Академический Документы
Профессиональный Документы
Культура Документы
1- PURPOSE
2 - SCOPE
3 - REFERENCES
4 - DIFINITION
5 - RESPONSIBILITY
6 – PROCEDURE
7 – FLOW CHART
8 - DOCUMENTATION
9 - APPENDICES
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITION
5. RESPONSIBILITY
5.1 The Planning Engineer is responsible for the preparation of Master Schedule of
production process, issuance of appropriate specification, drawing, materials
and monitoring of the production progress in accordance with the agreed
delivery schedule.
5.2 Shop Manager shall be responsible for co-ordinating and monitoring that all the
process are carried out under the controlled conditions and in accordance with
the master schedule.
5.3 Quality Control Engineer is responsible for verify the production process
compliance with specification, reference standards/codes, shop drawings and
quality plan.
5.4 Quality Control Supervisor is responsible for monitoring and control of suitable
parameters and product characteristics by way of Inspection and Testing in
accordance with the documented Inspection and Test Plan.
5.6 The Welding Supervisor shall be responsible for selection of appropriate welding
consumables, compliance of welding procedure specification (WPS), welding
procedure qualification record (PQR) and to ensure that only qualified welders
are used for welding work.
6. PROCEDURE
6.1.1.3. The marking shall be carried out with a hard tipped sharp marking pin or thin white
crayon.
6.1.1.4. During marking the base reference line, center line and checking points shall be
provided on marking to avoid any mistakes.
6..1.5. A surplus length and width shall be provided in addition to the cutting allowance for
the 1items on which large welding shrinkage will be predicted.
6.1.1.6. Application to the center punch in the marking shall be minimized in plate except
for those, areas where marking can be completely erased afterwards by means which
of drilling
6.1.1.7. Marking shall not be used for the outer face to be bent or the parts which become easily
defective
6.1.1.8. As much as possible original plate number which is stamped by mill must be
retained and marking should be avoid on the identification numbers shall be transfer
by means of hard punch at unusable corner of the plate.
6.1.1.9. Drawing number, mark number, submark number, shall be clearly marked by paint
or by means of hard stamps.
6.1.2. Cutting
6.1.2.1. The Material shall be placed on the skirt in a fully flattened position and shall be
verified the heat number, thickness and size prior to start cutting.
6.1.2.4. Cutting tip shall be kept perpendicular to the surface for Material thickness 10 mm
or more. For less than 10 mm thickness the tip can be titled in the direction of cut.
Titling increases cutting speed and helps prevent slag from freezing across the kerf.
6.1.2.5. The cut face of each member shall be perpendicular to the axis line unless otherwise
specified on the drawing.
6.1.2.6. Cut face shall be free from remarkable uneven notch or slag attachment. In case of
occurrence of notch, such part shall be welded and finished to flatness by means of
grinder.
6.2.1. Prior to start drilling, the hole diameter and number of holes shall be verified and
ensure the hole centre punch visible and deep enough to penetrate the drill point.
6.2.2 Drilling of bolt holes shall be carried out by a radial drilling, CNC Drilling machine
or portable magnetic bottom drilling machine where applicable.
6.2.3. For angle thickness less than 12mm, hydraulic punching machine shall be used
6.2.4. Post drilled areas shall be cleared enough around thoroughly by grinder
6.2.5 After punch, the hole and angle shall be flattened
6.3.1. Fitter shall inspect the items visually for any surface damages, bends and
deformations, if so it shall be properly corrected in accordance with shop detail
drawings prior to start building and fitting up the items.
6.3.3. Upon receiving of Material, the fitter shall verify them against the drawing and
ensure the mart number and sub-mark number written in the Materials matching
with shop drawing.
6.3.4. It is the responsibility of fitter /QC Supervisor to verify the size, thickness, hole
details, hole diameter, spacing and number of holes. The contact surfaces of the
components shall be free of burs and foreign materials that would prevent solid
seating of the parts.
6.3.5. Center line and working points reference lines on the members shall be drawn and
fitter shall mark the fitting locations in the main member and he re-check again prior
to start fitting in accordance with shop drawing.
6.3.6. All the edge preparation and site assembly profile on both main members and
components shall be carried out prior to start fitting and in accordance with shop
drawing.
6.3.7. Assembly work shall be carried out with suitable tools and equipment, such as surface
material positioners, jacks, lever blocks, chain blocks and strong backs.
6.3.8. For all full penetration weld joints of fitting shall have minimum root gap of 3 mm
and the edge preparation strictly in accordance with shop drawing.
6.3.9. The fitter performing the tack welding shall be qualified for the process in accordance
with the applicable welding procedure specification.
6.3.10. The tack welding shall be performed in accordance with the table below and a short
bead is to be avoided.
t < 6 mm 30 mm over
6.3.11. Tack welding shall not be used at the end of the welding line or at the corners. The
slag of the welding beads shall be completely removed with suitable tools and arc
strike on the parent metal shall not be permitted.
6.3.12. Where stitch welding is specified the seam shall be marked prior to fitting and the
tack welding shall be done on the location such that they are covered by full welding.
6.3.13. Electrode for tack welding shall be in accordance with the specification and as per
the approved welding procedure. Tack weld shall be carried out by qualified fitters.
6.3.14. The fitter shall write down the applicable welding symbol on all the parts that would
be welded in the shop, in accordance with shop drawing.
6.4. Welding
6.4.1. Welding process shall be in accordance with the approved welding procedure
specification (WPS) and procedure qualification record (PQR). Appropriate WPS
and PQR document reference shall be clearly stated in the project quality plan or in
the inspection and test plan.
6.4.2. WPS and PQR shall be in accordance with AWS D1.1 .WPS shall be approved by
third party inspection agency. PQR shall be in accordance with the appropriate
Code and Standard.
6.4.3. All the welders shall have approved welder performance qualification test record
prior to engage on the welding process. Before starting the welding, welder shall
measure the output current and voltage. Appropriate and calibrated measuring
instrument shall be used for such measurement.
6.4.4 The welding work piece shall be placed in a skid into stabilized position, and the
position shall be ideally either flat or horizontal as much as possible.
6.4.5. All the joint to be welded shall be cleaned and dry condition. Prior to the welding
cleared of all the scale, rust, dust, paint, grease, or any other foreign matters, by
mechanically using wire brush or grinding.
6.4.7. The stable arc shall be maintained during welding, a better arc stability is important
to procedure high quality welds and also it will avoid defects such as inconsistent
fusion, entrapped slag, blow holes and porosity. Keep in mind the following are
important factors influencing arc stability.
a) The open circuit voltage of the power source.
b) Transient voltage recovery characteristics of the power source.
c) Size of the molten drops of filler metal and slag in the arc.
d) Ionization of the arc path from the electrode to the work.
6.4.8 The arc blow during welding shall be controlled and eliminate. Arc blow is
encountered principally with DC welding. Back blow is encountered when welding
toward the work piece connection near the end of joint or into a corner. Forward
blow is encountered when welding away from the lead at the start of the joint.
6.4.9 Welding shall be done in flat position if Steel Material of thickness 4 mm or more this
position permits easiest manipulation of the electrode and allows use of high-deposition.
6.4.10 Welding gaps or bevels must be accurately controlled over the entire joint during
welding operation. Sufficient bevel is required for good bead shape and adequate
penetration.
6.4.11. Root face of the fillet weld should touch steadily to the base metal. Shape of joint
shall be in accordance with the drawing and any discrepancy of the location shall be
eliminated
64..12. For butt weld and fillet weld, the start and end points of the welded parts shall be
installed with end tab which is in possession of the same edge preparation shape as
that member. End tab should be gas-cut and finished by grinder after completion of
welding.
6.4.13. In case of fillet weld of unequal leg has assigned, care should be taken in order to
secure the specified dimension and also to keep the weld surface as smooth as
possible
6.4.14. In case of any crack shall occur in the part where tack welding has been applied, it
should be gouged/ grind up to the bottom of deposit metal and re-welded.
6.4.15. The following steps shall be taken to control the excessive spatter during welding:
a) Lower the current and ensure the current is within the recommended range
for the type and size of electrode.
b) Be sure the polarity is correct for the electrode type.
c) Try to maintain shorter arc length.
d) If the molten metal running in front of the arc. Change the electrode angle.
e) Watch for any arc blow.
f) Be sure the electrode is baked and should not be wet..
6.4.16. The following action shall be taken to minimize the under cut during welding:
a) Reduce current, travel speed or electrode size until the weld puddle is
manageable.
b) Change electrode angle so the metal in corners. Use a uniform travel speed
and avoid excessive weaving.
b) Keep the puddle molten for a long time, so that gases may boil out before the
metal freezes.
d) Minimize the admixture of base metal with weld metal by using low current and
fast travel speed for less penetration.
6.4.18. Lack of fusion shall be avoided for sound weld. To avoid poor fusion:
c) If gap is excessive, try to get refit or use a weave technique to fill the gap.
b) Examine the specifications given by the customer applicable to the class of work,
quality required, end use of the product, etc.
d) Only the tested and defect-free materials and as per the approved specification or
drawing should be used for the structure to be welded.
j) Welds which would become inaccessible or more difficult to inspect at a later stage
shall be inspected at stage.
k) Inspection if carried out during welding will help identify potential sources of
defects and thus eliminate them at the early stage.
l) Inspection during welding will help finding any deviation from approved procedures
consumables, etc. which if goes unnoticed may deteriorate weld quality.
m) Visual inspection during welding will reduce the chances of rejecting the weldment at final
stage
c) Extent of welding
d) Dimensional of accuracy
e) Amount of distortion
f) Surface cracks
g) Under cut
h) Overlap
i) Exposed porosity
6.5. Finishing
6.5.1. A finishing process that would bring the fabricated product into the acceptable level
in accordance with the drawing and standard workmanship. Final dimensional
inspection, general appearance, final visual inspection, revision and any
modification and final repair activities are carried out in this process, includes final
identification and traceability of the product.
6.5.2. Q.C Inspector shall inspect the product visually and identify the area that would be
required to carry out finishing work and mark by means of crayons.
6.5.3. Concern fitter shall select the appropriate tools and equipment depending on the
nature of work to be carried out such as grinder, wire brush, chisel, hammers, and
heating torches and reformer machine etc.
6.5.4. Welding slag and spatter shall be clean properly and wire brush or power brush
shall be used as post cleaning operation.
6.5.6. If any crater observed the QC inspector shall note down the welder identification
number which is written near the welding and call the same welder for repair.
6.5.7. All the bolt holes must be clean and trimming by means of grinder, round file and
reamer if it is necessary.
6.5.8. All the cutting edges must be grind smooth and all the sharp edges must be radius
and smooth.
6.5.9. All the Gas notches must be rebuilt by (touch up) qualified welders and grind
smooth.
6.5.10. Shop fitting supervisor shall arrange the finished product systematically that would
facilitate the QC. Inspector can inspect the product without any difficulty.
6.5.11. Rejected or defective items must be separated immediately and sent for corrective
action to the process concern.
Prior to start painting blasted surface shall be cleaned by dry compressed air and
ensure the surface is dust free.
All ingredients in any container of paint shall be thoroughly mixed before use and
shall be agitated often enough during application to keep the paint uniform.
The type of thinner shall comply with paint manufacturer’s instructions. Correct
amount of thinner to be added to particular application when the use of thinner is
permissible, thinner shall be added slowly to paint during mixing process.
The equipment used for painting application shall be suitable for the appropriate
purpose and coating system and shall be capable of properly atomizing the paint to
be applied.
All the paint pot shall be equipped with suitable pressure regulators and gauges.
Paint shall be applied in a uniform layer with overlapping at the edges of the
pattern. During application, the painting spray gun shall be hold perpendicular to
the surface which will ensure that a wet layer of paint is deposited on the surface.
The trigger of the gun should be released at the end of each stroke.
The air caps, nozzles and needles shall be those recommended by the paint
manufacturers of material being sprayed and equipment being used.
Traps or separators shall be provided to remove oil and condensed water from air. The
traps or separators must be of adequate size and must be drained periodically during
operations.
The pressure on the material in the pot and of the air at the gun shall be adjusted for
optimum spraying effectiveness.
The pressure on the material in the pot shall be adjusted when necessary for changes
in elevation of the gun above the pot. The atomizing air pressure at the gun shall be
high enough to properly atomize the paint.
For airless application, the distance should be from 250 mm to 350 mm. At the end
of each pass, the gun trigger should be released.
Each spray pass should overlap the previous one by 50%, and where possible, a
cross hatch technique should be used. This requires a duplicate series of pass at 90o
to the first to ensure complete and uniform coverage.
Paint shall not be applied when the temperature of steel or the paint is below 4o C.
Paint shall not be in rain, wind, fog, mist or when the steel surface temperature is
less than 3o C above the dew point.
Paint shall not be applied when the relative humidity is above 85%. The
manufacturer’s instructions shall be followed regarding the acceptable humidity
range for the particular paint.
SPECIAL CIRCUMSTANCES:
All the changes from this procedure and matters not contained in this procedure
should be settled upon the consultation with customer engineer or client authorized
agent including any third party inspection agency.
Any discrepancy regarding the workmanship standard and criteria with respect to
the acceptable level has to have customer consent.
7. FLOW CHART
MILL CERTIFICATE SQUARENESS CHECK LOCATION, Q'TY & CHECK WELDING OPERATOR,WELD.
THICKNESS & SIZE HOLE DIA. ORIENTATION OF PLATES SIZE, VISUAL APERANCE ACCORDING
VISUAL HOLE'S LOACATION OVERALL DIMENTIONAL INSPECTION TO WELD MAP
QUANTITY HOLE'S DISTANCE
Correction
of Surface Painting/
Drilling QC5 QC5 Packing Shipping
Distortion & QC3 &4 Treatment for Marking-
Finishing Paint Work Stenciling
8. DOCUMENTATION
NIL.
9. APPENDICES