Вы находитесь на странице: 1из 7

Qty per One No of

SNO DESCRIPTION UNITS Total Qty RATE AMOUNT


Tower Towers
CIVIL WORKS
Detailed Survey: Which included follwing activities like pegging, Providing survey Pillar
at an interval of 2-3Km in the route, jungle clearance for survey, tree cutting whever
1 necessary, preparation of approved route on graph sheet and marking of offset on Line Kms -
either side of line as per the procedure/Technical Specification and as directed by
Engineer Incharge
Check Survey: Re Checking of the approved profile, chainage, marking of tower centre
2 line, Pit marking, bisection of angle tower as required at site as per the Line Kms -
procedure/Technical Specification and as directed by Engineer Incharge

Soil Classification: Making 150mm nominal diameter bore holes at various locations in
soil using suitable approved method of boring including cleaning the bore holes,
collection of samples, observation of ground water level, collection of
3 undisturbed/disturbed sample and back filling of bore holes on completion of work as Loc -
per specification and instruction of engineer in charge of work .The scope also includes
the submission of final report containing the bore log details with classification of soil for
the purpose of providing foundation along with GPS co-ordinates of each boreholes.

Soil Resistivity: Conducting Soil resistivity test along the selected route and submitting
4 the test results in the form of report as detailed in the technical specifications at an Loc -
interval of 1km (4 point ERM method)

Earth work Excavation in Normal Soil foundation in all types of soils including Soft
Disintegreted Rock as defined by IS-1200 in but dry and wet conditions including
shoring and strutting de-watering sub-soil and rain water to keep the excavation dry.
Levelling and dressing the bottom of excavation to correct level and slope., with all
leads and lifts, including cleaning and Grubbing for removal of rank, vegetation, shrubs,
trees, bushes, stumps, weeds, grass including roots, debris, unusable materials, using
5 Cum -
manual or mechanical method and disposal of the same by burning or any other means,
if required bailing /pumping out of water to keep site dry at all times until completion of
work; stepping, dressing, grading, cleaning, removing and excavating loose pockets as
directed etc. all complete as detailed in specification and drawings and as directed by
Engineer-in-charge.compleate all as per drawings, specifications and as directed by
Engineer-in-charge.

Excavation in Hard Rock/ Boulders using breakers and trimming to required level.
Rate shall include for Excavation at required depth at all leads; dressing of sides;
including cleaning and Grubbing for removal of rank, vegetation, shrubs, trees, bushes,
stumps, weeds, grass including roots, debris, unusable materials, using manual or
mechanical method and disposal of the same by burning or any other means, if required
bailing /pumping out of water to keep site dry at all times until completion of work;
6 Cum
stepping, dressing, grading, cleaning, removing and excavating loose pockets as
directed etc. all complete as detailed in specification and drawings and as directed by
Engineer-in-charge.
Note : Hard Rock/ Boulder is a rock fragment usually rounded by weathering,
disintegration and abrasion by water or ice having a maximum dimension in any
direction of more than 600 mm)
Sand filling below the foundations as per the standard specifications of KPTCL in
7 uniform horizantal layers including cost and conveyance of all materials, watering and Cum
ramming, tools & tackles all labour charges all leads and lifts etc
PCC 1:5:10 Providing & Laying of PCC mix using 40mm size Machine Crushed Metal for
foundations including cost and conveyance of all materials labour charges, all leads and
8 Cum
lifts, centering, ramming, curing , complete for finished item of work as per the
directions of the Engineer-in-charge.
PCC 1:4:8 Providing & Laying of PCC mix using 40mm size Machine Crushed Metal for
foundations including cost and conveyance of all materials labour charges , all leads and
9 Cum
lifts, centering, ramming, curing , complete for finished item of work as per the
directions of the Engineer-in-charge.
PCC 1:3:6 Providing & Laying of PCC mix using 40mm & 20mm size Machine Crushed
Metal for foundations including cost and conveyance of all materials labour charges , all
10 Cum
leads and lifts, centering, ramming, curing , complete for finished item of work as per
the directions of the Engineer-in-charge.
Stubs : Setting of stubs in all soils with stub setting templates -Erection of stubs, stub
template fixing of jacks for supporting template alignment and levelling for exact
11 location of stubs of stub setting template, dismantling of template after completion of Towers -
initial curing of C.C movement of template from one location to other location, 33kV
MC/DC ABCD type towers
Shoring & Shuttering either with country wooden planks and scantlings or with steel
sheets and props for excavation of pits for tower foundations where ever necessary
12 (Shoring is used when the location or depth of the cut makes sloping back to the Sqm
maximum allowable slope impractical) including cost and conveyance of all materials,
labour charges tools & tackles leads & lifts e.t.c
Qty per One No of
SNO DESCRIPTION UNITS Total Qty RATE AMOUNT
Tower Towers
CIVIL WORKS
M15 Grade Concrete: Providing & Laying of RCC (1:2:4) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
13 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum -
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)

M20 Grade Concrete: Providing & Laying of RCC (1:1.5:3) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
14 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)

M25 Grade Concrete: Providing & Laying of RCC (1:1:2) using 20mm graded HBG
metal conforming to IS 383 for foundations including centering/shuttering, machine
mixing, placing of concrete, spreading and compacting with vibrator, curing, 12mm
15 Platering with CM 1:3 for exposed concrete pedestals above NGL and cost & conveyance Cum
of all materials labour charges excluding cost of reinforcement steel and its fabrication
charges, complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-456)

Reinforcement: Supply, cutting, bending, placing in position and tying reinforcement


steel of all sizes (TISCO/ SAIL/ VSP make) for RCC works in all heights including cost &
16 conveyance of reinforcement steel, fabrication charges and binding wire with all leads MT
and lifts , complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-1786, IS-2062):Fe 415 HYSD deformed bars TMT

Reinforcement: Supply, cutting, bending, placing in position and tying reinforcement


steel of all sizes (TISCO/ SAIL/ VSP make) for RCC works in all heights including cost &
17 conveyance of reinforcement steel, fabrication charges and binding wire with all leads MT
and lifts , complete for finished item of work as per the directions of the Engineer-in-
charge. (IS-1786, IS-2062):Fe 500 HYSD deformed bars TMT

Cubes for Testing: Casting, curing, transporting and testing of 150mm


x150mmx150mm size cement concrete cubes 1 set consisting of 3 cubes For 28 days
18 Sets -
compressive strength at approved test laboratory including cost andconveyance of all
materials, submission of test reports as directed by the Engineer - In - Chrage.

Back Filling: Filling of foundation with excavated earth in 150mm thick layers, watering
and consolidating to required density including cost & conveyance of all materials,
19 Cum -
labour charges, leads, lifts , complete as per the directions of the Engineer in charge for
the finished item of work
Boulder Packing packing with Boulders of Size min 300mm filling with CM 1:4 as per
20 Cum
the drawing or as directed by engineer in charge
RR Masonry Wall: Construction of R.R.Masonary in CM(1:6) using hard granite stone
including Flush Pointing in CM1:4, cost & conveyance of all materials, labour charges,
21 Cum
leads, lifts and curing, complete as per the directions of the Engineer in charge for the
finished item of work .
Weep Holes: Supply and fixing of 110 mm dia PVC pipe 4kg/sq cm for weep holes in
22 RR masonary retaining walls including cost and conveyance of material and labour Rm
charges for fixing etc. complete for finished item of work
Total -

Note:
> Type of Soil Considered for estimation is Soft Rock/ F&F Rock
> Type of Tower Considered for Estimation
ABSTRACT QTY AS PER DRAWING ABSTRACT QTY AS PER DRAWING
400 KV "A" type Normal Tower 400 KV "A+3,6,9" type Normal tower
Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC
No of Towers Nos 1 1 1 1 1 1 1 1 No of Towers Nos 1 1 1 1 1 1 1 1
Excavation Cum 200.11 318.00 389.45 465.95 191.42 284.75 404.84 577.47 Excavation Cum 211.12 333.71 407.58 488.84 203.19 300.23 427.64 602.93
PCC Cum 5.63 9.20 11.45 13.83 7.46 10.77 14.98 63.77 PCC Cum 5.96 9.72 12.00 14.54 7.88 11.32 15.77 18.12
RCC Cum 22.50 34.18 41.55 51.60 29.38 40.97 55.62 17.32 RCC Cum 26.14 37.28 45.24 54.12 29.64 41.87 56.75 67.33
Reinforcement MT 2.13 3.30 4.02 4.50 2.62 3.63 4.83 5.70 Reinforcement MT 2.16 3.52 4.24 4.95 3.07 4.29 5.76 6.31

400 KV "B" type Normal tower 400 KV "B+3,6,9" type tower


Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC
No of Towers Nos 1 1 1 1 1 1 1 1 No of Towers Nos 1 1 1 1 1 1 1 1
Excavation Cum 400.56 589.00 702.00 828.35 371.17 532.25 733.67 955.53 Excavation Cum 406.17 601.22 717.71 846.54 383.33 541.96 748.88 988.20
PCC Cum 11.79 17.70 21.26 25.22 14.21 19.88 26.90 29.24 PCC Cum 11.97 18.06 21.77 25.79 14.64 20.22 27.42 30.27
RCC Cum 54.26 78.40 93.23 109.19 64.70 88.22 115.97 187.00 RCC Cum 55.59 80.55 94.83 111.59 66.34 89.18 118.18 187.53
Reinforcement MT 6.50 9.00 10.50 12.32 7.34 9.87 13.24 9.70 Reinforcement MT 6.67 9.17 11.05 12.90 7.70 10.28 13.66 10.01

400 KV "C" type Normal tower 400 KV "C+3,6,9" type tower


Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC
No of Towers Nos 1 1 1 1 1 1 1 1 No of Towers Nos 1 1 1 1 1 1 1 1
Excavation Cum 472.00 689.00 820.33 964.20 454.11 672.24 869.66 1091.80 Excavation Cum 485.76 710.24 842.50 990.40 466.44 641.13 878.27 1110.34
PCC Cum 14.02 20.85 24.96 29.52 16.79 24.34 31.11 33.56 PCC Cum 14.45 21.49 25.66 30.35 17.21 23.72 31.89 34.15
RCC Cum 69.26 91.15 106.64 123.56 79.69 110.06 137.44 234.89 RCC Cum 70.77 97.86 114.35 132.84 81.57 112.46 147.52 238.84
Reinforcement MT 7.90 12.00 14.36 17.09 9.10 12.95 16.48 11.01 Reinforcement MT 8.57 11.94 14.40 16.94 9.55 12.27 16.48 11.44

400 KV "D" type Normal tower 400 KV "D+3,6,9" type tower


Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC Type of Soil>> UOM Dry Wet PS FS DFR WFR SFR WBC
No of Towers Nos 1 1 1 1 1 1 1 1 No of Towers Nos 1 1 1 1 1 1 1 1
Excavation Cum 613.77 883.00 1041.60 1217.56 597.85 828.38 1117.34 1375.97 Excavation Cum 623.69 898.12 1055.18 1234.68 609.87 844.55 1129.26 1386.35
PCC Cum 18.44 27.00 31.90 37.56 21.67 140.04 190.12 42.60 PCC Cum 18.77 27.42 32.40 38.10 22.08 30.14 39.92 42.93
RCC Cum 98.13 135.00 157.13 181.94 106.67 29.58 39.44 249.25 RCC Cum 103.08 144.23 168.06 194.56 108.21 142.23 202.34 253.31
Reinforcement MT 10.10 15.10 17.82 21.07 13.01 17.63 22.44 18.81 Reinforcement MT 10.14 14.70 17.40 20.79 13.48 18.65 21.82 18.55
SL Name of soil encountered
1 In good soil (silty sand mixed with clay)
Where top layer of Black Cotton soil extends upto 50% of the
2
depth with good soil there after.
Where top layer of black cotton soil exceeds 50% and extends
3
upto full depth or is followed by good soil.
Where top layer is good soil upto 50% of the depth but the
4
lower layer is a black cotton soil
Where subsoil water is met at 1.5 ml or more below the ground
5
level in good soil
Good soil locations which are in surface water for long period
6 with water penetration not exceeding 1.0 m below ground level
(e.g. paddy fields).
In good soil where subsoil water is encountered between
7
0.75m and 1.5m depth from ground level.
In good soil where subsoil water is encountered within 0.75m
8
depth from ground level
Where top layer of normal dry soil extends upto 85% of the
9
depth followed by fissured rock without presence of water.
Where top layer is lissured rock followed by good soil/sandy
10
soil with/without presence of water

Where normal soil/tissured rock extends upto 85% of the depth


11
followed by hard rock

Where fissure rock os encountered with subsoil water within


12 0.75m or below 0.75m from G.L. (Top layer may be either a
good soil or black cotton soil)
Where Hard Rock is encountered at 1.5 m or less below
13
ground level.

Where Hard Rock is encountered from 1.5 m to 2.5m below


14
G.L. (Top layer being good soil)

Where hard rock is encountered from 1.5m to 2.5 m below


15
G./L. (Top layer either in Black cotton) soil or fissured Rock

Where fissured rock is encountered at the bottom of pit (with


16
black cotton soil at top)

Where hard rock is encountered at bottom with water and black


17
cotton soil at top and hard rock layer depth is less than 1.5 m.
18 Sandy soil with clay content not exceeding 10%
19 Sandy soil with water table in the pits

Where top layer upto 1.5 m below G.L. is normal dry soil and
20
thereafter hard soil/murrum

Where bottom layer is marshy soil with top layer of good


21
soil/fissured rock/black cotton

Where the top layers are a combination of clinker mixed with


22 firm soil, gravel and stone chips upto 60% of foundation deapth
from ground level followed by hard murrum

Where top layers are combination of hard murrum, soft rock


23
etc. followed by yellow/black clayee soil
Type of foundation to be
adopted
Normal Dry
Partial Black Cotton

Black Cotton

Black Cotton

Wet

Wet

Partially submerged

Fully Submerged

Dry Fissured Rock

Special foundation

Dry fissured Rock with under


cut in Fisured Rock combined
with anchor bar for hard rock
design

Submerged Fissured Rock

Hard Rock

with chimney for Normal Soil


Hard Rock Foundation

Hard Rock Foundation design


with chimneys designed for
wet black cotton soil.

Composite Foundation

Hard Rock

Dry Sandy soil foudation


Wet sandy soil design to be
developed considering the
depth of water

Normal dry with undercut

Soil investigation is to be
carried out and special
foundation design to be
developed.

Normal dry with undercut

Special foundation design is


to be developed after carrying
out soil investigation.

Вам также может понравиться