Construction Cost Control

Basic Course
Lesson : 1.3
This Course Sponsored by : PlanningEngineer Est.
www.planningEngineer.net

Presented by : Hany Ismael MSC,PMP


Construction Cost Control Basic Course

Section (1) : Cost Control General View and Definitions

• What is Cost Control In Construction Projects?

• Why We Need Cost Control in Construction Projects ?

• How to Perform Cost Control ?

• What we will and What we will Not Study During this Course ?

www.engineerbook.net
Construction Cost Control Basic Course

How to Perform Cost Control ?

In order to Perform Cost Control , We Need to Process Fours Steps

Step1
Baseline

Step 4
Report Step 2
Progress
Forms
& Take
Actions

Step 3
Collect
Progress
www.engineerbook.net
Construction Cost Control Basic Course

Develop Cost Control Baseline Plan

Step 1 : Develop Cost Control Baseline Plan

First Sep is Preparing the Cost Control Baseline Plan Which Should
Includes the Following Data :

A : Activities Required Man-hours Per Profession

B : Activities Required Equipment

C : Activities Required Materials

www.engineerbook.net
Construction Cost Control Basic Course

Step(1) : Baseline

www.engineerbook.net
Construction Cost Control Basic Course

Develop Cost Control Baseline Plan

Step 2 : Develop Cost Control Forms

Second Step is Preparing the Cost Control Forms Which Should


Includes the Following Data :
From the Site engineer
A : Daily Report
From the Store Keeper
B : Materials Store Daily Report
From the Equipment
C : Equipment Daily Report Supervisor

www.engineerbook.net
Construction Cost Control Basic Course

Step 2 : Develop Cost Control Forms

A : Daily Report

www.engineerbook.net
Construction Cost Control Basic Course

Step 2 : Develop Cost Control Forms

B : Materials Store Daily Report

www.engineerbook.net
Construction Cost Control Basic Course

Step 2 : Develop Cost Control Forms

C : Equipment Daily Report

www.engineerbook.net
Construction Cost Control Basic Course
Collect Progress

Step 3 : Collect Progress

Since the Cost Control is more Complicated than Planning and


Controlling Time Only , You Should Prepare Some Special Forms
and Templates to Collect the Progress.

www.engineerbook.net
Construction Cost Control Basic Course

Step(3) : Progress Updates

Project Progress Updates


Material Updates

Labors Updates

Equipment Updates

www.engineerbook.net
Construction Cost Control Basic Course

Material Updates

www.engineerbook.net
Construction Cost Control Basic Course

Labors Updates

www.engineerbook.net
Construction Cost Control Basic Course

Equipment Updates

www.engineerbook.net
Construction Cost Control Basic Course
Report Progress

Step 4 : Report Progress

There are Several Areas Where you Need to Report the Cost Control
Progress Such As :

www.engineerbook.net
Construction Cost Control Basic Course
Report Progress

 Productivity Performance

 Material Usage / Wastage Performance

 Equipment Usage Performance

 Engineers Performance

 Items Performance

 Project Overall Performance

www.engineerbook.net
Construction Cost Control Basic Course

Take Actions

Further Actions Could be Taken Based on Progress Observations


and you May Need to Revise Your Baseline or Develop Catch Up
Plans.

www.engineerbook.net
Construction Cost Control Basic Course

Thanks!
Hope to receive your
feedback, recommendations , questions?
This Course Sponsored by : PlanningEngineer Est.
www.planningengineer.net

Contact Info.
/PlanningEngineerDotNet
www.engineerbook.net
info@engineerbook.net /groups/4809645
Mobile : +20 1277767728

Вам также может понравиться