Академический Документы
Профессиональный Документы
Культура Документы
2.5 Relevant Standards design. The main difference arises because metocean is
There are a wide range of offshore energy industry stand- now also the resource itself. A diverse range of recent
ards and guidance notes released to inform offshore standards consider some specific requirements for off-
Developers of the importance of metocean data, suitable shore wind, tidal and wave energy.
acquisition methods, and analysis to achieve development
requirements. Some also address resource assessment Some differences exist between the various guidelines,
requirements, design, survivability and environmental for example in relation to wind profile relationships.
impacts. In many cases, metocean information is con- Reliable results may not always be produced by sim-
tained within guidelines with a much broader remit. ply following one guideline, especially if it is out of date
or not relevant to the region or application. A notable
Standards and guidelines have been issued by organisa- example is provided by UK HSE OTR 2001/010 (details
tions such as the International Organization for Stand- in Appendix 1). This was published in 2002, but is only
ardization (ISO), the International Electrotechnical a reissue of Department of Energy Guidance Notes from
Commission (IEC), the International Association of Oil 1990. This is very much out of date and all more recent
and Gas Producers (IOGP) and DNV GL. A summary of standards take precedence, especially those highlighted
some widely used key documents is given below, with a below. Despite this, OTR 2001/010 is still cited in some
more extensive list provided in Appendix 1. offshore renewable energy projects.
Following the historical development of offshore energy, A suitably experienced metocean practitioner must
the first standards originate from the oil and gas indus- ensure appropriate data and methods are used to
try. Most of the metocean content is equally applicable to quantify the key metocean processes of critical engi-
offshore renewables from the perspective of engineering neering impact.
IOGP Report 447 International Association of Oil and Gas Producers, (2011). Health, Safety and
Environmental guidelines for metocean and Arctic surveys, Report No. 477.
Typically, an OR project will be broken down into smaller The briefing note should identify the conditions that
components (or work packages), each requiring special- may prevent the technical feasibility and economic
ist metocean inputs. The metocean process is iterative, viability of a potential project. If a specific risk is identi-
improving in accuracy and quality at every phase of the fied, it may be that further investigation is required at an
project lifecycle, with prior metocean information being early stage of the project.
added to, or superseded, as the project progresses.
3.2 Development and Consents
Due to the importance of metocean input in all aspects Early in the development and consents phase, defini-
of the project lifecycle, it is recommended that any tion of the preliminary metocean dataset is required,
metocean expertise be embedded within, or directly fulfilling the requirements of the project for the pur-
available to, a project development team and close rela- poses of consenting and concept design. This data-
tionships developed with work packages throughout set provides a best estimate of metocean conditions
every phase. A strategy, to be adopted to ensure that based on available measured data or coarse, uncali-
metocean decisions, requirements and products appro- brated, unvalidated model data if insufficient measured
priate to an OR project are delivered throughout its life- data is available, obtained for little or no cost. Online
cycle, is provided in Section 3.7. metocean databases based upon regional metocean
models may be utilised.
It should be noted that the metocean process may be
entwined with energy resource assessment. It is therefore Preliminary data and analyses will generally include:
necessary to consider requirements in each phase from • Conservative, quantified description of conditions at
the resource perspective, as well as that of engineering. a representative location or locations.
• Quantification of potential hazards and assessment
3.1 Site Selection and Feasibility of associated risk.
Within this phase, it is necessary to understand the • Concurrent time series of wind, wave, current and
general metocean conditions across the geographi- water level
cal region of interest, and to identify any conditions or • Derivation of operational, extreme and weather
processes that may pose a significant risk to the project downtime statistics and preliminary loads cases.
(examined further in Section 4).
Preliminary metocean data and analyses will also con-
It is pertinent to conduct a literature review, identify any tribute to other aspects of the project, such as defini-
available data sources in the region, and to summarise tion of the environmental baseline and impact stud-
the information obtained in a short briefing note. The ies regarding foundation impact on metocean regime,
amount of work that is required at this phase depends scour, and sediment dispersion due to piling, seabed
on the lease award process. In some European coun- preparation or cable burial. Estimates of weather down-
tries, much of this work is carried out by the awarding time based on preliminary data will be used to inform
authority. the contractual basis for site characterisation surveys
(such as geophysical and geotechnical).
A briefing note would typically include:
• General description of the proposed site. Requirements for this dataset will be project specific
• Summary of available data sources and data gap as a combined consequence of site conditions, project
analysis. definition, project team and the methodologies used
• Identification of potential hazards. for preliminary design. It is therefore recommended
• Estimates of wind, wave, current and water level that the detailed content of the preliminary engineer-
conditions. ing data and analyses be defined in coordination with
• Recommendations for the intended metocean strategy. the project team.
Data analysisD
Environmental
impact analysisDMS
Full In-situ
engineering measurementS
dataset and
analyses Fully calibrated
modellingM
Data analysisD
Real-time in-situ
measurementS
Strategy optimisation
and condition
monitoringDMS
End of life
assessment
D
Data analysis and desktop studies, including satellite observations M
Numerical hindcast and forecast modelling S
In-situ measurement
Photo credit: Wello
Numerical models provide the required longer term con- Where effects of climate change on site conditions are
text, but require validation and calibration using in-situ understood, those effects should be incorporated into
measurement or satellite observations. Numerical models the metocean analysis, for example, the poleward migra-
and satellite observations both provide valuable spatial tion of tropical cyclones, or changes in sea-ice cover.
coverage, well beyond a limited set of in-situ measure-
ment sites, but have limitations in terms of temporal and Although OR projects need site-specific (and possibly
spatial resolution. As such, a good metocean database is technology-specific) information, a general understand-
the result of careful combination of different data sources. ing of the broader metocean conditions in a region is
Further details are provided in Appendices 3 and 4. useful. These can be found in the regional annexes of
ISO 19901-1 (2015). Metocean processes control all key
4.2 Key Processes metocean parameters, including those relating to wind,
Selected data sources must represent the key metocean wave, current and water level. A summary of specific
processes that impact the development site. These pro- parameters under each of these categories is given in
cesses vary considerably from region to region. the Glossary (Appendix 2).
ORGANISATION URL
BOOS hiip://eurogoos.eu/roos/baltic-operational-oceanographic-system-boos
CMEMS hiip://marine.copernicus.eu
EMODnet hiip://www.emodnet.eu
EuroGOOS hiip://eurogoos.eu
ICES hiip://www.ices.dk
IOOS hiips://ioos.noaa.gov
MEDIN hiip://www.oceannet.org
MDE hiip://www.marinedataexchange.co.uk
NOOS hiip://eurogoos.eu/roos/north-west-european-shelf-operational-oceanographic-system-noos
iMarDIS hiips://www.imardis.org
Figure 2: Website links for respective observational systems and collaborative initiatives
Figure 3: Joint frequency table depicting percentage occurrence of significant wave height versus peak wave period
(courtesy of MetOceanWorks Toolbox)
This allows closer scrutiny of the metocean regime at of two variables, in order to reduce the conservatism
the site, taking into account sheltering from the coast or inherent in combining parameters assumed to be
exposure from the open sea. independent of one another, which is often the case.
As such, it is highly recommended that extreme value
In the earlier phases of the project, operational climate analysis is conducted by persons possessing demon-
may be summarised in less detail. However, as the pro- strable competence.
ject progresses, and particularly in approach to final
design, the full suite of operational climate descriptions The outcomes of extreme value analysis may include,
will be required, including consideration of parameter but are not limited to, the 1, 10, 50, 100, 1000 and 10000
relationships by intensity bins and directionality. It is year return period of relevant metocean parameters,
typical for information to be presented in more than one omni-directional and for each directional sector, all year
way, for example, significant wave height direction vs. and by month. Directional sectors should be 30 degrees
wind direction by wind and wave intensity bins. or lower. Consideration should be given to the pres-
ence of wave breaking, which may limit wave growth for
5.2 Extreme Climate selected sites.
The extreme climate is a statistical description of the
abnormal metocean conditions experienced at the site. 5.3 Weather Windows and Adverse Weather Downtime
Weather window persistence statistics (for example,
Exact values of metocean parameters for a selection Figure 6) may be required by any work package result-
of return periods are derived from statistical meth- ing in offshore works, including survey, civil and struc-
ods of extreme value analysis (see Figure 5). Extreme tural engineering, turbine engineering and cabling.
value analysis theory is complex and evolving, and it
is necessary to understand the drivers of fluctuations Persistence statistics may be requested as part of a
in metocean parameters, such as large scale atmos- metocean study, however, specific combinations of
pheric circulation patterns. To account for inter- operational limits for particular or combined series of
annual variability, it is fundamental that time series operations are difficult to pre-empt early in the pro-
of data to be analysed are both long enough (>30 ject lifecycle. It is therefore recommended that more
years) and have the temporal resolution to capture complex assessments of operability are conducted in
peaks. Extreme value analysis should, where possible, close partnership with logistics and construction plan-
take into account the joint probability of occurrence ning teams.
Dedicated studies with regards to persistence may also Figure 6: Percentage probability of the condition significant
be contracted, once the operational limits and weather wave height (Hs) <1.5m existing for varying weather window
window durations are fully understood. Alternatively, durations.
simulation of the installation programme against time
series may be conducted by a competent practitioner ture). Such derivations should be conducted by special-
to build up probability distributions regarding the likely ist practitioners and may not be within the capability of
time taken to complete the installation sequence. the metocean contractor.
5.4 Input to Design Loads Cases As noted in the introduction, this procedures guide is
In fixed offshore wind, numerous loads cases are con- heavily focused on offshore wind developments involv-
ducted according to the key standards (Section 2.5). The ing a fixed structure, due to relative technical maturity.
majority of loads cases will incorporate descriptions of Many of the general principles will also apply to floating
the combined hydrodynamic and aerodynamic condi- wind, wave and tidal, however, some specific details will
tions impacting upon the structure with varying severity differ. The project team should be consulted at an early
referred to as reference sea states and reference wave stage in order to correctly scope the metocean require-
heights, for example: ments for wave, tidal and floating wind developments,
in conjunction with the available guidance and stand-
• Normal Sea State ards (see Section 2.5).
Characterised by a significant wave height, a peak period
and a wave direction and associated with a concurrent For floating wind energy and wave energy, a major dif-
mean wind speed, such that the significant wave height ference from a metocean perspective will be the charac-
is the expected value for the associated wind speed. terisation of metocean conditions required to quantify
impact upon a floating structure, which reacts dynami-
• Severe Sea State cally to its environment. For example, it is necessary to
Characterised by a significant wave height, a peak characterise details of the full directional wave spectra.
period and a wave direction and associated with a con- A major challenge is designing for platform motion with
current mean wind speed, such that the combined wave corresponding motion of the wind turbine blades, or
height and wind speed has a return period of 50 years. electrical power take-off in the case of wave energy.
• Extreme Sea State With regard to tidal energy, one major difference will be
Characterised by a significant wave height, a peak period the need to characterise ocean turbulence. This is analo-
and a wave direction, wherein the significant wave height gous to the need to characterise atmospheric turbulence
has a specified return period of 1 and 50 years. for wind turbine engineering, but may bring specific
new challenges to the data collection strategy. Potential
The derivation of these sea state scenarios requires tidal energy development sites are situated in regions of
detailed knowledge of structural design in order to strong tidal flow, which are often highly turbulent. Exten-
ensure that the most appropriate combinations of sive guidance for characterisation of ocean turbulence for
parameters are applied (for example, taking into current turbine engineering are available from the Car-
account the eigen-frequency sensitivity of the struc- bon Trust-funded (TiME) project (see Appendix 1).
Device type and number required Define preferred device of known, and
number of locations
Data Delivery: Raw and processed Raw and/or processed data archive
archive required and spec
HSE Plan A full HSE plan is required for all Detailed HSE plan to be provided
offshore works ahead of each offshore activity.
Parameters required Define parameters required Depth averaged current speed and
direction
Intended use of data Define onward use of data (design criteria, Construction support
operational support, structural integrity)
Deployment duration Define how many months data should 2 years starting March 2015
be collected and start date
Device type and number required Define preferred device of known, and Bottom mounted ADCP x1
number of locations
Sampling depths Define levels (relative to seabed OR Entire water column at 1m intervals
surface) that data is required. with first data 2m from surface
Servicing interval If required define servicing interval Equipment to be serviced at least once
every six months. Contractor to define
required servicing interval
Final report Define report requirements in detail Full report to company standard as
defined in Appendix Y* required within 4
weeks of equipment demobilisation.
Interim reports Is interim reporting required? When? Interim data reports to be supplied
within 1 month of service visits.
Deployment reports Are deployment reports required? Deployment reports detailing final
location, time of deployment and
vessel schedule, conditions at time of
deployment.
Emergency response reports Are emergency response reports In the event of an emergency, such
required? as missing equipment, reporting
detailing all aspects of recovery and
redeployment.
Data Delivery: Real Time Yes/no? If yes then define where Real time data to be displayed on
require. WWW within 15 minute of collection.
Data also required via direct radio link
on Vessel “Big Crane”
Data Delivery: Raw and processed Raw and/or processed data archive Archived data should be delivered in
archive required and spec .ascii format.
Sediment Client
distribution