Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 1 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Access to the place of work shall be
by designated pedestrian safe routes
where in place.
Injury due to Work area to be kept clear of non‐
accessing essential tools & equipment.
works by Main contractor (civil contractor)
means other
shall provide a safe access to the
Access to the work than safe
Fall, Personnel injuries, property 3 3 9 M area. Site engineer 3 1 3 L
area access /
damage, slip & trip. All workforces/vehicles have access
egress routes
provided and pass for entering in land/air side.
coming in to Method of statement, risk
contact with assessment to be brief to all involved
site hazard. by supervisor.
Ensure PPE (safety shoes, helmet, jacket,
glasses, gloves etc.) worn for the work
place.
Competent operators and banks
Loading/unloading of man to be engaged with 3rd
Forklift truck party test certificate for fork lift.
Grease interceptors
struck I hit Fatal I serious injuries/ amputations
with forklift truck 4 3 12 H Forklift I Truck drivers shall follow Site engineer 4 1 4 L
over men and and Damage to properties.
onto the trucks and site safety requirements i.e.
other vehicles
from the trucks maintaining stipulated speed
limit, switch off engine in
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061
Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 2 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
basement areas when idle and
wearing seat belt etc.
Separate truck traffic and other
workers where possible.
Restrict the unloading works near
duty start I finish times, breaks,
test rooms, canteens, and main
exits, particularly when the flow
of workers on foot is at a
peak(such as at the end of a shift
or during breaks).
Evaluate intersections and other
blind corners to determine
whether overhead dome mirrors
could improve the visibility of
trailer /crane operator or
workers on foot.
Engage competent drivers &
signal man.
Coordination while
loading/unloading team with the
vehicle driver. By using
lag/whistle/radios.
Maintenance of side &rear
mirrors and engage reverse horns
and engage assistant/banks man
while reversing of trailers.
Engage revolving flash light beacons.
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061
Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 3 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061
Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 4 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061
Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 7 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
assessment to be done.
Chain block to be certified by
3rdparty
Ensure safe anchoring point for
chain block which should be 3rd
party approved.
Ensure competent
workers/supervisors
Follow safe system of work.
Task briefing I tool box talk meetings
before any heavy lifts.
Tool box talk meeting for safe use
of hand tools used
Tools to be kept secured once after
Use of hand Body injuries, Amputations from incorrect 3 3 9 M work completion in the tool boxes. Site engineer 3 1 3 L
tools use of hand tools.
Tool boxes shall be inspected
periodically by foreman and
storesin charge.
Adequate ventilation to be
provided and adequate rest to be
Working in high provided.
humid areas Adequate provision of drinking
due to Heat stress/ heat stroke. 3 3 9 M water I consuming drinking water Site engineer 3 1 3 L
inadequate regularly+ electrolyte drink to
ventilation. replenish electrolytes lost due to
sweat.
Dust creating
Adequate area ventilation with
adverse 3 2 6 M draught fans. Site engineer 3 1 3 L
Breathing discomfort
working Use PPE (Safety hand gloves, dust mask
condition. and eye goggles)
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061
Assessment Number: RA-100089653 Assessment Date: 28/04/17 Revision Date: 27/10/2017 Page Number: 8 of 8
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes :S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-004-MAR-2017-DAEP-FORM- 061