Вы находитесь на странице: 1из 2

Material Supplier Qualification Process Issue Purchase Order Signature and Delivery

Description Start Date Finish Date Days Description Start Date Finish Date Days

Gate Equipments 13-Jul-20 8-Dec-20 148


(Gates Included)

Utility Networks and Utility Networks and


External Areas 31-Dec-19 12-Nov-20 312 External Areas 1-Jan-20 19-Feb-21 409
Material Materials

Sewerage Network
Manholes and Covers 31-Dec-19 2-Feb-20 30 and Sewage 17-Mar-20 1-Dec-20 258
Treatment System
Reused Rainwater 11-Mar-20 16-Oct-20 218
System

Main Water Tank,


Feed and Water Wells 6-Feb-20 4-Sep-20 211

Pipes for Stormwater 5-Jan-20 2-Feb-20 25 Pipes for Stormwater 2-Feb-20 20-Feb-20 18
Manholes and Covers 2-Feb-20 20-Feb-20 18

Helipad Light 6-Jul-20 9-Feb-21 216

Road/Safe/Direction 29-Jun-20 19-Feb-21 233


Signs

KerbStone 29-Apr-20 9-Jul-20 70 KerbStone 11-Sep-20 11-Nov-20 60


Pavement Asphalt 30-May-20 8-Aug-20 70 Pavement Asphalt 8-Aug-20 7-Nov-20 90
Pavement Block 29-Jun-20 7-Sep-20 70 Pavement Block 7-Sep-20 7-Oct-20 30

Landscaping Lighting 10-Feb-20 16-Sep-20 219


Sod, Shrub and Tree Sod, Shrub and Tree 11-Sep-20 12-Nov-20
10-Jan-20 18-Mar-20 65 61
(landscape) (landscape)

Sports 1-Jan-20 29-Jan-21 388

Вам также может понравиться