Soil Classification: Making 150mm nominal diameter bore holes at various locations in
soil using suitable approved method of boring including cleaning the bore holes,
collection of samples, observation of ground water level, collection of
3 undisturbed/disturbed sample and back filling of bore holes on completion of work as Loc -
per specification and instruction of engineer in charge of work .The scope also includes
the submission of final report containing the bore log details with classification of soil for
the purpose of providing foundation along with GPS co-ordinates of each boreholes.
Soil Resistivity: Conducting Soil resistivity test along the selected route and submitting
4 the test results in the form of report as detailed in the technical specifications at an Loc -
interval of 1km (4 point ERM method)
Earth work Excavation in Normal Soil foundation in all types of soils including Soft
Disintegreted Rock as defined by IS-1200 in but dry and wet conditions including
shoring and strutting de-watering sub-soil and rain water to keep the excavation dry.
Levelling and dressing the bottom of excavation to correct level and slope., with all
leads and lifts, including cleaning and Grubbing for removal of rank, vegetation, shrubs,
trees, bushes, stumps, weeds, grass including roots, debris, unusable materials, using
5 Cum -
manual or mechanical method and disposal of the same by burning or any other means,
if required bailing /pumping out of water to keep site dry at all times until completion of
work; stepping, dressing, grading, cleaning, removing and excavating loose pockets as
directed etc. all complete as detailed in specification and drawings and as directed by
Engineer-in-charge.compleate all as per drawings, specifications and as directed by
Engineer-in-charge.
Excavation in Hard Rock/ Boulders using breakers and trimming to required level.
Rate shall include for Excavation at required depth at all leads; dressing of sides;
including cleaning and Grubbing for removal of rank, vegetation, shrubs, trees, bushes,
stumps, weeds, grass including roots, debris, unusable materials, using manual or
mechanical method and disposal of the same by burning or any other means, if required
bailing /pumping out of water to keep site dry at all times until completion of work;
6 Cum
stepping, dressing, grading, cleaning, removing and excavating loose pockets as
directed etc. all complete as detailed in specification and drawings and as directed by
Engineer-in-charge.
Note : Hard Rock/ Boulder is a rock fragment usually rounded by weathering,
disintegration and abrasion by water or ice having a maximum dimension in any
direction of more than 600 mm)
Sand filling below the foundations as per the standard specifications of KPTCL in
7 uniform horizantal layers including cost and conveyance of all materials, watering and Cum
ramming, tools & tackles all labour charges all leads and lifts etc
PCC 1:5:10 Providing & Laying of PCC mix using 40mm size Machine Crushed Metal for
foundations including cost and conveyance of all materials labour charges, all leads and
8 Cum
lifts, centering, ramming, curing , complete for finished item of work as per the
directions of the Engineer-in-charge.
PCC 1:4:8 Providing & Laying of PCC mix using 40mm size Machine Crushed Metal for
foundations including cost and conveyance of all materials labour charges , all leads and
9 Cum
lifts, centering, ramming, curing , complete for finished item of work as per the
directions of the Engineer-in-charge.
PCC 1:3:6 Providing & Laying of PCC mix using 40mm & 20mm size Machine Crushed
Metal for foundations including cost and conveyance of all materials labour charges , all
10 Cum
leads and lifts, centering, ramming, curing , complete for finished item of work as per
the directions of the Engineer-in-charge.
Stubs : Setting of stubs in all soils with stub setting templates -Erection of stubs, stub
template fixing of jacks for supporting template alignment and levelling for exact
11 location of stubs of stub setting template, dismantling of template after completion of Towers -
initial curing of C.C movement of template from one location to other location, 33kV
MC/DC ABCD type towers
Shoring & Shuttering either with country wooden planks and scantlings or with steel
sheets and props for excavation of pits for tower foundations where ever necessary
12 (Shoring is used when the location or depth of the cut makes sloping back to the Sqm
maximum allowable slope impractical) including cost and conveyance of all materials,
labour charges tools & tackles leads & lifts e.t.c
Qty per One No of
SNO DESCRIPTION UNITS Total Qty RATE AMOUNT
Tower Towers
CIVIL WORKS
M15 Grade Concrete: Providing & Laying of RCC (1:2:4) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
13 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum -
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)
M20 Grade Concrete: Providing & Laying of RCC (1:1.5:3) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
14 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)
M25 Grade Concrete: Providing & Laying of RCC (1:1:2) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
15 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)
Back Filling: Filling of foundation with excavated earth in 150mm thick layers, watering
and consolidating to required density including cost & conveyance of all materials,
19 Cum -
labour charges, leads, lifts , complete as per the directions of the Engineer in charge for
the finished item of work
Boulder Packing packing with Boulders of Size min 300mm filling with CM 1:4 as per
20 Cum
the drawing or as directed by engineer in charge
RR Masonry Wall: Construction of R.R.Masonary in CM(1:6) using hard granite stone
including Flush Pointing in CM1:4, cost & conveyance of all materials, labour charges,
21 Cum
leads, lifts and curing, complete as per the directions of the Engineer in charge for the
finished item of work .
Weep Holes: Supply and fixing of 110 mm dia PVC pipe 4kg/sq cm for weep holes in
22 RR masonary retaining walls including cost and conveyance of material and labour Rm
charges for fixing etc. complete for finished item of work
Total -
Note:
> Type of Soil Considered for estimation is Soft Rock/ F&F Rock
> Type of Tower Considered for Estimation
ABSTRACT QTY AS PER DRAWING ABSTRACT QTY AS PER DRAWING
400 KV "A" type Normal Tower 400 KV "A+3,6,9" type Normal tower
Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC
No of Towers Nos 1 1 1 1 1 1 1 1 No of Towers Nos 1 1 1 1 1 1 1 1
Excavation Cum 200.11 318.00 389.45 465.95 191.42 284.75 404.84 577.47 Excavation Cum 211.12 333.71 407.58 488.84 203.19 300.23 427.64 602.93
PCC Cum 5.63 9.20 11.45 13.83 7.46 10.77 14.98 63.77 PCC Cum 5.96 9.72 12.00 14.54 7.88 11.32 15.77 18.12
RCC Cum 22.50 34.18 41.55 51.60 29.38 40.97 55.62 17.32 RCC Cum 26.14 37.28 45.24 54.12 29.64 41.87 56.75 67.33
Reinforcement MT 2.13 3.30 4.02 4.50 2.62 3.63 4.83 5.70 Reinforcement MT 2.16 3.52 4.24 4.95 3.07 4.29 5.76 6.31
Where top layer upto 1.5 m below G.L. is normal dry soil and
20
thereafter hard soil/murrum
Black Cotton
Black Cotton
Wet
Wet
Partially submerged
Fully Submerged
Special foundation
Hard Rock
Composite Foundation
Hard Rock
Soil investigation is to be
carried out and special
foundation design to be
developed.