlight (100mm dia) with 7W LED 22.00 pc 850.00 255.00 24,310.00 1,701.70 26,011.70 1,820.82 27,832.52

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

7.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00 600.00 20,800.00 1,456.00 22,256.00 1,557.92 23,813.92
7.4.4.3 Emergency Light 1.00 set 2,000.00 600.00 2,600.00 182.00 2,782.00 194.74 2,976.74
7.4.4.4 Ceiling Fan 8.00 set 2,500.00 750.00 26,000.00 1,820.00 27,820.00 1,947.40 29,767.40
7.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 255.00 4,420.00 309.40 4,729.40 331.06 5,060.46
7.4.4.6 Aircon Outlet 2.00 pc 270.00 81.00 702.00 49.14 751.14 52.58 803.72
7.4.4.7 Three Gang Switch 2.00 pc 105.00 31.50 273.00 19.11 292.11 20.45 312.56
7.4.4.8 Ceiling Fan Switch 4.00 pc 250.00 75.00 1,300.00 91.00 1,391.00 97.37 1,488.37

Sub-Total 109,384.60 7,656.92 117,041.52 8,192.91 125,234.43

7.5 OTHERS
7.5.1 Demolition of existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 18,900.00 18,900.00 1,323.00 20,223.00 1,415.61 21,638.61
Whiteboard Screen with Integrated Smart TV Enclosure,
7.5.2 1.00 set 50,275.00 15,082.50 65,357.50 4,575.03 69,932.53 4,895.28 74,827.80
laminate mounted on plywood on sliding rollers
7.5.3 Furniture & Appliances
7.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 2,250.00 17,250.00 1,207.50 18,457.50 1,292.03 19,749.53
7.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 15,300.00 132,600.00 9,282.00 141,882.00 9,931.74 151,813.74
7.5.3.3 Working Table fit with 8 Ergonomic Chairs 9.00 set 33,000.00 4,950.00 341,550.00 23,908.50 365,458.50 25,582.10 391,040.60
Sub-Total 575,657.50 40,296.03 615,953.53 43,116.75 659,070.27

7.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


7.6.1 D-1: White Steel Door / view pane on Metal Jamb 2.00 set 18,160.00 5,448.00 47,216.00 3,305.12 50,521.12 3,536.48 54,057.60
7.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 3,600.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
7.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 1,680.00 29,120.00 2,038.40 31,158.40 2,181.09 33,339.49

Sub-Total 138,736.00 9,711.52 148,447.52 10,391.33 158,838.85

8.0 THEATER TYPE LECTURE RM (A-5) (SECOND FLR)


8.1 FLOOR FINISHES
8.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00 308.40 168,386.40 11,787.05 180,173.45 12,612.14 192,785.59

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

8.1.2 Tile Adhesive 87.50 bag 250.00 75.00 28,437.50 1,990.63 30,428.13 2,129.97 32,558.09
8.1.3 Tile Grout 8.75 kg 70.00 21.00 796.25 55.74 851.99 59.64 911.63
8.1.4 Vinyl Adhesive 2.00 gal 650.00 195.00 1,690.00 118.30 1,808.30 126.58 1,934.88
8.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00 267.30 23,166.00 1,621.62 24,787.62 1,735.13 26,522.75

Sub-Total 222,476.15 15,573.33 238,049.48 16,663.46 254,712.94

8.2 PAINTING
8.2.1 Semi Gloss Latex 28.00 gal 695.00 208.50 25,298.00 1,770.86 27,068.86 1,894.82 28,963.68
8.2.2 Flat Latex 6.00 gal 480.00 144.00 3,744.00 262.08 4,006.08 280.43 4,286.51

8.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,800.00 840.00 3,640.00 254.80 3,894.80 272.64 4,167.44

Sub-Total 32,682.00 2,287.74 34,969.74 2,447.88 37,417.62

8.3 CEILING WORKS


8.3.1 9mm thk Gypsum bd on Metal Furring 50.00 m² 125.40 37.62 8,151.00 570.57 8,721.57 610.51 9,332.08
8.3.2 Metal Double Furring 245.90 m 32.33 9.70 10,335.00 723.45 11,058.45 774.09 11,832.54
8.3.3 Wall Angle 28.28 m 30.62 9.19 1,125.80 78.81 1,204.61 84.32 1,288.93
8.3.4 Carrying Channel 150.00 m 23.00 6.90 4,485.00 313.95 4,798.95 335.93 5,134.88
8.3.5 W-Clamps/Clips 300.00 m 3.50 1.05 1,365.00 95.55 1,460.55 102.24 1,562.79
8.3.6 Blind rivets(1/8) 75.00 box 350.00 105.00 34,125.00 2,388.75 36,513.75 2,555.96 39,069.71
8.3.7 Black Screws 1,500.00 pc 0.75 0.23 1,462.50 102.38 1,564.88 109.54 1,674.42
8.3.8 T-Runner (White) 650.00 m 11.77 3.53 9,945.00 696.15 10,641.15 744.88 11,386.03
8.3.9 Wall Angle (White) 40.00 m 10.50 3.15 546.00 38.22 584.22 40.90 625.12
8.3.10 600 x 600 acoustic board on T-Runner 100.00 m² 457.50 137.25 59,475.00 4,163.25 63,638.25 4,454.68 68,092.93

Sub-Total 131,015.30 9,171.07 140,186.37 9,813.05 149,999.42

8.4 ELECTRICAL WORKS AND FIXTURES

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

8.4.1 Conduits
8.4.1.1 15mm dia PVC (Lighting) 200.00 m 25.00 7.50 6,500.00 455.00 6,955.00 486.85 7,441.85
8.4.1.2 15mm dia PVC (power lines) 200.00 m 25.00 7.50 6,500.00 455.00 6,955.00 486.85 7,441.85
8.4.2 Wires and Cables (Ground Floor Toilet Only)
8.4.2.1 2-3.5mm THHN CU, Stranded Wires 400.00 m 28.00 8.40 14,560.00 1,019.20 15,579.20 1,090.54 16,669.74
8.4.2.2 2-5.5mm THHN CU, Stranded Wires 400.00 m 38.00 11.40 19,760.00 1,383.20 21,143.20 1,480.02 22,623.22
8.4.3 Others
8.4.3.1 Junction and Utility Box 90.00 pc 33.06 9.92 3,867.50 270.73 4,138.23 289.68 4,427.90
8.4.4 Electrical fixtures
8.4.4.1 Pinlight (100mm dia) with 7W LED 24.00 set 850.00 255.00 26,520.00 1,856.40 28,376.40 1,986.35 30,362.75
8.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 12.00 set 2,000.00 600.00 31,200.00 2,184.00 33,384.00 2,336.88 35,720.88
8.4.4.3 Emergency Light 2.00 set 2,000.00 600.00 5,200.00 364.00 5,564.00 389.48 5,953.48
8.4.4.4 Ceiling Fan 12.00 set 2,500.00 750.00 39,000.00 2,730.00 41,730.00 2,921.10 44,651.10
8.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 255.00 4,420.00 309.40 4,729.40 331.06 5,060.46
8.4.4.6 Aircon Outlet 3.00 pc 270.00 81.00 1,053.00 73.71 1,126.71 78.87 1,205.58
8.4.4.7 Three Gang Switch 2.00 pc 215.00 64.50 559.00 39.13 598.13 41.87 640.00
8.4.4.8 Two Gang Switch 1.00 pc 165.00 49.50 214.50 15.02 229.52 16.07 245.58
8.4.4.9 Ceiling Fan Switch 5.00 pc 250.00 75.00 1,625.00 113.75 1,738.75 121.71 1,860.46

Sub-Total 160,979.00 11,268.53 172,247.53 12,057.33 184,304.86

8.5 OTHERS
8.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 18,900.00 18,900.00 1,323.00 20,223.00 1,415.61 21,638.61
Whiteboard Screen with Integrated Smart TV Enclosure,
8.5.2 1.00 set 50,275.00 15,082.50 65,357.50 4,575.03 69,932.53 4,895.28 74,827.80
laminate mounted on plywood on sliding rollers
8.5.3 Furniture & Appliances
8.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00 2,250.00 17,250.00 1,207.50 18,457.50 1,292.03 19,749.53
8.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00 15,300.00 198,900.00 13,923.00 212,823.00 14,897.61 227,720.61
8.5.3.3 Fixed Retractable Theatre Arm Chair 111.00 pc 8,000.00 1,600.00 1,065,600.00 74,592.00 1,140,192.00 79,813.44 1,220,005.44

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Sub-Total 1,366,007.50 95,620.53 1,461,628.03 102,313.96 1,563,941.99

8.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


8.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,295.00 5,788.50 50,167.00 3,511.69 53,678.69 3,757.51 57,436.20
8.6.2 W-1: Clear Glass powder coated white awning window 6.00 set 12,000.00 3,600.00 93,600.00 6,552.00 100,152.00 7,010.64 107,162.64
8.6.3 W-2: Clear Glass powder coated white pivot window 6.00 set 5,600.00 1,680.00 43,680.00 3,057.60 46,737.60 3,271.63 50,009.23

Sub-Total 187,447.00 13,121.29 200,568.29 14,039.78 214,608.07

9.0 LECTURE ROOM (A-7) (SECOND FLOOR)


9.1 FLOOR FINISHES
9.1.1 600 x 600 Homogenous Granite Tiles 68.00 m² 1,028.00 308.40 90,875.20 6,361.26 97,236.46 6,806.55 104,043.02
9.1.2 Tile Adhesive 47.22 bag 250.00 75.00 15,346.50 1,074.26 16,420.76 1,149.45 17,570.21
9.1.3 Tile Grout 4.72 kg 70.00 21.00 429.52 30.07 459.59 32.17 491.76
9.1.4 Vinyl Adhesive 0.90 gal 650.00 195.00 760.50 53.24 813.74 56.96 870.70
9.1.5 150 x 900 Vinyl tiles 9.00 m² 892.22 267.67 10,439.00 730.73 11,169.73 781.88 11,951.61

Sub-Total 117,850.72 8,249.55 126,100.27 8,827.02 134,927.29

9.2 PAINTING
9.2.1 Semi Gloss Latex 15.00 gal 695.00 208.50 13,552.50 948.68 14,501.18 1,015.08 15,516.26
9.2.2 Flat Latex 10.00 gal 480.00 144.00 6,240.00 436.80 6,676.80 467.38 7,144.18

9.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,365.00 709.50 3,074.50 215.22 3,289.72 230.28 3,520.00

Sub-Total 1,062.00 22,867.00 1,600.69 24,467.69 1,712.74 26,180.43

9.3 CEILING WORKS


9.3.1 9mm thk Gypsum Board on Metal Furring 30.00 m² 121.00 36.30 4,719.00 330.33 5,049.33 353.45 5,402.78
9.3.2 Metal Double Furring 147.54 m 38.26 11.48 7,338.50 513.70 7,852.20 549.65 8,401.85

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

9.3.3 Wall Angle 21.91 m 34.69 10.41 988.00 69.16 1,057.16 74.00 1,131.16
9.3.4 Carrying Channel 76.00 m 23.00 6.90 2,272.40 159.07 2,431.47 170.20 2,601.67
9.3.5 W-clamps/clips 152.00 pc 3.50 1.05 691.60 48.41 740.01 51.80 791.81
9.3.6 Blind rivets(1/8) 38.00 box 350.00 105.00 17,290.00 1,210.30 18,500.30 1,295.02 19,795.32
9.3.7 Black Screws 900.00 pc 0.75 0.23 877.50 61.43 938.93 65.72 1,004.65
9.3.8 T-Runner (White) 299.00 m 11.94 3.58 4,641.00 324.87 4,965.87 347.61 5,313.48
9.3.9 Wall Angle (White) 27.13 m 10.50 3.15 370.32 25.92 396.25 27.74 423.98
9.3.10 600 x 600 acoustic board on T-Runner 46.00 m² 456.52 136.96 27,300.00 1,911.00 29,211.00 2,044.77 31,255.77

Sub-Total 66,488.32 4,654.18 71,142.51 4,979.98 76,122.48

9.4 ELECTRICAL WORKS AND FIXTURES


9.4.1 Conduits
9.4.1.1 15mm dia PVC (Lighting) 88.00 m 25.00 7.50 2,860.00 200.20 3,060.20 214.21 3,274.41
9.4.1.2 15mm dia PVC (Power Lines) 88.00 m 25.00 7.50 2,860.00 200.20 3,060.20 214.21 3,274.41
9.4.2 Wires and Cables (Ground Floor Toilet Only)
9.4.2.1 2-3.5mm THHN cu. Stranded Wires 176.00 m 28.00 8.40 6,406.40 448.45 6,854.85 479.84 7,334.69
9.4.2.2 2-5.5mm THHN cu. Stranded Wires 176.00 m 38.00 11.40 8,694.40 608.61 9,303.01 651.21 9,954.22
9.4.3 Others
9.4.3.1 Junction and Utility Box 60.00 pc 33.00 9.90 2,574.00 180.18 2,754.18 192.79 2,946.97
9.4.4 Electrical fixtures
9.4.4.1 Pinlight (100mm dia) with 7W LED 9.00 pc 850.00 255.00 9,945.00 696.15 10,641.15 744.88 11,386.03
9.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00 600.00 15,600.00 1,092.00 16,692.00 1,168.44 17,860.44
9.4.4.3 Emergency Light 1.00 set 2,000.00 600.00 2,600.00 182.00 2,782.00 194.74 2,976.74
9.4.4.4 Ceiling Fan 6.00 set 2,500.00 750.00 19,500.00 1,365.00 20,865.00 1,460.55 22,325.55
9.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 255.00 4,420.00 309.40 4,729.40 331.06 5,060.46
9.4.4.6 Aircon Outlet 2.00 pc 270.00 81.00 702.00 49.14 751.14 52.58 803.72
9.4.4.7 Three Gang Switch 1.00 pc 215.00 64.50 279.50 19.57 299.07 20.93 320.00
9.4.4.8 Ceiling Fan Switch 2.00 pc 250.00 75.00 650.00 45.50 695.50 48.69 744.19

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Sub-Total 77,091.30 5,396.39 82,487.69 5,774.14 88,261.83

9.5 OTHERS
9.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 10,200.00 10,200.00 714.00 10,914.00 763.98 11,677.98
Whiteboard Screen with Integrated Smart TV Enclosure,
9.5.2 1.00 set 50,275.00 15,082.50 65,357.50 4,575.03 69,932.53 4,895.28 74,827.80
laminate mounted on plywood on sliding rollers
9.5.3 Furniture & Appliances
9.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00 2,250.00 17,250.00 1,207.50 18,457.50 1,292.03 19,749.53
9.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00 15,300.00 132,600.00 9,282.00 141,882.00 9,931.74 151,813.74
9.5.3.3 PVC Student Armchair 50.00 pc 950.00 142.50 54,625.00 3,823.75 58,448.75 4,091.41 62,540.16

Sub-Total 280,032.50 19,602.28 299,634.78 20,974.43 320,609.21

9.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


9.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00 5,766.00 49,972.00 3,498.04 53,470.04 3,742.90 57,212.94
9.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 3,600.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
9.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 1,680.00 29,120.00 2,038.40 31,158.40 2,181.09 33,339.49

Sub-Total 141,492.00 9,904.44 151,396.44 10,597.75 161,994.19

10.0 LECTURE ROOM (THIRD FLOOR)


10.1 FLOOR FINISHES
10.1.1 600 x 600 Homogenous Granite Tiles 63.00 m² 1,028.00 308.40 84,193.20 5,893.52 90,086.72 6,306.07 96,392.79
10.1.2 Tile Adhesive 43.75 bag 250.00 75.00 14,218.75 995.31 15,214.06 1,064.98 16,279.05
10.1.3 Tile Grout 4.38 kg 70.00 21.00 398.58 27.90 426.48 29.85 456.33
10.1.4 Vinyl Adhesive 1.00 gal 650.00 195.00 845.00 59.15 904.15 63.29 967.44
10.1.5 150 x 900 Vinyl tiles 10.00 m² 891.00 267.30 11,583.00 810.81 12,393.81 867.57 13,261.38

Sub-Total 866.70 111,238.53 7,786.70 119,025.23 8,331.77 127,356.99

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

10.2 PAINTING
10.2.1 Semi Gloss Latex 14.00 gal 695.00 208.50 12,649.00 885.43 13,534.43 947.41 14,481.84
10.2.2 Flat Latex 5.00 gal 480.00 144.00 3,120.00 218.40 3,338.40 233.69 3,572.09

10.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 1,730.00 519.00 2,249.00 157.43 2,406.43 168.45 2,574.88

Sub-Total 18,018.00 1,261.26 19,279.26 1,349.55 20,628.81

10.3 CEILING WORKS


10.3.1 9mm thk Gypsum Board on Metal Furring 21.00 m² 125.71 37.71 3,432.00 240.24 3,672.24 257.06 3,929.30
10.3.2 Metal Double Furring 103.28 m 33.31 9.99 4,472.00 313.04 4,785.04 334.95 5,119.99
10.3.3 Wall Angle 18.33 m 36.55 10.97 871.00 60.97 931.97 65.24 997.21
10.3.4 Carrying Channel 71.00 m 23.00 6.90 2,122.90 148.60 2,271.50 159.01 2,430.51
10.3.5 W-Clamps/Clips 142.00 pc 3.50 1.05 646.10 45.23 691.33 48.39 739.72
10.3.6 Blind rivets(1/8) 35.50 box 350.00 105.00 16,152.50 1,130.68 17,283.18 1,209.82 18,493.00
10.3.7 Black Screws 630.00 pc 0.75 0.23 614.25 43.00 657.25 46.01 703.25
10.3.8 T-Runner (White) 325.00 m 13.08 3.92 5,525.00 386.75 5,911.75 413.82 6,325.57
10.3.9 Wall Angle (White) 28.28 m 10.50 3.15 386.02 27.02 413.04 28.91 441.96
10.3.10 600 x 600 acoustic board on T-Runner 50.00 m² 456.00 136.80 29,640.00 2,074.80 31,714.80 2,220.04 33,934.84

Sub-Total 315.72 63,861.77 4,470.32 68,332.10 4,783.25 73,115.34

10.4 ELECTRICAL WORKS AND FIXTURES


10.4.1 Conduits
10.4.1.1 15mm dia PVC (Lighting) 120.00 m 25.00 7.50 3,900.00 273.00 4,173.00 292.11 4,465.11
10.4.1.2 15mm dia PVC (Power Lines) 120.00 m 25.00 7.50 3,900.00 273.00 4,173.00 292.11 4,465.11
10.4.2 Wires and Cables (Ground Floor Toilet Only)
10.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00 8.40 8,736.00 611.52 9,347.52 654.33 10,001.85
10.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00 11.40 11,856.00 829.92 12,685.92 888.01 13,573.93
10.4.3 Others

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

10.4.3.1 Junction and Utility Box 60.00 pc 33.00 9.90 2,574.00 180.18 2,754.18 192.79 2,946.97
10.4.4 Electrical fixtures
10.4.4.1 Pinlight (100mm dia) with 7W LED 6.00 set 850.00 255.00 6,630.00 464.10 7,094.10 496.59 7,590.69
10.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 4.00 set 2,000.00 600.00 10,400.00 728.00 11,128.00 778.96 11,906.96
10.4.4.3 Emergency Light 1.00 set 2,000.00 600.00 2,600.00 182.00 2,782.00 194.74 2,976.74
10.4.4.4 Ceiling Fans 3.00 set 2,500.00 750.00 9,750.00 682.50 10,432.50 730.28 11,162.78
10.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00 255.00 4,420.00 309.40 4,729.40 331.06 5,060.46
10.4.4.6 Aircon Outlet 2.00 pc 270.00 81.00 702.00 49.14 751.14 52.58 803.72
10.4.4.7 Three Gang Switch 1.00 pc 215.00 64.50 279.50 19.57 299.07 20.93 320.00
10.4.4.8 Ceiling Fan Switch 3.00 pc 250.00 75.00 975.00 68.25 1,043.25 73.03 1,116.28

Sub-Total 66,722.50 4,670.58 71,393.08 4,997.52 76,390.59

10.5 OTHERS
10.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0 9,450.00 9,450.00 661.50 10,111.50 707.81 10,819.31
Whiteboard Screen with Integrated Smart TV Enclosure
10.5.2 1.00 set 50,275.00 15,082.50 65,357.50 4,575.03 69,932.53 4,895.28 74,827.80
laminate mounted on plywood on sliding rollers
10.5.3 Furniture & Appliances
10.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00 2,250.00 17,250.00 1,207.50 18,457.50 1,292.03 19,749.53
10.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00 15,300.00 198,900.00 13,923.00 212,823.00 14,897.61 227,720.61
10.5.3.3 Student Armchair 30.00 pc 950.00 142.50 32,775.00 2,294.25 35,069.25 2,454.85 37,524.10

Sub-Total 323,732.50 22,661.28 346,393.78 24,247.56 370,641.34

10.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)

10.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00 5,766.00 49,972.00 3,498.04 53,470.04 3,742.90 57,212.94
10.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00 3,600.00 62,400.00 4,368.00 66,768.00 4,673.76 71,441.76
10.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00 1,680.00 29,120.00 2,038.40 31,158.40 2,181.09 33,339.49

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

Sub-Total 141,492.00 9,904.44 151,396.44 10,597.75 161,994.19

11.0 OPENINGS & PATHWAY TO ADJACENT BUILDINGS


11.1 ACCESS PATHWAY (to Library)
11.1.1 Demolition Works of existing including hauling 1.00 lot 0 5,785.50 5,785.50 404.99 6,190.49 433.33 6,623.82
11.1.2 Site clearing, Soil preparation 60.00 m² 0 600.00 36,000.00 2,520.00 38,520.00 2,696.40 41,216.40
11.1.3 Burrow Fill & compaction 15.00 m³ 0 600.00 9,000.00 630.00 9,630.00 674.10 10,304.10
11.1.4 Concreting 15.00 m³ 4,100.00 1,230.00 79,950.00 5,596.50 85,546.50 5,988.26 91,534.76
11.1.5 10mm dia Reinforcing Bars 1,200.00 kg 42.00 12.60 65,520.00 4,586.40 70,106.40 4,907.45 75,013.85
11.1.6 Formworks 60.00 m² 221.42 66.43 17,270.57 1,208.94 18,479.50 1,293.57 19,773.07
11.1.7 Railings and Balusters 26.00 m² 1,560.00 468.00 52,728.00 3,690.96 56,418.96 3,949.33 60,368.29
11.1.8 Roll-up Door 1.00 set 85,000.00 25,500.00 110,500.00 7,735.00 118,235.00 8,276.45 126,511.45
11.1.9 Paver blocks 250.00 m² 400.00 120.00 130,000.00 9,100.00 139,100.00 9,737.00 148,837.00
11.1.10 Wall & Slab Soffit Painting Works 200.00 m² 118.23 35.47 30,738.50 2,151.70 32,890.20 2,302.31 35,192.51

Sub-Total 537,492.57 37,624.48 575,117.04 40,258.19 615,375.24

11.2 ACCESS PATHWAY (to Pond)


11.2.1 Demolition Works of existing including hauling 1.00 lot 0 2,250.00 2,250.00 157.50 2,407.50 168.53 2,576.03
11.2.2 Site clearing, Soil preparation 60.00 m² 0 600.00 36,000.00 2,520.00 38,520.00 2,696.40 41,216.40
11.2.3 Burrow Fill & Compaction 15.00 m³ 0 600.00 9,000.00 630.00 9,630.00 674.10 10,304.10
11.2.4 Concreting 12.00 m³ 4,100.00 1,230.00 63,960.00 4,477.20 68,437.20 4,790.60 73,227.80
11.2.5 10mm dia Reinforcing Bars 960.00 kg 42.00 12.60 52,416.00 3,669.12 56,085.12 3,925.96 60,011.08
11.2.6 Formworks 50.00 m² 223.26 66.98 14,511.90 1,015.83 15,527.73 1,086.94 16,614.67
11.2.7 Railings and Balusters 26.00 m² 1,560.00 468.00 52,728.00 3,690.96 56,418.96 3,949.33 60,368.29
11.2.8 Roll-up Door 1.00 set 85,000.00 25,500.00 110,500.00 7,735.00 118,235.00 8,276.45 126,511.45
11.2.9 Paver blocks 250.00 m² 400.00 120.00 130,000.00 9,100.00 139,100.00 9,737.00 148,837.00
11.2.10 Wall & Slab Soffit Painting Works 200.00 m² 107.50 32.25 27,950.00 1,956.50 29,906.50 2,093.46 31,999.96

Sub-Total 499,315.90 34,952.11 534,268.01 37,398.76 571,666.77

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Direct Cost Indirect Cost

Overhead, Total Direct & Value Added


Item No. Work Description Quantity Unit Labor and Contingencies, Indirect Cost Total Cost
Material Total Tax
Equipment Miscellaneous
& Profit

AMOUNT IN FIGURES ### 2,889,657.42 ### ### ###

AMOUNT IN WORDS FORTY-SEVEN MILLION SIX HUNDRED SEVENTY-FOUR THOUSAND THREE HUNDRED SIXTY-ONE PESOS AND TWENTY CENTAVOS

Submitted By:
-

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

(12)

58,850.00
117,700.00

176,550.00

58,850.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

171.74
114.49
114.49
515.21
967.44
1,339.53
148.84

6,182.46
6,182.46
6,182.46
6,182.46
6,182.46
6,182.46
6,182.46
5,770.30
6,182.46
6,182.46
6,182.46

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

65.49
65.49

65.49
62.51

65.49
62.51
62.51

65.49
62.51

65.49
62.51

282.79
195.35
5,983.25

62.51
62.51

62.51

62.51

818.60

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

62.51

62.51
62.51
104.19

314.17
525.79
574.57
543.69
474.24
509.92
741.29
608.34
547.91
522.44
528.48

448.45

649.74

22.33

357.21

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

967.44

62.51

104.19

744.19

59.53

3,709,476.00

10,418.59
71,441.76

54,623.18

4,871.03

32.47
311.79

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

96,744.05

1,098.91

13,097.66

825.19

439.92
116.09
355.19
90.42

818.60
1,034.42
1,205.58
714.42
161,607.21
902.25
595.35

1,097.54

192.14

178.60

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

184.56

818.60

1,034.42
714.42
893.02
714.42
520.93
446.51

99,274.28

773.95
342.33
119.07

1,413.95
215.81
647.44
1,064.18
766.51

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

163.72
320.00

1,911.60
282.79
1,700.99

193.49

37.21
44.65
32.74
44.65
1,116.28
11,162.78
19,348.81
66,976.65

111.63
178.60
647.44
302.14
245.58
275.35
386.98
587.91

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

662.32
28.28
37.21
44.65
66.98
71.44
93.77
86.33
126.51
3,170.23
260.46
186.05
1,413.95

41.67
56.56
96.74
145.86
245.58
334.88
759.07
1,160.93

41.67
56.56
96.74
245.58
617.67
1,116.28

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

49.12

18,604.63
12,651.15

18,604.63

18,604.63

18,604.63

18,604.63

24,930.20

24,930.20

24,930.20

29,023.22

163,720.70

334,883.25

171,162.55

1,265.11
2,976.74
744.19
3,572.09

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

1,265.11

1,786.04
156.28
245.58

37.21
11.91
5.21
26.79
44.65
96.74
133.95
1,294.88

81.86
1,294.88
27,534.85
26,046.48
96,744.05

28,130.19

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

2,723.72
1,433.30
1,433.30
952.56
751.63
453.95
336.37
290.23
215.81

1,220.46
647.44
245.58
327.44
111.63
498.60
483.72
171.16
126.51
89.30
1,205.58
647.44
647.44
647.44
647.44
573.02
573.02
573.02
573.02

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

424.19
491.16
520.93
364.65
260.46
186.05
1,979.53
729.30
818.60
275.35
275.35
200.93
171.16
141.40
178.60
119.07
81.86
111.63
171.16
818.60
520.93
349.77
349.77
290.23
215.81
171.16
133.95
133.95
126.51

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

327.44

513.49

23,367.41
10,939.52
1,562.79
1,116.28
1,175.81
7,025.11
9,674.41

22,325.55

10,865.10
148,502.12

14,401.47

92.78

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

2,699,101.75

111,913.98

54,170.71

11,500.52
566.73
372.09
104.19

22,697.64

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

6,697.67
27,534.85
1,034.42
714.42

15,784.16

773.95
342.33

1,413.95
215.81
647.44
1,064.18
766.51
163.72
320.00
200.93

37.21
37.21
37.21
37.21
1,116.28

3,720.93

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

10,418.59
7,441.85
12,204.63
20,837.18
16,193.47

45.48
45.48

41.67
49.61

1,265.11
2,976.74
5,953.48
245.58

1,530.04
372.09

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

104.19
1,326.14
967.44

1,034.42
714.42

4,733.02

185.25
58.50
52.13
621.12
17.33
15.63
34.23
5.21
520.93
1.12

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

53.09
53.09

41.67
56.56

49.12

1,265.11
2,976.74
2,976.74
3,720.93
1,265.11
401.86
320.00
372.09

11,489.07

74,827.80

19,749.53
75,906.87
1,250.80

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

26,999.03
17,860.44
8,334.87

1,332.69
967.44

1,034.42
714.42

7,039.99

187.42
44.90
55.92
34.23
5.21

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

520.93
1.12

53.09
53.09

41.67
56.56

50.23

1,265.11
2,976.74
2,976.74
3,720.93
1,265.11
156.28
372.09

1,116.28
82.72
520.93

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

1.12
8,586.75

43,448.96
1,579.96
17,860.44
5,953.48

27,010.19
8,334.87

1,530.04
372.09
104.19
967.44
1,326.14

1,034.42
714.42

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

3,564.65

192.61
44.15
48.97
34.23
5.21
520.93
1.12
18.41
15.63
681.83

52.93
52.93

41.67
56.56

49.12

1,265.11

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

2,976.74
2,976.74
3,720.93
1,265.11
401.86
156.28
372.09

21,638.61

74,827.80

19,749.53
75,906.87
43,448.96

27,028.80
17,860.44
8,334.87

1,530.04

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

372.09
104.19
967.44
1,326.14

1,034.42
714.42

4,167.44

186.64
48.12
45.58
34.23
5.21
520.93
1.12
17.52
15.63
680.93

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

37.21
37.21

41.67
56.56

49.20

1,265.11
2,976.74
2,976.74
3,720.93
1,265.11
401.86
320.00
245.58
372.09

21,638.61

74,827.80

19,749.53
75,906.87
10,991.04

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

28,718.10
17,860.44
8,334.87

1,530.04
372.09
104.19
967.44
1,327.96

1,034.42
714.42

3,520.00

180.09
56.95

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

51.63
34.23
5.21
520.93
1.12
17.77
15.63
679.47

37.21
37.21

41.67
56.56

49.12

1,265.11
2,976.74
2,976.74
3,720.93
1,265.11
401.86
320.00
372.09

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

11,677.98

74,827.80

19,749.53
75,906.87
1,250.80

28,606.47
17,860.44
8,334.87

1,530.04
372.09
104.19
967.44
1,326.14

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

1,034.42
714.42

2,574.88

187.11
49.57
54.40
34.23
5.21
520.93
1.12
19.46
15.63
678.70

37.21
37.21

41.67
56.56

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

49.12

1,265.11
2,976.74
2,976.74
3,720.93
1,265.11
401.86
320.00
372.09

10,819.31

74,827.80

19,749.53
75,906.87
1,250.80

28,606.47
17,860.44
8,334.87

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

6,623.82
686.94
686.94
6,102.32
62.51
329.55
2,321.86
126,511.45
595.35
175.96

2,576.03
686.94
686.94
6,102.32
62.51
332.29
2,321.86
126,511.45
595.35
160.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Cost per
Unit of Work
Item

CENTAVOS

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City
PAY ITEM: 1 QTY/UNIT: 1.00 LOT
DESCRIPTION: GENERAL REQUIREMENTS
a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a
TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
1.1 Mobilization/Demobilization 1.00 lot 5,000.00
1.2 Temporary Facilities 1.00 lot 10,000.00
1.2.1 Temporary Barracks & Storage
1.2.2 Temporary Fence/Board-up
1.2.3 Temporary Water and Power Consumption
1.3 Permits and Licenses 1.00 lot 15,000.00
1.3.1 Building Permit Processing, fire clearance, occupancy
1.3.2 Licenses and certifications - operations
1.4 Safety and Health 1.00 lot 5,000.00
1.4.1 Pre-cautionary Signages, Safety nets & Scaffolds
1.4.2 Personal Protective Equipment for personnel
TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
1.1 Mobilization/Demobilization
1.2 Temporary Facilities 1.00 lot 50,000.00
1.2.1 Temporary Barracks & Storage 1.00 lot 100,000.00
1.2.2 Temporary Fence/Board-up
1.2.3 Temporary Water and Power Consumption
1.3 Permits and Licenses
1.3.1 Building Permit Processing, fire clearance, occupancy 1.00 lot 150,000.00
1.3.2 Licenses and certifications - operations
1.4 Safety and Health
1.4.1 Pre-cautionary Signages, Safety nets & Scaffolds 1.00 lot 50,000.00
1.4.2 Personal Protective Equipment for personnel
TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager /01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 2 QTY/UNIT: 1.00 LOT


DESCRIPTION:SUNSHADING, STAIRCASE, ELEVATOR, PUMP RM, CISTERN

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
2.1 EARTHWORKS
2.1.1 Site Clearing (including cutting & bases) 1,120.00 m² 150.00
2.1.2 Demolition (selected windows and plantboxes) see dwgs 160.00 m² 100.00
2.1.3 Layout and Staking 1,120.00 m² 100.00
2.1.4 Excavation 575.00 m³ 450.00
2.1.5 Backfill / Compaction 412.00 m³ 195.00
2.1.6 Gravelbase Coarse 20.00 m³ 270.00
2.1.7 Soil Poisoning 280.00 m² 30.00

2.2 CONCRETING
2.2.1 Footing 100.00 m³ 900.00
2.2.2 Shear Wall of Elevator Shaft & Cistern Tank 47.00 m³ 900.00
2.2.3 Pedestal, Encasement & Pull Box (Service Entrance) 20.00 m³ 900.00
2.2.4 Columns 86.00 m³ 900.00
2.2.5 Beams 148.00 m³ 900.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
2.2.6 Roof Beams 58.00 m³ 900.00
2.2.7 Suspended Slab. Ledges, Staircase 157.00 m³ 900.00
2.2.8 Slab on fill 14.00 m³ 840.00
2.2.9 Concrete Trellis (Sunshading) 10.00 m³ 900.00
2.2.10 Vertical Fins (Sunshading) 155.00 m³ 900.00
2.2.11 Stiffener Columns 19.00 m³ 900.00

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg 13.20
2.3.1.2 16mm Dia Rebar 615.00 kg 13.20
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg 13.20
2.3.2.2 12mm Dia Rebar 1,780.00 kg 12.60
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg 13.20
2.3.3.2 10mm Dia Rebar 920.00 kg 12.60
2.3.3.3 12mm dia rebar 19.00 kg 12.60
2.3.4 Beam Rebars
2.3.4.1 20mm Dia Rebar 20,404.00 kg 13.20
2.3.4.2 10mm Dia Rebar 7,230.00 kg 12.60
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg 13.20
2.3.5.2 10mm Dia Rebar 2,930.00 kg 12.60
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m 57.00
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m 39.38
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot 1,206.00
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg 12.60
2.3.7.2 10mm dia rebar 2,834.00 kg 12.60
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg 12.60
2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg 12.60
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m² 165.00
2.3.10.2 12mm dia Rebar 9,720.00 kg 12.60
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg 12.60
2.3.11.2 10mm Dia Rebar 1,150.00 kg 12.60
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg 21.00

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m² 63.33
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m² 105.98
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m² 115.81
2.4.4 Columns 61.92 m² 109.59
2.4.5 Beams 106.56 m² 95.59
2.4.6 Roof Beams 41.76 m² 102.78
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m² 149.42
2.4.8 Slab on fill 10.08 m² 122.62
2.4.9 Concrete Trellis (Sunshading) 72.00 m² 110.44
2.4.10 Vertical Fins (Sunshading) 486.00 m² 105.30
2.4.11 Stiffener Columns 120.00 m² 106.52

2.5 MASONRY & WATERPROOFING


2.5.1 Integral Waterproofing (decks, cistern & elevator pit) 1,600.00 kg 90.39

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
2.5.2 Cementitious waterproofing lining (decks, plantbox & cistern) 1,100.00 m² 130.96

2.5.3 6" thk CHB parapet Walls 1,144.00 pc 4.50


2.5.4 mortar and Plastering
2.5.4.1 Cement 210.00 bag 72.00
2.5.4.2 Sand 20.00 m³ 195.00
2.5.5 10mm dia horiz and Vertical rebars for CHB and Deco Blocks 1,820.00 kg 12.60
2.5.6 #16 Gi Tie Wire 182.00 kg 21.00
2.5.7 Heavy Duty Cement-based Adhesive for Decorative Blocks 450.00 bag 150.00
2.5.8 Decorative Blocks (Sunshading) 250 x 250 x 88 9,300.00 pc 12.00

2.6 EQUIPMENT

Machine roomless elevator Equipment 1500 kg, 3 stops (3 front


openings) 1m/s, steel hoist Silver brushed car Walls, w/ gray
Black Granite Car Floor, Silver brushed skirting, mirror on walls,
2.6.1 1.00 set 540,000.00
LED direct light 7.6kW, 31A-43A, 3P, 230V 60Hz incl reqd
electrical outlets, breakers and exhaust fans, incl I-Beams or any
strucl steel reqd for installation

2.6.2 Electric Water Heater (complete with telephone Shower) 6.00 set 2,100.00
2.6.3 2HP Electric Submersible Pump (at Elevator pit) 1.00 set 14,400.00
Booster Pump (1HP) (40PSI) (65% efficiency) w/ foot valve w/
2.6.4 1.00 set 11,010.00
Bladder Tank (30gal) w/ complete accessories

2.7 FINISHING WORKS


Engineer weatherproof wood planks (25mm thk)- 150mm x
2.7.1 880.00 m² 981.82
900mm
2.7.1.1 Cement Glue for Floor Plank 880.00 m² 6.55
2.7.2 Non-Skid Rubberized Painted Finish (Hallways) 232.00 m² 62.84
Built-up Acrylic LED Lighted Signage with 9mm thk Acrylic built-
2.7.3 1.00 set 19,500.00
up letters, LED lighting, mounting and installation

Elevator & Pump Room Roof, Rib Type G.I. (0.5mm), prepainted
2.7.4 120.00 m² 221.50
Longspan incl flushings; w/ insulation
2.7.5 Roof Works Miscellaneous (Tuxscrews, Silicon, blind rivets) 1.00 lot 2,640.00
2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m² 166.33
2.7.7 Balcony & Stair Handrails & railing (painted Finish)
2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m² 88.67
2.7.7.2 12mm Square Bar 28.00 m 23.40
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m 71.59
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m² 18.23
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal 165.00
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal 208.50
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal 243.00
2.7.9.4 Flat Latex Paint 185.00 gal 144.00
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot 32,574.00
2.7.10 uPVC Clear Transparent Rib Type Roof + misc. 250.00 m² 181.86
2.7.11 Paver blocks 250.00 m² 120.00

TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
2.1 EARTHWORKS
2.1.1 Site Clearing (including cutting & bases) 1,120.00 m² 0
2.1.2 Demolition (selected windows and plantboxes) see dwgs 160.00 m² 0
2.1.3 Layout and Staking 1,120.00 m² 0
2.1.4 Excavation 575.00 m³ 0

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
2.1.5 Backfill / Compaction 412.00 m³ 650.00
2.1.6 Gravelbase Coarse 20.00 m³ 900.00
2.1.7 Soil Poisoning 280.00 m² 100.00

2.2 CONCRETING
2.2.1 Footing 100.00 m³ 4,500.00
2.2.2 Shear Wall of Elevator Shaft & Cistern Tank 47.00 m³ 4,500.00
2.2.3 Pedestal, Encasement & Pull Box (Service Entrance) 20.00 m³ 4,500.00
2.2.4 Columns 86.00 m³ 4,500.00
2.2.5 Beams 148.00 m³ 4,500.00
2.2.6 Roof Beams 58.00 m³ 4,500.00
2.2.7 Suspended Slab. Ledges, Staircase 157.00 m³ 4,500.00
2.2.8 Slab on fill 14.00 m³ 4,200.00
2.2.9 Concrete Trellis (Sunshading) 10.00 m³ 4,500.00
2.2.10 Vertical Fins (Sunshading) 155.00 m³ 4,500.00
2.2.11 Stiffener Columns 19.00 m³ 4,500.00

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg 44.00
2.3.1.2 16mm Dia Rebar 615.00 kg 44.00
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg 44.00
2.3.2.2 12mm Dia Rebar 1,780.00 kg 42.00
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg 44.00
2.3.3.2 10mm Dia Rebar 920.00 kg 42.00
2.3.3.3 12mm dia rebar 19.00 kg 42.00
2.3.4 Beam Rebars
2.3.4.1 20mm Dia Rebar 20,404.00 kg 44.00
2.3.4.2 10mm Dia Rebar 7,230.00 kg 42.00
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg 44.00
2.3.5.2 10mm Dia Rebar 2,930.00 kg 42.00
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m 190.00
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m 131.25
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot 4,020.00
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg 42.00
2.3.7.2 10mm dia rebar 2,834.00 kg 42.00
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg 42.00
2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg 42.00
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m² 550.00
2.3.10.2 12mm dia Rebar 9,720.00 kg 42.00
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg 42.00
2.3.11.2 10mm Dia Rebar 1,150.00 kg 42.00
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg 70.00

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m² 211.08
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m² 353.27
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m² 386.04
2.4.4 Columns 61.92 m² 365.29

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
2.4.5 Beams 106.56 m² 318.63
2.4.6 Roof Beams 41.76 m² 342.60
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m² 498.06
2.4.8 Slab on fill 10.08 m² 408.73
2.4.9 Concrete Trellis (Sunshading) 72.00 m² 368.13
2.4.10 Vertical Fins (Sunshading) 486.00 m² 351.02
2.4.11 Stiffener Columns 120.00 m² 355.07

2.5 MASONRY & WATERPROOFING


2.5.1 Integral Waterproofing (decks, cistern & elevator pit) 1,600.00 kg 301.30

2.5.2 Cementitious waterproofing lining (decks, plantbox & cistern) 1,100.00 m² 436.55

2.5.3 6" thk CHB parapet Walls 1,144.00 pc 15.00


2.5.4 mortar and Plastering
2.5.4.1 Cement 210.00 bag 240.00
2.5.4.2 Sand 20.00 m³ 650.00
2.5.5 10mm dia horiz and Vertical rebars for CHB and Deco Blocks 1,820.00 kg 42.00
2.5.6 #16 Gi Tie Wire 182.00 kg 70.00
2.5.7 Heavy Duty Cement-based Adhesive for Decorative Blocks 450.00 bag 500.00
2.5.8 Decorative Blocks (Sunshading) 250 x 250 x 88 9,300.00 pc 40.00

2.6 EQUIPMENT

Machine roomless elevator Equipment 1500 kg, 3 stops (3 front


openings) 1m/s, steel hoist Silver brushed car Walls, w/ gray
Black Granite Car Floor, Silver brushed skirting, mirror on walls,
2.6.1 1.00 set ###
LED direct light 7.6kW, 31A-43A, 3P, 230V 60Hz incl reqd
electrical outlets, breakers and exhaust fans, incl I-Beams or any
strucl steel reqd for installation

2.6.2 Electric Water Heater (complete with telephone Shower) 6.00 set 7,000.00
2.6.3 2HP Electric Submersible Pump (at Elevator pit) 1.00 set 48,000.00
Booster Pump (1HP) (40PSI) (65% efficiency) w/ foot valve w/
2.6.4 1.00 set 36,700.00
Bladder Tank (30gal) w/ complete accessories

2.7 FINISHING WORKS


Engineer weatherproof wood planks (25mm thk)- 150mm x
2.7.1 880.00 m² 3,272.73
900mm
2.7.1.1 Cement Glue for Floor Plank 880.00 m² 21.82
2.7.2 Non-Skid Rubberized Painted Finish (Hallways) 232.00 m² 209.48
Built-up Acrylic LED Lighted Signage with 9mm thk Acrylic built-
2.7.3 1.00 set 65,000.00
up letters, LED lighting, mounting and installation

Elevator & Pump Room Roof, Rib Type G.I. (0.5mm), prepainted
2.7.4 120.00 m² 738.33
Longspan incl flushings; w/ insulation
2.7.5 Roof Works Miscellaneous (Tuxscrews, Silicon, blind rivets) 1.00 lot 8,800.00
2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m² 554.43
2.7.7 Balcony & Stair Handrails & railing (painted Finish)
2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m² 295.57
2.7.7.2 12mm Square Bar 28.00 m 78.00
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m 238.64
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m² 60.75
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal 550.00
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal 695.00
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal 810.00
2.7.9.4 Flat Latex Paint 185.00 gal 480.00
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot 108,580.00
2.7.10 uPVC Clear Transparent Rib Type Roof + misc. 250.00 m² 606.20
2.7.11 Paver blocks 250.00 m² 400.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 3 QTY/UNIT: 1.00 LOT


DESCRIPTION: GENERAL REPAIR & IMPROVEMENTS ON CAFA BUILDING

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
3.1 ROOFING AND EAVES SOFFIT
Replacement of delapidated roofing, (pre-painted longspan,
3.1.1 1,100.00 m 290.45
ribtype, G.I. 0.5mm thk)
3.1.2 Insulation (double sided aluminum) (w/ chicken wire) 1,100.00 m² 38.73
Replacement of Eaves Soffit - Spandrel (110mm wide), (pre-
3.1.3 2,000.00 m 36.00
painted G.I., 0.5mm thk) complete w/ misc.

Spandrel Mouldings/Edging Wall Angles, complete w/


3.1.4 450.00 m 37.20
misc./silicon

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal 165.00

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal 208.50

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.2.3 Flat Latex for Existing Ceiling 90.00 gal 144.00
3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal 180.00
3.2.5 Flat Latex Primer 150.00 gal 144.00
3.2.6 Metal Primer, rust Converters 5.00 gal 105.00
3.2.7 Paint Thinner 2.00 gal 90.00

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot 20,010.00

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m 156.00
3.3.1.2 100mm Ø 29.00 m 69.00
3.3.1.3 50mm Ø 29.00 m 24.00
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc 285.00
3.3.2.2 Wye 100 x 100 4.00 pc 43.50
3.3.2.3 Elbow 90" x 100 44.00 pc 130.50
3.3.2.4 Elbow 45" x 200 3.00 pc 214.50
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc 154.50
3.3.2.6 Sanitary Tee 100 x 50 25.00 pc 33.00
3.3.2.7 P-Trap 100 22.00 pc 64.50
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc 385.31
3.3.3.2 Solvent / Adhesive 20.00 qt 57.00
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc 342.86
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56.00 m 39.00
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57.00 pc 7.50
3.3.4.2.2 25mm Tee 30.00 pc 9.00
3.3.4.2.3 25mm Coupling 9.00 pc 6.60
3.3.4.2.4 25mm Reducer 10.00 pc 9.00
3.3.4.2.5 25mm Gate Valve 6.00 pc 225.00
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4.00 set 2,250.00
3.3.4.5 1000L Polyethylene Water Tank 1.00 pc 3,900.00
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1.00 set 13,500.00

3.4 ELECTRICAL WORKS & FIXTURES


3.4.1 Conduits
3.4.1.1 1/2" Ø PVC 214.00 pc 22.50
3.4.1.2 3/4" Ø PVC 527.00 pc 36.00
3.4.1.3 2 1/2" Ø PVC 63.00 pc 130.50
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set 60.90
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set 49.50
3.4.1.6 3/4" Ø EMT 10.00 pc 55.50
3.4.1.7 1" Ø EMT 75.00 pc 78.00
3.4.1.8 1 1/4" Ø EMT 14.00 pc 118.50
3.4.1.9 1 1/2" Ø EMT 12.00 pc 133.50
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc 5.70
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set 7.50
3.4.1.12 1" Ø EMT Coupling 72.00 pc 9.00
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set 13.50
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc 14.40
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set 18.90
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc 17.40
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set 25.50
3.4.1.18 2 1/2" Ø RSC 29.00 pc 639.00
3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc 52.50

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set 37.50
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc 285.00
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m 8.40
3.4.2.2 5.5mm2 THHN Cu 483.00 m 11.40
3.4.2.3 8.0mm2 THHN Cu 118.00 m 19.50
3.4.2.4 14mm2 THHN Cu 106.00 m 29.40
3.4.2.5 22mm2 THHN Cu 39.00 m 49.50
3.4.2.6 30mm2 THHN Cu 12.00 m 67.50
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m 153.00
3.4.2.8 125mm2 THHN Cu 853.00 m 234.00
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m 8.40
3.4.3.2 5.5mm2 Cu Grounding 257.00 m 11.40
3.4.3.3 8.0mm2 Cu Grounding 104.00 m 19.50
3.4.3.4 30mm2 Cu Grounding 73.00 m 49.50
3.4.3.5 60mm2 Cu Grounding 5.00 m 124.50
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc 225.00
3.4.4 Others
3.4.4.1 Junction and Utility Boxes 800.00 pc 9.90
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set 3,750.00
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set 2,550.00
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P +
3.4.5.3 1.00 set 3,750.00
2 Spare
3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 3,750.00
3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 3,750.00
3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set 3,750.00
3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set 5,025.00
90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P +
3.4.5.8 1.00 set 5,025.00
2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P +


3.4.5.9 1.00 set 5,025.00
2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-40AT,


3.4.5.10 1.00 set 5,850.00
2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set 33,000.00
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P + 100AT,
3.4.5.12 1.00 set 67,500.00
3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set 34,500.00
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set 255.00
3.4.6.2 Emergency Light 24.00 set 600.00
3.4.6.3 Strip Light (Cove Light) 500.00 m 150.00
3.4.6.4 36 W Up Light Garden Light 70.00 pc 720.00
3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc 255.00
3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc 360.00
3.4.6.7 One Gang Switch 30.00 pc 31.50
3.4.6.8 Two gang Switch 30.00 pc 49.50

3.5 FIRE ALARM WORKS & FIXTURES


3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes
3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m 7.50
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc 2.40
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc 1.05
3.5.1.4 15mm Ø St. Connector 100.00 pc 5.40
3.5.1.5 Utility Box 100.00 pc 9.00
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc 19.50
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc 27.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.5.1.8 Fire Alarm Pull Box 25.00 pc 261.00
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m 16.50
3.5.3 Smoke Detectors 141.00 set 261.00
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set 5,550.00
3.5.5 Monitoring Switches (6 zones) 1.00 set 5,250.00
3.5.6 Fire Alarm Check Valve 1.00 set 19,500.00
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot 5,670.00
Accessories, Solvents)

3.6 FIRE PROTECTION/SPRINKLER SYSTEM


3.6.1 BI Pipe and Fittings
3.6.1.1 150mm Ø S40 BI Pipes 29.00 m 549.00
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m 288.90
3.6.1.3 80mm Ø S40 BI Pipes 60.00 m 288.90
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m 192.00
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m 151.50
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m 91.50
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m 67.80
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m 58.50
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m 43.50
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc 246.00
3.6.2.2 BI Tee welded type 100mm 3.00 pc 130.50
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc 49.50
3.6.2.4 BI Tee threaded type 50mm 3.00 pc 66.00
3.6.2.5 BI Tee threaded type 25mm 50.00 pc 22.50
3.6.2.6 BI Elbow welded type 150mm 2.00 pc 100.50
3.6.2.7 BI Elbow welded type 100mm 9.00 pc 97.50
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc 34.50
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc 25.50
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc 18.00
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc 243.00
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc 130.50
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc 130.50
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc 130.50
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc 130.50
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc 115.50
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc 115.50
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc 115.50
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc 115.50
3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc 85.50
3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc 99.00
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc 105.00
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc 73.50
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc 52.50
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc 37.50
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc 399.00
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc 147.00
3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc 165.00
3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc 55.50
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc 55.50
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc 40.50
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc 34.50
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc 28.50
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc 36.00
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc 24.00
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc 16.50

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc 22.50
3.6.2.38 BI Union Patente 25mm 3.00 pc 34.50
3.6.2.39 Slip on flange 150mm 36.00 pc 165.00
3.6.2.40 Slip on flange 100mm 84.00 pc 105.00
3.6.2.41 Slip on flange 80mm 12.00 pc 70.50
3.6.2.42 Slip on flange 75mm 6.00 pc 70.50
3.6.2.43 Slip on flange 65mm 18.00 pc 58.50
3.6.2.44 Rubber Gasket 150mm 18.00 pc 43.50
3.6.2.45 Rubber Gasket 100mm 42.00 pc 34.50
3.6.2.46 Rubber Gasket 80mm 6.00 pc 27.00
3.6.2.47 Rubber Gasket 75mm 3.00 pc 27.00
3.6.2.48 Rubber Gasket 65mm 9.00 pc 25.50
3.6.3 Valve, Sprinkler, FHC and Accessories

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc 66.00
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc 103.50
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc 4,710.00


3.6.3.4 Fire Hose Valve 65mm 7.00 pc 2,205.00
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc 315.00
3.6.3.6 Inspector Test valve 25mm 7.00 pc 225.00
3.6.3.7 Sight Glass 25mm 7.00 pc 237.00
3.6.3.8 Water Flow Switch 7.00 pc 1,416.00
3.6.3.9 Supervisory Switch 7.00 pc 1,950.00

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc 4,500.00
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc 2,190.00


3.6.4 Hanger and Brackets 1.00 lot 29,932.50
3.6.4.1 Bolt and Nut and Washer 5/8 x 4"
3.6.4.2 Angle Bar 2" x 2" x 1/4"
3.6.4.3 Full threaded 3/8
3.6.4.4 Loop Hanger 75mm
3.6.4.5 Loop Hanger 25mm
3.6.4.6 U-Bolt 75mm x 1/2
3.6.4.7 U-Bolt 150mm x 5/8
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot 2,902.80
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe)
3.6.5.1 Clear Silicon Sealant
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m² 18.70
3.6.7 Fire Fighting Equipment & Installation

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set 307,500.00
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set 12,750.00
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot 10,918.80
3.6.8.1 teflon tape
3.6.8.2 red Oxide
3.6.8.3 grip anchor 3/8
3.6.8.4 expansion Shield 3/8 x 2
3.6.8.5 grinding stone 4"
3.6.8.6 cut off disks 14"
3.6.8.7 weldingrRod 6011
3.6.8.8 welding rod 6013
3.6.8.9 Abaca sacks

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.6.8.10 Flinknote

TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
3.1 ROOFING AND EAVES SOFFIT
Replacement of delapidated roofing, (pre-painted longspan,
3.1.1 1,100.00 m 668.18
ribtype, G.I. 0.5mm thk)
3.1.2 Insulation (double sided aluminum) (w/ chicken wire) 1,100.00 m² 129.09
Replacement of Eaves Soffit - Spandrel (110mm wide), (pre-
3.1.3 2,000.00 m 120.00
painted G.I., 0.5mm thk) complete w/ misc.

Spandrel Mouldings/Edging Wall Angles, complete w/


3.1.4 450.00 m 124.00
misc./silicon

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal 550.00

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal 695.00
3.2.3 Flat Latex for Existing Ceiling 90.00 gal 480.00
3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal 600.00
3.2.5 Flat Latex Primer 150.00 gal 480.00
3.2.6 Metal Primer, rust Converters 5.00 gal 350.00
3.2.7 Paint Thinner 2.00 gal 300.00

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot 66,700.00

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m 520.00
3.3.1.2 100mm Ø 29.00 m 230.00
3.3.1.3 50mm Ø 29.00 m 80.00
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc 950.00
3.3.2.2 Wye 100 x 100 4.00 pc 145.00
3.3.2.3 Elbow 90" x 100 44.00 pc 435.00
3.3.2.4 Elbow 45" x 200 3.00 pc 715.00
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc 515.00
3.3.2.6 Sanitary Tee 100 x 50 25.00 pc 110.00
3.3.2.7 P-Trap 100 22.00 pc 215.00
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc 1,284.36
3.3.3.2 Solvent / Adhesive 20.00 qt 190.00
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc 1,142.86
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56.00 m 130.00
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57.00 pc 25.00
3.3.4.2.2 25mm Tee 30.00 pc 30.00
3.3.4.2.3 25mm Coupling 9.00 pc 22.00
3.3.4.2.4 25mm Reducer 10.00 pc 30.00
3.3.4.2.5 25mm Gate Valve 6.00 pc 750.00
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4.00 set 7,500.00
3.3.4.5 1000L Polyethylene Water Tank 1.00 pc 13,000.00
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1.00 set 45,000.00

3.4 ELECTRICAL WORKS & FIXTURES


3.4.1 Conduits

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.4.1.1 1/2" Ø PVC 214.00 pc 75.00
3.4.1.2 3/4" Ø PVC 527.00 pc 120.00
3.4.1.3 2 1/2" Ø PVC 63.00 pc 435.00
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set 203.00
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set 165.00
3.4.1.6 3/4" Ø EMT 10.00 pc 185.00
3.4.1.7 1" Ø EMT 75.00 pc 260.00
3.4.1.8 1 1/4" Ø EMT 14.00 pc 395.00
3.4.1.9 1 1/2" Ø EMT 12.00 pc 445.00
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc 19.00
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set 25.00
3.4.1.12 1" Ø EMT Coupling 72.00 pc 30.00
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set 45.00
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc 48.00
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set 63.00
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc 58.00
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set 85.00
3.4.1.18 2 1/2" Ø RSC 29.00 pc 2,130.00
3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc 175.00
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set 125.00
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc 950.00
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m 28.00
3.4.2.2 5.5mm2 THHN Cu 483.00 m 38.00
3.4.2.3 8.0mm2 THHN Cu 118.00 m 65.00
3.4.2.4 14mm2 THHN Cu 106.00 m 98.00
3.4.2.5 22mm2 THHN Cu 39.00 m 165.00
3.4.2.6 30mm2 THHN Cu 12.00 m 225.00
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m 510.00
3.4.2.8 125mm2 THHN Cu 853.00 m 780.00
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m 28.00
3.4.3.2 5.5mm2 Cu Grounding 257.00 m 38.00
3.4.3.3 8.0mm2 Cu Grounding 104.00 m 65.00
3.4.3.4 30mm2 Cu Grounding 73.00 m 165.00
3.4.3.5 60mm2 Cu Grounding 5.00 m 415.00
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc 750.00
3.4.4 Others
3.4.4.1 Junction and Utility Boxes 800.00 pc 33.00
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set 12,500.00
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set 8,500.00
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P +
3.4.5.3 1.00 set 12,500.00
2 Spare
3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00
3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set 12,500.00
3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set 12,500.00
3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set 16,750.00
90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P +
3.4.5.8 1.00 set 16,750.00
2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P +


3.4.5.9 1.00 set 16,750.00
2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-40AT,


3.4.5.10 1.00 set 19,500.00
2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set 110,000.00
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P + 100AT,
3.4.5.12 1.00 set 225,000.00
3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set 115,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set 850.00
3.4.6.2 Emergency Light 24.00 set 2,000.00
3.4.6.3 Strip Light (Cove Light) 500.00 m 500.00
3.4.6.4 36 W Up Light Garden Light 70.00 pc 2,400.00
3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc 850.00
3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc 1,200.00
3.4.6.7 One Gang Switch 30.00 pc 105.00
3.4.6.8 Two gang Switch 30.00 pc 165.00

3.5 FIRE ALARM WORKS & FIXTURES


3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes
3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m 25.00
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc 8.00
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc 3.50
3.5.1.4 15mm Ø St. Connector 100.00 pc 18.00
3.5.1.5 Utility Box 100.00 pc 30.00
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc 65.00
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc 90.00
3.5.1.8 Fire Alarm Pull Box 25.00 pc 870.00
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m 55.00
3.5.3 Smoke Detectors 141.00 set 870.00
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set 18,500.00
3.5.5 Monitoring Switches (6 zones) 1.00 set 17,500.00
3.5.6 Fire Alarm Check Valve 1.00 set 65,000.00
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot 18,900.00
Accessories, Solvents)

3.6 FIRE PROTECTION/SPRINKLER SYSTEM


3.6.1 BI Pipe and Fittings
3.6.1.1 150mm Ø S40 BI Pipes 29.00 m 1,830.00
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m 963.00
3.6.1.3 80mm Ø S40 BI Pipes 60.00 m 963.00
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m 640.00
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m 505.00
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m 305.00
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m 226.00
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m 195.00
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m 145.00
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc 820.00
3.6.2.2 BI Tee welded type 100mm 3.00 pc 435.00
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc 165.00
3.6.2.4 BI Tee threaded type 50mm 3.00 pc 220.00
3.6.2.5 BI Tee threaded type 25mm 50.00 pc 75.00
3.6.2.6 BI Elbow welded type 150mm 2.00 pc 335.00
3.6.2.7 BI Elbow welded type 100mm 9.00 pc 325.00
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc 115.00
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc 85.00
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc 60.00
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc 810.00
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc 435.00
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc 435.00
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc 435.00
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc 435.00
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc 385.00
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc 385.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc 385.00
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc 385.00
3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc 285.00
3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc 330.00
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc 350.00
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc 245.00
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc 175.00
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc 125.00
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc 1,330.00
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc 490.00
3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc 550.00
3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc 185.00
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc 185.00
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc 135.00
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc 115.00
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc 95.00
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc 120.00
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc 80.00
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc 55.00
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc 75.00
3.6.2.38 BI Union Patente 25mm 3.00 pc 115.00
3.6.2.39 Slip on flange 150mm 36.00 pc 550.00
3.6.2.40 Slip on flange 100mm 84.00 pc 350.00
3.6.2.41 Slip on flange 80mm 12.00 pc 235.00
3.6.2.42 Slip on flange 75mm 6.00 pc 235.00
3.6.2.43 Slip on flange 65mm 18.00 pc 195.00
3.6.2.44 Rubber Gasket 150mm 18.00 pc 145.00
3.6.2.45 Rubber Gasket 100mm 42.00 pc 115.00
3.6.2.46 Rubber Gasket 80mm 6.00 pc 90.00
3.6.2.47 Rubber Gasket 75mm 3.00 pc 90.00
3.6.2.48 Rubber Gasket 65mm 9.00 pc 85.00
3.6.3 Valve, Sprinkler, FHC and Accessories

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc 220.00
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc 345.00
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc 15,700.00


3.6.3.4 Fire Hose Valve 65mm 7.00 pc 7,350.00
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc 1,050.00
3.6.3.6 Inspector Test valve 25mm 7.00 pc 750.00
3.6.3.7 Sight Glass 25mm 7.00 pc 790.00
3.6.3.8 Water Flow Switch 7.00 pc 4,720.00
3.6.3.9 Supervisory Switch 7.00 pc 6,500.00

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc 15,000.00
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc 7,300.00


3.6.4 Hanger and Brackets 1.00 lot 99,775.00
3.6.4.1 Bolt and Nut and Washer 5/8 x 4"
3.6.4.2 Angle Bar 2" x 2" x 1/4"
3.6.4.3 Full threaded 3/8
3.6.4.4 Loop Hanger 75mm
3.6.4.5 Loop Hanger 25mm
3.6.4.6 U-Bolt 75mm x 1/2
3.6.4.7 U-Bolt 150mm x 5/8
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot 9,676.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe) 1.00 lot 7,876.00
3.6.5.1 Clear Silicon Sealant 15.00 tubes 120.00
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m² 62.33
3.6.7 Fire Fighting Equipment & Installation

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set ###
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set 85,000.00
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot 36,396.00
3.6.8.1 teflon tape
3.6.8.2 red Oxide
3.6.8.3 grip anchor 3/8
3.6.8.4 expansion Shield 3/8 x 2
3.6.8.5 grinding stone 4"
3.6.8.6 cut off disks 14"
3.6.8.7 weldingrRod 6011
3.6.8.8 welding rod 6013
3.6.8.9 Abaca sacks
3.6.8.10 Flinknote

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 4 QTY/UNIT: 1.00 LOT


DESCRIPTION: TOILETS (2 @Ground, 1 @ Third Flr)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot 10,045.00
4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m² 114.23
4.1.3 Tile Adhesive 86.67 bag 75.00
4.1.4 Tile Grout 8.67 kg 21.00

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set 4,575.00
4.2.2 Powder Coated Window (see schedule) 12.00 set 1,350.00
4.2.3 Laminated Modular partitions with SS accessories 15.00 set 5,550.00
4.2.4 Semi Gloss Latex 15.00 gal 208.50
4.2.5 Flat Latex Paint 15.00 gal 144.00
4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 3,181.50

4.3 PLUMBING WORKS


4.3.1 PVC Pipes Series 1000
4.3.1.1 150mm Ø 77.00 m 156.00
4.3.1.2 100mm Ø 188.00 m 69.00
4.3.2 PVC Fittings Series 1000
4.3.2.1 Wye 150 x 150 21.00 pc 285.00
4.3.2.2 Wye 100 x 100 24.00 pc 43.50
4.3.2.3 Elbow 90" x 100 66.00 pc 130.50
4.3.2.4 Elbow 45" x 200 6.00 pc 214.50
4.3.2.5 Sanitary Tee 150 x 100 24.00 pc 154.50
4.3.2.6 Sanitary Tee 100 x 50 39.00 pc 33.00
4.3.2.7 P-Trap 100 39.00 pc 64.50
4.3.3 19mm Ø PPR Pipes (PN20) 100.00 m 40.50
4.3.4 PPR Fittings
4.3.4.1 Elbow 90 x 19 85.50 pc 7.50
4.3.4.2 Tee 19 x 19 45.00 pc 7.50

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
4.3.4.3 Coupling 25 x 25 13.50 pc 7.50
4.3.4.4 Coupling 25 x 19 15.00 pc 7.50
4.3.4.5 Gate Valve 19 6.00 pc 225.00
4.3.5 Sanitary Fixtures
4.3.5.1 Shower Head and Shower Valves 6.00 set 750.00
4.3.5.2 Telephone Water Heater 6.00 set 2,100.00
4.3.5.3 Lavatory Sink 15.00 set 1,500.00
4.3.5.4 Water Closet dual flush 12.00 set 2,460.00
4.3.5.5 Waterless Urinal 7.00 set 4,200.00
4.3.6 Miscellaneous/Consumables 1.00 lot 3,264.00
4.3.6.1 Pipe Sleeves
4.3.6.2 Pipe Hangers & Support
4.3.6.3 Teflon, Solvent etc.

4.4 ELECTRICAL WORKS & FIXTURES


4.4.1 Conduits
4.4.1.1 15mm dia PVC (Lighting) 270.00 m 9.17
4.4.1.2 15mm dia PVC (power lines) 270.00 m 9.17
4.4.2 Wires and Cables (Ground Floor Toilet Only)
4.4.2.1 2-3.5mm THHN cu. Stranded Wires 540.00 m 8.40
4.4.3 Junction and utility Boxes 120.00 pc 10.00
4.4.4 Electrical Fixtures
4.4.4.1 100mm dia Cylindrical Downlight Fixture with LED 13W 33.00 pc 255.00
4.4.4.2 Emergency Light 6.00 pc 600.00
4.4.4.3 Ceiling Exhaust Fan & Switch (heavy duty) 6.00 pc 1,200.00
4.4.4.4 Two Gang Switch 9.00 pc 49.50

TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot 0
4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m² 380.77
4.1.3 Tile Adhesive 86.67 bag 250.00
4.1.4 Tile Grout 8.67 kg 70.00

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set 15,250.00
4.2.2 Powder Coated Window (see schedule) 12.00 set 4,500.00
4.2.3 Laminated Modular partitions with SS accessories 15.00 set 18,500.00
4.2.4 Semi Gloss Latex 15.00 gal 695.00
4.2.5 Flat Latex Paint 15.00 gal 480.00
4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 10,605.00

4.3 PLUMBING WORKS


4.3.1 PVC Pipes Series 1000
4.3.1.1 150mm Ø 77.00 m 520.00
4.3.1.2 100mm Ø 188.00 m 230.00
4.3.2 PVC Fittings Series 1000
4.3.2.1 Wye 150 x 150 21.00 pc 950.00
4.3.2.2 Wye 100 x 100 24.00 pc 145.00
4.3.2.3 Elbow 90" x 100 66.00 pc 435.00
4.3.2.4 Elbow 45" x 200 6.00 pc 715.00
4.3.2.5 Sanitary Tee 150 x 100 24.00 pc 515.00
4.3.2.6 Sanitary Tee 100 x 50 39.00 pc 110.00
4.3.2.7 P-Trap 100 39.00 pc 215.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
4.3.3 19mm Ø PPR Pipes (PN20) 100.00 m 135.00
4.3.4 PPR Fittings
4.3.4.1 Elbow 90 x 19 85.50 pc 25.00
4.3.4.2 Tee 19 x 19 45.00 pc 25.00
4.3.4.3 Coupling 25 x 25 13.50 pc 25.00
4.3.4.4 Coupling 25 x 19 15.00 pc 25.00
4.3.4.5 Gate Valve 19 6.00 pc 750.00
4.3.5 Sanitary Fixtures
4.3.5.1 Shower Head and Shower Valves 6.00 set 2,500.00
4.3.5.2 Telephone Water Heater 6.00 set 7,000.00
4.3.5.3 Lavatory Sink 15.00 set 5,000.00
4.3.5.4 Water Closet dual flush 12.00 set 8,200.00
4.3.5.5 Waterless Urinal 7.00 set 14,000.00
4.3.6 Miscellaneous/Consumables 1.00 lot 10,880.00
4.3.6.1 Pipe Sleeves
4.3.6.2 Pipe Hangers & Support
4.3.6.3 Teflon, Solvent etc.

4.4 ELECTRICAL WORKS & FIXTURES


4.4.1 Conduits
4.4.1.1 15mm dia PVC (Lighting) 270.00 m 30.56
4.4.1.2 15mm dia PVC (power lines) 270.00 m 30.56
4.4.2 Wires and Cables (Ground Floor Toilet Only)
4.4.2.1 2-3.5mm THHN cu. Stranded Wires 540.00 m 28.00
4.4.3 Junction and utility Boxes 120.00 pc 33.33
4.4.4 Electrical Fixtures
4.4.4.1 100mm dia Cylindrical Downlight Fixture with LED 13W 33.00 pc 850.00
4.4.4.2 Emergency Light 6.00 pc 2,000.00
4.4.4.3 Ceiling Exhaust Fan & Switch (heavy duty) 6.00 pc 4,000.00
4.4.4.4 Two Gang Switch 9.00 pc 165.00

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 5 QTY/UNIT: 1.00 LOT


DESCRIPTION: LECTURE ROOM A-1 (GROUND FLOOR)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1 n/a n/a n/a n/a
TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m² 308.40
5.1.2 Tile Adhesive 46.46 bag 75.00
5.1.3 Tile Grout 4.65 kg 21.00
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m² 267.30
5.1.5 Vinyl Adhesive 1.00 gal 195.00
5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal 208.50
5.2.2 Flat Latex Primer 7.00 gal 144.00
5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot 954.00
5.3 CEILING WORKS
5.3.1 9mm thk Gypsum Board 58.33 m² 37.34
5.3.2 Metal Double Furring 286.87 m 11.79
5.3.3 Wall Angle 30.55 m 10.51
5.3.4 600 x 600 acoustic boards 44.93 m² 125.19
5.3.5 T-runners (white) 292.05 m 3.49
5.3.6 Wall Angle (White) 26.81 m 3.15
5.3.7 Carrying Channel 103.26 m 6.90
5.3.8 W-Clamps/Clips 206.52 pc 1.05
5.3.9 Blind Rivets 1/8 20.65 box 105.00
5.3.10 Black Screws 1,749.90 pc 0.23
5.4 ELECTRICAL WORKS AND FIXTURES
5.4.1 Conduits
5.4.1.1 15mm dia PVC (Lighting) 120.00 m 10.70
5.4.1.2 15mm dia PVC (power lines) 120.00 m 10.70
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m 8.40
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m 11.40
5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc 9.90
5.4.4 Electrical fixtures
5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc 255.00
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 600.00
5.4.4.3 Emergency Light 1.00 set 600.00
5.4.4.4 Ceiling Fans 6.00 set 750.00
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 255.00
5.4.4.6 Aircon Outlet 2.00 pc 81.00
5.4.4.7 Three Gang Switch 1.00 pc 64.50
5.4.4.8 Ceiling Fan Switch 2.00 pc 75.00
5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 10,035.00
Whiteboard Screen with Integrated Smart TV Enclosure laminate
5.5.2 1.00 set 15,082.50
mounted on plywood on sliding rollers
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 2,250.00
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 15,300.00
5.5.3.3 PVC Student Armchair 45.00 set 142.50
5.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
5.6.1 D-1: Metal Door Jams and Panel (w/ knobs & hinges) 2.00 set 5,442.00
5.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 3,600.00
5.6.3 W-2: Clear glass powder coated white pivot window 4.00 set 1,680.00
TOTAL LABOR COST

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m² 1,028.00
5.1.2 Tile Adhesive 46.46 bag 250.00
5.1.3 Tile Grout 4.65 kg 70.00
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m² 891.00
5.1.5 Vinyl Adhesive 1.00 gal 650.00
5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal 695.00
5.2.2 Flat Latex Primer 7.00 gal 480.00
5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot 3,180.00
5.3 CEILING WORKS
5.3.1 9mm thk Gypsum Board 58.33 m² 124.46
5.3.2 Metal Double Furring 286.87 m 39.30
5.3.3 Wall Angle 30.55 m 35.02
5.3.4 600 x 600 acoustic boards 44.93 m² 417.32
5.3.5 T-runners (white) 292.05 m 11.64
5.3.6 Wall Angle (White) 26.81 m 10.50
5.3.7 Carrying Channel 103.26 m 23.00
5.3.8 W-Clamps/Clips 206.52 pc 3.50
5.3.9 Blind Rivets 1/8 20.65 box 350.00
5.3.10 Black Screws 1,749.90 pc 0.75
5.4 ELECTRICAL WORKS AND FIXTURES
5.4.1 Conduits
5.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67
5.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m 28.00
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m 38.00
5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc 33.00
5.4.4 Electrical fixtures
5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc 850.00
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00
5.4.4.3 Emergency Light 1.00 set 2,000.00
5.4.4.4 Ceiling Fans 6.00 set 2,500.00
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00
5.4.4.6 Aircon Outlet 2.00 pc 270.00
5.4.4.7 Three Gang Switch 1.00 pc 215.00
5.4.4.8 Ceiling Fan Switch 2.00 pc 250.00
5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0
Whiteboard Screen with Integrated Smart TV Enclosure laminate
5.5.2 1.00 set 50,275.00
mounted on plywood on sliding rollers
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00
5.5.3.3 PVC Student Armchair 45.00 set 950.00
5.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
5.6.1 D-1: Metal Door Jams and Panel (w/ knobs & hinges) 2.00 set 18,140.00
5.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00
5.6.3 W-2: Clear glass powder coated white pivot window 4.00 set 5,600.00
TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 6 QTY/UNIT: 1.00 LOT


DESCRIPTION: STUDENT ORG ROOMS (GROUND FLOOR)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a
TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m² 268.62
6.1.2 Vinyl Adhesive 5.00 gal 195.00

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal 208.50
6.2.2 Flat Latex 10.00 gal 144.00

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot 1,419.00

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m² 37.78
6.3.2 Metal Double Furring 373.77 m 9.05
6.3.3 Wall Angle 34.87 m 11.27
6.3.4 Carrying Channel 76.00 m 6.90
6.3.5 W-clamps/Clips 152.00 pc 1.05

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
6.3.6 Blind rivets(1/8) 15.00 box 105.00
6.3.7 Black Screws 2,280.00 pc 0.23

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m 10.70
6.4.1.2 15mm dia PVC (power lines) 120.00 m 10.70
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 8.40
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 11.40
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc 10.13
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set 255.00
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 600.00
6.4.4.3 Emergency Light 4.00 set 600.00
6.4.4.4 Ceiling Fan 4.00 set 750.00
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc 255.00
6.4.4.6 One Gang Switch 4.00 pc 31.50
6.4.4.7 Ceiling Fan Switch 4.00 pc 75.00

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc 225.00
6.5.1.2 2 x 3 Metal Stud 250.82 m 16.67
6.5.1.3 Blind rivets (1/8) 4.00 box 105.00
6.5.1.4 Black Screws 1,530.00 pc 0.23
6.5.2 Demolition of existing tiles, fixtures, hauling of debris, etc. 1.00 lot 7,500.00
6.5.3 Furniture & Appliances
6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set 4,950.00
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc 180.00
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set 3,600.00
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc 1,200.00

6.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


6.6.1 D-1: White Steel Door / view panel on Metal Jamb 4.00 set 5,444.25
6.6.2 W-2: Clear Glass powder coated white pivot window 4.00 set 1,680.00
TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m² 895.40
6.1.2 Vinyl Adhesive 5.00 gal 650.00

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal 695.00
6.2.2 Flat Latex 10.00 gal 480.00

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot 4,730.00

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m² 125.92
6.3.2 Metal Double Furring 373.77 m 30.17
6.3.3 Wall Angle 34.87 m 37.57
6.3.4 Carrying Channel 76.00 m 23.00
6.3.5 W-clamps/Clips 152.00 pc 3.50
6.3.6 Blind rivets(1/8) 15.00 box 350.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
6.3.7 Black Screws 2,280.00 pc 0.75

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m 35.67
6.4.1.2 15mm dia PVC (power lines) 120.00 m 35.67
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc 33.75
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set 850.00
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00
6.4.4.3 Emergency Light 4.00 set 2,000.00
6.4.4.4 Ceiling Fan 4.00 set 2,500.00
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc 850.00
6.4.4.6 One Gang Switch 4.00 pc 105.00
6.4.4.7 Ceiling Fan Switch 4.00 pc 250.00

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc 750.00
6.5.1.2 2 x 3 Metal Stud 250.82 m 55.58
6.5.1.3 Blind rivets (1/8) 4.00 box 350.00
6.5.1.4 Black Screws 1,530.00 pc 0.75
6.5.2 Demolition of existing tiles, fixtures, hauling of debris, etc. 1.00 lot 0
6.5.3 Furniture & Appliances
6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set 33,000.00
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc 1,200.00
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set 12,000.00
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc 4,000.00

6.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


6.6.1 D-1: White Steel Door / view panel on Metal Jamb 4.00 set 18,147.50
6.6.2 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00
TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 04 September 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 7 QTY/UNIT: 1.00 LOT


DESCRIPTION: LECTURE ROOM A-4 (GROUND FLOOR)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a
TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
7.1 FLOOR FINISHES
7.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 308.40
7.1.2 Tile Adhesive 87.50 bag 75.00
7.1.3 Tile Grout 8.75 kg 21.00
7.1.4 Vinyl Adhesive 2.00 gal 195.00
7.1.5 150 x 900 Vinyl tiles 20.00 m² 267.30
7.2 PAINTING
7.2.1 Semi Gloss Latex 4.00 gal 208.50
7.2.2 Flat Latex 7.00 gal 144.00
7.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 718.50
7.3 CEILING WORKS
7.3.1 9mm thk Gypsum bd on Metal Furring 51.00 m² 38.82
7.3.2 Metal Double Furring 250.82 m 8.90
7.3.3 Wall Angle 28.57 m 9.87
7.3.4 Carrying Channel 125.00 m 6.90
7.3.5 W-clamps/clips 250.00 pc 1.05
7.3.6 Blind rivets(1/8) 25.00 box 105.00
7.3.7 Black Screws 1,530.00 pc 0.23
7.3.8 T-Runner (White) 481.00 m 3.71
7.3.9 Wall Angle (White) 34.41 m 3.15
7.3.10 600 x 600 acoustic board 74.00 m² 137.43
7.4 ELECTRICAL WORKS AND FIXTURES
7.4.1 Conduits
7.4.1.1 15mm dia PVC (Lighting) 100.00 m 10.67
7.4.1.2 15mm dia PVC (Power Lines) 100.00 m 10.67
7.4.2 Wires and Cables (Ground Floor Toilet Only)
7.4.2.1 2-3.5mm THHN CU, Stranded Wires 200.00 m 8.40
7.4.2.2 2-5.5mm THHN CU, Stranded Wires 200.00 m 11.40
7.4.3 Others
7.4.3.1 Junction and Utility Box 60.00 pc 9.90
7.4.4 Electrical fixtures
7.4.4.1 Pinlight (100mm dia) with 7W LED 22.00 pc 255.00
7.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 600.00
7.4.4.3 Emergency Light 1.00 set 600.00
7.4.4.4 Ceiling Fan 8.00 set 750.00
7.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 255.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
7.4.4.6 Aircon Outlet 2.00 pc 81.00
7.4.4.7 Three Gang Switch 2.00 pc 31.50
7.4.4.8 Ceiling Fan Switch 4.00 pc 75.00
7.5 OTHERS
7.5.1 Demolition of existing tiles, fixtures, hauling of debris, etc 1.00 lot 18,900.00
Whiteboard Screen with Integrated Smart TV Enclosure,
7.5.2 1.00 set 15,082.50
laminate mounted on plywood on sliding rollers
7.5.3 Furniture & Appliances
7.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 2,250.00
7.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 15,300.00
7.5.3.3 Working Table fit with 8 Ergonomic Chairs 9.00 set 4,950.00
7.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
7.6.1 D-1: White Steel Door / view pane on Metal Jamb 2.00 set 5,448.00
7.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 3,600.00
7.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 1,680.00
TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
7.1 FLOOR FINISHES
7.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00
7.1.2 Tile Adhesive 87.50 bag 250.00
7.1.3 Tile Grout 8.75 kg 70.00
7.1.4 Vinyl Adhesive 2.00 gal 650.00
7.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00
7.2 PAINTING
7.2.1 Semi Gloss Latex 4.00 gal 695.00
7.2.2 Flat Latex 7.00 gal 480.00
7.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,395.00
7.3 CEILING WORKS
7.3.1 9mm thk Gypsum bd on Metal Furring 51.00 m² 129.41
7.3.2 Metal Double Furring 250.82 m 29.66
7.3.3 Wall Angle 28.57 m 32.90
7.3.4 Carrying Channel 125.00 m 23.00
7.3.5 W-clamps/clips 250.00 pc 3.50
7.3.6 Blind rivets(1/8) 25.00 box 350.00
7.3.7 Black Screws 1,530.00 pc 0.75
7.3.8 T-Runner (White) 481.00 m 12.37
7.3.9 Wall Angle (White) 34.41 m 10.50
7.3.10 600 x 600 acoustic board 74.00 m² 458.11
7.4 ELECTRICAL WORKS AND FIXTURES
7.4.1 Conduits
7.4.1.1 15mm dia PVC (Lighting) 100.00 m 35.56
7.4.1.2 15mm dia PVC (Power Lines) 100.00 m 35.56
7.4.2 Wires and Cables (Ground Floor Toilet Only)
7.4.2.1 2-3.5mm THHN CU, Stranded Wires 200.00 m 28.00
7.4.2.2 2-5.5mm THHN CU, Stranded Wires 200.00 m 38.00
7.4.3 Others
7.4.3.1 Junction and Utility Box 60.00 pc 33.00
7.4.4 Electrical fixtures
7.4.4.1 Pinlight (100mm dia) with 7W LED 22.00 pc 850.00
7.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set 2,000.00
7.4.4.3 Emergency Light 1.00 set 2,000.00
7.4.4.4 Ceiling Fan 8.00 set 2,500.00
7.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00
7.4.4.6 Aircon Outlet 2.00 pc 270.00
7.4.4.7 Three Gang Switch 2.00 pc 105.00
7.4.4.8 Ceiling Fan Switch 4.00 pc 250.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
7.5 OTHERS
7.5.1 Demolition of existing tiles, fixtures, hauling of debris, etc 1.00 lot 0
Whiteboard Screen with Integrated Smart TV Enclosure,
7.5.2 1.00 set 50,275.00
laminate mounted on plywood on sliding rollers
7.5.3 Furniture & Appliances
7.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00
7.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00
7.5.3.3 Working Table fit with 8 Ergonomic Chairs 9.00 set 33,000.00
7.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
7.6.1 D-1: White Steel Door / view pane on Metal Jamb 2.00 set 18,160.00
7.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00
7.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 04 September 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 8 QTY/UNIT: 1.00 LOT


DESCRIPTION: THEATER TYPE LECTURE RM (A-5) (SECOND FLR)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
8.1 FLOOR FINISHES
8.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 308.40
8.1.2 Tile Adhesive 87.50 bag 75.00
8.1.3 Tile Grout 8.75 kg 21.00
8.1.4 Vinyl Adhesive 2.00 gal 195.00
8.1.5 150 x 900 Vinyl tiles 20.00 m² 267.30

8.2 PAINTING
8.2.1 Semi Gloss Latex 28.00 gal 208.50
8.2.2 Flat Latex 6.00 gal 144.00
8.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 840.00

8.3 CEILING WORKS


8.3.1 9mm thk Gypsum bd on Metal Furring 50.00 m² 37.62
8.3.2 Metal Double Furring 245.90 m 9.70
8.3.3 Wall Angle 28.28 m 9.19
8.3.4 Carrying Channel 150.00 m 6.90
8.3.5 W-Clamps/Clips 300.00 m 1.05
8.3.6 Blind rivets(1/8) 75.00 box 105.00
8.3.7 Black Screws 1,500.00 pc 0.23
8.3.8 T-Runner (White) 650.00 m 3.53
8.3.9 Wall Angle (White) 40.00 m 3.15
8.3.10 600 x 600 acoustic board on T-Runner 100.00 m² 137.25

8.4 ELECTRICAL WORKS AND FIXTURES


8.4.1 Conduits
8.4.1.1 15mm dia PVC (Lighting) 200.00 m 7.50
8.4.1.2 15mm dia PVC (power lines) 200.00 m 7.50
8.4.2 Wires and Cables (Ground Floor Toilet Only)
8.4.2.1 2-3.5mm THHN CU, Stranded Wires 400.00 m 8.40
8.4.2.2 2-5.5mm THHN CU, Stranded Wires 400.00 m 11.40
8.4.3 Others
8.4.3.1 Junction and Utility Box 90.00 pc 9.92
8.4.4 Electrical fixtures
8.4.4.1 Pinlight (100mm dia) with 7W LED 24.00 set 255.00
8.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 12.00 set 600.00
8.4.4.3 Emergency Light 2.00 set 600.00
8.4.4.4 Ceiling Fan 12.00 set 750.00
8.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 255.00
8.4.4.6 Aircon Outlet 3.00 pc 81.00
8.4.4.7 Three Gang Switch 2.00 pc 64.50
8.4.4.8 Two Gang Switch 1.00 pc 49.50
8.4.4.9 Ceiling Fan Switch 5.00 pc 75.00

8.5 OTHERS
8.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 18,900.00
Whiteboard Screen with Integrated Smart TV Enclosure,
8.5.2 1.00 set 15,082.50
laminate mounted on plywood on sliding rollers
8.5.3 Furniture & Appliances
8.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 2,250.00
8.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 15,300.00
8.5.3.3 Fixed Retractable Theatre Arm Chair 111.00 pc 1,600.00

8.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


8.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 5,788.50
8.6.2 W-1: Clear Glass powder coated white awning window 6.00 set 3,600.00
8.6.3 W-2: Clear Glass powder coated white pivot window 6.00 set 1,680.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
8.1 FLOOR FINISHES
8.1.1 600 x 600 Homogenous Granite Tiles 126.00 m² 1,028.00
8.1.2 Tile Adhesive 87.50 bag 250.00
8.1.3 Tile Grout 8.75 kg 70.00
8.1.4 Vinyl Adhesive 2.00 gal 650.00
8.1.5 150 x 900 Vinyl tiles 20.00 m² 891.00

8.2 PAINTING
8.2.1 Semi Gloss Latex 28.00 gal 695.00
8.2.2 Flat Latex 6.00 gal 480.00
8.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,800.00

8.3 CEILING WORKS


8.3.1 9mm thk Gypsum bd on Metal Furring 50.00 m² 125.40
8.3.2 Metal Double Furring 245.90 m 32.33
8.3.3 Wall Angle 28.28 m 30.62
8.3.4 Carrying Channel 150.00 m 23.00
8.3.5 W-Clamps/Clips 300.00 m 3.50
8.3.6 Blind rivets(1/8) 75.00 box 350.00
8.3.7 Black Screws 1,500.00 pc 0.75
8.3.8 T-Runner (White) 650.00 m 11.77
8.3.9 Wall Angle (White) 40.00 m 10.50
8.3.10 600 x 600 acoustic board on T-Runner 100.00 m² 457.50

8.4 ELECTRICAL WORKS AND FIXTURES


8.4.1 Conduits
8.4.1.1 15mm dia PVC (Lighting) 200.00 m 25.00
8.4.1.2 15mm dia PVC (power lines) 200.00 m 25.00
8.4.2 Wires and Cables (Ground Floor Toilet Only)
8.4.2.1 2-3.5mm THHN CU, Stranded Wires 400.00 m 28.00
8.4.2.2 2-5.5mm THHN CU, Stranded Wires 400.00 m 38.00
8.4.3 Others
8.4.3.1 Junction and Utility Box 90.00 pc 33.06
8.4.4 Electrical fixtures
8.4.4.1 Pinlight (100mm dia) with 7W LED 24.00 set 850.00
8.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 12.00 set 2,000.00
8.4.4.3 Emergency Light 2.00 set 2,000.00
8.4.4.4 Ceiling Fan 12.00 set 2,500.00
8.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00
8.4.4.6 Aircon Outlet 3.00 pc 270.00
8.4.4.7 Three Gang Switch 2.00 pc 215.00
8.4.4.8 Two Gang Switch 1.00 pc 165.00
8.4.4.9 Ceiling Fan Switch 5.00 pc 250.00

8.5 OTHERS
8.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0
Whiteboard Screen with Integrated Smart TV Enclosure,
8.5.2 1.00 set 50,275.00
laminate mounted on plywood on sliding rollers
8.5.3 Furniture & Appliances
8.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set 15,000.00
8.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00
8.5.3.3 Fixed Retractable Theatre Arm Chair 111.00 pc 8,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
8.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
8.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,295.00
8.6.2 W-1: Clear Glass powder coated white awning window 6.00 set 12,000.00
8.6.3 W-2: Clear Glass powder coated white pivot window 6.00 set 5,600.00

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager / 01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 9 QTY/UNIT: 1.00 LOT


DESCRIPTION: LECTURE ROOM (A-7) (SECOND FLOOR)

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
9.1 FLOOR FINISHES
9.1.1 600 x 600 Homogenous Granite Tiles 68.00 m² 308.40
9.1.2 Tile Adhesive 47.22 bag 75.00
9.1.3 Tile Grout 4.72 kg 21.00
9.1.4 Vinyl Adhesive 0.90 gal 195.00
9.1.5 150 x 900 Vinyl tiles 9.00 m² 267.67

9.2 PAINTING
9.2.1 Semi Gloss Latex 15.00 gal 208.50
9.2.2 Flat Latex 10.00 gal 144.00
9.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 709.50

9.3 CEILING WORKS


9.3.1 9mm thk Gypsum Board on Metal Furring 30.00 m² 36.30
9.3.2 Metal Double Furring 147.54 m 11.48
9.3.3 Wall Angle 21.91 m 10.41
9.3.4 Carrying Channel 76.00 m 6.90
9.3.5 W-clamps/clips 152.00 pc 1.05
9.3.6 Blind rivets(1/8) 38.00 box 105.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
9.3.7 Black Screws 900.00 pc 0.23
9.3.8 T-Runner (White) 299.00 m 3.58
9.3.9 Wall Angle (White) 27.13 m 3.15
9.3.10 600 x 600 acoustic board on T-Runner 46.00 m² 136.96

9.4 ELECTRICAL WORKS AND FIXTURES


9.4.1 Conduits
9.4.1.1 15mm dia PVC (Lighting) 88.00 m 7.50
9.4.1.2 15mm dia PVC (Power Lines) 88.00 m 7.50
9.4.2 Wires and Cables (Ground Floor Toilet Only)
9.4.2.1 2-3.5mm THHN cu. Stranded Wires 176.00 m 8.40
9.4.2.2 2-5.5mm THHN cu. Stranded Wires 176.00 m 11.40
9.4.3 Others
9.4.3.1 Junction and Utility Box 60.00 pc 9.90
9.4.4 Electrical fixtures
9.4.4.1 Pinlight (100mm dia) with 7W LED 9.00 pc 255.00
9.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 600.00
9.4.4.3 Emergency Light 1.00 set 600.00
9.4.4.4 Ceiling Fan 6.00 set 750.00
9.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 255.00
9.4.4.6 Aircon Outlet 2.00 pc 81.00
9.4.4.7 Three Gang Switch 1.00 pc 64.50
9.4.4.8 Ceiling Fan Switch 2.00 pc 75.00

9.5 OTHERS
9.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 10,200.00
Whiteboard Screen with Integrated Smart TV Enclosure,
9.5.2 1.00 set 15,082.50
laminate mounted on plywood on sliding rollers
9.5.3 Furniture & Appliances
9.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 2,250.00
9.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 15,300.00
9.5.3.3 PVC Student Armchair 50.00 pc 142.50

9.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


9.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 5,766.00
9.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 3,600.00
9.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 1,680.00

TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
9.1 FLOOR FINISHES
9.1.1 600 x 600 Homogenous Granite Tiles 68.00 m² 1,028.00
9.1.2 Tile Adhesive 47.22 bag 250.00
9.1.3 Tile Grout 4.72 kg 70.00
9.1.4 Vinyl Adhesive 0.90 gal 650.00
9.1.5 150 x 900 Vinyl tiles 9.00 m² 892.22

9.2 PAINTING
9.2.1 Semi Gloss Latex 15.00 gal 695.00
9.2.2 Flat Latex 10.00 gal 480.00
9.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 2,365.00

9.3 CEILING WORKS


9.3.1 9mm thk Gypsum Board on Metal Furring 30.00 m² 121.00
9.3.2 Metal Double Furring 147.54 m 38.26
9.3.3 Wall Angle 21.91 m 34.69

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
9.3.4 Carrying Channel 76.00 m 23.00
9.3.5 W-clamps/clips 152.00 pc 3.50
9.3.6 Blind rivets(1/8) 38.00 box 350.00
9.3.7 Black Screws 900.00 pc 0.75
9.3.8 T-Runner (White) 299.00 m 11.94
9.3.9 Wall Angle (White) 27.13 m 10.50
9.3.10 600 x 600 acoustic board on T-Runner 46.00 m² 456.52

9.4 ELECTRICAL WORKS AND FIXTURES


9.4.1 Conduits
9.4.1.1 15mm dia PVC (Lighting) 88.00 m 25.00
9.4.1.2 15mm dia PVC (Power Lines) 88.00 m 25.00
9.4.2 Wires and Cables (Ground Floor Toilet Only)
9.4.2.1 2-3.5mm THHN cu. Stranded Wires 176.00 m 28.00
9.4.2.2 2-5.5mm THHN cu. Stranded Wires 176.00 m 38.00
9.4.3 Others
9.4.3.1 Junction and Utility Box 60.00 pc 33.00
9.4.4 Electrical fixtures
9.4.4.1 Pinlight (100mm dia) with 7W LED 9.00 pc 850.00
9.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set 2,000.00
9.4.4.3 Emergency Light 1.00 set 2,000.00
9.4.4.4 Ceiling Fan 6.00 set 2,500.00
9.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00
9.4.4.6 Aircon Outlet 2.00 pc 270.00
9.4.4.7 Three Gang Switch 1.00 pc 215.00
9.4.4.8 Ceiling Fan Switch 2.00 pc 250.00

9.5 OTHERS
9.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0
Whiteboard Screen with Integrated Smart TV Enclosure,
9.5.2 1.00 set 50,275.00
laminate mounted on plywood on sliding rollers
9.5.3 Furniture & Appliances
9.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00
9.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set 51,000.00
9.5.3.3 PVC Student Armchair 50.00 pc 950.00

9.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


9.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00
9.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00
9.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager /01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 10 QTY/UNIT: 1.00 LOT


DESCRIPTION: LECTURE ROOM (THIRD FLOOR)
a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a
TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
10.1 FLOOR FINISHES
10.1.1 600 x 600 Homogenous Granite Tiles 63.00 m² 308.40
10.1.2 Tile Adhesive 43.75 bag 75.00
10.1.3 Tile Grout 4.38 kg 21.00
10.1.4 Vinyl Adhesive 1.00 gal 195.00
10.1.5 150 x 900 Vinyl tiles 10.00 m² 267.30
10.2 PAINTING
10.2.1 Semi Gloss Latex 14.00 gal 208.50
10.2.2 Flat Latex 5.00 gal 144.00
10.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 519.00
10.3 CEILING WORKS
10.3.1 9mm thk Gypsum Board on Metal Furring 21.00 m² 37.71
10.3.2 Metal Double Furring 103.28 m 9.99
10.3.3 Wall Angle 18.33 m 10.97
10.3.4 Carrying Channel 71.00 m 6.90
10.3.5 W-Clamps/Clips 142.00 pc 1.05
10.3.6 Blind rivets(1/8) 35.50 box 105.00
10.3.7 Black Screws 630.00 pc 0.23
10.3.8 T-Runner (White) 325.00 m 3.92
10.3.9 Wall Angle (White) 28.28 m 3.15
10.3.10 600 x 600 acoustic board on T-Runner 50.00 m² 136.80
10.4 ELECTRICAL WORKS AND FIXTURES
10.4.1 Conduits
10.4.1.1 15mm dia PVC (Lighting) 120.00 m 7.50
10.4.1.2 15mm dia PVC (Power Lines) 120.00 m 7.50
10.4.2 Wires and Cables (Ground Floor Toilet Only)
10.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 8.40
10.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 11.40
10.4.3 Others
10.4.3.1 Junction and Utility Box 60.00 pc 9.90
10.4.4 Electrical fixtures
10.4.4.1 Pinlight (100mm dia) with 7W LED 6.00 set 255.00
10.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 4.00 set 600.00
10.4.4.3 Emergency Light 1.00 set 600.00
10.4.4.4 Ceiling Fans 3.00 set 750.00
10.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 255.00
10.4.4.6 Aircon Outlet 2.00 pc 81.00
10.4.4.7 Three Gang Switch 1.00 pc 64.50
10.4.4.8 Ceiling Fan Switch 3.00 pc 75.00
10.5 OTHERS
10.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 9,450.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Whiteboard Screen with Integrated Smart TV Enclosure laminate
10.5.2 1.00 set 15,082.50
mounted on plywood on sliding rollers
10.5.3 Furniture & Appliances
10.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 2,250.00
10.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 15,300.00
10.5.3.3 Student Armchair 30.00 pc 142.50
10.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
10.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 5,766.00
10.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 3,600.00
10.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 1,680.00
TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
10.1 FLOOR FINISHES
10.1.1 600 x 600 Homogenous Granite Tiles 63.00 m² 1,028.00
10.1.2 Tile Adhesive 43.75 bag 250.00
10.1.3 Tile Grout 4.38 kg 70.00
10.1.4 Vinyl Adhesive 1.00 gal 650.00
10.1.5 150 x 900 Vinyl tiles 10.00 m² 891.00
10.2 PAINTING
10.2.1 Semi Gloss Latex 14.00 gal 695.00
10.2.2 Flat Latex 5.00 gal 480.00
10.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot 1,730.00
10.3 CEILING WORKS
10.3.1 9mm thk Gypsum Board on Metal Furring 21.00 m² 125.71
10.3.2 Metal Double Furring 103.28 m 33.31
10.3.3 Wall Angle 18.33 m 36.55
10.3.4 Carrying Channel 71.00 m 23.00
10.3.5 W-Clamps/Clips 142.00 pc 3.50
10.3.6 Blind rivets(1/8) 35.50 box 350.00
10.3.7 Black Screws 630.00 pc 0.75
10.3.8 T-Runner (White) 325.00 m 13.08
10.3.9 Wall Angle (White) 28.28 m 10.50
10.3.10 600 x 600 acoustic board on T-Runner 50.00 m² 456.00
10.4 ELECTRICAL WORKS AND FIXTURES
10.4.1 Conduits
10.4.1.1 15mm dia PVC (Lighting) 120.00 m 25.00
10.4.1.2 15mm dia PVC (Power Lines) 120.00 m 25.00
10.4.2 Wires and Cables (Ground Floor Toilet Only)
10.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m 28.00
10.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m 38.00
10.4.3 Others
10.4.3.1 Junction and Utility Box 60.00 pc 33.00
10.4.4 Electrical fixtures
10.4.4.1 Pinlight (100mm dia) with 7W LED 6.00 set 850.00
10.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 4.00 set 2,000.00
10.4.4.3 Emergency Light 1.00 set 2,000.00
10.4.4.4 Ceiling Fans 3.00 set 2,500.00
10.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc 850.00
10.4.4.6 Aircon Outlet 2.00 pc 270.00
10.4.4.7 Three Gang Switch 1.00 pc 215.00
10.4.4.8 Ceiling Fan Switch 3.00 pc 250.00
10.5 OTHERS
10.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot 0
Whiteboard Screen with Integrated Smart TV Enclosure laminate
10.5.2 1.00 set 50,275.00
mounted on plywood on sliding rollers
10.5.3 Furniture & Appliances

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
10.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set 15,000.00
10.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set 51,000.00
10.5.3.3 Student Armchair 30.00 pc 950.00
10.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)
10.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set 19,220.00
10.6.2 W-1: Clear Glass powder coated white awning window 4.00 set 12,000.00
10.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set 5,600.00
TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager /01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
UNIT COST ANALYSIS

TITLE : Rehabilitation/Renovation of Academic Building-College of Architecture and Fine Arts Building (Rebid)
INVITATION TO BID NO. INFRA 024-08-2019A
LOCATION : San Isidro Extension Campus, Barangay San Isidro Tarlac City

PAY ITEM: 11 QTY/UNIT: 1.00 LOT


DESCRIPTION: OPENINGS & PATHWAY TO ADJACENT BUILDINGS

a. EQUIPMENT
NO. OF NO. OF
REF.NO NAME AND SPECIFICATION OF EQUIPMENT UNIT COST
UNITS DAYS
1 n/a n/a n/a n/a

TOTAL EQUIPMENT COST

b. LABOR
REF. NO. DESIGNATION OF PERSONNEL QTY UNIT UNIT COST
11.1 ACCESS PATHWAY (to Library)
11.1.1 Demolition Works of existing including hauling 1.00 lot 5,785.50
11.1.2 Site clearing, Soil preparation 60.00 m² 600.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
11.1.3 Burrow Fill & compaction 15.00 m³ 600.00
11.1.4 Concreting 15.00 m³ 1,230.00
11.1.5 10mm dia Reinforcing Bars 1,200.00 kg 12.60
11.1.6 Formworks 60.00 m² 66.43
11.1.7 Railings and Balusters 26.00 m² 468.00
11.1.8 Roll-up Door 1.00 set 25,500.00
11.1.9 Paver blocks 250.00 m² 120.00
11.1.10 Wall & Slab Soffit Painting Works 200.00 m² 35.47

11.2 ACCESS PATHWAY (to Pond)


11.2.1 Demolition Works of existing including hauling 1.00 lot 2,250.00
11.2.2 Site clearing, Soil preparation 60.00 m² 600.00
11.2.3 Burrow Fill & Compaction 15.00 m³ 600.00
11.2.4 Concreting 12.00 m³ 1,230.00
11.2.5 10mm dia Reinforcing Bars 960.00 kg 12.60
11.2.6 Formworks 50.00 m² 66.98
11.2.7 Railings and Balusters 26.00 m² 468.00
11.2.8 Roll-up Door 1.00 set 25,500.00
11.2.9 Paver blocks 250.00 m² 120.00
11.2.10 Wall & Slab Soffit Painting Works 200.00 m² 32.25

TOTAL LABOR COST

c. MATERIALS
REF. NO. DESIGNATION OF MATERIALS QTY UNIT UNIT COST
11.1 ACCESS PATHWAY (to Library)
11.1.1 Demolition Works of existing including hauling 1.00 lot 0
11.1.2 Site clearing, Soil preparation 60.00 m² 0
11.1.3 Burrow Fill & compaction 15.00 m³ 0
11.1.4 Concreting 15.00 m³ 4,100.00
11.1.5 10mm dia Reinforcing Bars 1,200.00 kg 42.00
11.1.6 Formworks 60.00 m² 221.42
11.1.7 Railings and Balusters 26.00 m² 1,560.00
11.1.8 Roll-up Door 1.00 set 85,000.00
11.1.9 Paver blocks 250.00 m² 400.00
11.1.10 Wall & Slab Soffit Painting Works 200.00 m² 118.23

11.2 ACCESS PATHWAY (to Pond)


11.2.1 Demolition Works of existing including hauling 1.00 lot 0
11.2.2 Site clearing, Soil preparation 60.00 m² 0
11.2.3 Burrow Fill & Compaction 15.00 m³ 0
11.2.4 Concreting 12.00 m³ 4,100.00
11.2.5 10mm dia Reinforcing Bars 960.00 kg 42.00
11.2.6 Formworks 50.00 m² 223.26
11.2.7 Railings and Balusters 26.00 m² 1,560.00
11.2.8 Roll-up Door 1.00 set 85,000.00
11.2.9 Paver blocks 250.00 m² 400.00
11.2.10 Wall & Slab Soffit Painting Works 200.00 m² 107.50

TOTAL MATERIAL COST

D. TOTAL DIRECT COST

E. OVERHEAD, CONTINGENCIES & MISC.

F. PROFIT

G. VALUE ADDED TAX

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
H. TOTAL COST

I. UNIT COST

Submitted by:

Name and Signature of Bidder's Representative : RICHARD B. SORIANO

Designation / Date : General Manager /01 October 2019

Name of Bidder : R.B. SORIANO CONSTRUCTION

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a
n/a

TOTAL COST
5,000.00
10,000.00

15,000.00

5,000.00

35,000.00

TOTAL COST

50,000.00
100,000.00

150,000.00

50,000.00

350,000.00

385,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
26,950.00

411,950.00

411,950.00

Arts Building (Rebid)

TOTAL COST

n/a

n/a

TOTAL COST

168,000.00
16,000.00
112,000.00
258,750.00
80,340.00
5,400.00
8,400.00

90,000.00
42,300.00
18,000.00
77,400.00
133,200.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
52,200.00
141,300.00
11,760.00
9,000.00
139,500.00
17,100.00

79,794.00
8,118.00

63,426.00
22,428.00

16,632.00
11,592.00
239.40

269,332.80
91,098.00

157,911.60
36,918.00

1,710.00
7,875.00
1,206.00

153,883.80
35,708.40

19,152.00

18,270.00

31,185.00
122,472.00

18,900.00
14,490.00
90,300.00

4,559.40
20,983.95
1,667.70
6,785.70
10,185.90
4,292.10
16,890.15
1,236.00
7,951.50
51,178.05
12,782.55

144,624.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
144,060.00

5,148.00

15,120.00
3,900.00
22,932.00
3,822.00
67,500.00
111,600.00

540,000.00

12,600.00
14,400.00

11,010.00

864,000.00

5,760.00
14,580.00

19,500.00

26,580.00

2,640.00
11,643.00

5,409.00
655.20
1,119.00
3,390.00

47,850.00
16,680.00
972.00
26,640.00
32,574.00
45,465.00
30,000.00

5,043,978.20

TOTAL COST

0
0
0
0

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
267,800.00
18,000.00
28,000.00

450,000.00
211,500.00
90,000.00
387,000.00
666,000.00
261,000.00
706,500.00
58,800.00
45,000.00
697,500.00
85,500.00

265,980.00
27,060.00

211,420.00
74,760.00

55,440.00
38,640.00
798.00

897,776.00
303,660.00

526,372.00
123,060.00

5,700.00
26,250.00
4,020.00

512,946.00
119,028.00

63,840.00

60,900.00

103,950.00
408,240.00

63,000.00
48,300.00
301,000.00

15,198.00
69,946.50
5,559.00
22,619.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
33,953.00
14,307.00
56,300.50
4,120.00
26,505.00
170,593.50
42,608.50

482,080.00

480,200.00

17,160.00

50,400.00
13,000.00
76,440.00
12,740.00
225,000.00
372,000.00

2,700,000.00

42,000.00
48,000.00

36,700.00

2,880,000.00

19,200.00
48,600.00

65,000.00

88,600.00

8,800.00
38,810.00

18,030.00
2,184.00
3,730.00
11,300.00

159,500.00
55,600.00
3,240.00
88,800.00
108,580.00
151,550.00
100,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
17,083,694.00

22,127,672.20

221,276.72

1,327,660.33

1,657,362.65

25,333,971.90

25,333,971.90

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a

n/a

TOTAL COST

319,500.00

42,600.00

72,000.00

16,740.00

35,475.00

33,360.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
12,960.00
1,800.00
21,600.00
525.00
180.00

20,010.00

9,672.00
2,001.00
696.00

1,140.00
174.00
5,742.00
643.50
2,317.50
825.00
1,419.00

10,788.60
1,140.00
9,600.00

2,184.00

427.50
270.00
59.40
90.00
1,350.00
9,000.00
3,900.00
13,500.00

4,815.00
18,972.00
8,221.50
487.20
198.00
555.00
5,850.00
1,659.00
1,602.00
57.00
15.00
648.00
175.50
201.60
18.90
52.20
306.00
18,531.00
630.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
75.00
1,140.00

61,194.00
5,506.20
2,301.00
3,116.40
1,930.50
810.00
22,338.00
199,602.00

7,837.20
2,929.80
2,028.00
3,613.50
622.50
450.00

7,920.00

3,750.00
2,550.00

3,750.00

3,750.00
3,750.00
3,750.00
5,025.00

5,025.00

5,025.00

5,850.00

33,000.00

67,500.00

34,500.00

12,240.00
14,400.00
75,000.00
50,400.00
12,750.00
720.00
945.00
1,485.00

2,565.00
360.00
157.50
540.00
900.00
4,875.00
1,890.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
6,525.00

11,286.00
36,801.00
5,550.00
5,250.00
19,500.00

5,670.00

15,921.00
18,489.60
17,334.00
12,864.00
4,848.00
2,562.00
542.40
468.00
14,137.50

738.00
391.50
49.50
198.00
1,125.00
201.00
877.50
897.00
3,009.00
5,544.00
486.00
130.50
1,305.00
391.50
4,698.00
346.50
1,848.00
346.50
2,772.00
171.00
99.00
1,575.00
1,323.00
315.00
112.50
399.00
735.00
165.00
166.50
166.50
40.50
103.50
85.50
72.00
2,760.00
2,442.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
337.50
103.50
5,940.00
8,820.00
846.00
423.00
1,053.00
783.00
1,449.00
162.00
81.00
229.50

6,204.00

4,968.00

4,710.00
15,435.00
945.00
1,575.00
1,659.00
9,912.00
13,650.00

63,000.00

6,570.00
29,932.50

2,902.80

2,244.00

307,500.00

12,750.00

10,918.80

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
2,125,488.60

TOTAL COST

735,000.00

142,000.00

240,000.00

55,800.00

118,250.00

111,200.00
43,200.00
6,000.00
72,000.00
1,750.00
600.00

66,700.00

32,240.00
6,670.00
2,320.00

3,800.00
580.00
19,140.00
2,145.00
7,725.00
2,750.00
4,730.00

35,962.00
3,800.00
32,000.00

7,280.00

1,425.00
900.00
198.00
300.00
4,500.00
30,000.00
13,000.00
45,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
16,050.00
63,240.00
27,405.00
1,624.00
660.00
1,850.00
19,500.00
5,530.00
5,340.00
190.00
50.00
2,160.00
585.00
672.00
63.00
174.00
1,020.00
61,770.00
2,100.00
250.00
3,800.00

203,980.00
18,354.00
7,670.00
10,388.00
6,435.00
2,700.00
74,460.00
665,340.00

26,124.00
9,766.00
6,760.00
12,045.00
2,075.00
1,500.00

26,400.00

12,500.00
8,500.00

12,500.00

12,500.00
12,500.00
12,500.00
16,750.00

16,750.00

16,750.00

19,500.00

110,000.00

225,000.00

115,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
40,800.00
48,000.00
250,000.00
168,000.00
42,500.00
2,400.00
3,150.00
4,950.00

8,550.00
1,200.00
525.00
1,800.00
3,000.00
16,250.00
6,300.00
21,750.00

37,620.00
122,670.00
18,500.00
17,500.00
65,000.00

18,900.00

53,070.00
61,632.00
57,780.00
42,880.00
16,160.00
8,540.00
1,808.00
1,560.00
47,125.00

2,460.00
1,305.00
165.00
660.00
3,750.00
670.00
2,925.00
2,990.00
10,030.00
18,480.00
1,620.00
435.00
4,350.00
1,305.00
15,660.00
1,155.00
6,160.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1,155.00
9,240.00
570.00
330.00
5,250.00
4,410.00
1,050.00
375.00
1,330.00
2,450.00
550.00
555.00
555.00
135.00
345.00
285.00
240.00
9,200.00
8,140.00
1,125.00
345.00
19,800.00
29,400.00
2,820.00
1,410.00
3,510.00
2,610.00
4,830.00
540.00
270.00
765.00

20,680.00

16,560.00

15,700.00
51,450.00
3,150.00
5,250.00
5,530.00
33,040.00
45,500.00

210,000.00

21,900.00
99,775.00

9,676.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
7,480.00

2,050,000.00

85,000.00

36,396.00

7,822,462.00

9,947,950.60

99,479.51

596,877.04

745,101.50

11,389,408.64

11,389,408.64

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a

n/a

TOTAL COST

10,045.00
14,850.00
6,500.25
182.07

68,625.00
16,200.00
83,250.00
3,127.50
2,160.00
3,181.50

12,012.00
12,972.00

5,985.00
1,044.00
8,613.00
1,287.00
3,708.00
1,287.00
2,515.50
4,050.00

641.25
337.50

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
101.25
112.50
1,350.00

4,500.00
12,600.00
22,500.00
29,520.00
29,400.00
3,264.00

2,475.00
2,475.00

4,536.00
1,200.00

8,415.00
3,600.00
7,200.00
445.50

396,267.82

TOTAL COST

0
49,500.00
21,667.50
606.90

228,750.00
54,000.00
277,500.00
10,425.00
7,200.00
10,605.00

40,040.00
43,240.00

19,950.00
3,480.00
28,710.00
4,290.00
12,360.00
4,290.00
8,385.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
13,500.00

2,137.50
1,125.00
337.50
375.00
4,500.00

15,000.00
42,000.00
75,000.00
98,400.00
98,000.00
10,880.00

8,250.00
8,250.00

15,120.00
4,000.00

28,050.00
12,000.00
24,000.00
1,485.00

1,287,409.40

1,683,677.22

16,836.77

101,020.63

126,107.42

1,927,642.05

1,927,642.05

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
n/a
n/a

TOTAL COST

20,631.96
3,484.50
97.65
2,673.00
195.00

2,710.50
1,008.00
954.00

2,178.00
3,382.50
321.00
5,625.00
1,020.00
84.45
712.49
216.85
2,168.25
393.73

1,284.00
1,284.00

2,016.00
2,736.00

594.00

3,315.00
3,600.00
600.00
4,500.00
1,020.00
162.00
64.50
150.00

10,035.00

15,082.50

2,250.00
30,600.00
6,412.50

10,884.00
14,400.00
6,720.00
165,566.38

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
TOTAL COST

68,773.20
11,615.00
325.50
8,910.00
650.00

9,035.00
3,360.00
3,180.00

7,260.00
11,275.00
1,070.00
18,750.00
3,400.00
281.51
2,374.98
722.82
7,227.50
1,312.43

4,280.00
4,280.00

6,720.00
9,120.00

1,980.00

11,050.00
12,000.00
2,000.00
15,000.00
3,400.00
540.00
215.00
500.00

50,275.00

15,000.00
102,000.00
42,750.00

36,280.00
48,000.00
22,400.00
547,312.93

712,879.31

7,128.79

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
42,772.76

53,394.66

816,175.52

816,175.52

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a
n/a

TOTAL COST

13,431.00
975.00

4,795.50
1,440.00

1,419.00

2,871.00
3,382.50
393.00
524.40
159.60

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1,575.00
513.00

1,284.00
1,284.00

2,016.00
2,736.00

607.50

4,080.00
4,800.00
2,400.00
3,000.00
2,040.00
126.00
300.00

4,050.00
4,182.00
420.00
344.25
7,500.00

19,800.00
54,000.00
21,600.00
4,800.00

21,777.00
6,720.00
201,345.75

TOTAL COST

44,770.00
3,250.00

15,985.00
4,800.00

4,730.00

9,570.00
11,275.00
1,310.00
1,748.00
532.00
5,250.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1,710.00

4,280.00
4,280.00

6,720.00
9,120.00

2,025.00

13,600.00
16,000.00
8,000.00
10,000.00
6,800.00
420.00
1,000.00

13,500.00
13,940.00
1,400.00
1,147.50
0

132,000.00
360,000.00
72,000.00
16,000.00

72,590.00
22,400.00
892,152.50

1,093,498.25

10,934.98

65,609.90

81,903.02

1,251,946.15

1,251,946.15

ptember 2019

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a
n/a

TOTAL COST

38,858.40
6,562.50
183.75
390.00
5,346.00

834.00
1,008.00
718.50

1,980.00
2,232.00
282.00
862.50
262.50
2,625.00
344.25
1,785.00
108.39
10,170.00

1,066.80
1,066.80

1,680.00
2,280.00

594.00

5,610.00
4,800.00
600.00
6,000.00
1,020.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
162.00
63.00
300.00

18,900.00

15,082.50

2,250.00
30,600.00
44,550.00

10,896.00
14,400.00
6,720.00
243,193.89

TOTAL COST

129,528.00
21,875.00
612.50
1,300.00
17,820.00

2,780.00
3,360.00
2,395.00

6,600.00
7,440.00
940.00
2,875.00
875.00
8,750.00
1,147.50
5,950.00
361.31
33,900.00

3,556.00
3,556.00

5,600.00
7,600.00

1,980.00

18,700.00
16,000.00
2,000.00
20,000.00
3,400.00
540.00
210.00
1,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
0

50,275.00

15,000.00
102,000.00
297,000.00

36,320.00
48,000.00
22,400.00

903,646.31

1,146,840.20

11,468.40

68,810.41

85,898.33

1,313,017.34

1,313,017.34

ptember 2019

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a

n/a

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
TOTAL COST

38,858.40
6,562.50
183.75
390.00
5,346.00

5,838.00
864.00
840.00

1,881.00
2,385.00
259.80
1,035.00
315.00
7,875.00
337.50
2,295.00
126.00
13,725.00

1,500.00
1,500.00

3,360.00
4,560.00

892.50

6,120.00
7,200.00
1,200.00
9,000.00
1,020.00
243.00
129.00
49.50
375.00

18,900.00

15,082.50

2,250.00
45,900.00
177,600.00

11,577.00
21,600.00
10,080.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
429,255.45

TOTAL COST

129,528.00
21,875.00
612.50
1,300.00
17,820.00

19,460.00
2,880.00
2,800.00

6,270.00
7,950.00
866.00
3,450.00
1,050.00
26,250.00
1,125.00
7,650.00
420.00
45,750.00

5,000.00
5,000.00

11,200.00
15,200.00

2,975.00

20,400.00
24,000.00
4,000.00
30,000.00
3,400.00
810.00
430.00
165.00
1,250.00

50,275.00

15,000.00
153,000.00
888,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
38,590.00
72,000.00
33,600.00

1,671,351.50

2,100,606.95

21,006.07

126,036.42

157,335.46

2,404,984.90

2,404,984.90

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a

n/a

TOTAL COST

20,971.20
3,541.50
99.12
175.50
2,409.00

3,127.50
1,440.00
709.50

1,089.00
1,693.50
228.00
524.40
159.60
3,990.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
202.50
1,071.00
85.46
6,300.00

660.00
660.00

1,478.40
2,006.40

594.00

2,295.00
3,600.00
600.00
4,500.00
1,020.00
162.00
64.50
150.00

10,200.00

15,082.50

2,250.00
30,600.00
7,125.00

11,532.00
14,400.00
6,720.00

163,516.58

TOTAL COST

69,904.00
11,805.00
330.40
585.00
8,030.00

10,425.00
4,800.00
2,365.00

3,630.00
5,645.00
760.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1,748.00
532.00
13,300.00
675.00
3,570.00
284.87
21,000.00

2,200.00
2,200.00

4,928.00
6,688.00

1,980.00

7,650.00
12,000.00
2,000.00
15,000.00
3,400.00
540.00
215.00
500.00

50,275.00

15,000.00
102,000.00
47,500.00

38,440.00
48,000.00
22,400.00

542,305.27

705,821.84

7,058.22

42,349.31

52,866.06

808,095.43

808,095.43

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a
n/a

TOTAL COST

19,429.20
3,281.25
91.98
195.00
2,673.00

2,919.00
720.00
519.00

792.00
1,032.00
201.00
489.90
149.10
3,727.50
141.75
1,275.00
89.08
6,840.00

900.00
900.00

2,016.00
2,736.00

594.00

1,530.00
2,400.00
600.00
2,250.00
1,020.00
162.00
64.50
225.00

9,450.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
15,082.50

2,250.00
45,900.00
4,275.00

11,532.00
14,400.00
6,720.00
169,572.76

TOTAL COST

64,764.00
10,937.50
306.60
650.00
8,910.00

9,730.00
2,400.00
1,730.00

2,640.00
3,440.00
670.00
1,633.00
497.00
12,425.00
472.50
4,250.00
296.94
22,800.00

3,000.00
3,000.00

6,720.00
9,120.00

1,980.00

5,100.00
8,000.00
2,000.00
7,500.00
3,400.00
540.00
215.00
750.00

50,275.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
15,000.00
153,000.00
28,500.00

38,440.00
48,000.00
22,400.00
555,492.54

725,065.30

7,250.65

43,503.92

54,307.39

830,127.26

830,127.26

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
Arts Building (Rebid)

TOTAL COST

n/a

n/a

TOTAL COST

5,785.50
36,000.00

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
9,000.00
18,450.00
15,120.00
3,985.52
12,168.00
25,500.00
30,000.00
7,093.50

2,250.00
36,000.00
9,000.00
14,760.00
12,096.00
3,348.90
12,168.00
25,500.00
30,000.00
6,450.00

314,675.42

TOTAL COST

0
0
0
61,500.00
50,400.00
13,285.05
40,560.00
85,000.00
100,000.00
23,645.00

0
0
0
49,200.00
40,320.00
11,163.00
40,560.00
85,000.00
100,000.00
21,500.00

722,133.05

1,036,808.47

10,368.08

62,208.51

77,656.95

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
1,187,042.01

1,187,042.01

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
To : TARLAC SATE UNIVERSITY Date: 01 October 2019
Re : INVITATION TO BID NO. INFRA 024-08-2019A

CASH FLOW BY QUARTER AND PAYMENT SCHEDULE

PARTICULAR % WT 1st QUARTER 2nd QUARTER 3rd QUARTER


ACCOMPLISHMENT 100.00% 25.00% 30.00% 30.00%
CASH FLOW 47,674,361.20 11,918,590.30 14,302,308.36 14,302,308.36
CUMULATIVE ACCOMPLISHMENT 25.00% 55.00% 85.00%
CUMULATIVE CASH FLOW 11,918,590.30 26,220,898.66 40,523,207.02

Submitted By:

RICHARD B. SORIANO
General Manager
October 01, 2019

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
4th QUARTER
15.00%
7,151,154.18
100.00%
47,674,361.20

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
11 Lauren Street Simeona Village Concepcion Marikina City
942-4714/942-7180
To : TARLAC SATE UNIVERSITY
Re : INVITATION TO BID NO. INFRA 024-08-2019A

THE FOLLOWING CONSTRUCTION MATERIALS ARE SUBJECT FOR TRANSPORTATION INSURANCE:

Item No. Work Description Quantity Unit

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg
HIDE 20mm Dia Rebar @6m 408 pcs
2.3.1.2 16mm Dia Rebar 615.00 kg
HIDE 16mm Dia Rebar @6m 65 pcs
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg
HIDE 16mm Dia Rebar @6m 507 pcs
2.3.2.2 12mm Dia Rebar 1,780.00 kg
HIDE 12mm Dia Rebar @6mm 334 pcs
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg
HIDE 16mm Dia Rebar @6m 133 pcs
2.3.3.2 10mm Dia Rebar 920.00 kg
HIDE 10mm Dia Rebar @6m 248 pcs
2.3.3.3 12mm dia rebar 19.00 kg
HIDE 12mm dia rebar @6m 4 pcs
2.3.4 Beam Rebars
2.3.4.1 20mm Dia Rebar 20,404.00 kg
HIDE 20mm Dia Rebar @6m 1,377 pcs
2.3.4.2 10mm Dia Rebar 7,230.00 kg
HIDE 10mm Dia Rebar @6m 1,952 pcs
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg
HIDE 20mm Dia Rebar @6m 808 pcs
2.3.5.2 10mm Dia Rebar 2,930.00 kg
HIDE 10mm Dia Rebar @6m 791 pcs
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m
HIDE 2 x 6 x 1.5mm C Channel Rafter (GI) 6.00 pcs
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m
HIDE 2 x 4 x 1.5mm C Purlins (GI) 35.00 pcs
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot
Welding Rods 10.00 kgs
Cutting Disk 3.00 pcs
Grinding Disk 3.00 pcs
Red oxide primer 4.00 gals
Paint thinner 1.00 gal
Baby roller 2.00 pcs
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg
HIDE 12mm Dia Rebar @6mm 2,290 pcs
2.3.7.2 10mm dia rebar 2,834.00 kg
HIDE 10mm Dia Rebar @6m 765 pcs
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg
HIDE 10mm Dia Rebar @6m 410 pcs
2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg
HIDE 10mm Dia Rebar @6m 392 pcs
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m²
2.3.10.2 12mm dia Rebar 9,720.00 kg
HIDE 12mm Dia Rebar @6mm 1,823 pcs
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg
HIDE 12mm Dia Rebar @6mm 281 pcs
2.3.11.2 10mm Dia Rebar 1,150.00 kg
HIDE 10mm Dia Rebar @6m 311 pcs
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg
HIDE #16 GI Tie Wire @25kg per roll 154.00 rolls

Sub-Total

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m²
12mm formply 13.00 pcs
2"x2"x10' good lumber 106.56 bd.ft.
CWN 6.00 kgs
GI tie wire #16 6.00 kgs
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m²
12mm formply 49.00 pcs
2"x2"x10' good lumber 269.73 bd.ft.
2"x3"x10' good lumber 405.00 bd.ft.
CWN 16.00 kgs
GI tie wire #16 16.00 kgs
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m²
12mm formply 4.00 pcs
2"x2"x10' good lumber 19.98 bd.ft.
2"x3"x10' good lumber 30.00 bd.ft.
CWN 2.00 kgs
GI tie wire #16 2.00 kgs
2.4.4 Columns 61.92 m²
12mm formply 16.00 pcs
2"x2"x10' good lumber 86.58 bd.ft.
2"x3"x10' good lumber 130.00 bd.ft.
CWN 5.00 kgs
GI tie wire #16 5.00 kgs
2.4.5 Beams 106.56 m²
12mm formply 26.00 pcs
2"x2"x10' good lumber 73.26 bd.ft.
2"x3"x10' good lumber 220.00 bd.ft.
CWN 9.00 kgs
GI tie wire #16 9.00 kgs
2.4.6 Roof Beams 41.76 m²
12mm formply 9.00 pcs
2"x2"x10' good lumber 59.94 bd.ft.
2"x3"x10' good lumber 90.00 bd.ft.
CWN 4.00 kgs
GI tie wire #16 4.00 kgs
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m²
12mm formply 49.00 pcs
2"x2"x10' good lumber 189.81 bd.ft.
2"x3"x10' good lumber 230.00 bd.ft.
CWN 10.00 kgs
GI tie wire #16 10.00 kgs
2.4.8 Slab on fill 10.08 m²
12mm formply 3.00 pcs
2"x2"x10' good lumber 15.00 bd.ft.
2"x3"x10' good lumber 23.00 bd.ft.
CWN 1.00 kgs
GI tie wire #16 1.00 kgs
2.4.9 Concrete Trellis (Sunshading) 72.00 m²
12mm formply 19.00 pcs
2"x2"x10' good lumber 99.90 bd.ft.
2"x3"x10' good lumber 150.00 bd.ft.
CWN 6.00 kgs
GI tie wire #16 6.00 kgs
2.4.10 Vertical Fins (Sunshading) 486.00 m²
12mm formply 119.00 pcs
2"x2"x10' good lumber 662.67 bd.ft.
2"x3"x10' good lumber 990.00 bd.ft.
CWN 39.00 kgs
GI tie wire #16 39.00 kgs
2.4.11 Stiffener Columns 120.00 m²
12mm formply 30.00 pcs
2"x2"x10' good lumber 163.17 bd.ft.
2"x3"x10' good lumber 245.00 bd.ft.
CWN 10.00 kgs
GI tie wire #16 10.00 kgs

Sub-Total

2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m²

4.5mm thk Ficem board 34.00 pcs


Wall Angle 33.00 pcs
Carrying Channel 24.00 pcs
Double Furring 36.00 pcs
W-clip 148.00 pcs
Suspension clip 119.00 pcs
Threaded Rod 3/8" 39.00 pcs
Expansion Shield 3/8" 119.00 pcs
Nut and Washer 3/8" 119.00 pcs
Blind Rivets 1/8x1/2 5.00 boxes
Blind Rivets 1/8x3/4 5.00 boxes
Drill Bit 1/8 5.00 pcs
Drive Pin and Gas 118.00 sets
2.7.7 Balcony & Stair Handrails & railing (painted Finish)
2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m²
2 1/2" x 2 1/2" x 3/16" Angle bar 11.00 pcs
Grinding disc 2.00 pc
HIDE Cutting disc 2.00 pc
Welding Rod 2.00 kg
Painting Works 1.00 lot
2.7.7.2 12mm Square Bar 28.00 m
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m
75 x 75 x 1.2mm tubular (GI) 3.00 pcs
Grinding disc 1.00 pc
HIDE
Cutting disc 1.00 pc
Welding Rod 1.00 kg
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m²
Rubber Type Stair Nosings(2mm thk) @3m 32.00 pcs
HIDE
Adhesive 2.00 gal
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal
Epoxy primer 4.00 gals
Baby roller 3.00 pcs
HIDE
Paint brush 3.00 pcs
Paint thinner 1.00 gals
2.7.9.4 Flat Latex Paint 185.00 gal
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot
Boral Compound 35.00 bags
Patching Compound 50.00 bags
Skim coat 45.00 bags
Mesh Tape 28.00 rolls
Paint Roller 23.00 pcs
Baby Roller 20.00 pcs
Sand Paper 8.00 rolls
Paint Brush 17.00 pcs
Rugs 25.00 kgs

Sub-Total

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal


3.2.3 Flat Latex for Existing Ceiling 90.00 gal
3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal
3.2.5 Flat Latex Primer 150.00 gal
3.2.6 Metal Primer, rust Converters 5.00 gal
3.2.7 Paint Thinner 2.00 gal

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot

Boral Compound 30.00 bags


Patching Compound 45.00 bags
Paint Roller 100.00 pcs
Baby Roller 100.00 pcs
Sand Paper 500.00 pcs
Paint Brush 40.00 pcs
Rugs 25.00 kgs

Sub-Total

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m
3.3.1.2 100mm Ø 29.00 m
3.3.1.3 50mm Ø 29.00 m
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc
3.3.2.2 Wye 100 x 100 4.00 pc
3.3.2.3 Elbow 90" x 100 44.00 pc
3.3.2.4 Elbow 45" x 200 3.00 pc
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc
3.3.2.6 Sanitary Tee 100 x 50 25.00 pc
3.3.2.7 P-Trap 100 22.00 pc
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc
10mm dia bar 46.00 kg
HIDE
concrete catch basin 8.30 cu.m.
3.3.3.2 Solvent / Adhesive 20.00 qt
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc
Floor Drain 12.00 pcs
hide
Roof Drain, dome type 16.00 pcs
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56.00 m
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57.00 pc
3.3.4.2.2 25mm Tee 30.00 pc
3.3.4.2.3 25mm Coupling 9.00 pc
3.3.4.2.4 25mm Reducer 10.00 pc
3.3.4.2.5 25mm Gate Valve 6.00 pc
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4.00 set
3.3.4.5 1000L Polyethylene Water Tank 1.00 pc
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1.00 set

Sub-Total
3.4 ELECTRICAL WORKS & FIXTURES
3.4.1 Conduits
3.4.1.1 1/2" Ø PVC 214.00 pc
3.4.1.2 3/4" Ø PVC 527.00 pc
3.4.1.3 2 1/2" Ø PVC 63.00 pc
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set
3.4.1.6 3/4" Ø EMT 10.00 pc
3.4.1.7 1" Ø EMT 75.00 pc
3.4.1.8 1 1/4" Ø EMT 14.00 pc
3.4.1.9 1 1/2" Ø EMT 12.00 pc
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set
3.4.1.12 1" Ø EMT Coupling 72.00 pc
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set
3.4.1.18 2 1/2" Ø RSC 29.00 pc
3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m
3.4.2.2 5.5mm2 THHN Cu 483.00 m
3.4.2.3 8.0mm2 THHN Cu 118.00 m
3.4.2.4 14mm2 THHN Cu 106.00 m
3.4.2.5 22mm2 THHN Cu 39.00 m
3.4.2.6 30mm2 THHN Cu 12.00 m
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m
3.4.2.8 125mm2 THHN Cu 853.00 m
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m
3.4.3.2 5.5mm2 Cu Grounding 257.00 m
3.4.3.3 8.0mm2 Cu Grounding 104.00 m
3.4.3.4 30mm2 Cu Grounding 73.00 m
3.4.3.5 60mm2 Cu Grounding 5.00 m
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc
3.4.4 Others
3.4.4.1 Junction and Utility Boxes 800.00 pc
Junction Boxes w/ cover 480.00 pcs
HIDE
Utility Box 320.00 pcs
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P
3.4.5.3 1.00 set
+ 2 Spare
3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set

3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set

3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set

3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set

90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.8 1.00 set
+ 2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.9 1.00 set
+ 2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-


3.4.5.10 1.00 set
40AT, 2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P +
3.4.5.12 1.00 set
100AT, 3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set
3.4.6.2 Emergency Light 24.00 set
3.4.6.3 Strip Light (Cove Light) 500.00 m
3.4.6.4 36 W Up Light Garden Light 70.00 pc

3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc

3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc


3.4.6.7 One Gang Switch 30.00 pc
3.4.6.8 Two gang Switch 30.00 pc

Sub-Total

3.5 FIRE ALARM WORKS & FIXTURES


3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes
3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc
3.5.1.4 15mm Ø St. Connector 100.00 pc
3.5.1.5 Utility Box 100.00 pc
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc
3.5.1.8 Fire Alarm Pull Box 25.00 pc
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m
3.5.3 Smoke Detectors 141.00 set
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set
3.5.5 Monitoring Switches (6 zones) 1.00 set
3.5.6 Fire Alarm Check Valve 1.00 set
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot
Accessories, Solvents)
Hangers 220.00 pcs
Wiring Accessories 1.00 lot
Electrical tape 50.00 rolls
Solvents @400cc 10.00 pcs

Sub-Total

3.6 FIRE PROTECTION/SPRINKLER SYSTEM


3.6.1 BI Pipe and Fittings
3.6.1.1 150mm Ø S40 BI Pipes 29.00 m
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m
3.6.1.3 80mm Ø S40 BI Pipes 60.00 m
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc
3.6.2.2 BI Tee welded type 100mm 3.00 pc
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc
3.6.2.4 BI Tee threaded type 50mm 3.00 pc
3.6.2.5 BI Tee threaded type 25mm 50.00 pc
3.6.2.6 BI Elbow welded type 150mm 2.00 pc
3.6.2.7 BI Elbow welded type 100mm 9.00 pc
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc
3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc
3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc
3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc
3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc
3.6.2.38 BI Union Patente 25mm 3.00 pc
3.6.2.39 Slip on flange 150mm 36.00 pc
3.6.2.40 Slip on flange 100mm 84.00 pc
3.6.2.41 Slip on flange 80mm 12.00 pc
3.6.2.42 Slip on flange 75mm 6.00 pc
3.6.2.43 Slip on flange 65mm 18.00 pc
3.6.2.44 Rubber Gasket 150mm 18.00 pc
3.6.2.45 Rubber Gasket 100mm 42.00 pc
3.6.2.46 Rubber Gasket 80mm 6.00 pc
3.6.2.47 Rubber Gasket 75mm 3.00 pc
3.6.2.48 Rubber Gasket 65mm 9.00 pc
3.6.3 Valve, Sprinkler, FHC and Accessories

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc


3.6.3.4 Fire Hose Valve 65mm 7.00 pc
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc
3.6.3.6 Inspector Test valve 25mm 7.00 pc
3.6.3.7 Sight Glass 25mm 7.00 pc
3.6.3.8 Water Flow Switch 7.00 pc
3.6.3.9 Supervisory Switch 7.00 pc

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc


3.6.4 Hanger and Brackets 1.00 lot
3.6.4.1 Bolt and Nut and Washer 5/8 x 4" 150.00 pc
3.6.4.2 Angle Bar 2" x 2" x 1/4" 25.00 pc
3.6.4.3 Full threaded 3/8 374.00 pc
3.6.4.4 Loop Hanger 75mm 70.00 pc
3.6.4.5 Loop Hanger 25mm 152.00 pc
3.6.4.6 U-Bolt 75mm x 1/2 70.00 pc
3.6.4.7 U-Bolt 150mm x 5/8 17.00 pc
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe) 1.00 lot
2" DIA 8.00 pcs
HIDE 4" DIA 4.00 pcs
6" DIA 2.00 pcs
3.6.5.1 Clear Silicon Sealant 15.00 tubes
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m²
Red Oxide Primer 8.00 gals
QDE international Red 6.00 gals
HIDE
HIDE
Paint Brush 4.00 pcs
Paint Roller 2.00 pcs
3.6.7 Fire Fighting Equipment & Installation

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot
3.6.8.1 teflon tape 5.00 pc
3.6.8.2 red Oxide 2.00 gal
3.6.8.3 grip anchor 3/8 12.00 pc
3.6.8.4 expansion Shield 3/8 x 2 20.00 pc
3.6.8.5 grinding stone 4" 8.00 pc
3.6.8.6 cut off disks 14" 12.00 pc
3.6.8.7 weldingrRod 6011 4.00 box
3.6.8.8 welding rod 6013 4.00 box
3.6.8.9 Abaca sacks 10.00 pc
3.6.8.10 Flinknote 1.00 lot

Sub-Total

TOTAL ITEM 3

4.0 TOILETS (2 @Ground, 1 @ Third Flr)


4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot

Demolition of Existing tiles, fixtures, hauling of debris, etc. 100.45 m²

4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m²


HIDE 300 x 300 Vitrified Floor and Wall Tiles 1,500.00 pcs
4.1.3 Tile Adhesive 86.67 bag
4.1.4 Tile Grout 8.67 kg

Sub-Total

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set
Male & Female entry/interior door 12.00 pcs
PWD entry door 3.00 pcs
HIDE
Door Knob 15.00 pcs
Door Stoppers 15.00 pcs
4.2.2 Powder Coated Window (see schedule) 12.00 set
4.2.3 Laminated Modular partitions with SS accessories 15.00 set
4.2.4 Semi Gloss Latex 15.00 gal
4.2.5 Flat Latex Paint 15.00 gal

4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Boral Compound 6.00 bags


Patching Compound 6.00 bags
Mesh Tape 9.00 rolls
Paint Roller 9.00 pcs
Baby Roller 9.00 pcs
Sand Paper 41.00 pcs
Paint Brush 3.00 pcs
Rugs 3.00 kgs

Sub-Total

TOTAL ITEM 4

5.0 LECTURE ROOM A-1 (GROUND FLOOR)


5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m²
600 X 600 Homogenous Granite Tiles 204.00 pcs
HIDE
Cement 48.00 bags
5.1.2 Tile Adhesive 46.46 bag
5.1.3 Tile Grout 4.65 kg
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m²
HIDE 150 x 900 Vinyl Tiles 81.00 pcs
5.1.5 Vinyl Adhesive 1.00 gal

Sub-Total

5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal
5.2.2 Flat Latex Primer 7.00 gal

5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot

Boral Compound 2.00 bags


Patching Compound 2.00 bags
Mesh Tape 2.00 rolls
Paint Roller 2.00 pcs
Baby Roller 2.00 pcs
Sand Paper 10.00 pcs
Paint Brush 1.00 pcs
Rugs 1.00 kgs

Sub-Total

5.3 CEILING WORKS


5.3.1 9mm thk Gypsum Board 58.33 m²
HIDE 9mm thk Gypsum Board 22.00 pcs
5.3.2 Metal Double Furring 286.87 m
Double furring 60.00 pcs
HIDE
Threaded rod 25.00 pcs
5.3.3 Wall Angle 30.55 m
Wall angle 11.00 pcs
HIDE
Expansion shield 65.00 pcs
5.3.4 600 x 600 acoustic boards 44.93 m²
HIDE 600 x 600 acoustic boards 125.00 pcs
5.3.5 T-runners (white) 292.05 m
Main tee 12" 20.00 pcs
HIDE Cross tee 4' 20.00 pcs
Cross tee 2' 20.00 pcs
5.3.6 Wall Angle (White) 26.81 m
5.3.7 Carrying Channel 103.26 m
5.3.8 W-Clamps/Clips 206.52 pc
5.3.9 Blind Rivets 1/8 20.65 box
5.3.10 Black Screws 1,749.90 pc

Sub-Total

5.4 ELECTRICAL WORKS AND FIXTURES


5.4.1 Conduits
5.4.1.1 15mm dia PVC (Lighting) 120.00 m
15mm PVC pipe 120.00 ln.m
HIDE 15mm adaptor 80.00 pcs
15mm locknut and bushing 80.00 pcs
5.4.1.2 15mm dia PVC (power lines) 120.00 m
15mm PVC pipe 120.00 ln.m
HIDE 15mm adaptor 80.00 pcs
15mm locknut and bushing 80.00 pcs
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m
5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc
Junction boxes w/ cover 36.00 pcs
HIDE
Utility Boxes 24.00 pcs
5.4.4 Electrical fixtures
5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set
5.4.4.3 Emergency Light 1.00 set
5.4.4.4 Ceiling Fans 6.00 set
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
5.4.4.6 Aircon Outlet 2.00 pc
5.4.4.7 Three Gang Switch 1.00 pc
5.4.4.8 Ceiling Fan Switch 2.00 pc

Sub-Total

5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot

hide Demolition of Existing tiles, fixtures, hauling of debris, etc 66.90 m²

Whiteboard Screen with Integrated Smart TV Enclosure


5.5.2 1.00 set
laminate mounted on plywood on sliding rollers
Smart TV 55" 1.00 unit
Sliding laminated White board (1.2m x 2.4m) 1.00 pcs
HIDE Fixed laminated White board (1.2m x 2.1m) 2.00 pcs
HIDE
3/4" thk Class A Plyboard 3.00 pcs
Screws 100.00 pcs
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set
Professor's desk 1.00 pc
HIDE Ergonomic chair 1.00 pc
Podium 1.00 pc
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set
2 HP Inverter Window type Aircon Unit 2.00 units
HIDE
Angle Bar Frame 2.00 sets
5.5.3.3 PVC Student Armchair 45.00 set

Sub-Total

TOTAL ITEM 5

6.0 STUDENT ORG ROOMS (GROUND FLOOR)


6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m²
HIDE 150 X 900 Vinyl Tiles 407.00 pcs
6.1.2 Vinyl Adhesive 5.00 gal

Sub-Total

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal
6.2.2 Flat Latex 10.00 gal

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot

Boral Compound 2.00 bags


Patching Compound 2.00 bags
Mesh Tape 6.00 rolls
Paint Roller 6.00 pcs
Baby Roller 6.00 pcs
Sand Paper 28.00 pcs
Paint Brush 2.00 pcs
Rugs 1.00 kgs

Sub-Total

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m²
HIDE 9mm thk Gypsum Board 29.00 pcs
6.3.2 Metal Double Furring 373.77 m
Double furring 60.00 pcs
HIDE
Threaded rod 25.00 pcs
6.3.3 Wall Angle 34.87 m
Wall angle 15.00 pcs
HIDE
Expansion shield 70.00 pcs
6.3.4 Carrying Channel 76.00 m
6.3.5 W-clamps/Clips 152.00 pc
6.3.6 Blind rivets(1/8) 15.00 box
6.3.7 Black Screws 2,280.00 pc

Sub-Total

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m
15mm PVC pipe 120.00 ln.m
HIDE 15mm adaptor 80.00 pcs
15mm locknut and bushing 80.00 pcs
6.4.1.2 15mm dia PVC (power lines) 120.00 m
15mm PVC pipe 120.00 ln.m
HIDE 15mm adaptor 80.00 pcs
15mm locknut and bushing 80.00 pcs
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc
Junction boxes w/ cover 45.00 pcs
hide
Utility Boxes 15.00 pcs
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set
6.4.4.3 Emergency Light 4.00 set
6.4.4.4 Ceiling Fan 4.00 set
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc
6.4.4.6 One Gang Switch 4.00 pc
6.4.4.7 Ceiling Fan Switch 4.00 pc

Sub-Total

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc
6.5.1.2 2 x 3 Metal Stud 250.82 m
Metal stud 84.00 pcs
HIDE
Metal tracks 20.00 pcs
6.5.1.3 Blind rivets (1/8) 4.00 box
6.5.1.4 Black Screws 1,530.00 pc
Demolition of existing tiles, fixtures, hauling of debris,
6.5.2 1.00 lot
etc.
Demolition of existing tiles, fixtures, hauling of debris, etc. 50.00 sq.m

6.5.3 Furniture & Appliances


6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set
Working Table 4.00 pc
hide
Ergonomic chair 32.00 pcs
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc

Sub-Total

TOTAL ITEM 6

AMOUNT IN FIGURES

Submitted By:

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION
Date: 01 October 2019
To : TARLAC SATE UNIVERSITY
Re : INVITATION TO BID NO. INFRA 024-08-2019A

BILL OF QUANTITIES

Item No. Work Description Quantity Unit

(1) (2) (3) (4)


1.0 GENERAL REQUIREMENTS
1.1 Mobilization/Demobilization 1.00 lot
1.2 Temporary Facilities 1.00 lot
1.2.1 Temporary Barracks & Storage
1.2.2 Temporary Fence/Board-up
1.2.3 Temporary Water and Power Consumption
1.3 Permits and Licenses 1.00 lot
1.3.1 Building Permit Processing, fire clearance, occupancy
1.3.2 Licenses and certifications - operations
1.4 Safety and Health 1.00 lot
1.4.1 Pre-cautionary Signages, Safety nets & Scaffolds
1.4.2 Personal Protective Equipment for personnel

Sub-Total

SUNSHADING, STAIRCASE, ELEVATOR, PUMP RM,


2.0
CISTERN
2.1 EARTHWORKS
2.1.1 Site Clearing (including cutting & bases) 1,120.00 m²
2.1.2 Demolition (selected windows and plantboxes) see dwgs 160.00 m²
2.1.3 Layout and Staking 1,120.00 m²
2.1.4 Excavation 575.00 m³
2.1.5 Backfill / Compaction 412.00 m³
2.1.6 Gravelbase Coarse 20.00 m³
2.1.7 Soil Poisoning 280.00 m²
Sub-Total

2.2 CONCRETING
2.2.1 Footing 100.00 m³
2.2.2 Shear Wall of Elevator Shaft & Cistern Tank 47.00 m³
2.2.3 Pedestal, Encasement & Pull Box (Service Entrance) 20.00 m³
2.2.4 Columns 86.00 m³
2.2.5 Beams 148.00 m³
2.2.6 Roof Beams 58.00 m³
2.2.7 Suspended Slab. Ledges, Staircase 157.00 m³
2.2.8 Slab on fill 14.00 m³
2.2.9 Concrete Trellis (Sunshading) 10.00 m³
2.2.10 Vertical Fins (Sunshading) 155.00 m³
2.2.11 Stiffener Columns 19.00 m³

Sub-Total

2.3 REINFORCING BARS & STRUCTURAL STEEL


2.3.1 Footing Rebars
2.3.1.1 20mm Dia Rebar 6,045.00 kg
2.3.1.2 16mm Dia Rebar 615.00 kg
2.3.2 Shear Wall of Elevator Shaft & Cistern Tank
2.3.2.1 16mm Dia Rebar 4,805.00 kg
2.3.2.2 12mm Dia Rebar 1,780.00 kg
2.3.3 Pedestal, Encasement & Pull Box (Service Entrance)
2.3.3.1 16mm Dia Rebar 1,260.00 kg
2.3.3.2 10mm Dia Rebar 920.00 kg
2.3.3.3 12mm dia rebar 19.00 kg
Item No. Work Description Quantity Unit

2.3.4 Beam Rebars


2.3.4.1 20mm Dia Rebar 20,404.00 kg
2.3.4.2 10mm Dia Rebar 7,230.00 kg
2.3.5 Column Rebars
2.3.5.1 20mm Dia Rebar 11,963.00 kg
2.3.5.2 10mm Dia Rebar 2,930.00 kg
2.3.6 Roof Framing (elevator Stairs, Pump room)
2.3.6.1 2 x 6 x 1.5mm C Channel Rafter (GI) 30.00 m
2.3.6.2 2 x 4 x 1.5mm C Purlins (GI) 200.00 m
2.3.6.3 Consumables (welding rods, cutting & grinding disk) 1.00 lot
2.3.7 Suspended Slab & Staircase
2.3.7.1 12mm dia rebar 12,213.00 kg
2.3.7.2 10mm dia rebar 2,834.00 kg
2.3.8 Slab on Fill
2.3.8.1 10mm dia rebar 1,520.00 kg
2.3.9 Concrete Trellis
2.3.9.1 10mm dia rebar 1,450.00 kg
2.3.10 Vertical (Sunshading)
2.3.10.1 Wire Mesh 50 x 50 x 4mm 189.00 m²
2.3.10.2 12mm dia Rebar 9,720.00 kg
2.3.11 Stiffener Columns
2.3.11.1 12mm Dia Rebar 1,500.00 kg
2.3.11.2 10mm Dia Rebar 1,150.00 kg
2.3.12 Tie Wire, Gauge No. 16 GI Wire 4,300.00 kg

Sub-Total

2.4 SCAFFOLDING &FORMWORKS


2.4.1 Footing 72.00 m²
2.4.2 Shear Wall of Elevator Shaft & Cistern Tank 198.00 m²
2.4.3 Pedestal, Encasement & Pull Box (Service Entrance) 14.40 m²
2.4.4 Columns 61.92 m²
2.4.5 Beams 106.56 m²
2.4.6 Roof Beams 41.76 m²
2.4.7 Suspended Slab. Ledges, Staircase3 113.04 m²
2.4.8 Slab on fill 10.08 m²
2.4.9 Concrete Trellis (Sunshading) 72.00 m²
2.4.10 Vertical Fins (Sunshading) 486.00 m²
2.4.11 Stiffener Columns 120.00 m²

Sub-Total

2.5 MASONRY & WATERPROOFING


2.5.1 Integral Waterproofing (decks, cistern & elevator pit) 1,600.00 kg

2.5.2 Cementitious waterproofing lining (decks, plantbox & cistern) 1,100.00 m²

2.5.3 6" thk CHB parapet Walls 1,144.00 pc


2.5.4 mortar and Plastering
2.5.4.1 Cement 210.00 bag
2.5.4.2 Sand 20.00 m³

2.5.5 10mm dia horiz and Vertical rebars for CHB and Deco Blocks 1,820.00 kg

2.5.6 #16 Gi Tie Wire 182.00 kg

2.5.7 Heavy Duty Cement-based Adhesive for Decorative Blocks 450.00 bag

2.5.8 Decorative Blocks (Sunshading) 250 x 250 x 88 9,300.00 pc

Sub-Total
Item No. Work Description Quantity Unit

2.6 EQUIPMENT

Machine roomless elevator Equipment 1500 kg, 3 stops (3 front


openings) 1m/s, steel hoist Silver brushed car Walls, w/ gray
Black Granite Car Floor, Silver brushed skirting, mirror on walls,
2.6.1 1.00 set
LED direct light 7.6kW, 31A-43A, 3P, 230V 60Hz incl reqd
electrical outlets, breakers and exhaust fans, incl I-Beams or
any strucl steel reqd for installation

2.6.2 Electric Water Heater (complete with telephone Shower) 6.00 set
2.6.3 2HP Electric Submersible Pump (at Elevator pit) 1.00 set
Booster Pump (1HP) (40PSI) (65% efficiency) w/ foot valve w/
2.6.4 1.00 set
Bladder Tank (30gal) w/ complete accessories

Sub-Total

2.7 FINISHING WORKS


Engineer weatherproof wood planks (25mm thk)- 150mm x
2.7.1 880.00 m²
900mm
2.7.1.1 Cement Glue for Floor Plank 880.00 m²
2.7.2 Non-Skid Rubberized Painted Finish (Hallways) 232.00 m²
Built-up Acrylic LED Lighted Signage with 9mm thk Acrylic
2.7.3 1.00 set
built-up letters, LED lighting, mounting and installation

Elevator & Pump Room Roof, Rib Type G.I. (0.5mm), prepainted
2.7.4 120.00 m²
Longspan incl flushings; w/ insulation
2.7.5 Roof Works Miscellaneous (Tuxscrews, Silicon, blind rivets) 1.00 lot

2.7.6 Ceiling: 4.5mm thk Ficem board on Metal Furring (staircase) 70.00 m²

2.7.7 Balcony & Stair Handrails & railing (painted Finish)


2.7.7.1 62mm x 4.1 mm Angle Bar 61.00 m²
2.7.7.2 12mm Square Bar 28.00 m
2.7.7.3 75 x 75 x 1.2mm tubular (G.I.) 15.63 m
2.7.8 Stair Nosings (rubber type) (30mm) (2mm thk) 186.00 m²
2.7.9 Painting Works
2.7.9.1 Elastomeric paint for vertical fins & deco blocks 290.00 gal
2.7.9.2 Semi Gloss latex (elev shaft, stairs, pump rm, cistern) 80.00 gal
2.7.9.3 Existing Staircase Handrails & Railings 4.00 gal
2.7.9.4 Flat Latex Paint 185.00 gal
2.7.9.5 Consumables (brushes, putty, sandpaper) 1.00 lot
2.7.10 uPVC Clear Transparent Rib Type Roof + misc. 250.00 m²
2.7.11 Paver blocks 250.00 m²

Sub-Total

3.0 GENERAL REPAIR & IMPROVEMENTS ON CAFA BUILDING


3.1 ROOFING AND EAVES SOFFIT
Replacement of delapidated roofing, (pre-painted longspan,
3.1.1 1,100.00 m
ribtype, G.I. 0.5mm thk)
3.1.2 Insulation (double sided aluminum) (w/ chicken wire) 1,100.00 m²
Replacement of Eaves Soffit - Spandrel (110mm wide), (pre-
3.1.3 2,000.00 m
painted G.I., 0.5mm thk) complete w/ misc.

Spandrel Mouldings/Edging Wall Angles, complete w/


3.1.4 450.00 m
misc./silicon

Sub-Total

3.2 PAINTING WORKS

3.2.1 Elastomeric paint for Conc Gutters, parapet walls, plantboxes 215.00 gal

3.2.2 Semi gloss Latex for Existing Walls 160.00 gal


3.2.3 Flat Latex for Existing Ceiling 90.00 gal
Item No. Work Description Quantity Unit

3.2.4 Repainting of Grills, Railings, Metal Framings 10.00 gal


3.2.5 Flat Latex Primer 150.00 gal
3.2.6 Metal Primer, rust Converters 5.00 gal
3.2.7 Paint Thinner 2.00 gal

3.2.8 Consumables (Brushes, rollers, putty, patching compound, etc) 1.00 lot

Sub-Total

3.3 PLUMBING WORKS


3.3.1 PVC Pipes Series 1000
3.3.1.1 150mm Ø 62.00 m
3.3.1.2 100mm Ø 29.00 m
3.3.1.3 50mm Ø 29.00 m
3.3.2 PVC Fittings Series 1000
3.3.2.1 Wye 150 x 150 4.00 pc
3.3.2.2 Wye 100 x 100 4.00 pc
3.3.2.3 Elbow 90" x 100 44.00 pc
3.3.2.4 Elbow 45" x 200 3.00 pc
3.3.2.5 Sanitary Tee 150 x 100 15.00 pc
3.3.2.6 Sanitary Tee 100 x 50 25.00 pc
3.3.2.7 P-Trap 100 22.00 pc
3.3.3 Others
3.3.3.1 Catch basin 28.00 pc
3.3.3.2 Solvent / Adhesive 20.00 qt
3.3.3.3 Strainer (Floor/Roof Drain) 28.00 pc
3.3.4 Waterline System
3.3.4.1 PPR Pipe (25mm) (PN20) 56 m
3.3.4.2 PPR fittings
3.3.4.2.1 25mm Elbow 57 pc
3.3.4.2.2 25mm Tee 30 pc
3.3.4.2.3 25mm Coupling 9 pc
3.3.4.2.4 25mm Reducer 10 pc
3.3.4.2.5 25mm Gate Valve 6 pc
3.3.4.4 Studio Sink Fixtures for Existing Rooms: A-2, A-14, A-15, A-17 4 set
3.3.4.5 1000L Polyethylene Water Tank 1 pc
3.3.4.6 2HP Transfer Pump w/ 16L Bladder Tank 1 set

Sub-Total

3.4 ELECTRICAL WORKS & FIXTURES


3.4.1 Conduits
3.4.1.1 1/2" Ø PVC 214.00 pc
3.4.1.2 3/4" Ø PVC 527.00 pc
3.4.1.3 2 1/2" Ø PVC 63.00 pc
3.4.1.4 2 1/2" Ø PVC Elbow 8.00 set
3.4.1.5 2 1/2" Ø PVC Adaptor w/ bushing and locknut 4.00 set
3.4.1.6 3/4" Ø EMT 10.00 pc
3.4.1.7 1" Ø EMT 75.00 pc
3.4.1.8 1 1/4" Ø EMT 14.00 pc
3.4.1.9 1 1/2" Ø EMT 12.00 pc
3.4.1.10 3/4" Ø EMT Coupling 10.00 pc
3.4.1.11 3/4" Ø EMT Adaptor w/ bushing and locknut 2.00 set
3.4.1.12 1" Ø EMT Coupling 72.00 pc
3.4.1.13 1" Ø EMT Adaptor w/ bushing and locknut 13.00 set
3.4.1.14 1 1/4" Ø EMT Coupling 14.00 pc
3.4.1.15 1 1/4" Ø EMT Adaptor w/ bushing and locknut 1.00 set
3.4.1.16 1 1/2" Ø EMT Coupling 3.00 pc
3.4.1.17 1 1/2" Ø EMT Adaptor w/ bushing and locknut 12.00 set
Item No. Work Description Quantity Unit

3.4.1.18 2 1/2" Ø RSC 29.00 pc


3.4.1.19 2 1/2" Ø RSC Coupling 12.00 pc
3.4.1.20 2 1/2" Ø bushing and locknut 2.00 set
3.4.1.21 2 1/2" Ø Entrance Cap 4.00 pc
3.4.2 Wires and Cables
3.4.2.1 3.5mm2 THHN Cu 7,285.00 m
3.4.2.2 5.5mm2 THHN Cu 483.00 m
3.4.2.3 8.0mm2 THHN Cu 118.00 m
3.4.2.4 14mm2 THHN Cu 106.00 m
3.4.2.5 22mm2 THHN Cu 39.00 m
3.4.2.6 30mm2 THHN Cu 12.00 m
3.4.2.7 80mm2 THHN Cu (FR Cable) 146.00 m
3.4.2.8 125mm2 THHN Cu 853.00 m
3.4.3 Grounding Wires (green)
3.4.3.1 3.5mm2 Cu Grounding 933.00 m
3.4.3.2 5.5mm2 Cu Grounding 257.00 m
3.4.3.3 8.0mm2 Cu Grounding 104.00 m
3.4.3.4 30mm2 Cu Grounding 73.00 m
3.4.3.5 60mm2 Cu Grounding 5.00 m
3.4.3.6 5/8 Ø x 3m Grounding Rod 2.00 pc
3.4.4 Others
3.4.4.1 Junction and Utility Boxes 800.00 pc
3.4.5 Panelboard and Equipment
3.4.5.1 40AT MCB, 2P - 6 Branches: 5-20AT, 2P + 1 Spare 1.00 set
3.4.5.2 40AT MCB, 2P - 4 Branches: 2-20AT, 2P + 2 Spare 1.00 set
40AT MCB, 3P - 6 Branches: 40AT, 2P + 30AT, 2P + 2-20AT, 2P
3.4.5.3 1.00 set
+ 2 Spare

3.4.5.4 40AT MCB, 3P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set

3.4.5.5 50AT MCB, 2P - 6 Branches: 2-30AT, 2P + 2-20AT, 2P + 2 Spare 1.00 set

3.4.5.6 50AT MCB, 3P - 6 Branches: 2-40AT, 3P + 3-20AT, 2P + 1 Spare 1.00 set

3.4.5.7 60AT MCB, 3P - 8 Branches: 3-40AT, 2P + 4-20AT, 2P + 1 Spare 1.00 set

90AT MCB, 3P - 8 Branches: 60AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.8 1.00 set
+ 2 Spare

90AT MCB, 3P - 8 Branches: 70AT, 3P + 40AT, 3P + 4-20AT, 2P


3.4.5.9 1.00 set
+ 2 Spare

100AT MCB, 3P - 12 Branches: 50AT, 3P + 2-50AT, 2P + 2-40AT,


3.4.5.10 1.00 set
2P + 1-30AT, 2P +5-20AT, 2P + 1 Spare
3.4.5.11 300AT MCB, 3P - 2 Branches: 600AT, 3P + 30AT, 3P 1.00 set
1000AT MCB, 3P - 6 Branches: 700AT, 3P + 300AT, 3P + 100AT,
3.4.5.12 1.00 set
3P + 2-90AT, 3P + 1 Spare, 3P
3.4.5.13 1000AT, 3P on NEMA 3R (on pedestal) 1.00 set
3.4.6 Electrical Fixtures
3.4.6.1 100mm dia Cylindrical downlight Fixture with LED 13W 48.00 set
3.4.6.2 Emergency Light 24.00 set
3.4.6.3 Strip Light (Cove Light) 500.00 m
3.4.6.4 36 W Up Light Garden Light 70.00 pc

3.4.6.5 3-Prong Two-Gang Convenience Outlet (w/ WP Cover) 50.00 pc

3.4.6.6 36 W Compact Fluorescent Lights 2.00 pc


3.4.6.7 One Gang Switch 30.00 pc
3.4.6.8 Two gang Switch 30.00 pc

Sub-Total

3.5 FIRE ALARM WORKS & FIXTURES


Item No. Work Description Quantity Unit

3.5.1 Conduits, Fittings, Junction, Utility, Pull Boxes


3.5.1.1 15mm Ø (1/2") PVC Pipes 342.00 m
3.5.1.2 15mm Ø (1/2") PVC Connector 150.00 pc
3.5.1.3 15mm Ø (1/2") PVC Coupling 150.00 pc
3.5.1.4 15mm Ø St. Connector 100.00 pc
3.5.1.5 Utility Box 100.00 pc
3.5.1.6 Octagonal Junction Box w/ Cover 250.00 pc
3.5.1.7 4 x 4" Square Box w/ Cover 70.00 pc
3.5.1.8 Fire Alarm Pull Box 25.00 pc
3.5.2 Wires and Cables
3.5.2.1 26 AWG FA Cable 684.00 m
3.5.3 Smoke Detectors 141.00 set
3.5.4 Addressable Fire Alarm Control Panel, FDAS 1.00 set
3.5.5 Monitoring Switches (6 zones) 1.00 set
3.5.6 Fire Alarm Check Valve 1.00 set
Miscellaneous/Consumables (Conduits, hangers, Wiring
3.5.7 1.00 lot
Accessories, Solvents)

Sub-Total

3.6 FIRE PROTECTION/SPRINKLER SYSTEM


3.6.1 BI Pipe and Fittings
3.6.1.1 150mm Ø S40 BI Pipes 29.00 m
3.6.1.2 100mm Ø S40 BI Pipes 64.00 m
3.6.1.3 80mm Ø S40 BI Pipes 60.00 m
3.6.1.4 75mm Ø S40 BI Pipes 67.00 m
3.6.1.5 65mm Ø S40 BI Pipes 32.00 m
3.6.1.6 50mm Ø S40 BI Pipes 28.00 m
3.6.1.7 40mm Ø S40 BI Pipes 8.00 m
3.6.1.8 32mm Ø S40 BI Pipes 8.00 m
3.6.1.9 25mm Ø S40 BI Pipes 325.00 m
3.6.2 Fittings (Sched 40)
3.6.2.1 BI Tee welded type 150mm 3.00 pc
3.6.2.2 BI Tee welded type 100mm 3.00 pc
3.6.2.3 BI 45 deg welded type 80mm 1.00 pc
3.6.2.4 BI Tee threaded type 50mm 3.00 pc
3.6.2.5 BI Tee threaded type 25mm 50.00 pc
3.6.2.6 BI Elbow welded type 150mm 2.00 pc
3.6.2.7 BI Elbow welded type 100mm 9.00 pc
3.6.2.8 BI Elbow threaded type 40mm 26.00 pc
3.6.2.9 BI Elbow threaded type 32mm 118.00 pc
3.6.2.10 BI Elbow threaded type 25mm 308.00 pc
3.6.2.11 BI Tee Reducer welded type 150mm x 100mm 2.00 pc
3.6.2.12 BI Tee Reducer welded type 100mm x 80mm 1.00 pc
3.6.2.13 BI Tee Reducer welded type 100mm x 65mm 10.00 pc
3.6.2.14 BI Tee Reducer welded type 100mm x 40mm 3.00 pc
3.6.2.15 BI Tee Reducer welded type 100mm x 32mm 36.00 pc
3.6.2.16 BI Tee Reducer welded type 80mm x 40mm 3.00 pc
3.6.2.17 BI Tee Reducer welded type 80mm x 32mm 16.00 pc
3.6.2.18 BI Tee Reducer welded type 75mm x 40mm 3.00 pc
3.6.2.19 BI Tee Reducer welded type 75mm x 32mm 24.00 pc
3.6.2.20 BI Tee Reducer welded type 65mm x 40mm 2.00 pc
3.6.2.21 BI Tee Reducer welded type 50mm x 40mm 1.00 pc
3.6.2.22 BI Tee Reducer welded type 65mm x 32mm 15.00 pc
3.6.2.23 BI Tee Reducer welded type 50mm x 32mm 18.00 pc
3.6.2.24 BI Tee Reducer welded type 40mm x 32mm 6.00 pc
3.6.2.25 BI Tee Reducer welded type 32mm x 25mm 3.00 pc
3.6.2.26 BI Elbow Reducer welded type 150mm x 100mm 1.00 pc
3.6.2.27 BI Elbow Reducer welded type 100mm x 65mm 5.00 pc
Item No. Work Description Quantity Unit

3.6.2.28 BI Coupling Reducer welded type 150mm x 100mm 1.00 pc


3.6.2.29 BI Coupling Reducer welded type 100mm x 80mm 3.00 pc
3.6.2.30 BI Coupling Reducer welded type 80mm x 75mm 3.00 pc
3.6.2.31 BI Coupling Reducer welded type 80mm x 40mm 1.00 pc
3.6.2.32 BI Coupling Reducer welded type 75mm x 65mm 3.00 pc
3.6.2.33 BI Coupling Reducer welded type 65mm x 50mm 3.00 pc
3.6.2.34 BI Coupling Reducer welded type 50mm x 40mm 2.00 pc
3.6.2.35 BI Coupling Reducer threaded type 32mm x 25mm 115.00 pc
3.6.2.36 BI Coupling Reducer threaded type 25mm x 15mm 148.00 pc
3.6.2.37 BI End Cap threaded type 32mm 15.00 pc
3.6.2.38 BI Union Patente 25mm 3.00 pc
3.6.2.39 Slip on flange 150mm 36.00 pc
3.6.2.40 Slip on flange 100mm 84.00 pc
3.6.2.41 Slip on flange 80mm 12.00 pc
3.6.2.42 Slip on flange 75mm 6.00 pc
3.6.2.43 Slip on flange 65mm 18.00 pc
3.6.2.44 Rubber Gasket 150mm 18.00 pc
3.6.2.45 Rubber Gasket 100mm 42.00 pc
3.6.2.46 Rubber Gasket 80mm 6.00 pc
3.6.2.47 Rubber Gasket 75mm 3.00 pc
3.6.2.48 Rubber Gasket 65mm 9.00 pc
3.6.3 Valve, Sprinkler, FHC and Accessories

Pendent type sprinkler head w/ escutcheon plate,


3.6.3.1 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 94.00 pc
(150 F)

Side wall type sprinkler head w/ escutcheon plate,


3.6.3.2 12mm orifice, chrome plated, bulb type UL/FM (k=5.6) 48.00 pc
(150 F)

3.6.3.3 OS & Y Control Valve 100mm 1.00 pc


3.6.3.4 Fire Hose Valve 65mm 7.00 pc
3.6.3.5 Auxilliary Drain Valve 32mm 3.00 pc
3.6.3.6 Inspector Test valve 25mm 7.00 pc
3.6.3.7 Sight Glass 25mm 7.00 pc
3.6.3.8 Water Flow Switch 7.00 pc
3.6.3.9 Supervisory Switch 7.00 pc

Fire Hose Cabinet complete with 40mm Angle Valve,


3.6.3.10 10mm lbs. ABC Fire Extinguisher 40mm ft x 100ft long, 14.00 pc
fire hose and 40mm adjustable fog nozzle

3.6.3.11 Siamese fire 65mm x 65mm x 100mm 3.00 pc


3.6.4 Hanger and Brackets 1.00 lot
3.6.4.1 Bolt and Nut and Washer 5/8 x 4"
3.6.4.2 Angle Bar 2" x 2" x 1/4"
3.6.4.3 Full threaded 3/8
3.6.4.4 Loop Hanger 75mm
3.6.4.5 Loop Hanger 25mm
3.6.4.6 U-Bolt 75mm x 1/2
3.6.4.7 U-Bolt 150mm x 5/8
3.6.5 Sleeving Works (Pipe Sleeves) 1.00 lot
3.6.5.1 PVC Pipe (one pipe larger than penetrating BI Pipe)
3.6.5.1 Clear Silicon Sealant
3.6.6 Painting Works (Primer and QDE Red Finish) 120.00 m²
3.6.7 Fire Fighting Equipment & Installation

Fire Pump (System duty point: 400gpm vs 120 psi),


3.6.7.1 Vertical Turbine Type, UL/FM, complete w/ accessories, 1.00 set
Electric motor 40HP/230V/3P/60Hz w/ accessories

Jockey Pump (System duty point: 20gpm vs 120psi),


3.6.7.2 1.00 set
4HP/Electric Motor 230VAC/3P/60Hz w/ accessories
3.6.8 Hardwares, consumables/Miscellaneous 1.00 lot
3.6.8.1 teflon tape
Item No. Work Description Quantity Unit

3.6.8.2 red Oxide


3.6.8.3 grip anchor 3/8
3.6.8.4 expansion Shield 3/8 x 2
3.6.8.5 grinding stone 4"
3.6.8.6 cut off disks 14"
3.6.8.7 weldingrRod 6011
3.6.8.8 welding rod 6013
3.6.8.9 Abaca sacks
3.6.8.10 Flinknote

Sub-Total

4.0 TOILETS (2 @Ground, 1 @ Third Flr)


4.1 FLOOR AND WALL FINISHES
4.1.1 Demolition of Existing tiles, fixtures, hauling of debris, etc. 1.00 lot
4.1.2 300 x 300 Vitrified Floor and Wall Tiles 130.00 m²
4.1.3 Tile Adhesive 86.67 bag
4.1.4 Tile Grout 8.67 kg

Sub-Total

4.2 FIXTURES & OTHER FINISHES


4.2.1 Steel Door with complete accessories (knobs & hinges) 15.00 set
4.2.2 Powder Coated Window (see schedule) 12.00 set
4.2.3 Laminated Modular partitions with SS accessories 15.00 set
4.2.4 Semi Gloss Latex 15.00 gal
4.2.5 Flat Latex Paint 15.00 gal

4.2.6 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Sub-Total

4.3 PLUMBING WORKS


4.3.1 PVC Pipes Series 1000
4.3.1.1 150mm Ø 77.00 m
4.3.1.2 100mm Ø 188.00 m
4.3.2 PVC Fittings Series 1000
4.3.2.1 Wye 150 x 150 21.00 pc
4.3.2.2 Wye 100 x 100 24.00 pc
4.3.2.3 Elbow 90" x 100 66.00 pc
4.3.2.4 Elbow 45" x 200 6.00 pc
4.3.2.5 Sanitary Tee 150 x 100 24.00 pc
4.3.2.6 Sanitary Tee 100 x 50 39.00 pc
4.3.2.7 P-Trap 100 39.00 pc
4.3.3 19mm Ø PPR Pipes (PN20) 100.00 m
4.3.4 PPR Fittings
4.3.4.1 Elbow 90 x 19 85.50 pc
4.3.4.2 Tee 19 x 19 45.00 pc
4.3.4.3 Coupling 25 x 25 13.50 pc
4.3.4.4 Coupling 25 x 19 15.00 pc
4.3.4.5 Gate Valve 19 6.00 pc
4.3.5 Sanitary Fixtures
4.3.5.1 Shower Head and Shower Valves 6.00 set
4.3.5.2 Telephone Water Heater 6.00 set
4.3.5.3 Lavatory Sink 15.00 set
4.3.5.4 Water Closet dual flush 12.00 set
4.3.5.5 Waterless Urinal 7.00 set
4.3.6 Miscellaneous/Consumables 1.00 lot
4.3.6.1 Pipe Sleeves
Item No. Work Description Quantity Unit

4.3.6.2 Pipe Hangers & Support


4.3.6.3 Teflon, Solvent etc.

Sub-Total

4.4 ELECTRICAL WORKS & FIXTURES


4.4.1 Conduits
4.4.1.1 15mm dia PVC (Lighting) 270.00 m
4.4.1.2 15mm dia PVC (power lines) 270.00 m
4.4.2 Wires and Cables (Ground Floor Toilet Only)
4.4.2.1 2-3.5mm THHN cu. Stranded Wires 540.00 m
4.4.3 Junction and utility Boxes 120.00 pc
4.4.4 Electrical Fixtures
4.4.4.1 100mm dia Cylindrical Downlight Fixture with LED 13W 33.00 pc
4.4.4.2 Emergency Light 6.00 pc
4.4.4.3 Ceiling Exhaust Fan & Switch (heavy duty) 6.00 pc
4.4.4.4 Two Gang Switch 9.00 pc

Sub-Total

5.0 LECTURE ROOM A-1 (GROUND FLOOR)


5.1 FLOOR FINISHES
5.1.1 600 X 600 Homogenous Granite Tiles 66.90 m²
5.1.2 Tile Adhesive 46.46 bag
5.1.3 Tile Grout 4.65 kg
5.1.4 150 x 900 Vinyl Tiles on platform 10.00 m²
5.1.5 Vinyl Adhesive 1.00 gal

Sub-Total

5.2 PAINTING
5.2.1 Semi Gloss Latex 13.00 gal
5.2.2 Flat Latex Primer 7.00 gal

5.2.3 Consumbales (Paint Brushes, Rollers, Sand Paper, Putty etc) 1.00 lot

Sub-Total

5.3 CEILING WORKS


5.3.1 9mm thk Gypsum Board 58.33 m²
5.3.2 Metal Double Furring 286.87 m
5.3.3 Wall Angle 30.55 m
5.3.4 600 x 600 acoustic boards 44.93 m²
5.3.5 T-runners (white) 292.05 m
5.3.6 Wall Angle (White) 26.81 m
5.3.7 Carrying Channel 103.26 m
5.3.8 W-Clamps/Clips 206.52 pc
5.3.9 Blind Rivets 1/8 20.65 box
5.3.10 Black Screws 1,749.90 pc

Sub-Total

5.4 ELECTRICAL WORKS AND FIXTURES


5.4.1 Conduits
5.4.1.1 15mm dia PVC (Lighting) 120.00 m
5.4.1.2 15mm dia PVC (power lines) 120.00 m
5.4.2 Wires and Cables (Ground Floor Toilet Only)
5.4.2.1 2-3.5mm THHN cu. Stranded Wires 240.00 m
5.4.2.2 2-5.5mm THHN cu. Stranded Wires 240.00 m
Item No. Work Description Quantity Unit

5.4.3 Others
5.4.3.1 Junction and Utility Box 60.00 pc
5.4.4 Electrical fixtures
5.4.4.1 Pinlight (100mm dia) with 7W LED 13.00 pc
5.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set
5.4.4.3 Emergency Light 1.00 set
5.4.4.4 Ceiling Fans 6.00 set
5.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
5.4.4.6 Aircon Outlet 2.00 pc
5.4.4.7 Three Gang Switch 1.00 pc
5.4.4.8 Ceiling Fan Switch 2.00 pc

Sub-Total

5.5 OTHERS
5.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot
Whiteboard Screen with Integrated Smart TV Enclosure
5.5.2 1.00 set
laminate mounted on plywood on sliding rollers
5.5.3 Furniture & Appliances
5.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set
5.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set
5.5.3.3 PVC Student Armchair 45.00 set

Sub-Total

5.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)

5.6.1 D-1: Metal Door Jams and Panel (w/ knobs & hinges) 2.00 set
5.6.2 W-1: Clear Glass powder coated white awning window 4.00 set
5.6.3 W-2: Clear glass powder coated white pivot window 4.00 set

Sub-Total

6.0 STUDENT ORG ROOMS (GROUND FLOOR)


6.1 FLOOR FINISHES
6.1.1 150 X 900 Vinyl Tiles 50.00 m²
6.1.2 Vinyl Adhesive 5.00 gal

Sub-Total

6.2 PAINTING
6.2.1 Semi Gloss Latex 23.00 gal
6.2.2 Flat Latex 10.00 gal

6.2.3 consumbales ( paint brushes, rollers, sand papers, putty etc) 1.00 lot

Sub-Total

6.3 CEILING WORKS


6.3.1 9mm thk Gypsum board 76.00 m²
6.3.2 Metal Double Furring 373.77 m
6.3.3 Wall Angle 34.87 m
6.3.4 Carrying Channel 76.00 m
6.3.5 W-clamps/Clips 152.00 pc
6.3.6 Blind rivets(1/8) 15.00 box
6.3.7 Black Screws 2,280.00 pc

Sub-Total
Item No. Work Description Quantity Unit

6.4 ELECTRICAL WORKS AND FIXTURES


6.4.1 Conduits
6.4.1.1 15mm dia PVC (Lighting) 120.00 m
6.4.1.2 15mm dia PVC (power lines) 120.00 m
6.4.2 Wires and Cables (Ground Floor Toilet Only)
6.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m
6.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m
6.4.3 Others
6.4.3.1 Junction and Utility Box 60.00 pc
6.4.4 Electrical fixtures
6.4.4.1 Pinlight (100mm dia) with 7W LED 16.00 set
6.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set
6.4.4.3 Emergency Light 4.00 set
6.4.4.4 Ceiling Fan 4.00 set
6.4.4.5 3-Prong Two-Gang Convenience Outlet 8.00 pc
6.4.4.6 One Gang Switch 4.00 pc
6.4.4.7 Ceiling Fan Switch 4.00 pc

Sub-Total

6.5 OTHERS
6.5.1 Drywall Partition
6.5.1.1 9mm thk fiber cement Board 18.00 pc
6.5.1.2 2 x 3 Metal Stud 250.82 m
6.5.1.3 Blind rivets (1/8) 4.00 box
6.5.1.4 Black Screws 1,530.00 pc
6.5.2 Demolition of existing tiles, fixtures, hauling of debris, etc. 1.00 lot
6.5.3 Furniture & Appliances
6.5.3.1 Working Table with 8 Ergonomic office chairs 4.00 set
6.5.3.2 Stackable outdoor plastic chairs (see technical specs) 300.00 pc
6.5.3.3 400mm depth Metal Lockers (6 meters) 6.00 set
6.5.3.4 Cork board Bulletin Board (4ft x 8ft) 4.00 pc

Sub-Total

6.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


6.6.1 D-1: White Steel Door / view panel on Metal Jamb 4.00 set
6.6.2 W-2: Clear Glass powder coated white pivot window 4.00 set

7.0 LECTURE ROOM A-4 (GROUND FLOOR)


7.1 FLOOR FINISHES
7.1.1 600 x 600 Homogenous Granite Tiles 126.00 m²
7.1.2 Tile Adhesive 87.50 bag
7.1.3 Tile Grout 8.75 kg
7.1.4 Vinyl Adhesive 2.00 gal
7.1.5 150 x 900 Vinyl tiles 20.00 m²

Sub-Total

7.2 PAINTING
7.2.1 Semi Gloss Latex 4.00 gal
7.2.2 Flat Latex 7.00 gal

7.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Sub-Total
Item No. Work Description Quantity Unit

7.3 CEILING WORKS


7.3.1 9mm thk Gypsum bd on Metal Furring 51.00 m²
7.3.2 Metal Double Furring 250.82 m
7.3.3 Wall Angle 28.57 m
7.3.4 Carrying Channel 125.00 m
7.3.5 W-clamps/clips 250.00 pc
7.3.6 Blind rivets(1/8) 25.00 box
7.3.7 Black Screws 1,530.00 pc
7.3.8 T-Runner (White) 481.00 m
7.3.9 Wall Angle (White) 34.41 m
7.3.10 600 x 600 acoustic board 74.00 m²

Sub-Total

7.4 ELECTRICAL WORKS AND FIXTURES


7.4.1 Conduits
7.4.1.1 15mm dia PVC (Lighting) 100.00 m
7.4.1.2 15mm dia PVC (Power Lines) 100.00 m
7.4.2 Wires and Cables (Ground Floor Toilet Only)
7.4.2.1 2-3.5mm THHN CU, Stranded Wires 200.00 m
7.4.2.2 2-5.5mm THHN CU, Stranded Wires 200.00 m
7.4.3 Others
7.4.3.1 Junction and Utility Box 60.00 pc
7.4.4 Electrical fixtures
7.4.4.1 Pinlight (100mm dia) with 7W LED 22.00 pc
7.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 8.00 set
7.4.4.3 Emergency Light 1.00 set
7.4.4.4 Ceiling Fan 8.00 set
7.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
7.4.4.6 Aircon Outlet 2.00 pc
7.4.4.7 Three Gang Switch 2.00 pc
7.4.4.8 Ceiling Fan Switch 4.00 pc

Sub-Total

7.5 OTHERS
7.5.1 Demolition of existing tiles, fixtures, hauling of debris, etc 1.00 lot
Whiteboard Screen with Integrated Smart TV Enclosure,
7.5.2 1.00 set
laminate mounted on plywood on sliding rollers
7.5.3 Furniture & Appliances
7.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set
7.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set
7.5.3.3 Working Table fit with 8 Ergonomic Chairs 9.00 set
Sub-Total

7.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


7.6.1 D-1: White Steel Door / view pane on Metal Jamb 2.00 set
7.6.2 W-1: Clear Glass powder coated white awning window 4.00 set
7.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set

Sub-Total

8.0 THEATER TYPE LECTURE RM (A-5) (SECOND FLR)


8.1 FLOOR FINISHES
8.1.1 600 x 600 Homogenous Granite Tiles 126.00 m²
8.1.2 Tile Adhesive 87.50 bag
8.1.3 Tile Grout 8.75 kg
8.1.4 Vinyl Adhesive 2.00 gal
Item No. Work Description Quantity Unit

8.1.5 150 x 900 Vinyl tiles 20.00 m²

Sub-Total

8.2 PAINTING
8.2.1 Semi Gloss Latex 28.00 gal
8.2.2 Flat Latex 6.00 gal

8.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Sub-Total

8.3 CEILING WORKS


8.3.1 9mm thk Gypsum bd on Metal Furring 50.00 m²
8.3.2 Metal Double Furring 245.90 m
8.3.3 Wall Angle 28.28 m
8.3.4 Carrying Channel 150.00 m
8.3.5 W-Clamps/Clips 300.00 m
8.3.6 Blind rivets(1/8) 75.00 box
8.3.7 Black Screws 1,500.00 pc
8.3.8 T-Runner (White) 650.00 m
8.3.9 Wall Angle (White) 40.00 m
8.3.10 600 x 600 acoustic board on T-Runner 100.00 m²

Sub-Total

8.4 ELECTRICAL WORKS AND FIXTURES


8.4.1 Conduits
8.4.1.1 15mm dia PVC (Lighting) 200.00 m
8.4.1.2 15mm dia PVC (power lines) 200.00 m
8.4.2 Wires and Cables (Ground Floor Toilet Only)
8.4.2.1 2-3.5mm THHN CU, Stranded Wires 400.00 m
8.4.2.2 2-5.5mm THHN CU, Stranded Wires 400.00 m
8.4.3 Others
8.4.3.1 Junction and Utility Box 90.00 pc
8.4.4 Electrical fixtures
8.4.4.1 Pinlight (100mm dia) with 7W LED 24.00 set
8.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 12.00 set
8.4.4.3 Emergency Light 2.00 set
8.4.4.4 Ceiling Fan 12.00 set
8.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
8.4.4.6 Aircon Outlet 3.00 pc
8.4.4.7 Three Gang Switch 2.00 pc
8.4.4.8 Two Gang Switch 1.00 pc
8.4.4.9 Ceiling Fan Switch 5.00 pc

Sub-Total

8.5 OTHERS
8.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot
Whiteboard Screen with Integrated Smart TV Enclosure,
8.5.2 1.00 set
laminate mounted on plywood on sliding rollers
8.5.3 Furniture & Appliances
8.5.3.1 Professor's Desk with Ergonomic Chair and Podium 1.00 set
8.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set
8.5.3.3 Fixed Retractable Theatre Arm Chair 111.00 pc

Sub-Total
Item No. Work Description Quantity Unit

8.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


8.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set
8.6.2 W-1: Clear Glass powder coated white awning window 6.00 set
8.6.3 W-2: Clear Glass powder coated white pivot window 6.00 set

Sub-Total

9.0 LECTURE ROOM (A-7) (SECOND FLOOR)


9.1 FLOOR FINISHES
9.1.1 600 x 600 Homogenous Granite Tiles 68.00 m²
9.1.2 Tile Adhesive 47.22 bag
9.1.3 Tile Grout 4.72 kg
9.1.4 Vinyl Adhesive 0.90 gal
9.1.5 150 x 900 Vinyl tiles 9.00 m²

Sub-Total

9.2 PAINTING
9.2.1 Semi Gloss Latex 15.00 gal
9.2.2 Flat Latex 10.00 gal

9.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Sub-Total

9.3 CEILING WORKS


9.3.1 9mm thk Gypsum Board on Metal Furring 30.00 m²
9.3.2 Metal Double Furring 147.54 m
9.3.3 Wall Angle 21.91 m
9.3.4 Carrying Channel 76.00 m
9.3.5 W-clamps/clips 152.00 pc
9.3.6 Blind rivets(1/8) 38.00 box
9.3.7 Black Screws 900.00 pc
9.3.8 T-Runner (White) 299.00 m
9.3.9 Wall Angle (White) 27.13 m
9.3.10 600 x 600 acoustic board on T-Runner 46.00 m²

Sub-Total

9.4 ELECTRICAL WORKS AND FIXTURES


9.4.1 Conduits
9.4.1.1 15mm dia PVC (Lighting) 88.00 m
9.4.1.2 15mm dia PVC (Power Lines) 88.00 m
9.4.2 Wires and Cables (Ground Floor Toilet Only)
9.4.2.1 2-3.5mm THHN cu. Stranded Wires 176.00 m
9.4.2.2 2-5.5mm THHN cu. Stranded Wires 176.00 m
9.4.3 Others
9.4.3.1 Junction and Utility Box 60.00 pc
9.4.4 Electrical fixtures
9.4.4.1 Pinlight (100mm dia) with 7W LED 9.00 pc
9.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 6.00 set
9.4.4.3 Emergency Light 1.00 set
9.4.4.4 Ceiling Fan 6.00 set
9.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
9.4.4.6 Aircon Outlet 2.00 pc
9.4.4.7 Three Gang Switch 1.00 pc
9.4.4.8 Ceiling Fan Switch 2.00 pc

Sub-Total
Item No. Work Description Quantity Unit

9.5 OTHERS
9.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot
Whiteboard Screen with Integrated Smart TV Enclosure,
9.5.2 1.00 set
laminate mounted on plywood on sliding rollers
9.5.3 Furniture & Appliances
9.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set
9.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 2.00 set
9.5.3.3 PVC Student Armchair 50.00 pc

Sub-Total

9.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)


9.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set
9.6.2 W-1: Clear Glass powder coated white awning window 4.00 set
9.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set

Sub-Total

10.0 LECTURE ROOM (THIRD FLOOR)


10.1 FLOOR FINISHES
10.1.1 600 x 600 Homogenous Granite Tiles 63.00 m²
10.1.2 Tile Adhesive 43.75 bag
10.1.3 Tile Grout 4.38 kg
10.1.4 Vinyl Adhesive 1.00 gal
10.1.5 150 x 900 Vinyl tiles 10.00 m²

Sub-Total

10.2 PAINTING
10.2.1 Semi Gloss Latex 14.00 gal
10.2.2 Flat Latex 5.00 gal

10.2.3 Consumables (paint brushes, rollers, sand paper, putty etc) 1.00 lot

Sub-Total

10.3 CEILING WORKS


10.3.1 9mm thk Gypsum Board on Metal Furring 21.00 m²
10.3.2 Metal Double Furring 103.28 m
10.3.3 Wall Angle 18.33 m
10.3.4 Carrying Channel 71.00 m
10.3.5 W-Clamps/Clips 142.00 pc
10.3.6 Blind rivets(1/8) 35.50 box
10.3.7 Black Screws 630.00 pc
10.3.8 T-Runner (White) 325.00 m
10.3.9 Wall Angle (White) 28.28 m
10.3.10 600 x 600 acoustic board on T-Runner 50.00 m²

Sub-Total

10.4 ELECTRICAL WORKS AND FIXTURES


10.4.1 Conduits
10.4.1.1 15mm dia PVC (Lighting) 120.00 m
10.4.1.2 15mm dia PVC (Power Lines) 120.00 m
10.4.2 Wires and Cables (Ground Floor Toilet Only)
10.4.2.1 2-3.5mm THHN CU, Stranded Wires 240.00 m
10.4.2.2 2-5.5mm THHN CU, Stranded Wires 240.00 m
10.4.3 Others
Item No. Work Description Quantity Unit

10.4.3.1 Junction and Utility Box 60.00 pc


10.4.4 Electrical fixtures
10.4.4.1 Pinlight (100mm dia) with 7W LED 6.00 set
10.4.4.2 2 - T5 (4ft) (daylight) on reflective housing 4.00 set
10.4.4.3 Emergency Light 1.00 set
10.4.4.4 Ceiling Fans 3.00 set
10.4.4.5 3-Prong Two-Gang Convenience Outlet 4.00 pc
10.4.4.6 Aircon Outlet 2.00 pc
10.4.4.7 Three Gang Switch 1.00 pc
10.4.4.8 Ceiling Fan Switch 3.00 pc

Sub-Total

10.5 OTHERS
10.5.1 Demolition of Existing tiles, fixtures, hauling of debris, etc 1.00 lot
Whiteboard Screen with Integrated Smart TV Enclosure
10.5.2 1.00 set
laminate mounted on plywood on sliding rollers
10.5.3 Furniture & Appliances
10.5.3.1 Professor's Desk with Ergonomic Chiar and Podium 1.00 set
10.5.3.2 2.4 HP Inverter Window type Aircon Unit with Frame 3.00 set
10.5.3.3 Student Armchair 30.00 pc

Sub-Total

10.6 DOORS AND WINDOWS (WITH COMPLETE ACCESSORIES)

10.6.1 D-1: White Steel Door / view panel on Metal Jamb 2.00 set
10.6.2 W-1: Clear Glass powder coated white awning window 4.00 set
10.6.3 W-2: Clear Glass powder coated white pivot window 4.00 set

Sub-Total

11.0 OPENINGS & PATHWAY TO ADJACENT BUILDINGS


11.1 ACCESS PATHWAY (to Library)
11.1.1 Demolition Works of existing including hauling 1.00 lot
11.1.2 Site clearing, Soil preparation 60.00 m²
11.1.3 Burrow Fill & compaction 15.00 m³
11.1.4 Concreting 15.00 m³
11.1.5 10mm dia Reinforcing Bars 1,200.00 kg
11.1.6 Formworks 60.00 m²
11.1.7 Railings and Balusters 26.00 m²
11.1.8 Roll-up Door 1.00 set
11.1.9 Paver blocks 250.00 m²
11.1.10 Wall & Slab Soffit Painting Works 200.00 m²

Sub-Total

11.2 ACCESS PATHWAY (to Pond)


11.2.1 Demolition Works of existing including hauling 1.00 lot
11.2.2 Site clearing, Soil preparation 60.00 m²
11.2.3 Burrow Fill & Compaction 15.00 m³
11.2.4 Concreting 12.00 m³
11.2.5 10mm dia Reinforcing Bars 960.00 kg
11.2.6 Formworks 50.00 m²
11.2.7 Railings and Balusters 26.00 m²
11.2.8 Roll-up Door 1.00 set
11.2.9 Paver blocks 250.00 m²
11.2.10 Wall & Slab Soffit Painting Works 200.00 m²
Item No. Work Description Quantity Unit

Sub-Total

Submitted By:

RICHARD B. SORIANO
General Manager
R.B. SORIANO CONSTRUCTION

Вам также может понравиться