Вы находитесь на странице: 1из 6

340 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 16, NO.

4, DECEMBER 2001

Budget Constrained Energy Conservation—An


Experience With a Textile Industry
C. Palanichamy, C. Nadarajan, P. Naveen, Natarajan Sundar Babu, and Dhanalakshmi

Abstract—Conservation and efficient use of energy in industry In this paper, the energy conservation experience of the au-
has for a long time been a priority of the Government of India. thors with a textile industry is presented. The selection, in par-
In anticipation of enactment of federal legislation on energy ticular, of a textile industry has been considered because of i) the
management for industry, the State of Government of Tamilnadu,
Kerala, and other Southern States, made energy audits mandatory higher magnitude of electrical energy used in such industries,
for large-scale energy-consuming industries. So among industrial and ii) the large number of textile industries in this country.
consumers, the aspect of energy conservation is gaining due Since there is a constraint on the investment budget for energy
importance of the realization that “Energy Saved is Energy conservation measures imposed by the Management of the tex-
Produced and that too at Economical Cost.” This paper shares tile industry considered, projects conserving only electrical en-
the experiences of the authors on Energy Conservation Projects
carried out in a Textile Industry situated in Tamilnadu State. ergy have been identified and implemented since the electricity
Economic and efficient measures of Energy Conservation have cost in the total energy cost of the textile industry is found to
been followed subject to budget constraint and the effect of such be around 65%. All other energy conservation measures are re-
measures were realized through reduction in energy cost with the served for next stage of implementation at a higher budget level.
added advantage of environmental safety.
Index Terms—Energy audit, energy conservation, environ- II. STUDY OF EXISTING CONDITIONS
mental benefits, payback period, return on investment, textile
industry. A. Industry Considered
A privately owned medium size Spinning and Sewing Thread
I. INTRODUCTION industry in Tamilnadu, producing 15 Tons of yarn and 10 Tons
of sewing thread/day, is the site for which energy conservation

T ODAY, energy and environment are two areas that have


sought the greatest attention at the international level. With
the issue of the global environment [1], [2] becoming as impor-
measures were carried out during the financial year 1998–1999.

B. Electrical Demand
tant as never before, energy particularly its conservation in in-
dustries [3]–[7], has become the main target for all parts of the The textile industry considered is a High-Tension consumer,
World that has to be achieved as soon as possible. Textile indus- receiving electricity from the State Electricity Board (SEB)
tries are found to be energy-intensive (4% energy cost in total under Tariff I. The permitted Maximum Demand is 3250 KVA,
input cost) compared to other industries like chemical, food, and the Sanctioned Demand is 2600 KVA.
computer manufacturing, etc., and hence extensive research has
been focused [8]–[10] on such industries in the past to reduce C. Consumption
the energy cost and the total input cost. Energy Consumption: 58 250 kWh/day
In post-independence India, the industrial sector [11] has Steam Requirement: 0.6 Tons/hr
reached to a level of consuming 50% of the total commercial Furnace Oil Requirement: 1000 Liters/day.
energy available in the country. Indian manufacturing industries
like fertilizer, cement, sugar, textile, aluminum, paper, etc., are D. Electricity Tariff
found to be highly energy-intensive and their energy efficiency The textile industry is situated in a Non-Metropolitan locality
is well below that of industrialized countries. Research [12] on and HT Tariff I is applicable at the following rates:
Indian industrial sector indicates that around 25% of the total
Maximum Demand (KVA) charges: US $3.75/month.
energy consumed by the industrial sector can be saved through
Energy (kWh) charges: US $0.0875/kWh
energy conservation means.
(1 US $ IRS 40 approximately.)

E. Machineries/Equipments Inventory
Manuscript received May 8, 2000.
C. Palanichamy is with Sultan Saiful Rijal Technical College, Ministry of The Mill Engineer’s report indicates the availability of the
Education, Brunei Darussalam (e-mail: drcpc@brunet.bn). following machineries and equipments:
C. Nadarajan and P. Naveen are with Magnum Power, 21, Kumaran
Kudil, Madurai-625006, Tamilnadu, India (e-mail: ernada@pronet.net.in; Blow Rooms—2 lines
nav_p80@yahoo.com). Ring frames—96
N. S. Babu and Dhanalakshmi are with Drexel University, Philadelphia, USA
(e-mail: babu@drexel.edu; dhanam@joymail.com). Twisting frames—48
Publisher Item Identifier S 0885-8969(01)10058-6. Cone and Cheese Winding machines
0885–8969/01$10.00 © 2001 IEEE
PALANICHAMY et al.: BUDGET CONSTRAINED ENERGY CONSERVATION—AN EXPERIENCE WITH A TEXTILE INDUSTRY 341

Sewing Thread machines this project too. The details of the package were not given due
Cards, Preparatory machines, Draw frames, Combers, Lap to space constraint.
formers, etc.
Power Transformers: 2 2500 KVA D. Time Span
Power Transformers: 3 1000 KVA For This Textile Industry’s Energy Conservation project, the
Diesel Generators: 3 900 KVA EC team took 3 months for conducting the detailed Energy
Boilers: 1 2 Ton Audit; the Board took two weeks for its approval and budget
Boilers: 2 0.5 Ton. sanctioning, and again the EC team took another three months
for the implementation.

III. ENERGY AUDITING E. Criteria Set by EC Team for Energy Auditing


The Board of Directors of the Textile industry decided to go The EC team set the criteria for energy auditing as i) Cross-
for Energy Conservation measures due to the following reasons: checking the Machineries/Equipments Inventory produced
• the Industry has served for more than a decade by the industry, ii) Analyzing the Monthly Electricity Bills
• the rise in cost of energy input due to periodic tariff revi- from the commencement of the industry, iii) Study of Load
sions by the SEB and also the frequent diesel price rise in growth, Loading pattern, and Demand control, iv) Analysis
every year of Distribution Systems, Cables, routing of Wires and Cables,
• the Board of the industry is considering the option of going v) Checking of Indoor and Outdoor lighting, vi) Determining
for Renewable Energy Sources in the near future for eco- Motor efficiency, Air Conditioning systems, etc., vii) Ways of
nomic reasons and also to avail the Government’s incen- improving internal gains from Equipments, viii) Study of Solar
tives, and gain, Heating systems, Thermal Envelopes, Time Clocking
• the repeated instructions from the Electricity Board, Elec- systems, Ventilation levels, etc.
trical Inspectorate and State Pollution Control Board to go
F. Audit Outcome
in for Energy Conservation.
The EC team identified the following areas (projects) through
A. The Energy Conservation Team (EC Team) which energy conservation could be achieved:
i) Electrical Services and Distribution System, ii) Insulation
The Energy Conservation team (EC team) consists of i) A and Distribution Losses, iii) Lighting, iv) Motors and Drives,
Professor in Electrical and Electronic Engineering with Power v) Equipment and Process Modification, vi) Building Envelope,
Systems as the area of specialization and Chartered Engineer vii) Heating, Ventilation and Air Conditioning, viii) Steam Trap
status, ii) A field Electrical Engineer with 25 years of experience Maintenance, ix) Operation and Maintenance, x) Co-generation
and authorized A-Certificate holder of the SEB to work with HT and Energy Management System, and xi) Water Treatment
installations, iii) A Scientist with Post Doctoral qualification de- Program.
veloped interest in inter-disciplinary areas, iv) A Computer Sci- For each project, i) the annual energy savings, ii) project fu-
ence Engineer specialized in Software Development for Engi- ture energy costs and annual cost savings, iii) project capital or
neering Power applications, v) A qualified Business Adminis- first cost, iv) payback period, return on investment, and v) pri-
trator with Computer skills, and vi) Three qualified Electricians orities to projects based on investment merit, were provided to
with authorized C-Certificate holder of the SEB. the Board of Directors for its approval and capital authoriza-
tion. The Board permitted to implement those energy conserva-
B. Service Agreement tion projects related to Electrical demand and energy costs as
The EC team received a fixed charge on monthly installment the first phase subject to a budget of US $300 000 with a con-
basis during the Energy Conservation period, and 25% of profit dition that the savings through such projects should offset the
sharing from the profit by way of the Energy Conservation. implementation cost over a short period of time.
The EC Team was responsible for conducting a detailed En-
ergy Audit with the support of the Mill Engineer and the Mill IV. ELECTRICAL ENERGY CONSERVATION
Maintenance personnel. At the end of the Audit, a detailed re- Based on the Board’s approval, the EC team decided to go for
port on the Machineries/Equipment inventory, existing condi- the following electrical energy conservation projects:
tions, possibility of energy conservation, plan for implementa-
tion, implementation cost and carrying out the plan, payback pe- A. Reducing In-Service Transformers’ Capacity
riod, and rate of return, was given to the Board of Directors for Findings:
its approval. Based on the decision of the Board and the budget
Transformers in service: 1 2500 KVA and 2
sanctioned, the EC team carried out its responsibility.
1000 KVA
Transformers in standby: 1 2500 KVA and 1
C. Software Package 1000 KVA.
The EC team developed a software package—MAGNUM For an industrial consumer of Permitted Maximum demand
SOFT for Energy Conservation purposes, suitable for different as 3250 KVA and Sanctioned demand of 2600 KVA, the ca-
kinds of industries and such an own use package was used for pacity of the in-service transformers of 4500 KVA is very high.
342 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 16, NO. 4, DECEMBER 2001

Even in case of total failure of the in-service transformers, the power losses for a total load current of 300 A was worked
capacity of the Standby transformers is good enough to service out as: 300 0.048 037 5 4.3234 KW. Assuming
the Sanctioned demand. 8000 hours of operation/year, the energy loss in the cables was
Team Recommendation: The EC team recommended, as one 8000 4.3234 34 587 kWh.
of the Energy conservation measures, to disconnect one of the For parallel cables:
1000 KVA transformers from service with the written permis- Assuming equal load sharing, the current in each cable
sion of the SEB. In case of future expansion of the industry, is 300/2 150 A. The power loss in each cable is 150
the disconnected transformer will be put back in service; until 0.048 037 5 1.0808 KW. Total power loss for both cables is
then the disconnected transformer shall be maintained without 2 1.0808 2.1616 KW and total energy loss is 17 293 kWh.
energizing. Saving in energy loss/year is (34 587 17 293) kWh
Benefits: As per the norms of the SEB, where metering of 17 294 kWh (50% saving as expected). Annual saving in energy
the High Tension service connection is on the Low Tension side, cost due to parallel cables @ $0.0875/kWh $1513.23. Cost of
i.e., on the secondary side of the transformer of capacity above 3 400 square mm cable per meter length $20. Expenditure
50 KVA, on additional 175 m cable $20 175 $3500. Labor on
i) average losses in the transformer will be calculated as running additional cable is $140, and hence total expenditure
(720 1.0 divided by 100) kWh per month where on running additional cable is $3640.
is the KVA rating of the transformer and added to the Payback period (3640/1513.23) 12 28.87 say
energy consumption indicated by the meter. The trans- 29 months.
former loss arrived shall be added to the energy consump- Return on investment 1/29 3.45% per month.
tion, even when the recorded energy consumption is nil.
ii) 1% of the transformer capacity for transformers above C. Change of Motor Connections
50 KVA will be added to the recorded maximum demand Findings: The EC team identified 21 numbers of 7.5 KW,
on the Low Tension side to arrive at the equivalent High three phase Induction Motors in the Spinning floor and 15 num-
Tension demand. The transformer loss so arrived shall be bers of 3.75 KW, three phase Induction Motors of the Polishing
added to the demand even when the recorded demand is machines, as of over capacity. These motors were connected in
nil. Delta and the torque developed by them was very high, such a
Therefore, monthly saving due to disconnected transformer high torque was not essential.
loss @ $0.0875/kWh $0.0875 (720 1.0 1000)/100 Recommendations: The EC team recommended to connect
$630. Monthly reduction in demand charges $3.75 (1000 the said Induction motors in Star. The torque developed was
1/100) $37.5. Total monthly savings due to transformer measured and found sufficient to drive the connected systems
disconnection equals $667.5 and hence an annual savings of and also the temperature rise was measured to be normal. The
$8010. change in connection resulted in a power reduction of 0.670 KW
Total expenditure (or investment) for disconnection and for a 7.5 KW motor, and 0.400 KW for a 3.75 KW motor.
off-line annual maintenance of the transformer is found to be Benefits: Assuming 8000 hours of operation/year, energy
$1325. saving by 21 7.5 KW motors is 8000 21 0.670
Therefore, Payback period (Expenditure/Total savings) 112 560 kWh, and 48 000 kWh by 15 3.75 KW motors.
12 (1325/8010) 12 1.985 say 2 months. Therefore total energy saving is 160 560 kWh and annual
Return on investment 1/Payback 1/2 50% per month. saving in cost is $0.0875 160 560 $14 049. Labor cost for
connection changes $100 (practically nil).
B. Running of Parallel Cables Payback period (100/14 049) 12 0.085 say a month.
Return on investment 1/1 100% per month.
Findings: Two Aluminum Armored, 3 core, 1.1 KV,
335 A, 400 square mm, 0.0915 resistance/core/km, PVC
Under-ground cables are running from the sub-station; one D. Power Factor Improvement
cable of length 100 meter to Air conditioning control panel Findings: The average power factor of the industry varies be-
and another of 75 meter to the Departmental over-head bus tween 0.91 and 0.93 since its commencement, which was well
bars. Considering the reliability of supply and the magnitude of above the requirement of the SEB. The average power factor of
cable power losses, it is not advisable to go for a single cable the industry was 0.92 and the Maximum demand reached has
feeding system to essential floors. been read as 2600 KVA from the Load duration curve. The load
Recommendations: The EC team recommended, as one of level reached above the sanctioned demand of 2600 KVA on cer-
the energy conservation measures, to run a similar cable in par- tain short period of time was not considered for the power factor
allel with the existing one. Since the existing cables were found improvement project. So, at the average power factor, the load
to be in sound working conditions, it was decided to retain the in KW was found to be 2600 0.92 2392 KW. 1000 KVAR
cable as it was. Instructions were given to mark the changes in Capacitors were already installed at the sub-station to improve
the Blue print for future reference. the power factor to 0.92 (average), which was not sufficient to
Benefits: Total length of both existing cables was 175 m. reduce the energy input of the industry to a great extent.
Total resistance of the cable, 3 0.0915 175/1000 Recommendations: The EC team decided to improve the
0.048 037 5 . For a load current of 300 A, the cable power factor to an average value of 0.98. The best locations
PALANICHAMY et al.: BUDGET CONSTRAINED ENERGY CONSERVATION—AN EXPERIENCE WITH A TEXTILE INDUSTRY 343

for the capacitors were identified as i) at the sub-station itself load of 2600 KVA at 0.92 power factor @ $0.0875 per kWh
to compensate the base load and ii) at the loads supply side as $150 696. Energy generated by the generator/month @
per the KW capacity, so that only when the load is on, the ca- 3 hours/day for the peaking load of 150 KVA at 0.92 power
pacitors will be on. The 1000 KVAR capacitors available at the factor lagging 150 0.92 3 30 12 420 kWh.
sub-station were just sufficient to compensate the base load to a Considering the capital investment, life time, the load factor,
power factor of 0.92. Additional capacitors of 500 KVAR were the annual operation and maintenance cost, the labor cost, the
installed to improve the power factor to 0.98. (Calculations not depreciation and the diesel fuel cost, the average energy cost
shown.) for the Diesel generator supply is worked out to be $0.19/kWhr.
Benefits: For a load of 2392 KW, the KVA demand at 0.98 Therefore, energy cost for the generator supply is $0.19
power factor is (2392/0.98) 2441. 12 420 $2359.8 and hence total charges incurred/month for
Therefore, saving in KVA is (2600 2441) 159. the peak shaving option is $162 805.8. The EC team suggested
Annual saving in cost due to KVA reduction $3.75 159 the Board that more saving in energy cost could have been
12 $7155. Cost on additional capacitors @ $12.5 per KVAR obtained through Renewable energy sources compared to the
$(12.5 500) $6250. Diesel generator supply due to reduced generation cost.
Payback period (6250/7155) 12 10.48 say 11 months. Net saving by peak shaving per month is $8021.7 and
Return on investment 1/11 9.1% per month. $96 260.4 for the whole year if peak shaving is applied for the
entire 12 months @ 3 hours/day.
E. Saving Through Peak Shaving
As per the norms of the SEB, the maximum demand charges
for any month at the point of supply shall be based on the highest F. Changing Air Conditioned Environment
KVA demand recorded during any consecutive thirty minutes
in that month or 100% of the sanctioned demand, whichever
is higher. In addition, for exceeding the sanctioned maximum Findings: The textile industry under our investigation has
demand, the charges per exceeded KVA shall be at double the 27 numbers of 1.5 Ton capacity air conditioners. Except 7, re-
normal rate (say penalty). maining 20 were used for the Computer room environment.
Findings: The Maximum Demand during the financial The general purpose air conditioned rooms and Computer room
years 1995–1996, 1996–1997, 1997–1998 and 1998–1999 has were maintained at an operating temperature of 24 C always
exceeded the Sanctioned Demand in March and April, due irrespective of the changing seasons.
to the early summer peak loads, and the production target Recommendations: Recent research [13] indicates that
initiative at the beginning of the financial year. During the Computers are working well even at 30 C. By raising the
EC project period (1998–1999), the peak demand was found computer room environment to a higher temperature of 28 C,
to be 2750 KVA. The industry did not want to apply for an energy saving of 3% has been noticed for every raise in
increased Sanctioned demand since for the rest of the period of room temperature by 1 C. Further it has been proved that,
10 months, the load was well within the Sanctioned demand. It blowing the cold air from the bottom of the air conditioner
was noticed that the available Diesel generators were used only instead from the top and sucking the warm air through the top
at the time of power-cut and at grid failure cases. instead through the bottom, can save energy to a level of 15%.
Recommendations: The EC team recommended for the use Ducts are connected to the cold air outlet and the warm air
of one 900 KVA Generator at the time of peak loads during suction inlet of the air conditioner, and the locations of the cold
1998–1999 and to transfer the excess loads to the generator air outlet and warm air inlet are switched between upper and
supply so as to avoid the excess KVA penalty charges. If critical lower portions to achieve the new method of airflow. Based on
loads also contribute to facility peaks, consider shifting these the research, the EC team decided to maintain the controlled
loads to generator power during peak periods. In case, if emer- temperature only in the computer rooms at 28 C and to modify
gency back up power is needed, the remaining two Diesel Gen- the airflow by adding ducts for 20 air conditioners as said.
erators shall be put in service even during peak periods. Note: Benefits: The energy consumption/air conditioner/hour to
For the present project, the concept of Peak shaving was applied maintain a room temperature of 24 C is found to be 3.85 kWh
only for the loads exceeding the Sanctioned demand and not for with conventional airflow. Assuming 8000 hours/year
all the loads above the base load. of working, energy consumed by 20 air conditioners is
Benefits: Considering the peak demand during March–April 616 000 kWh. The corresponding energy consumption/air
of the financial year 1998–1999, i.e., 2750 KVA exceeding the conditioner/hour to maintain a room temperature of 28 C is
Sanctioned demand by 150 KVA for duration of 3 hours/day: found to be 2.90 kWh with modified airflow. The total energy
SEB Supply: Maximum demand charges payable to consumed by 20 air conditioners 464 000 kWh. Therefore,
SEB/month $3.75 (2750 2 150) = $11 437.5. Energy energy saved per annum is 152 000 kWh. Annual saving in cost
consumption charges/month for a load of 2750 KVA at 0.92 due to change in air-conditioned environment $0.0875
power factor @ $0.0875/kWh $159 390. Total charges 152 000 $13 300. Material and Labor cost for providing the
payable/month is $170 827.5. ducts for 20 air conditioners $2700.
Generator Supply for a Load of 150 KVA: Maximum Payback period (2700/13 300) 12 2.44 months say
Demand charges $3.75 2600 $9750. Energy con- 3 month.
sumption charges/month for the energy fed by SEB for a Return on investment 1/3 33.33% per month.
344 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 16, NO. 4, DECEMBER 2001

G. By Energy Efficient Motors TABLE I


SPECIFIC ELECTRICITY CONSUMPTION
Replacing standard efficiency motors with premium or high
efficiency motors is a valuable energy conservation program.
Total energy required to operate the motor is equal to the me-
chanical load on the motor and the mechanical and electrical
losses in the motor.
Findings: There were 96 Induction Motors of capacities
each ranging from 13 KW to 15 KW for driving the Ring
frames. By load test, their full load efficiency was found
to be around 86% and an average energy consumption of
12 kWh/hour/Motor. The energy consumption of these motors
alone formed a major portion of 45% in the total electrical
energy requirement of the industry.
Recommendations: It is recommended to go for Energy effi-
cient motors of capacity 13 KW with 91% efficiency, uniformly
for all the frames.
Benefits: The standard motors were disposed of at a price
TABLE II
of $300 per motor and energy efficient motors were bought at ENVIRONMENTAL BENEFITS
a price of $1150 per motor. The additional cost involved for
procuring the energy efficient motors was $850 per motor.
For a load factor of 80% and annual working hours of 8000,
the annual saving in energy 13 96 8000 0.80 (1/0.86
1/0.91) 1 428 837 kWh. Annual saving in energy cost is
$0.0875 1 428 837 $125 023. The additional total cost in-
volved for procuring all the 96 energy efficient motors @ $850 not be expected. However, different electrical energy saving
per motor $81 600. Therefore, the simple Payback period measures ranging from 2 kWh/Ton to 172 kWh/Ton was carried
(81 600/125 023) 12 7.83 months say 8 months and the re- out with the approval of the Board. After the implementation
turn on investment is 12.5% per month. of the conservation projects, a total saving in electricity con-
sumption of 3.536 21 Million kWh/annum has been achieved.
H. Through Lighting The electricity charges/annum were brought down to a value of
1.387 841 Million Dollars from 1.697 260 Million Dollars with
Findings: Already energy conservation in lighting has been
a saving of 0.309 419 Million Dollars. Such a saving was found
carried out by the Electrical team of the industry, which re-
to be 18.23% on the annual electricity charges and 11.85%
sulted in a saving of around 15% according to their records. The
on the total energy cost of the textile industry. The average
lighting installation consisted of 1255 twin lamp industrial re-
specific electricity consumption/Ton of the textile product
flector luminaries, each luminaire was fitted with two 38 mm
before conservation was found to be 2330 kWh/Ton and due to
(T12) diameter each rated at 85 watts.
the implementation of the measures, it was brought down to
Recommendations: The EC team installed a voltage control
1905.23 kWh/Ton through a reduction of 424.77 kWh/Ton as
system for the lighting system in the industry, which made use
shown in Table I. In other words, 18.23% reduction or saving
of one autotransformer for every lighting control zones, and fi-
in specific electricity consumption charges has been achieved.
nally connected to a central control panel. The voltage control
The total investment for the energy conservation projects
system has reduced energy consumption in two ways: firstly,
and the saving in electricity cost per annum were found to be
following start-up, the supply voltage was reduced by 12.5%,
0.309 411 and 0.189 633 Million Dollars, respectively. Though
and secondly, using a photocell to monitor the daylight level in
the energy conservation measures exceeded the sanctioned
the industry, the supply voltage was reduced by up to a further
budget of 0.3 Million Dollars by 3%, the Board was very much
5%. The total power rating, including control gear was found to
pleased by the overall saving/investment ratio of 61.29% during
be 240 KW.
the first year itself.
Benefits: For 7000 hours of annual operation, due to the
Apart from the economical benefits, environmental benefits
voltage control system, a 30% reduction in energy consumption
are also achieved through the present EC projects. The Carbon
(504 000 kWh) by the lighting installation has been measured,
dioxide, Sulfur dioxide and Nitrous oxide emissions, in India,
resulting in an annual energy cost saving of $44 100. The cost
from Fossil-fuel generation [1] of electricity per kWh are found
of the control system and its installation was $65 700; so the
to be 0.22 Kg, 6.80 gm and 2.63 gm, respectively. The reduc-
simple payback period is worked out to be 18 months and the
tion in these emissions due to the present energy conservation
return on investment is 5.6% per month.
measures are calculated and shown in Table II. An appreciable
reduction in all the pollutants are noticed which helps not only
V. BENEFITS OVERVIEW
in safeguarding the environment and but also gets benefits from
Since the conservation measures carried out were budget con- reduced environmental penalty cost. The Board’s interest on
strained, a higher magnitude of saving in energy and cost could going for the Renewable Energy Sources will result in added
PALANICHAMY et al.: BUDGET CONSTRAINED ENERGY CONSERVATION—AN EXPERIENCE WITH A TEXTILE INDUSTRY 345

benefits since the direct renewable energy or renewable energy [7] S. Nadel and N. Elliott, “Overview of programmes to promote energy
through storage systems can be used for the Peak shaving option efficient motor systems in the United States,” in Energy Efficiency Im-
provements in Electric Motors and Drives: Springer, 1997, pp. 365–376.
to a great extent due to the economic cost of generation with en- [8] J. W. Tester et al., Energy and the Environment in the 21st Cen-
vironmental benefits. tury. Cambridge, England: The MIT Press, 1991.
[9] Textile Industry, “Handy manual. Output of a seminar on energy conser-
vation in textile industry UNIDO,”, 1992.
VI. CONCLUSION [10] “The textile industry and the environment technical report no. 16,”
United Nations Environmental Programme, 1993.
In this paper, the energy conservation experiences of the [11] C. Palanichamy, N. S. Babu, and C. Nadarajan et al., “Restructuring the
authors with a textile industry were presented. Since there was Indian power sector with energy conservation as the motive for economic
a constraint imposed by the Management of the Textile industry and environmental benefits,” IEEE Trans. Energy Conversion, vol. 14,
no. 4, pp. 1589–1596, Dec. 1999.
on the investment budget for energy conservation measures, [12] V. K. Garg and S. Paul. Energy conservation programme in rayon plant.
projects conserving only electrical energy have been considered [Online]. Available: http://www.exicom.org/cew/mar97/garg.htm
[13] M. Yamamoto and T. Abe, “The new energy saving way achieved by
and a saving of 18.23% on the electricity cost, i.e., 11.85% on
changing computer culture,” IEEE Trans. Power Systems, vol. 9, no. 3,
the total energy cost of the textile industry was achieved. An pp. 1563–1568, Aug. 1994.
attractive benefit/investment ratio of 61.29% during the first
year itself has been achieved along with an annual reduction
of 777.97 Tons of Carbon, 24.05 Tons of SO and 9.30 Tons
of NO through energy conservation. It has been pointed out C. Palanichamy was born in December 1953 in Tamilnadu, India. He received
the B.E., M.Sc. Engg. and the Ph.D. degrees of electrical and electronic engi-
to the Board that Peak shaving option could be applied to a neering in 1976, 1979, and 1991, respectively, all from Madurai Kamaraj Uni-
great extent even to meet the loads above the base load through versity, India. He started his academic career in 1979; he served in India, Iraq
renewable energy sources. The successful first stage energy and Malaysia and at present he is with the Ministry of Education, Brunei Darus-
salam. His areas of interest include economic operation of power systems, re-
conservation measures encouraged the industry and made them newable sources of energy, energy conservation and environmental impacts.
to grant permission to proceed with the next phase of energy
conservation at a higher budget capacity.

ACKNOWLEDGMENT C. Nadarajan was born in June 1948 in Tamilnadu, India. After his engineering
graduation in electrical engineering, he joined with the Tamilnadu Electricity
The authors sincerely thank the Management of the Textile Board, India. He served in India, Saudi Arabia and Malaysia for more than two
decades. He is the recipient of the Best Engineer Award consecutively for two
Industry and Mrs. Meena and Mrs. Loga, the Directors of years from the Hyundai Company.
Magnum Power, India for the permission given and their
uniform support.

REFERENCES P. Naveen was born in January 1980 in India. After her graduation, she is
working with Magnum Power, an electrical consultancy company in India. She
[1] S. Rahman and A. de Castro, “Environmental impacts of electricity gen- developed software packages for power system applications.
eration: A global perspective,” IEEE Trans. Energy Conversion, vol. 10,
no. 2, pp. 307–314, June 1995.
[2] J. B. Gaskell, “How green is your plant?,” IEE Power Engineering
Journal, vol. 13, no. 2, pp. 49–57, Apr. 1999.
[3] A. Z. Khan, “Electrical energy conservation and its application to a sheet N. Sundar Babu was born in January 1972 in Tamilnadu, India. He received
glass industry,” IEEE Trans. Energy Conversion, pp. 666–671, Sept. the B.Sc. degree in 1992 and the M.Sc. degree in applied chemistry in 1994,
1996. all from Madurai Kamaraj University, India and the Ph.D. degree from Univer-
[4] IEEE Bronze Book on Recommended Practice for Energy Conservation sity Malaya, Malaysia. He is currently with Drexel University, Philadelphia as
and Cost Effective Planning in Industrial Facilities. New York: IEEE, a Scientist.
1993.
[5] C. Palanichamy et al., “Refresher course on recent trends in mainte-
nance of industrial electrical equipments and energy conservation,” in
TCE Proc., Feb. 23–24, 1991.
[6] B. Cook, “High-efficiency lighting in industry and commercial build- Dhanalakshmi was born in February 1977 in India. After her graduation, she
ings,” IEE Power Engineering Journal, pp. 197–206, Oct. 1998. is working as a Software Engineer and Networking Consultant.

Вам также может понравиться