1. CONTRACTOR MUST SET-OUT THE PLAN ON 12.CONTRACTOR MUST VERIFY CLEARANCES OF 22.ALL WATERPROOFING WORKS & ENSUING
SITE AND VERIFY IF THERE ARE ALL CEILING HEIGHTS PRIOR TO LEAK TESTS SHALL BE CHECKED &
DISCREPANCIES BETWEEN INTERIOR DESIGN CONSTRUCTION TO ENSURE CONFORMITY TO APPROVED BY ABI PRIOR TO CONTINUATION
SET-OUT & EXISTING ARCHITECTURAL SHELL; DESIGN OF WORK.
2. CONTRACTOR MUST CONFIRM 13.USE 12MM THICK ORDINARY GYPSUM BOARD 23.SHOP DRAWINGS & MOCKUPS OF RAILINGS,
CORRECTNESS OF ALL ACTUAL SET-OUT ON ALL AREAS EXCEPT FOR BATHROOM & LADDER AND OTHER METALWORKS SHALL BE
PRIOR TO INSTALLATION OF PARTITIONS / WET AREAS. THESE SHALL USE 13MM THICK SUBMITTED FOR ABI APPROVAL PRIOR TO
FRAMES; MOISTURE RESISTANT GYPSUM BOARD. ALL FABRICATION / INSTALLATION.
3. ALL DISCREPANCIES SHALL BE ADDRESSED & CEILING SYSTEMS MUST BE ON METAL 24.FIRE EXIT DESIGN BY ABI MUST BE
DISCUSSED WITH ABI, PRIOR TO FURRING SYSTEM ADEQUATELY FIXED TO RECONCILED W/ THE FIRE CODE OF THE
COMMENCEMENT OF WORK. STRUCTURE PHILIPPINES FOR TECHNICAL STANDARDS
4. ALL LIGHTING FIXTURES & FITTINGS SAMPLES 14. VERIFY DOOR SCHEDULE FOR DOOR DESIGN COMPLIANCE. ANY DISCREPANCIES SHOULD
MATCHING ABI'S SPECS SHOULD BE & SPECIFICATIONS; VERIFY FLOOR PLANS BE DISCUSSED W/ ABI.
APPROVED AND TESTED ON SITE FOR LIGHT FOR REQUIRED DOOR & WINDOW 25.ALL SPECIFICATIONS FOR MECHANICAL
ADEQUACY PRIOR TO PURCHASE & QUANTITIES; WORKS & INSTALLATION SHOULD BE
INSTALLATION. 15.COORDINATE ALL MEPS AND AUXILIARY CONSULTED W/ THE MECHANICAL ENGINEER
5. ALL SAMPLE FINISHES SHOULD BE REQUIREMENT, LOCATIONS & HEIGHTS AND TO ENSURE ADEQUATE CAPACITY AS
SUBMITTED FOR ABI APPROVAL PRIOR TO COORDINATE WITH ABI ANY CONFLICT OR REQUIRED BY OWNER.
ANY PURCHASE, FABRICATION OR DESIGN ISSUE PRIOR TO INSTALLATION; 26.ALL SPECIFICATIONS FOR STRUCTURAL
INSTALLATION. 16. ALL FIRE HOSE CABINETS MUST BE WORKS & FABRICATION SHOULD BE
6. CONTRACTORS MUST STRICTLY COMPLY ADJUSTED AS NECESSARY TO SUIT THE NEW CONSULTED W/ THE STRUCTURAL ENGINEER
WITH ALL THE REQUIREMENTS & STANDARDS CABINET DESIGN BY ABI, CONTRACTOR MUST TO ENSURE ADEQUATE STRUCTURAL
SET BY THE ADMINISTRATION AND THE ENSURE SPECIFICATIONS FOR TECHNICAL INTEGRITY.
MUNICIPALITY HAVING JURISDICTION OVER STANDARDS CONFORM TO THE FIRE CODE OF 27.WALL FINISH SHALL BE ADEQUATELY
THE PROJECT. THE PHILIPPINES. FASTENED TO THE BUILDING WALL AND
7. ALL CORNERS OF THE METAL CLADDING 17.CONTRACTOR MUST VERIFY SPECIFICATIONS CEILING SYSTEM, PROVIDE COLOR SAMPLE
PANELS SHOULD BE MACHINE FOLDED. FOR ELEVATOR DOORS, JAMB, INDICATORS AND SHOP DRAWINGS FOR APPROVAL.
8. ALL FINISHES AND MATERIALS SHOULD BE AND BUTTONS / CONTROLS; 28.SHOP DRAWINGS, MATERIAL SAMPLES AND
ADEQUATELY FIXED TO THE BUILDING 18.SET-OUT FOR FLOOR DRAINS, BATHROOM MOCK-UP SHOULD BE PROVIDED FOR
SYSTEM, CONTRACTOR TO PROVIDE SHOP FIXTURES AND FITTINGS SHALL FOLLOW ABI APPROVAL PRIOR TO PROCUREMENT AND
DRAWINGS FOR APPROVAL. SPECIFICATIONS, OTHERWISE, CONTRACTOR INSTALLATION.
9. ALL SAMPLE FINISHES SHOULD BE SHALL COORDINATE & ASK ABI APPROVAL 29.ALL CORNERS OF THE METAL CLADDING
SUBMITTED FOR ABI APPROVAL PRIOR TO PRIOR TO FINISHING; PANELS SHOULD BE MACHINE FOLDED.
ANY PURCHASE, FABRICATION OR 19.SUBMIT SHOP DRAWINGS OF ALL STONE OR 30.ALL FINISHES AND MATERIALS SHOULD BE
INSTALLATION. TILE PATTERN FOR ABI'S APPROVAL PRIOR ADEQUATELY FIXED TO THE BUILDING
10. CONTRACTOR MUST PROVIDE SHOP TO INSTALLATION; SYSTEM, CONTRACTOR TO PROVIDE SHOP
DRAWINGS FOR ALL FLOOR PATTERNS AND 20.ALL EXPOSED CORNERS, STONE AND TILED DRAWINGS FOR APPROVAL.
CUTTINGS PRIOR TO FABRICATION AND JOINTS OF WALL FINISHES MUST BE MITERED; 31.THIS DOCUMENT SHOULD BE READ IN
INSTALLATION 21.ROOF SYSTEM SHOULD RESIST 250KPH WIND CONJUCTION WITH THE ARCHITECTS
11. CONTRACTOR MUST VERIFY ALL DOOR LOADS. SHOP DRAWINGS & MOCKUPS OF STANDARD TECHNICAL SPECIFICATIONS.
THRESHOLD, MATERIAL & TERMINATIONS OF GUTTERS & PROFILES SHOULD BE
ABI FINISHES; SUBMITTED FOR ABI APPROVAL PRIOR TO
FABRICATION / INSTALLATION.