Академический Документы
Профессиональный Документы
Культура Документы
1
2
COST PLAN AND PRELIMINARY ESTIMATE
INTRODUCTION
The Cost plan and the corresponding outline specification as shown below indicate the allocated cost target for the various elements
which if approved shall form the basis for the detail design.
The Estimated Cost of the African Reinsurance Office complex amounts to N12,887,882,821.23 (Twelve Billion, Eight Hundred
and Eighty Seven Million, Eight Hundred and Eighty Two Thousand, Eight Hundred and Twenty -One Naira, Twenty Three
Kobo. ) Only
The Estimates are upon the prevailing market price of materials and labour.
3
CONTENTS
4
The Estimates exclude the following under listed items, but we make reasonable cost forecast to cushion those items as need arises.
Completed application forms are to be accompanied with photocopies of title documents such as
Certificate of Occupancy or Right of Occupancy with receipts of payments
Title Deed Plan (TDP) properly prepared plans on standard A3 size in 3 copies drawn to scale of
not less than 1:500 site plan and floor plans of 1:200 and 1:100 architectural drawings.
All Plans and Report are to be sealed by the relevant Professional and submitted both in hard and
soft copies.
(2) Unprecedented Inflation - cannot be determined now but projection of 1.6% for the total ETC should be set
aside
6
1.0 DESCRIPTION OF PROJECT
The Proposed African Reinsurance Corporation is located at Central Business District. Abuja.
1) Main Building
7
2) Ground Floor
Diplomatic lounge
Security monitor room
Reception
Exhibition Lounge
Sick bay
Janitors
Toilets
Garden
Shop
Stairs
Lift / Lift lobby
Entrance lounge
Main lobby
Panty
Kitchenette
Buffet square
Staff canteen
Info desk
Ventilation corridor
Services
Car Park (7Nrs)
Emergency exit
Greens
Green Pots
Water cascade
8
3) First Floor (Ancillary Floor)
Lift / Lift lobby
Gym/fitness centre
Kitchenette
Toilets
Management canteen
Instructor
Info desk
Lobby
Open offices
Staff training centre
Janitor
Ventilation corridors
Green Area
Green pots
9
5) Fifth Floor (Executive Floor 01)
Lift / Lift lobby
Meeting room 01
Server
Data Centres
Toilets
Battery
Open offices
Info desk
Lobby
Green pots
Janitor
Ventilation corridors
Archive section 01
Stairs
10
7) Seventh Floor (Executive Floor 03)
Lift / Lift lobby
Meeting Room 03
Garden
Board Room
Library
Refreshment/Preparation/Pre-function room
Toilets
Open offices
Info desk
Lobby
Green pots
Janitor
Ventilation corridors
Stairs
12
1.0 PROPOSED AFRICAN REINSURANCE CORPORATION, OFFICE COMPLEX ,ABUJA
The breakdown of the Assumed specification used and the summary of the estimates are given below in elemental form:-
TOTAL
PILING
1 01 General requirement, piling works, pile cap, Ramp and Retaining wall 262,856,278.00
SUBSTRUCTURE/BASEMENT
1 02 Excavation and earthworks, laterite and hardcore, raft foundation, Basement 944,781,500.31
1 suspended slab 200mm thick, Beam in basement, reinforced concrete
column, Blockwall, Ground floor slab 200mm thick, Beam in ground floor,
liftwall in basements , staircase in basement, polythene, expansion, BRC
and additional works in foundation
FRAME
1 03 Reinforced concrete beam, lift wall and reinforced concrete column. 261,183,066.63
13
UPPER FLOORS
STAIRCASE
1 05 Reinforced concrete staircase, Granite floor finishes treads/risers & landing, 41,189,053.71
, rendering, screeding and emulsion paint to soffit of stair and landing.
1 06 Reinforced concrete roof beam, reinforced concrete suspended roof slab, 135,931,745.00
gutter slab and parapet, single layer felt waterproofing membrane with
backing, steel entrance canopy and roof drainage.
EXTERNAL/INTERNAL WALLS
1 07 Sandcrete hollow blockwall, window concrete box fins and reinforced 142,237,411.99
concrete lintel
1 08 Powder coated aluminium profile and tinted glazing with flyscreen as 1,727,098,260.70
sliding windows, curtain wall, aluminium sun breaker and sub frame
14
DOORS
1 09 Aluminium doors/Entrance doors, door, frame and ironmongery, sundries 121,490,924.15
and name plate
FINISHES
Floor Finishings
1 10 Vitrified ceramic floor tiles on screeded bed, granite finishes in public area, 251,917,049.15
raised floor, epoxy resin floor in controls, green pot, green cascade and
Garden
Wall Finishings
1 11 Glazed ceramic wall tiles on screeded backing, rendering, P.O.P screeded 246,117,456.65
wall internally, emulsion paint on rendered surfaces internally/externally
and Aluco bond cladding.
Ceiling Finishings
1 12 Armstrong suspended ceiling and Armstrong cellio Aluminium ceiling strips 587,749,500.00
in basement.
1 13 Stainless hand railing with glass and Aluminium duct cover grille. 19,125,000.00
15
SERVICES
Electrical Installation
1 12 Internal lightening fittings and switches, Internal power and A/C socket 2,753,687,315.53
outlets, uninterruptible power supply, distribution boards and RCCB’S, MV
Panels, Busbar Riser, MV Cabling, Fire detection and Alarm and public
system, External lightening, Lightening protection, Sundries, Complete
generator system, security system, ICT system, Solar Panel, Energy floor
and Sound responsive lightening.
Mechanical Installation
1 13 Sanitary fittings, cold water supply and distribution, water storage, treatment 2,158,204,382.45
and pumps, bore holes, soil/waste water drainage, storm water drainage,
kitchen equipment, fire fighting, air conditioning and ventilation, lift
installation, water heating and ventilation corridor.
16
PRELIMINARIES
1.15 Fixed preliminaries cost item, Running cost items & terminal cost items 822,119,812.25
CONTIGENCIES
1.16 Unforeseen circumstances 443,944,698.62
RESIDENCY FEES
1.18 Residency fees for Architect ,Structural Engineer, Quantity Surveyor, 120,000,000.00
Mechanical Engineer & Electrical Engineer
1.19 VAT
Statutory Value added tax @ 5% 613,708,705.77
17
FEASIBILITY STUDY
18
SPACE DISTRIBUTION
19
SPACE DISTRIBUTION
PROPOSED AFRICAN REINSURANCE CORPORATION AT CENTRAL BUSINESS DISTRICT ABUJA
S/no Floor Descriptions Total Area per Rentable area per square Usage pattern
square Meter Meter
a Basement 1 4144
b Basement 2 3914
c Ground floor 1980 1351 Commercial/Ancillary
d First floor 1291 1014 Commercial/Ancillary
e Second floor 1980 1656 Rentable floor
f Third floor 1980 1661 Rentable floor
g Fourth floor 1980 1653 Rentable floor
h Fifth floor 1980 1653 Executive floor
i Sixth floor 1980 1653 Executive floor
j Seventh floor 1980 1372 Executive floor
k Eighty floor 2016 1678 Executive floor
l Ninth floor 584 448 Executive floor
Total Area 25809 14139
20
Total 25809 square meter
Construction
Area
Total Rentable 14139 square meter
Area
Percentage of 54.78%
area to be rent
out
Available Land 5856.02 Square meter
Area
21
EXPECTED RENTAL INCOME
22
Expected Rental Income.
The propose site is in the heart of the city, our pricing formulas are determined by the availability of similar
construction and rental charge, level of demand for the office space.
Cost per Square meter for renting standard office space depending on the facilities available, from our findings down
floors is comparatively higher than the upper floors. We have considered the average charge of top and bottom floors.
For the purpose of this exercises our benchmark is N80, 000.00 per square meter.
23
Expected Rental Income calculation
Executives’ floor
Executives floor Rentable area Cost per square metre Total Expected income
(sq.m) /rentable floor per annum per annum
Amount
Executives floor 6804 80,000.00 N 544,320,000.00
24
AVERAGE RUNNING COST
25
Average running cost is the amounts sets aside for maintaining the premises and makes the entire office functional. The
fees is usually in the regions of 5-10% of the cost per square meter per rentable area
26
Average Running cost calculation
Executives’ floor
Executives floor Rentable area (sq.m) Cost per square metre Total Expected income
/rentable floor per annum per annum
Amount
Executives floor 6804 4,000.00 N 27,216,000.00
27
ESTIMATED PAYBACK PERIOD
28
S/no Stages Measure Rental value
/Earning per year
A Construction 1st -4th NILL
stages year
B Rental stages
1 1st year 1,131,120,000.00
2 2nd year 1,131,120,000.00
3 3rd year 1,131,120,000.00
4 4th year 1,131,120,000.00
5 5th year 1,131,120,000.00
6 6th year 1,131,120,000.00
7 7th year 1,131,120,000.00
8 8th year 1,131,120,000.00
9 9th year 1,131,120,000.00
10 10th year 1,131,120,000.00
11 11th year 1,131,120,000.00
12 12th year 1,131,120,000.00
Total N13,573,440,000.00
For the purpose of this exercises, we are not considering rent increase after certain period of years say 5
year to 10 year which can attract between 20%-45% increase depending on the economy status as of that
29
time. From our findings, Not all the space can be fully occupy at once this can take like 3 year for
maximum occupying of the space there by dropping the net rent earning for like 2 % to 5%.
Approximate 12 years
30
CONCLUSION
We find that this project is necessary cost effective and feasible from a technical and engineering stand point.
Pricing parameter is determined availability of similar construction and rental charge, the level of demand for the
product, and total costs required to complete the project.
31