Problem A:

In a 5day-week (8hrs each day), a subcontractor accomplished 368 sq.m of formworks and
21102 of rebar-works. The subcontractor has 14 skilled carpenter, 17 skilled steelmen. Each
skilled worker has one unskilled labor helper and one foreman each group. Foreman, Skilled ad
Unskilled are paid Php607, Php507, Php407 daily (8hrs-day) respectively.

a) Compute for the total labor hour for :


Rebar-works Ans. 1,400.00 LH
Forworks Ans. 1,160.00 LH
b) Compute for the productivity rate of:
Rebar-works Ans. 0.0663 LH/kg
Forworks Ans. 3.1522 LH/sqm
c) Compute for the total cost per accomplishment:
Rebar-works Ans. 3.825 Php/kg
Forworks Ans. 182.106 Php/sqm

Problem B:
If the same subcontractor has another construction site and wishes to estimate the length of time
to finish a job with 13257m2 of formworks and 486872 kg of reinforcing steel with same
amount of manpower as the other site.

a) How long to finish all of the:


formworks 1,440.98 Ans. 181.00
rebar-works 922.89 Ans. 116.00
b) How much would be the total billing for:
formworks Ans. ₱ 2,414,178.95
rebar-works Ans. ₱ 1,862,512.66

Problem C:
If the same contractor has another construction project that have 7986 sqm of formworks and
281078 kg or rebar to install. They target to finish the formworks and rebarworks each in 300
standard days. Compute how many skilled carpenter and skilled steelmen are required to finish
the job on time if each skilled worker has at least one skilled labor helper and each group has
one foreman.

a) :
Carpenters = Ans. 5 men
Steelmen= Ans. 4 men
b) How much would be the total break-even billing for:
formworks Ans. ₱ 1,454,298.34
rebar-works Ans. ₱ 1,075,254.55
Problem A:
A subcontractor has 14 carpenters and 13 steelmen, each having at least one labor helper and each
group is headed by a foreman. The foreman, skilled and unskilled worker are paid Php 594,Php
494, Php 394 per day (8hr-day). In one week of 7 days (8hrs each day), accomplished 475 sq.m of
formworks and 27221 kg of rebar-works.

a) Compute for the total labor hour for :


Rebar-works Ans. 1,512.00 LH
Forworks Ans. 1,624.00 LH
b) Compute for the productivity rate of:
Rebar-works Ans. 0.0555 LH/kg
Forworks Ans. 3.4189 LH/sqm
c) Compute for the total cost per accomplishment:
Rebar-works Ans. 3.121 Php/kg
Forworks Ans. 191.962 Php/sqm

Problem B:
Another project was awarded to the same subcontractor which have formworks and rebar-works
estimated upto 13210 sqm and 250395 kg, respectively. With the same amont of manpower as the
former project.

a) How long to finish all of the:


formworks Ans. 195.00 days
rebar-works Ans. 65.00 days
b) How much would be the total break-even billing for:
formworks Ans. ₱ 2,535,819.41
rebar-works Ans. ₱ 781,567.96

Problem C:
Another project was awarded to the same subcontractor. The project has an estimated 239298 kg ,
8198 sqm of rebar-works and formworks, respectively. Given that both of each works should be
done in 300 days. Determine how much carpenter and steelmen are needed if each has one labor
helper and one foreman heading each group.

a) :
Carpenters = Ans. 6 men
Steelmen= Ans. 3 men
b) How much would be the total break-even billing for:
formworks Ans. ₱ 1,573,705.34
rebar-works Ans. ₱ 746,930.45
Problem A:
In a 7day-week (10hrs each day), a subcontractor accomplished 191 sq.m of CHB to lay and 178
sqm of wall to plaster. The subcontractor has assigned 6 skilled CHB Layers, 5 skilled Plasterers.
Each skilled worker has one unskilled labor helper and one foreman each group. Foreman, Skilled
ad Unskilled are paid Php521, Php421, Php321 daily (8hrs-day) respectively.

a) Compute for the total labor hour for :


Plastering Ans. 770.00 LH
CHB laying Ans. 910.00 LH
b) Compute for the productivity rate of:
Plastering Ans. 4.3258 LH/kg
CHB laying Ans. 4.7644 LH/sqm
c) Compute for the total cost per accomplishment:
Plastering Ans. 207.98 Php/kg
CHB laying Ans. 227.82 Php/sqm

Problem B
If the same subcontractor has another construction site and wishes to estimate the length of time to
finish a job with 1688sqm of CHB to lay and 1121sqm of walls to plaster with same amount of man
power as the other site.

a) How long to finish all of the:


Plastering 618.64 Ans. 78.00
CHB laying 440.84 Ans. 56.00
b) How much would be the total billing for:
Plastering Ans. ₱ 384,561.31
CHB laying Ans. ₱ 233,150.68

Problem C
If the same contractor has another construction project that have 3449 sqm of CHB to lay and 5962
sqm or walls to plaster. They target to finish them each in 135 standard days. Compute how many
skilled mason are required to finish each job on time if each skilled worker has at least one skilled
labor helper and each group has one foreman.

a) :
Plastering Ans. 8 men
CHB laying Ans. 12 men
b) How much would be the total break-even billing for:
Plastering Ans. ₱ 785,753.53
CHB laying Ans. ₱ 1,240,003.89
Problem A:
A subcontractor has 5 Mason-CHB layers and 5 Mason-Plasterers, each having at least one labor
helper and each group is headed by a foreman. The foreman, skilled and unskilled worker are
paid Php 510,Php 410, Php 310 per day (8hr-day). In one week of 5 days (8hrs each day),
accomplished 168 sq.m of CHB and 193 sqm of plastered walls.

a) Compute for the total labor hour for :


Plastering Ans. 440.00 LH
CHB laying Ans. 440.00 LH
b) Compute for the productivity rate of:
Plastering Ans. 2.2798 LH/kg
CHB laying Ans. 2.6190 LH/sqm
c) Compute for the total cost per accomplishment:
Plastering Ans. 106.48 Php/kg
CHB laying Ans. 122.32 Php/sqm

Problem B
Another project was awarded to the same subcontractor which have CHB Laying and Plastering-
works estimated upto 1362 sqm and 1289 sqm, respectively. With the same amont of manpower
as the former project.

a) How long to finish all of the:


Plastering Ans. 41.00 days
CHB laying Ans. 34.00 days
b) How much would be the total break-even billing for:
Plastering Ans. ₱ 166,601.79
CHB laying Ans. ₱ 137,248.45

Problem C
Another project was awarded to the same subcontractor. The project has an estimated 4390 sqm
of Plastering, 4621 sqm of CHB to lay. Given that both of each works should be done in 187
days. Determine how many mason for each work are needed if each has one labor helper and one
foreman heading each group.

a) :
Plastering Ans. 4 men
CHB laying Ans. 3 men
b) How much would be the total break-even billing for:
Plastering Ans. ₱ 565,247.32
CHB laying Ans. ₱ 467,432.64