Академический Документы
Профессиональный Документы
Культура Документы
. 4th*
* 41$' \.
"*. I, '; a . ,, I,
',:;^$, ?
^;itt:
,-$4^'A. '. q-
^;tit*--. ;
.,. :.:.... .,
e?*, I' AL "
4:1, , .AT* ,
L*;$*I;** \* *
^;;**"
^;kt;*** "
?;itI'
pi4\ 4;:'
.,-'.,$
* 11_,?-:
,a'?-:
r:+:;a, .. I
$in - - - ;$1
age
,*$*,\ '*-
- t;i;!,$
':4*"
*^,,!;\, * $:*4.4 -
^it;-tit*$$;\:
^;;$;;;$;---;4$;;
;" t;'.;?:**.-, * ^j;. :
$44\;$***:,;;
; ';;^," ' I ' '
I . *,;*,\^ ; ,
ith', 111
11
at <11
#,* .
;,* I
^.~:^
F1
,
';11 I
a. .--- -. . i
;; I if I I '
I, ^;^- , i,
3.4;' '^.'I; I
$1:4**:,. .- ;*\
Code of
Estimating Practice .
100
The Institute of Building
Englemere, Kings Ride, Ascot, Berks, SL58Bi
Telephone: Ascot 23355
Contents
Page
COMPOSITION OF ESTIMATING PRACTICE COMMITTEE 4
FOREWORD To THIRD EDITION 5
FOREWORD To FIRST EDITION 5
I TERMINOLOGY 7
2 INTRODUCTION 9
4 COLLECTION OF INFORMATION 11
ENQUIRIES 11
4.02 Detailed Examination of Documents 11
ACKNOWLEDGEMENTS 26
BIBUOGRAPHY 26
Appendices
A INFORMATION To BE GIVEN IN ENQUIRIES
A I Enquiries to Suppliers
< A2 Enquiries to Sub-Contractors
C MODEL FORMS
Table of Forms
.
I
Deputy Chairman: a,
I. Tomlin, MioB ,
Members:
T. Appleton, MioB
N. Douglas, LioB
C. Walker-Smith, M A, F10B
A. D. Wilson (nominated by the Scottish Branch of The institute of Building) Q
F. H. Sunivan, F10B
Ex-officio Members:
H. V. G. Dunford, MioB
I. C. Lambe, MioB
E. I. Cook, BSC(ENG), F10B
P. M. Shepherd, F10B
Secretary :
M. I. V. POWell, MIOB
o
Foreword to the 3rd Edition
by JOHN N. CHIVERS, MBE, JP, F10B, President, The Institute of Building 1973-74
Since its first edition in 1966, this 10B publication, the Code of Estimating Practice, and its
attendant set of model forms have continuously proved of great value in educational estab-
lishments and within buttding firms. As expected, it has also proved of value to architects
and quantity surveyors in cost planning at the design stage.
A second edition was published in 1968, revised to incorporate minor changes to the text
and model forms, mainly as a result of comments received from the growing nilmber of
users of the Code. At the same time the all-in hourly rate calculation in Appendix B was
brought up to date.
Now, in 1973, further revision has taken place. These take account of the changes caused
by decimalisation of the UK currency, and by the adoption of the metric system (SI) in the
British building industry. Account has also been taken of further changes affecting the all-in
110urly rate calculation.
With these revisions the Code remains the most authoritative guide on estimating principles.
Whenever necessary, further revisions will be made to maintain the usefulness and relevance
o1' this work.
JOHN N. CHIVERS
Estimating is a function of every building organisation, large and small. Our industrial structure and
our technology increase in complexity daily. Estimates reflect that complexity and must take account
of new factors of far-reaching consequence. A logical and systematic approach to estimatin is
therefore essential.
This Code has been prepared by the Estimating Practice Committee of The Institute of Buildin
whicli is the most authoritative body on estimating in Great Britain, h sets out to define an anal tical
system which can be regarded by practising estimators, lecturers and students as a guide to the princi Ies
of good practice.
We envisage that this Code will be revised from time to time to take account of industrial and
technological developments. We hope that it will be discussed fully and we shall welcome comment
and constructive criticism.
After a prolonged period of separation, the design and construction functions in buildin are
becoming more closely integrated. it is anticipated that the Code will be of value to architects and
quantity surveyors in developing an understanding of how an estintate is prepared. This is an essential
pre-requisite of a sound and informed approach to cost planning at the design stage.
The National Council of the Institute wishes me to express its 'appreciation of the work of the
Estimating Practice Committee in preparing this Code.
GERALD A. HILL
I Terminology
These are the meanings of tlie principal specialist terms used in this Code. Terms used ill 111cir
normal dictionary sense are not defined.
Terms relating to management structure are lised with the meanings assigned to them in the
report Consiruciion Managemeni in Building. . Prese"I and rumre*.
. I
MANAGEMENT
The generic term 'management' means: 'The person carrying ou, the function of gcneral
management and responsible for making the decision to tender and for carrying out adjudication'.
ESTIMATING
Estimating is a technical function within the building commercial field.
COMMERCIAL
Concerned with the eXchange of goods and services.
ESTIMATOR
A person carrying out the estiniating function in a building organisation. Sucli a person niay
be a specialist or he may carry out the estimating function in conjunction with other functions,
such as quantity surveying, general management, etc.
COST RECORDS
Records of historical cost and notes of the conditions prevailing when such cost was incurred.
Cons!n, ctio" M@"@geme"t in Build^^g: Present and Fur", e published by the Board of Building Education in 1965
Obtainable from The institute of Building at t1.50 per copy, post free. (^1.00 to members of the institute).
8
GENERAL OVERHEADS
The cost of administering a company and providing off-site services.
The allocation of general overheads to projects and to the company as a whole is decided
by management as part of management policy.
PROJECT OVERHEADS
The cost of administering a project and providing general plant, facilities and site-based services
MATERIAL
Material or components.
TENDER DOCUMENTS
Documents submitted for the information of tenderers; documents, such as specifications, might
be included which would not necessarily become contract documents if the tender were accepted
.
,,
TENDER FIGURE
.
The sum of money forming part of the tender.
TENDER
The sum of money, time and other conditions required by the tenderers to carry out the specified
building work.
o
^
2 Introduction
This Code is intended to provide an authoritative guide to good practice in estimatin for build'n
work.
it is important to distinguish between 'Estimating' and 'Tendering'.
'ESTIMATING' is the technical process of predicting costs of construction.
'TENDERING' is a separate and subsequent commercial function based u on the estimate.
The responsibility of estimators should be limited to the proper preparation of the estimated cost
of projects. Management is responsible for. providing information on previous costs, roduction
outputs, building techniques and clerical assistance which are essential pre-requisites of o0d d^timatin
practice. They are also responsible for the conversion of estimates into tenders and for obtainin work
for their organisations. '
This Code is concerned primarily with Estimating. The formal steps in convertin an estimate ' t
a tender are outlined to give a coherent picture, but the commercial and policy factors which influence
the offer made are not discussed.
An estimate must be prepared in a way that is explicit and consistent and which takes account of
methods of construction and all circumstances which may affect the execution of work on the ro'ect.
it is believed that such a sound estimate can only be achieved when each operation or item is anal sed
into its simplest elements and the cost estimated methodicalIy on the basis of factual information.
it is expected that the nTethods described will be suitable for use by those estimatin for ever t
of building work. Some, whose work is in limited fields, may be able to sim Iif the rocedures, b t
the essential sequence of tasks and the ways in which information is sought and collated will not
be changed.
The use of ordered and logical methods of estimating can have important and far-reachin effects.
The extent of possible future demands on resources can be readily ap reciated. The estimat ,
conjunction with the project programme, provides a means of measuring the financial conse uences
of any delays that may occur during the execution of the project. Comparisons can be made between
estimated and actual levels of productivity and control action taken when required.
Estimators should work in close association with construction management. The basis on wh'ch
estimates have been prepared should be explained and information allowed to flow freel in both
directions. in the past, estimating has often been surrounded by an urinecessa aura of secrec .
Attention is drawn to the fundamental principle that an estimate should be re ared net, that ' , t
should be an estimate of cost (1.02). Project overheads (1.02) should be added aftef construction methods
and a programme have been determined and the total value of the measured work has been obtained.
Allowances for risk, general overheads (1.02) and profit should be added by management at the time of
adjudication. The way in which these allowances are incorporated into the priced Bills of Quantities
is the subject of a policy decision.
it can be seen from the network diagram 'Procedure for Estimating and Tendering', (Appendix D)
that the processes fall logically into five discernible stages. These stages form the sub'ects f S t'
3 to 7 of the text which follows:
SECTION 3 Management decides whether to accept or decline an invitation to t d
SECTION 4 Estimator gathers the information required and familiarises h' it 'th th
project.
SECTION 5 An estimate of the cost of the project is prepared.
SECTION 6 Management adjudicates the estimate and submits a tender.
SECrlON 7 if the tender is accepted, all relevant information is assed to con t t'
merit and information on actual cost is fed back for guidance in future estimatin .
The text assumes that Bills of Quantities measured in accordance with the Standard Method of
Measurement of Building Works have been provided by consultant quantit surve ors. If h B'11
are not provided, quantities must be taken off by the estimator before the rusedures r d d
in this Code can be used. Due allowance must be made in estimatin for an
measurement.
10
* A Code of Procedurejbr Selecti've Tendering. Revised Edition 1972. Published by the National Joint Consultative
Committee of Architects, Quantity Surveyors and Builders. Obtainable from the Royal Institute of British Architects,
66 Portland Place, London W. I
* A Code of Procedurejbr Setoc, ipe Tendering Appendix B, item b. t or supervising officer
4 Collection of Information
4.0 I Estimate Programme
Time allowed for tendering is generally limited. it is essential to determine in advance certain
key dates in order that the tender can be submitted on time. The most important dates are:
(a) Latest date for despatch of enquiries (4.03,4.04)
(b) Latest date for receipt of quotations (5.03, Son, s. 05)
(c) Visit to the architect's office (405)
(d) Visit to the site (4.06).
(e) Adjudication meeting (6.01). . .,
it is also necessary to arrange for discussions with those who will advise on construction
methods, programme and plant (4.07,4.08). .
ENQUIRIES
PROJECT APPRECIATION
V
The procedure for preparing a programme is outside the scope of this Code.
14
.02 Labour
These items may be resolved into all-in hourly rates for craftsmen, labourers and plant
operators.
in order to take account of seasonal variations, holidays and other disruptions, the year
should be used as the basic unit and an average rate calculated.
it is convenient to include in the all-in rate allowances for these costs:
co Lead money and supervision time for trades' foremen and chargehands
(ii) The cost of non-productive overtime which is worked as standard company practice
(iii) Plant operator's servicing time.
A fully-worked example of the calculation of an all-in hourly rate is given 'in Appendix B
' it gang costs are used (5,071) this element may be omitted and separate all-in rates calculated for trades' forernen
chargehands and gangers.
,
15
5.04 Material
The receipt of quotations in answer to enquiries (4.03) should be recorded methodicalIy. When
all the quotations invited for a particular item, or when the last date given for their return has
been reached, they must be compared and one quotation selected for use in calculating the all-in
rate.
Even though precise information was given in the enquiries (4.03), it is necessary to Labulate
the information from quotations in order to make a proper comparison and a wise choice.
Note the answers to these questions :
(a) Does the material comply with the specification ?
(b) Will the material be available to meet the requirements 6f the construction programme ?
(c) Are there any special delivery conditions ?
(d) Are there any onerous conditions applying to the quotation ?
(e) For what period does the quotation hold ?
(f) Does the quotation allow for small quantities, if requircd ?
(g) What are the trade and cash discounts offered ?
(Appendix C, Form 6).
The procediire for the comparison and selection of quotations from sub-contractors is similar
to that described for suppliers of materials (5.04).
Note the answers to these questions : .
(a) Does the work described in the quotation comply with the Bills of Quantities and the
specification?
.
(h) What services are required from the main contractor ? . 'I
(i) Do the conditions of the quotation comply with the terms of the main contract ?
(j) Are there any onerous conditions applying to the quotation ? .
5.06 Principles
...
.
-.
,
,
.\
,
.,
17
when a particular cost was incurred. Those conditions must be conipared critical I with th
cxpected on the pro^Ct now being considcred. Differences between CStiiiiatcd and act , I
on previous projects should be analysed and ally obvious coliclusions noted (7.03).
When a type of work is being inct for the first time, there will be no previous cost for uida
Specialists should be consulted whenever possible. Techiiical information froin outside sources
Inay have to be used; in this, great caution should bc excrciscd.
Proper allowances must be made for inccntive payments cither by incrcasiii 111e all-in
labour rate (5,021) or by using an appropriateIy modified production standard.
5.07 Labour Element
5,071 Labour cost is estimated in tcrms of the all-ill hourly ratcs previously established (5,021).
it is recommended that gang cost should bc used in preferencc to individual cost for conc t' ,
bricklaying, plastering and similar bulk work (Appendix C, Form 8). The timc to be allowed
for all operation or item will depcnd lipon many factors. d
5,072 The drawings, specification and Bills of Quantities (4.02,4.05) will illdic;11c:
(a) The quantity of work to be done
(b) The quality of finish and standard of workmanship required
(c) Whether operations are repetitive
(d) Whether excessive or detailed setting out will be needcd
(e) The degree of accuracy and tolerances requircd
(f) Whether the design of the work is intricate or straiglitforward
(g) Whether 111e operation is likely to bc with ill tlic cxperience or exist illg o eratives, or
hth
whethcr 'I'
special instruction or training will be necded or-' '
WITetlicr 111ere will be a,
need t
engage specially-trained operatives.
5,073 The Construction Programme and Method Statement (408) will indicate:
(a) The time of 111e year when work is to be carried out and hence likely seasonal conditions
(b) Whether work will be continuous or intermitteiit
(c) The degree of inter-dependence of trades and operations
(d) The pattern of production and the likelihood of buildiiio up to maxiiiiuin OSsible at
(e) Gang structure, i. e. relative proportions of supervisory skilled and unskilled o eratives.
5.074 The Visit to tile Site alld Locality (4.06) will nave SIIowii :
(a) Physical conditions likely to be encountercd
(b) Site layout and operating and storage facilities
(c) Likely skill and expericnce of local labour.
5,075 Cost Records
When considering labour cost records, it is important to note 111c ICvels of incentivcs wh' h
paid to acliieve a particular cost and to in akc sucli adjtistments as may be required (7.03).
5.08 Plant Element
5,081 Mechanical plant cost is estiiiiiitcd in terms of the all-ill Talcs reviousl t. b!"h d
(5,032). The tiine to be allowed for an operation will depend upon sucli factors as:
(a) The quantity of work to be dollc
(b) The physical conditions of the site
(c) Likely seasonal conditions at various stages in the work
(d) whether work will be contiiitious or in tel'mittcnt
(c) Tlic pattern of production and thc Iikcliliood of building up 10 niaximum iossiblc rates
(f) Thc typc and likely experience of oneratoi. s.
Average outputs should be assesscd and any necessary allowances made for jiltcrin'it t
working. Cost records should be consulted (703).
But when an item of mechanical plant is to scrvc a number of trades or DPCrations (for
example a crane, or a hoist, or a concrete Inixer being used in concrete work, brickwork and
drainage work), the allocation of its cost to measured itcms can only be made arbitrarily. 11
is therefore recommended that the cost of such plant should be included not in tile rates but in
the project overheads (5,161).
5,101 Before the rates for sub-contractors' work are transferred fro!IT lite selected quotations
(5.05) to the main Bills, the quotations should be re-examined to determine precisely what
allowances, if any, have been illcluded for the following items: .
(a) Unloading
(b) Protection of materials and equipment, inclLiding providing . any necessary security
arrangements
(c) Transfer of goods from stores to point of work*
(d) Provision of storage facilities
(6) Provision of othces, messrooms and other accommodation
(f) Provision of plant, equipment, access, liard standings and tile 11kc Q
(g) Provision of special scaffolding or other means of acccss
(11) Provision of water, electricity and telephone
co Protection of finished work
a) Supply of subsidiary materials.
An addition must be made to cover any of these itenis for which 110 allowancelias been made
by the sub-contractor and which is expected to attract a cost. This may be done in several ways
co By increasing the relevant unit rates
(ii) By adding a fixed percentage to the whole of the sub-contractor's quotation
(iii) By making an addition subsequently in the project overheads (5,161).
When the allowance is needed for items. such as unloading, or the supply of fixing materials
alternative co should be used but for general site facilities (storage, teleplionc, power etg)
alternative (iii) is preferable.
5,102 Attendance
Any work of attendance which the main contractor is required to carry out should be analysed
and the cost estimated on the basis of similar experience on previous projects (7.03)
* Although includcd here for accuracy, these factors are part of the laboLir eleiiicnt, (5.07) and 111ust bc taken Into
account whcn considcring the total labour ICquirciitcnts for thc project.
19
5,111 The tender documents (302) should include sufficient information to anow the value
of work of attendance on nominated sub-contractors to be estimated accurately. If, in the
course of estimating, it is found that adequate information is not given and if efforts to obtain
it are not successful, then the matter becomes an item of risk and should be taken forward
for discussion at the tender adjudication meeting (5,201,6,011).
Attendance on nominated sub-contractors may fall into two sections, i. e. the provision of:
(a) Specific services (5.1 12)
(by General facilities and assistance (5.1 13).
additions are made for project overheads and other allowances (^. 16 - 5.18,6012). e trans er
of rates to the Bills from working theets, extending and totalling should e callie ou
risk of clerical error is minimised. Mechanical aids should be used whenever possi e. ,
COMPLETING THE ESTIMATE
5.141 The values of 111e followiiig sections of the work should be cxtracte ront re ,
Bills and noted in tile appropriate places on the adjudication report (5.20").
(a) Main contractor's labour Furthcr analysed into trades or stages
(b) Main contractor's plant allocated to rates of work if required by managcment.
(c) Main contractor's materials
(d) Main contractor's own sub-contractors
I
(c) P. C. sums for nominated sub-contractors
(f) P. C. sums for noniinated suppliers ,
(g) Provisional sums*
(h) Contingencies*.
5,142 The following information may also be required by Inariagement all s ou ere ore
be noted :
(a) Amounts included for attendance o11 0w'n and nominalcd sub-contractors
(b) Amounts included for caslT discounts. These are a possible source of margin o ., e
project.
5,161 During the preparation of the estiiiiate, items will have been note or u or
in project ovcrheads. Thesc nlust now be brought forward (5,022,5,034,5,082,5.10 , ).
5,162 Summary of Main lienis
A comprehensive schedulc of project overheads is given in APPCn ix , orm
each item given in the schedule snOuld be estiinated separately. T e main groups
(a) Site staff (all people whosc cost has not bceii included ill rates, \vliatcvcr t eir me o
of remuneration)
(b) Cleaning site and clearing rubbish
(c) Site transport services
(d) Mechanical plant and hoisting (allitcms not previously illcluded in unit rates ( . )
(e) Scaffolding and gantries
( f) Site accommodation
(g) Small plant, including hand tools
(h) Temporary services and re-instatement
(i) Miscellaiicous
(j) Temporary water installatioii
(k) welfare, first aid and safety provisions
(1) Final clearance and handovcr
(in) Defects liability cost
(n) Transport I>f men to site (5,022)
(0) Abnormal overtinie (5,022).
Allowance must be made for non-recoverable increases in the cost of items, suc as, site s a , p ..
fuel, electricity, water, telephone, stationery in all estimates both on firm price an uc ua io .
* Provisional sums are kept separate from contingencies because a provision sum ' p. '
that the sum 1'0rms part of the true value of the project. There is an OPPosi e imp ' a '
5,163 Method of Estimating
The cost of many of the iteins will vary in direct proportion to the contract period and tilelen th
of time that staff, plant and equipment would be rcquired on site. This information on time is
readily available from the construction programnie (4.08).
The total estimate of the cost of project overlieads is transferred fronl the schedule (5162)
to the Final summary (5,202).
d
5.18 Allowance for a Firm Price Tender
\\ hen a firin price tender is to be given, an assessment must be made of likely \ariations in
cost during the proposed contract period (3.02).
Rccords of rates of wages, other labour costs and Ginolunicnts (5021) and the cost of basic
matsrials will indicate trends. Note should be taken of industrial negotiations and staiutor
measures which niay affect levels of wages, the financial obligations of employers or the costs
of basic commodities. Consideration must also be given to indirect charges such as tariffs, fuel and
freight.
Regard must be paid to economic and political situations at nomc and abroad and the state
of home and world markets.
The quotations of the contractor's own sub-contractors should be re-examined to ensure that
they are funi price offers and that there are no risks of claims for increased cost.
5.19 Review
Before the estimate is presented to management for adjudication (6.01) it should be carer1111y
reviewed.
The calculations for all-in rates (5.02 - 5.05) should be examined and checks made to ensure
that the correct figures were used in the build-up of unit rates (5.06 - 5.12). Each page of the
Bills should be inspected to ensure that no item or part of an item has been omitted. The total
unit rates (506) should appear reasonable and be correct for the unit of measurement. Particular
attention should be given to the major items in each trade and to those items in wliich the
materials specified are unusually costly. Any inaccuracy in rate build-up will have been magnified.
it is important to ensure that, when the tinie to be allowed for the project is given by the
Client, it is realistic in relation to the estimated labour cost and the number of men (407) which I
it would be physically possible to have working on the site.
The construction programme (4.08) should be reviewed criticalIy to ensure that no major
problem has been over-looked and that the method is the best that could have been devised
in the time available.
7<4""'
The original estimates and final costs of previous projects of a similar nature should be
examined and an opinion formed of the likely profitability of the project under consideration
(7.05).
(i) Any need for qualification of the tender or for an explanatory letter
(j) The terms of quotations from own sub-contractors which. have been included in the.
estimate (505)
(k) The time for which the tender is to remain open for acceptance (302).
,
.
..
,
23
he
6 The Tender
6.01 Adjudication
6.03 Records
it is recommended that a record is kept of all tenders submitted. Particular care should be
taken to preserve the Adjudication Report (incorporating the estimate summary) (5.20,6.01)
and all notes made at the adjudication meeting.
The calculations for all-in rates (5.02 - 5.05) and unit rates (5.06 - 5.12) should be retained as
they may be useful for a limited period in estimating for further similar projects
6.04 Results
When the result of the tender is known, the record should be completed when possible with a
full list of the tenders submitted and a percentage comparison made with the lowest (or the
accepted) tender (Appendix C, Form 11).
Suppliers and sub-contractors who submitted quotations should be informed of the results
promptly.
.
,
7 Action with a Successful Tender
7.01 Check Contract Documents
Before contract documents are signed, they must be cliecked thoroughly from all aspects
(technical, legal etc). Those who were responsible for estimating should ensure that:
(a) The drawings are those which were circulated with the tender documents (402)
(b) The dates, penalties etc, given in the Appendix to the Conditions of Contract arc those
stated in the tender documents (302,402)
(c) The Bills have been copied correctly from those originally submitted (6.02),
it is recommended that this comparison of documents is made on the Adjudicatiofi Report
(4.02, Appendix C, Form 10). .
If the tender was for a fixed price (518) and there has been any delay in acceptance, enquiries
should be made to ensure that there have been no changes which might necessitate reconsidera-
tion of the tender.
The collection and collation of data on a large scale is a specialised function involving the use of statistical and work
study techniques and is outside the scope of this Code.
26
Acknowledgements *
.
The Estimating Practice Cornmittee withes to express its indebtedness to:
The Working Party, con^isting of I. Tomtin (Chairman), D. Bishop, N. 09uglas and FH. Sunivan which
produced the first draft of the Code. Special responsibility was undertaken by Mr Bi op or e
Network Diagram and by Mr Douglas for the model forms.
Howard A. Close, M A, Legal Adviser to the National Fed, elation of Building Trades Employers who advised
on legal and contractual matters.
The Institute Secretariat, especially MJY. POWell who gave extremely able assistance to o e or '
Party and the Committee during all stages of the preparation of the Code.
LJ. BRADSHAW
Chairman
The Technical Coriumittee of the Estimating Section wishes to record its debt to the or ing ar y,
comprising HY. G. Dunford (convenor), D. R. Mudd and E. Slutsr, who were responsible for revising
the Code. - May 1973
Bibliography
I . National Joint Consultative Committee "A code of procedure for selective tendering
of Architects, Quantity Surveyors and Builders: 1972, RIBA.
A number of titles publislied under the Estimating Information Service are also of relevance. Detai s can
obtained from the Institute.
,.
APPENDICES
28
Appendix A
INFORMATION To BE GIVEN IN ENQUIRIES
A1 Enquiries to Suppliers
Enquiries to suppliers should state
(a) The specification of the material
(b) Quantity of the material
(c) The likely 'delivery programme, i. e. period during which}he supplies would be needed
and daily or weekly requirements*
(d) Address of the site ' ,
(e) Means of access
(f) Any traffic conditions and restrictions affecting delivery
(g) Period for which the quotation is required to remain
open for acceptance
firm
(h) Date by which quotation is to be submitted
(i) The person in the main contractor's organisation to whom reference concerning the
enquiry should be made
A2 Enquiries to Sub-contractors
A2.02 Enquiries should also define the responsibilities of sub-contractors ill rcspcct of:
(a) Purchasing of materials
(b) Off-loading and storage
(c) Cleaning and protection of work
(d) Disposal of rubbish
(e) Loss or damage to sub-colltractor's mater tills
( f) Compliance with specificatioii
(g) Inspection by the employing authority
(h) Payment of fees
co Insurances
co Any further sub-letting.
ed
30
Appendix B
*
Bl Summary of Procedure ,
An all-in hourly rate should be built up in accordance with the principles given in paragrap s
5021 and 5,022 of this Code. Details vary according to the trade of the operative (w e er
craftsman, labourer or mechanical plant operator), the finn, the area and the industrial an ^ga
conditions in force at any time. The calculation shown below should be regarde on y as a ypi a
example. it is on an annual basis and could apply to all projects for w to en ers a
submitted.
The calculation must be amended each time there is a variation in the cost o one o
factors included or when further factors are introduced. Alterations should e in a e as soo *
variations are notified, althougli there may be an interval of time before they become e ective.
The whole calculation should be reviewed from time to time.
There are four stages in the calculation:
(a) Determine the number of effective hours which an operative is expected to work during
a year.
(b) Calculate the cost per year for wages and each of the items of cost listed in the text
(5021).
(c) Total the individual costs obtained in (b).
(d) Obtain a rate per hour by dividing the total cost (c) by the number of hours (a).
Alternatively, in the case of very large projects it may be desirable to make a specia co cu a I
based on the anticipated construction period.
NOTE: All rates in the foUowiiig examples have been worked to the nearest t Tee ecima p \
-.
.,
31
B2 Calculation
SUMMER PERIOD
39 weeks at 49 hours per week 1911 hours
Less
1777
WINTER PERIOD
13 weeks at 44 hours per week 572
Less
472
> Note The Annual and Public Holidays have been taken as listed below and the total number of
days are as agreed in the National Working Rule. in some regions the actual day to which
the Holiday is allocated can vary according to local tradition
Revisions have been agreed and issued by the National Joint Counci or g g
Guaranteed Guaranteed
With effect on and from Standard
minimum minimum
Basic
Grade A bonus weekly
payment earnings
wage rate A
14 September 1972
Craftsman is26.00
t
Labourer $22.00
10 June 1974 .
$32.00
L29.00 t3.00
Craftsman
f. 2.60 L27.20
Labourer $24.60
*
The standard basic rates of wages effective from 25 June 1973 sha e su j j . . ,
effect on and from I October 1973 on the basis of any percentage nett rise a OV ,.'
Retail Prices Index between the figure published in August 1972 an t e Ig p
1973. The adjustment shall be by the addition of 20p a week to t e re es o . ,
labourers for each full 0.75% rise in the index beyond 8}5%. The addition wi Con ,
with the rates effective from 10 June 1974. "
,^
^
33
Payment will be made at normal hourly rate for time lost due to
inclement weather .
I
Time assumed lost is 45 hours
Cost of inclement weather time is
Hours worked 9 9 9 9 9 4 49
Hours to be
paid at flat 8 8 8 8 8 40
time rates
Hours to be
paid at time
5
and a quarter
Hours to be
paid at time 4 4
and a half
Hours to be
paid at
double time
Total
non-productive 0.25 0.25 0.25 0.25 0.25 2 3.25
time
aries accordin to t
Project r , Season o year, geograp ical area, etc; use an average allowance and adjust on
jMay vary, see para Bl.
by cu, Or Over line WOr e as normal practice; the cost of any additional overtime worked to meet the
34
126.75
39 weeks @ 3.25 hours per week
Less
2 weeks annual holiday @ 3.25 hours = 6.50
4 Bank Holidays @ 0.25 hour 1.00
7.50 7.50
8 8 8 8 8 4 44
Hours worked
Hours to be
8 8 8 8 8 40
paid at flat
time rates
Hours to be
paid at time
and a quarter
Hours to be
4 4
paid at time
and a half
*
Hours to be
paid at
double time
Total
2 2
non-productive
time
.*
26
13 weeks @ 2 hours per week
2
Less I week affected by Holidays
if a private insurance scheme is used instead of the statutory scheme, the cost of premiums chould be include4;^
instead of the statutory allowances
Trade Supervision
Assume:* (1) that tilere is one trade foreman for every eight tradesmen
(ii) that half his time is spent working and half on supervisory duties.
(in) that his rate of pay is ^0075 per hour above the trade rate
Hourly cost for the gang is:
I trade foreman @ ^0740 + too75 '08/5
8 tradesmen @ to. 740 x 8 ^5920
t6.735
f. 7131
to. 792
9
(g) Training
Allow for industrial Training Board Levy, + say allow
1.5%^ for this example. See Summary
(h) National Insurance
Employer's contribution to National insurance
(includes Industrial Injuries, National '10sO per week
Health and Redundancy Fund)
.'. Cost per year is 52 x f. 1050 $54,600
(1) National Graduated Pensions**
For employer's contributions to cost of National Graduated Pension Scheme contributions,
allow $1.850 per week (varies according to level of earnings but including incentive payments. )
.'. Cost of National Graduated Pension is
49 x t1.850 t90.650
fj) Holidays
(i) Cost of annual holiday stamp t1.800 per week
Cost of Holidays with Pay is
49 x 1:1800 L88.200
(Ii) Paid Public Holidays
6 x 8 hours x to. 740 f35.520
in vary from firm to firm; use firm's normal arrangements in basic calculations and ad'ust
t any Industrial Training Board Grant is received, this may be credited to the trainin co t ' I
* S based on Numbers and Type of Operatives employed and should be adjusted in accordance w'th k - f
ompany and the current rate.
Ubstitute cost of private pension scheme if firm has contracted out of the national schem .
36
L
B2.03 Summary
.
1630.960
, (a) Basic Wages 33.300
(b) inclement Weather 106.005
(c) Non-productive overtime 3,750
(d) Sick Pay 116,948
(e) Trade supervision 9800
(1) Working Rule allowance
1900.763
28.51 I
(g) Training. Add 1.50% 54,600
(h) National Insurance 90,650
(i) National Graduated Pensions 88,200
co Holidays (i) Annual 35,520
00 Pad Public Holidays
2198.244
32.974
00 Severance pay and sundry costs. Add 1.50%
2231.218
weather) is 2204.
*The etcentage allowed will vary from firm to firm according to expelienc .
IThe percentage will vary according to the firm, the insurance company an
*For adjustments in respect of incentive payments, see para. 5.06 *
37
~~..~
Appendix C
MODEL FORMS
These model forms have been designed to stimulate ideas and to illustrate ways in which estimating
procedure can be systemised. it is hoped that readers will be able to use or adapt them to suit the
requirements of their own organisations.
Form No. Title .
Purpose ,
EjRPj5 All-in Working Rate for The calculation of opcrating (as opposed to
Plant
standing) costs of mechanical plant.
EjSQj6 Summary of Suppliers'
Quotations To tabulate the terms of competing quotations
BISCQj7 Summary of Sub-Contractors' in order that a sound choice can be made.
Quotations
EjGq8 Gang Costs The calculation of all-in hourly rates for gangs
of men.
,
IRY RECORD
,>16'
PROJECT Date Tender Documents Received
TimejDat. to Submir
APPROXIMATE VALU E
Location
Archicect
ENQUIRY
DETAILS
DESCRIPTION
Form of Conrr. c. Note any onerous CondiL on, or Alter allon to standard For, n
CONTRACT
Def ECts Liability Period % for Profess, onal Fees Date for Possession Date for Completion
iquidated and Ascertained Damages Period of Delay PC. Sums for which Contractor may Tender
PARTICULARS
Period of Interim Certificates Retention Percentage
OF
APPENDIX
Period of Final Measurement and Period for Issue of Final Certificate
Valuation
TENDER FORM
SIGNEDg
PROJECT
SHEET No.
DATA FOR MATERIAL ENQUIRIES
SPECIFICATION B. Q. SPECIFICATION B. Q.
DESCRIPTION APPROX. UNIT DESCRIPTION APPROX
SHEET No.
PROJECT
,
,
. I
SITE VISITED BY
DATE OF VISIT
NEAREST
TOWN I_, rob km
DETAILS OF
PUBLIC
TRANSPORT I
,
SERVING
THE SITE .
I
.
4
LOCAL a
CG_o as
AUTHORITY
' "'^, ( e, ,, Q I ,
,
km ,
DISPOSAL
OF SPOIL km ..
km
..
6
I' I. ,;- ,,, ,, , _ I* C
>:-z<I N o
..
b v!. g ., .
*
OF SITE
"
IVo 61 VC
*
DETAILS
OF ANY OBSTRUCTIONS
PY
YESjNO
* 7
8 LOAD
DETAILS
WIDTH
CAPACITY
.
\
EXISTING ROADS .
ON SITE
\\ O
.
ACCESS
EXISTING ROADS
ADJACENT To SITE
To
< SITE
TEMPORARY ROADS
REQUIRED
"
.
ACCESS _:,,~
I, 0, a.\-".!^4.I' ,
o a1^- C\A .\,, J;". ^-.*:'\-'
DIFFICULTIES L. ,
,!
UV\, }-9.11 b, t
STRATA EXPECTED To BE
I I' I L' ,:=I Ok^!-
FOUND DURING EXCAVATION
( ,- r*,*a <.,,*e':; ^,,,*:\^, 2. ".~ ,'\, to ^ ^ C\, 9 e, ^~c.
BOREHOLES EXISTING
BOREHOLES.
BOREHOLES REQUIRED
\:ESjNO
YES/N (IF YES GIVE NUMBER
SURFACE
WATER
DEPTH OF
TABLE ,
TIDAL
I'
SPRINGS. yE5jNO PUMPING
(IF YES GIVE REQU ED
GRO U N D ::. ES{No ..-
in in
IYES/NO NUMBER
INO
CONDITIONS
(STATE MAX.
DEPTH AND A" S:, Viva_ as aCC .P
LOCATION OF ANY EXISTING FOUNDATIONS.
STARRED ROOTS. ROCK OR ANY OTHER v- ^
MATERIAL LIKELY To BE
ITEMS)
FOUND IN GROUND.
STABILITY OF EXCAVATIONS
TIMBERING REQUIRED.
^^,
^
WHEN DISTANCE
10
SFRVICE EXISTING AUTHORITY AVAILABLE in CHARGES ,
I~'~'
FOUL .
MAIN DRAINAGE
- - -.
SURFACE ,
^^
^.. 9 0.9 .
ELECTRICITY
'. Yea Y . e .it^^^ - ,-. .
is 3 PHASE SUPPLY
VOLTAGE
AVAILABLE YES1'!6';
,
WILL HOARDING BE
REQUIRED
.
,
POLICE REGULATIONS . I' '
,,, ,
I
,
."
12 CRAFTSMEN LABOURERS
LOCAL RATES OF PAY
I
LOCAL METHOD OF PAYMENT
(E. G. BONUS. INCREMENT. 4
\
HOURS WORKED)
V*,\by/I CF-)
E a
ADDRESS OF LOCAL
MINISTRY OF LABOUR OFFICE
'^:. S\, CoA, ':^'"A ',- '^C^
,
I
' DETAILS OF LOCAL
LABOUR STRENGTH ,.
.,
,.,
DETAILS OF OTHER MAIOR
WORKS IN NEIGHBOURHOOD
LABO U R ,
MUST LABOUR BE
TRANSPORTED DAILY
I\'ES'I N O MUST A LABOUR CAMP BE BUILT
YE'1!*";
,
REPORT ON LODGING
FACILITIES L6'Co_^. Co-^ ,
I,
QUALITY OF
LABOUR AND LIKELY
\i
OUTPUT
,
CATERING FACILITIES
.,
13 TYPE a
S
,
~.
"b
11^
^Eb^^'.
MATERIALS
DETAILS OF
LOCAL
SUPPLIERS
AND
S UB
SUB
CONTRACTORS
CONTRACTORS
PLANT
HIRE
TRANSPORT
14
DRAWINGS
(SKETCH PLANS
To BE
ATTACHED)
15
ANY
OTHER
USEFUL
INFORMATION
16
,
..
.
I
"
SKETCHES
,
*
,
16 CONTINUED
. I
SKETCHES
(:
~
PROJECT
REFERENCE
MECHANICAL PLANT
MACHINE
(TYPE AND
CAPACITY)
HIRE OF
SOURCE SOURCE SOURCE SOURCE
MACHINE
I. .
co
o
U
U
Z
a
Z
<
I-
co
OPERATOR
Of not included
und. , 'HIRE')
FUEL .
I.
co
o LUBRICANTS
U
U (Oil and rrea, e)
Z
Z \
Z
=
.C
SUNDRY
CONSUMABLE
STORES
, No's
su MMARY OF su B. co NTRACTORs' ou oTATioNs
PROJECT
REFERENCE
.
2
ESTIHATOR'S COMMENTS
GENERAL
MIXER DRIVER MIXER DRIVER BRICKLAYERS BRICKLAYERS CARPENTER
.
LABOURERS
@ ........ @. @ Ia,
@ ........
tt
CEMENT MAN CEMENT HAN LABOURERS LABOURERS PLUS RATES PLUS RATES
CONDITIONS
*,........ @.. MIXER DRIVER MIXER DRIVER
TIMBERMAN
.
WHEELERS WHEELERS
64 ........ Ia
PLACERS PLACERS
\
@........ 6a
fii . . . . . . . . @
TOTAL GANG TOTAL GANG TOTAL GANG TOTAL GANG TOTAL GANG To. 'AL GANG
COST PER COST PER COST PER COST PER COST PER COST PER
HOUR HOUR HOUR HOUR HOUR HOUR
~*.' , ,.... ." *
.. ,., ~. .. ,* . ..,, ..
.. I ". . , , . *.. .. 1.9. .~ -, . . ,. ...,..,. ~.,. .> .~,'\I .,' .. ., . . .. ,. ". .,,.~ ., ~. * ,,*.',' ......,~,' , ,~ ,*', ,-',' , , * , t I - . : ' ""
.,
, " , ,.. ..
^
REFERENCE
DATE
"
o
= PROJECT
31
. I
,.
CONTRACT PERIOD
SITE MANAGER
GENERAL FOREMAN
FOREMAN
ENGINEER
CHAINHAN
CHECKERS
TIME KEEPER . I
STORE ICEEPER
.
CASHIER
WAGES CLERK
MATERIALS CLERK
SITE
STAFF PLANT CLERK
QUANTITY SURVEYOR
JUNIOR SURVEYOR
PROGRESS SURVEYOR
.
BONUS SURVEYOR
SAFETY OFFICER
,
PLANT FinER
TYPIST
RECEPTIONIST
WATCHMAN
CANTEEN STAFF
2
DESCRIPTION TOTAL
HOURS RATE
.
CLEARING SURPLUS MATERIALS
.
CLEANING CLEANING OUT AFTER TRADES
SITE
AND CLEANING OUT AT COMPLETION
CLEARING
RUBBISH CLEARING RUBBISH
.
SITE LORRIES
VANS
STAFF CARS
E E
MIXING PLANT
CRANES
HOISTS
PUMPS
MECHANICAL
PLANT AND
HOISTING
11F NOT
INCLUDED ELECTRICAL GENERATORS
IN RATES)
MIXING PLANT
CRANES
HOISTS
5 RATE TOTAL
DESCRIPTION MEASUREMENT QTY. UNIT No. OF PER
.,
WEEKS WEEK
..
E
EXTERNAL SCAFFOLDING
*,
*
.^
INTERNAL SCAFFOLDING
,,
SCAFFOLDING
AND
GANTRIES
.
.. FLY SCREENS
. ,
,
GANTRIES
SUB TOTAL
HOURS RATE
*
LABOUR COSTS IN ERECTING. DISMANTLING AND ADAPTING
..
* RATE PER
, ,
6 TOTAL
WEEK
DESCRIPTION SIZE No. OF UNIT
WEEKS E E
..
,
CONTRACTOR'S OFFICES
STORES
.
,
SANITARY
.,
CANTEEN
DRYING ROOM
FIRST AID
SITE ACCOM.
MODATION
FITTERS
11NCLUDING HIRE.
ERECTION.
MAINTENANCE
CHECKERS
& DISMANTLING)
CARETAKERS
-RECREATION
-ABLUTIONS
DECORATION
.
CARAVANS
BASES
SMALL
PLANT ALL SHALL PLANT (LADDERS. WHEEL BARROWS, TRESTLES. SHOVELS. SPADES. PICKS. TOOL BOXES. SLEDGE
HAMMERS. COLD CHISELS. EfC. ) ,
,
8 TOTAL .
DESCRIPTION
E .
HOARDINGS
.
FENCES .
.,
SANITARY
TEMPORARY
SERVICES
ROADS
AN D RE.
INSTATEMENT
REINSTATEMENT OF PAVINGS
I
REINSTATEMENT OF KERBS
REINSTATEMENT OF GLASS
PLUMBING ~
.A
WINTER BUILDING
~
..
TOTAL
9 .
DESCRIPTION
E
ELECTRICITY
GAS
*
TELEPHONE
STATIONERY
POSTAGE
ELECTRICAl. FEES
GAS FEES
,,,
RATES ..
SUNDRY EXPENSES ,
,
10
DESCRIPTION TOTAL
TEMPORARY
WATER E
INSTAL- CHARGES (EXCLUDING WATER FOR
WORKS AND WATER SERVICE POINTS)
LATIONS
TOTAL To PAGE 7 OF ESTIMATE SUMMARY (FORM EjEs/10 C
11 TOTAL
DESCRIPTION
E
CANTEEN . ,
12
TOTAL
DESCRIPTION
(PERIOD OF LIABILITY -
DEFECTS
LIABILITY LABOUR
COST
MATERIALS
13
DESCRIPTION TOTAL
<- 14
TOTAL
DESCRIPTION
E
AVELLING TIME -
HOURS "
TRANSPORT AREs -
OF MEN DAYS ,"
To SITE
851STENCE ALLOWANCES - WEEKS ,i,
15
DESCRIPTION IOTAL
E
NORMAL OVERTIME WORKING HOURS 14
ABNORMAL
OVERTIME TRACTION MONEY
HOURS t, *
DATE
PROJECT
. I
<--
CONTRACT P. .lob
~
O Th. In. ticut. o1 Build". re, in No. EjESjlO.
DOCUMENTS ,
FORM OF CONTRACT
. I
C~ OTHER INFORMATION
*
DATE FOR COMPLETION
PERIOD OF DELAY
DRAWINGS AVAILABLE
\
I
BILL
No. TRADE LABOUR PLANT MATERIAL SUB. CONTRACTORS SUPPLIERS ,
E E E E E
..
^
\
.
,
.
*
.
\
,.
; ,
..
.;
*
,
*. -~
,
$1
~
4.
,
. \
,*
.4
$.
, ,
.*t
~.,
.
\
it .
L.
... ,
"
,
,
*
f
-.* ,.
\
,.
f "
*
,
a
F
..
*
,
if
,.
,
.,
"
*.
,
.,
I
OF QUANTITIES .
I
I
OWN SUB. CONTRACTORS
PROVISIONAL CONTINGENCIES TRADE TOTALS
NET 213; s% SUMS
E E E E E E
. ,
*
LATE QUOTATIONS AND ADJUSTMENTS {.
h
ADD
BILL DEDUCT
No. QTY. ADJUSTMENT LABOUR PLANT MATERIALS LABOUR PLANT MATERIALS
E E e e E E
.,
.
.
,
I
:,
-,
,.~
I.
t;~
I
AMOUNT
BILL QUOTATION USED AMOUNT ADD DEDUCT ..
E E
I,
E E
..
,
"
.
-. I
.*
,"
I
~I
.
,,
,F
,
? 41
,
*,
* $.
b
;*
I:
J.
>.
,:
AMOUNT ADD
DESCRIPTION
DEDUCT
ITEM DETAILS OF ADJUSTMENT
No. E E E
SITE STAFF
. I
6 SITE ACCOMMODATION
7 SMALL PLANT
<. a
TEMPORARY SERVICES AND
RE. INSTATEMENT
9 MISCELLANEOUS
.
,
,
11
WELFARE. FIRST AID
AND SAFETY PROVISIONS
.
15 ABNORMAL OVERTIME
<., .
., .
,.
,.
*!
*. ,
.. .
, .
-- I
5-
.,
a. ,
TOTAL C TOTALS C
;, I
,.
...
(ADD/DEDUCT)
a:.
.
.
FIRM PRICE RISK CALCULATION
, ..
AMOUNT TOTALS
11 ,
A
,
.
LABOUR . ,
..
"
.
, ,
PLANT *
..
.*
..
MATERIALS
*.
J. ,
*
~,
.
,.
" ,
, I'
$ *
OWN >.
I.
SUB-CONTRACTORS ,
,
* ':.
., ,,
..
t, .\:
.
.*
d
.,
q
,
.f
.
: A
, "
,.,,
,
PROJECT ,\
OVERHEADS .\
...
.;
TOTAL To FINAL SUMMARY ON PAGE 10 , ,
,,
.-:;,,
,
. JP
ESTIMATOR'S REPORT
*
,,
33
;'c
xi
,*
to^, CD{^d , k^ t~~ Q^i ^xi ^,, ^11^ 013 ^ ;^ ^co"
,^I^,^I; ,
POT
.^^. y, '^."c^'
^;; ?* P-~6by, ,,
A1 s;- o
A1 ';^,
19, ,., ^.,,,. a^^t:>
^,^> C^
,.,,,(, e/ v^' 'Y ^^;
^I)9
^^>^v^.~^^^^t^^
f'b^A, ^C>
^. i^
j, ^ A, ^,
';'^,,* ,,,. c, )0"
(^ {t^/ by~^
6'^,,^, o1 ,I
I^"'
^^
a, *^,*
I. .67"'
ADJUDICATION NOTES
* ,
*
,,
,
.
.
.,
. .
a
A-.
it
-*
,
,
, I
*
.
,,
,
C
,
.,
.t
,.
,
Aru'LhUl:\ \. I, ,\, I L, . I
COMPARISON OF RESULTS *
..
~
REFERENCE *, *
,
PROJECT :.
DATE .,..
... "
. ~
,
?
-,.
<
,.
.*
t.
, .*
..
, .*
TENDER
,,
LIST
.,
,.
.,
"L ", ~ ,.
".
..
, .:
..
*
,
,,
;,
.t, %, . . t ,.. .. it
,
..
~.
,,
ANALYSIS OF RESULT
*
C %
~.
% COMPARISON OF RESULTS -,
ANALYSIS OF TENDER
LABOUR
THIS COMPANY TENDER
MAIN CONTRACTOR'S WORK
'I
LOWEST TENDER
PLANT
,,
DIFFERENCE
a
MATERIAL
.
,
.
.,
4 OWN SUB-CONTRACTORS .,
a PROJECT OVERHEADS
I
,, . FIRM PRICE ^^
.
9 RISKS
OTHER
,
,..
~~
41C
^
Plan r
Erection &
Transport
Costs
Hired
Plant
Co, 13
O peratinE
Costs
Project
Own Plant V. riabl. O VC rhe. d,
SLandin, Labour
Costs Co 3.3
Cos.
Inform. ,. on
Check
Prol, in I n. ric, Di, tribute Final
Contract Construction
, Condition, Information Reconcilli. ,ion
Documents
o1 CONr. <1
~.~~.\--~~-~~-~. Check
Delivery &
All-in
Plan.
Costs Add Ri, k, 11
Labour Total
Reporr to Arr. e Unsuccessful
Completion Char8eable & General
Rates Tender Vi, 1.3 to
Dates To items
Review Hana, e men t Overhead, Record &
Figu re Site
Profit NORIly
Add
Costs
Allowances Records
of
&
Labour
Attendance
E. G. , ",^ \ " *in. r y
,. I
Check ,.",,.
nth,
Delive ry 70.1
D. t's Own Sub-
Review Contractor. "
.
Costs o
Quotations
^
& , Firm Pr
.
Select . R. ,k
=
.
. Calc ul. lions
.
Check Cos. , of Z
S PCcific. tion Materials L
e
8
"
.
.
a
PC. & ,
.-^^.
Code Build. up o1
E, .. blushm. n. o1 All-, n Rates
Unit R. ,e,
C0~., 1.1. RE the EMIm. IC Code Code
Section
Section Section
THE TENDER ACTION WITH A
5 PREPARATION OF E E
6 7 SUCCESSFUL TENDER
.
Visit
A FChirect Consultari
Ex. mine
Ch. rk & Selecti
Cons. rucrion
Cont, .c, Consultation of Plant
Work
Cond, ,. on, Selection
o .
Load
o1 Methods
Ex. min.
Condition, E. . min.
o1 . rid Li, , 0*"
Check
Con. ,. c, E. ,,. CG Sub.
Inform. ,, on Cent, .q, 0, , Operations
Pro. ramme Su b.
Estimate
Contracred
E. ,in, n.
Con, truc, ,on
.rid E, ,, in. ,, HB
Work
Lo. do
L. ,,
M, ,or. ,10
L", C , C n. ,.
Pro, ,,, 00.1
Sun, , 0.1, ..,, ,
On, ,.,."cb Conpj. ,,,.
D. ...
Code
Code
Seccion
THE DECISION S. ction ,. Q".,, S, .,.
Pro^CL Appreciation
To TENDER
4
COLLECTION OF INFORMATION
PRC