Академический Документы
Профессиональный Документы
Культура Документы
DEVELOPMENT PROJECT
ENVIRONMENTAL MANAGEMENT
PLAN
Public Disclosure Authorized
TABLE OF CONTENTS
1. INTRODUCTION................................................................................................. 3
1.1. Project Background ........................................................................................ 3
1.2 Objective, Strategy and Performance Indicator of EMP ............................... 3
1.2.1 Objective ..................................................................................................... 3
1.2.2 Strategy and Performance Indicator ............................................................. 4
1.3 Legal Basis and Applicable Standards ............................................................ 5
1.3.1 Legal Basis .................................................................................................. 5
1.3.2 Executive Standards..................................................................................... 8
1.3.3 Responsibility and Function of the Management Institutions ......................17
2. PROJECT DESCRIPTION.................................................................................18
2.1. Name, Features and Location of the Project.................................................18
2.2. Project Components.......................................................................................18
Page 1
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 2
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
1. INTRODUCTION
1.1. Project Background
The Word Bank (WB) financed Hanoi Urban Transport Development Project
(HUTDP) is an important component in the Master Plan of Urban Traffic of Hanoi
People’s Government for improvement of the urban traffic. This project will play an
important role in solving the three problems that Hanoi City is facing, improving the
urban ambient air quality and living conditions of the residents. It will stimulate the
coordinated social, economic and environmental development of Hanoi City.
The Environmental Impact Assessment of this project shows that the project will
negatively impact the environmental conditions along the project roads and in some
regional areas. However, it will positively impact the ambient air quality as well as the
control of the atmospheric pollution in the whole urban area, especially in the densely
populated central urban area. The Environmental Management Plan (EMP) of this
project, as a part of the environmental impact assessment documentation of HUTDP, is
one of the important documents requested by WB. The purpose of EMP is to ensure
the implementation of the mitigation measures proposed in EIA. For the project to be
environmental feasible, the necessary mitigation measures must be implemented.
Page 3
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Overall objective: maintaining the sustainability of the urban social economic and
environmental development, improving the urban environmental quality, and
minimizing and reducing or otherwise compensating adverse impacts to the
communities and the environment. The detailed actions and indicators are as follows.
Actions:
- Developing and implementing an EMP and monitoring program
- Developing and implementing the MVECS to mitigate the impact on the
ambient air
Indicators:
- Inspecting the monitoring results of the monitoring factors listed in the
environmental monitoring program during the construction and operation
phases
- Implementing all the environmental mitigation measures developed in the EIA
according to the specified schedule
- Developing the Motor Vehicle Emission Control Strategy (MVECS)
Page 4
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 5
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Water Legislations:
- The Building Code of Vietnam: was issued in 1997 which is a paralegal
document stipulating the minimum technical requirements mandatory to all
construction activities, the solutions and the standards that must be applied to
meet the requirements of the Building Code. Drainage and sewerage systems
are regulated under the Chapter 5: Urban Planning as follows:
- Article 5.17: Drainage systems
5.17.1: The urban drainage system;
5.17.2: Selection of type of sewer system
5.17.3: Storm water drainage
5.17.4: Conditions for sewage discharge
5.17.5: Waste treatment plants and water pumping stations
It stipulates that sanitary sewage from toilets (of housings, public and industrial
buildings) and hospital sewage must be treated through septic tanks, constructed
compliant with standards before discharge to urban drainage.
- Law on Water Resources dated May 20, 1998.
- Decree No. 149/2004/ND-CP, 2004, Government Decree on regulation on
licensing of water resources exploitation, extraction and utilisation and waste
water discharge in water sources: The Decree shall regulate the issue,
extension, amendment, termination and revoking of permits on exploration,
extraction, exploitation, utilisation of water resources and waste water
discharge into water sources.
Page 6
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 7
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
N° Title
1 Water Quality Standards
2 TCVN 5942-1995: Water Quality - Surface Water Quality Standard
3 TCVN 5943-1995: Water Quality - Coastal Water Quality Standards
4 TCVN 5944-1995: Water Quality - Ground Water Quality Standards
2 Environmental Standards
1 20 TCN-51-84: This set of National Standards replacing the 20-TCN-51-72, entered
into force on 22nd September 1984. It provides the design standards for the off-site and
on-site drainage and sewerage networks including septic tanks.
2 TCVN 5945: 1995: Industrial Wastewater – Discharge standards.
3 TCVN 6772: 2000: Water quality – Domestic wastewater standards.
4 TCVN 6773: 2000: Water quality – Water quality guidelines for irrigation.
Page 8
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
5 TCVN 6774: 2000: Water quality – Freshwater quality guidelines for protection of
aquatic sites.
6 TCVN 6980: 2001: Water quality – Standards for industrial effluents discharged into
rivers used for domestic water supply.
7 TCVN 6981: 2001: Water quality – Standards for industrial effluents discharged into
lakes used for domestic water supply.
8 TCVN 6982: 2001: Water quality – Standards for industrial effluents discharged into
rivers used for water sports and recreation.
9 TCVN 6983: 2001: Water quality – Standards for industrial effluents discharged into
lakes used for water sports and recreation.
10 TCVN 6984: 2001: Water quality – Standards for industrial effluents discharged into
rivers used for protection of aquatic life.
11 TCVN 6985: 2001: Water quality – Standards for industrial effluents discharged into
lakes used for protection of aquatic life.
Page 9
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Environmental
Standards Standard value or class Remarks
factors
Class I:
Daytime: Leq 50 dBA
Class I:
Nighttime: Leq 40dBA
All sensitive
receptorss such as
TCVN 5949-1998 “Noise
shools, hospitals,
in Public and Residential
kinderggartens etc.
Areas- Maximum permitted Class II:
noise level” Daytime: Leq 60 dBA
Class II:
Nighttime: Leq 50dBA
Houses, Hotels, Office
buildings etc.
Acoustic environment The detailed standard values are
shown in Table 1.4a.
Adopted from American
Standards
The detailed standard values are Boundaries of
“ Standard for Noise at
shown in Table 1.4b. Construction Sites
Boundaries of Construction
Sites”
TCVN 5948-1999 “Noise
emitted by accelerating The detailed standard values are
At road sites
road vehicles- Maximum shown in Annex 1.4c.
permitted noise level”
Executing the standard for ambient
areas (TSP, CO,NO2,SO2,O3 and
All the areas
Lead). The detailed standard values
Ambient TCVN 5937-1995 are shown in Table 1.5a.
air quality “Ambient Air Quality Executing the standard for
standard Standards” Maximum allowable concentration
All the areas except
of hazardous substances in ambient
Industrial areas
air. The detailed standard values
are shown in Table 1.5a.
Executing the standard for
Air environment
Page 10
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Unit : dB(A)
Time
No. Areas ( * ) From 6:00 From 18:00 From 22:00
To 18:00 to 22:00 to 6:00
Special Areas: 50 45 40
1 Hospitals, Libraries, Health
care centers, kindergartens ,
schools Pagodas
2 Residential areas, hotels, 60 55 50
restaurants, office buildings.
3 Mixed areas: Residential 75 70 50
within commercial.
Page 11
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 12
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 13
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Permissible value
No. Pollutants Unit Level Level Level Level Level
I II III IV V
1 pH mg/l 5-9 5-9 5-9 5-9 5-9
2 BOD5 mg/l 30 30 40 50 200
3 Suspended Solid (SS) mg/l 50 50 60 100 100
4 Total Solid (TS) mg/l 500 500 500 500 KQ
5 Sulfur ( as H2S) mg/l 1.0 1.0 3.0 4.0 KQ
6 Nitrate (NO3-) mg/l 30 30 40 50 KQ
7 Oil mg/l 20 20 20 20 100
8 Phosphorous (PO43-) mg/l 6 6 10 10 KQ
9 Total Coli form MPN/100 1000 1000 5000 5000 10 000
ml
KQ : Not required
Page 14
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Permissible value
No. Pollutants Unit Level Level Level Level Level
I II III IV V
1 pH mg/l 5-9 5-9 5-9 5-9 5-9
2 BOD5 mg/l 30 30 40 50 200
3 Suspended Solid (SS) mg/l 50 50 60 100 100
4 Total Solid (TS) mg/l 500 500 500 500 KQ
5 Sulfur ( as H2S) mg/l 1.0 1.0 3.0 4.0 KQ
6 Nitrate (NO3-) mg/l 30 30 40 50 KQ
7 Oil mg/l 20 20 20 20 100
8 Phosphorous (PO43-) mg/l 6 6 10 10 KQ
9 Total Coli form MPN/100 1000 1000 5000 5000 10 000
ml
KQ : Not required
1 Temperature 0C 40 40 45
2 pH 6 n9 5,5 n 9 5 n9
3 BOD5 (200c) mg/l 20 50 100
4 COD mg/l 50 100 400
5 Suspended Solid mg/l 50 100 200
6 Arsenic mg/l 0,05 0,1 0,5
7 Cadmium mg/l 0,01 0,02 0,5
8 Lead mg/l 0,1 0,5 1
9 Chromium (VI) mg/l 0,05 0,1 0,5
10 Chromium (III) mg/l 0,2 1 2
11 Mineral Oil mg/l ND 1 5
12 Fat mg/l 5 10 30
13 Cu mg/l 0,2 1 5
‘14 Zn mg/l 1 2 5
15 Manganese mg/l 0,2 1 5
16 Nickel mg/l 0,2 1 2
17 Total phosphorous mg/l 4 6 8
18 Fe mg/l 1 5 10
Page 15
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
19 Aluminum mg/l 0,2 1 5
20 Hg mg/l 0,005 0,005 0,01
21 Total Nitrogen mg/l 30 60 60
22 Ammoniac (as N) mg/l 0,1 1 10
23 Flour mg/l 1 2 5
24 Phenol mg/l 0,001 0,05 1
25 Sulfur mg/l 0,2 0,5 1
26 Cyanide mg/l 0,05 0,1 0,2
27 Total Coli form MPN/100 ml 5000 10 000 -
Note: KPH – Not Detective
Page 16
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Notes:
Column A: application to the surface water resources which are used a sources for water supply (need to be
treated as required).
Column B: application to the surface water resources which are used for other purposes.. The waster sued for
aquatic life and irrigation shall be followed other regulation.
Page 17
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
2. PROJECT DESCRIPTION
2.1. Name, Features and Location of the Project
Project name: Hanoi Urban Transport and Development Project
Project nature: New road and Road expansion and Bus Rapid Transit (BRT)
Investment
Components Contents of construction ( million
USD)
Cross Sections 2 cross sections
Road 1 road (including two cross sections)
New Road 60 - 100
construction with a total length of app. 7 km
Expansion Road 1 roads with length of 3.4 km
BRT system 2 routes: Lang Ha - Giang Vo ( 13 km)
BRT routes 79
and
6 interchanges and 40 bus stop points
Bus Interchanges
route Giai Phong (11.5 km)
Page 18
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Bus Terminals 2 terminals
Traffic Air quality management; road transport regional control system
management (ATC) of city proper; propagation and education of users of road;
and road safety enhancement of traffic management and safety etc..
18
Set up modernized mass transit dispatching and information
Public transport management system; technical aid project; mass transit system
reform; adjustment of public transit lanes
Total cost 157 - 197
Page 19
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
10 Hoa Muc Bridge 1350 Bus stop
11 Vu Ngoc Phan 360 Bus stop
12 Thai Ha 390 Bus stop
13 Thanh Cong 470 Bus stop
14 Giang Vo Exhibit 660 Bus stop
15 Nui Truc 600 2007 Interchange
16 Kim Ma 830 Bus stop
17 Le Truc 420 Bus stop
18 Hoang Dieu 680 Bus stop
19 Le Duan 260 Bus stop
20 Cua Nam 170 Bus stop
21 Hai Ba Trung 660 Bus stop
22 Ba Trieu A 375 Bus stop
23 Dinh Tien Hoang 475 2007 Interchange
24 Hoan Kiem 660 Bus stop
25 Le Thai To 670 Bus stop
26 Phu Doan 560 Bus stop
27 Tran Phu 880 Bus stop
28 Saint Paul hospital 520 Bus stop
Ong Ich Khiem 280
Source: Own estimates
Page 20
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
21 Tran Hung Dao 410 Bus stop
22 Nguyen Du 315 Bus stop
23 Vincom Building 875 2007 Interchange
Source: Own estimates
Cau Giay
450 - - 2007
Interchange
Extended
Road 3 400 0 3 400
Quoc Viet
Extension
2007
Hoang
2
Dam Bridge 1 330 2008
Nhue Bridge 2 330 2008
Total Total length of 14 067 m
Page 21
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
To guard against the adverse impact of the project, the following detailed actions shall
be taken in each stage of the implementation and operation.
In the period of choosing works and designing, various potential impact factors shall
be analyzed, and the best measures shall be designed to reduce the adverse impact on
the environment.
During the construction phase, environmental impact mitigation measure shall be
taken for the involved units or people, for example, to set acoustic barrier, and double-
layered sound insulated window, so as to reduce the noise impact on the environmental
sensitive receptors.
During the operation phase, it is necessary to carry out long-term action plan to
improve the urban environmental quality, such as traffic control, limits of downtown
traffic, vehicle end gas control strategy and rational allocation of the city’s layout.
Page 22
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Disadvantages
1. No transit for passengers at Truong Chinh
Advantages of BRT along barriers Transit station,
Alternative 3 1. BRT along pavements will allow for other 2. BRT to viaduct reduces flexibility of crossing
means to travel node - Nga Tu Vong;
3. Difficult for BRT passengers at Truong Chinh
stop where traffic density is high
Channel zed in Hai Ba Trung and Trang Thi
Disadvantages
1. Causing circle traveling for other means
Advantages:
which change directions;
1. Reduction of individual means;
Alternative 1 2. Affecting daily activities (and economics) of
2.Reduction of noise pollution, tail gas from
people in the streets whose direction are
individual means
changes;
3. Taking space in terminals/stops.
Advantages:
Disadvantages
1. Minimization of cycle way of alternative
1. The coordination with the West is reduced;
1;
2. Affecting daily activities (and economics) of
Alternative 2 2. Stop the disputes, safety for people;
people in the streets whose direction are
3. Reduction of noise pollution, emitted
changed;
gases from individual means (due to reduce
number of fleets)
Advantages Disadvantages
1. Improving traffic capacity for means to 1. Changing the traveling habit in city center;
the West (limitation of alternative 2); 2. Affecting daily activities (and economics) of
Alternative 3 2. Stop the disputes, safety for people; people in the streets whose direction are
3. Reduction of noise pollution, emitted changed;
gases from individual means (due to reduce 3. Causing big dispute in Le Duan/Nguyen
number of fleets) Khuyen).
Page 23
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Channelise in Hai Ba Trung and Trang Thi, there are three proposed alternatives with
its own strong and weak points. Table 4-1 shows that the alternative 2 is the optimal
one which can help to settle the circle traveling as those of alternative 1; Stop
conflicting points at junction Le Duan/Nguyen Khuyen, securing safety for people,
reduction of noise level as well as emission of toxic gases from individual means of
transport.
Table 4.2clearly presents the environmental impacts of the two options AI and AII.
Regarding Option AI, there are more advantages and negative impacts are less than
Option AII. The disadvantages of the option comprise traffic safety at terminals and
stops which can be overcome. As such, middle BRT routes are proposed in this
section.
Table 4-2a. Comparison of Alternatives
in term of Environmental Aspects
Operation phase:
Operation phase:
Impacts by CO, NO2, THC due to
CO, NO2, THC concentration due to
increasing of traffic flow.
increasing of traffic flow
Construction phase:
Construction phase:
Increasing of noise levels during the
Noise Increasing of noise levels during the
piling, transportation of construction
Pollution transportation of construction material ;
material ;
Page 24
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Operation phase:
Operation phase:
Impacts by noise levels due to increasing of
Impacts by noise levels due to increasing of
traffic flow.
traffic flow.
Construction phase:
Construction phase:
Less impacts due to construction activities will
In case of using bored pile industry, heavy
be at ground level ( max. noise level 64 dB at
truck is likely to cause biggest vibration
10 m from the source).
(about 79dB at 10 m far from source).
Vibration
Operation phase:
Operation phase:
Impact level is not significant
Impact level can be negneted
Water quality Limited impact on water quality Limited impact on water quality
Regarding the ones at Buoi and Cau Giay, there are three options (A,B,C) for technical
designs. As such, the assessment focused on these options. Details are summarized in
the Table 4.2b.
Table 4.2b. Comparison of technical design options for Buoi
and Cau Giay Interchanges
Page 25
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 26
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
4.1.1 Noise
Route selection and site selection for new roads and expended roads shall move
around the sensitive receptors as possible as it can be, and unless absolute needs,
viaduct will not be built. Mitigation measures at the design stage are those which are
considered during and/or incorporated into the design.
Table 4-3 lists the commonly used noise mitigation measures for roads in urban areas,
including the effectiveness, advantages/disadvantages, and estimated costs.
Overview of mitigation measures for the Ring road project. The World Bank
financed ring road project has been completed and operational since 2007 and noise
mitigation measures have been gradually implemented along the ring road. The actual
Page 27
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
noise barrier length is about 2700m . The additional noise barrier has been installed in
response to the strong public reaction on the increased noise from the inner ring road.
The other important noise mitigation measure, installation of double glazed windows
in sensitive receptors, has been gradually implemented.
In general, the noise barriers are most effective to three to six floors of the buildings
targeted for protection, with average noise reduction of about 2 to 4.7 dB(A). Higher
floors are generally beyond the noise barrier protected area and have no measurable
noise reduction. The lower floors on the other hand, are mostly impacted by the noise
from the ground level traffic for which the noise barriers mounted on the elevated
viaduct have no effect.
Double glazed windows have been installed in hospitals, school and houses next to the
road. The monitoring program at the two locations show that noise can be reduced by
26-27 dB(A) at the hospital (with a vacuum lawyer between two pieces of glasses) and
17-22 dB(A) at the school (ordinary design with two layers of windows put together)
when the windows are closed. When the windows are open, the reduction is about 6-10
dB(A) compared with the noise levels one meter outside the same windows.
The lessons learnt from the inner ring road noise mitigation, which will be included
into the consideration of mitigation measure planning and design for roads include:
- For multi stories buildings, the noise barriers should be higher. A noise barrier
5-7 m tall as originally designed, compared with the current height of 3 m,
would significantly increased the protected area;
- The lack of seal of noise barriers at the structural expansion joints and the poor
design in aluminum frame of the noise barriers are to blame for the less than
desired effectiveness of noise barriers;
- The noise barrier installation is not well planned. In some areas noise barriers
are installed where is no sensitive receptors to protect. Such waste of effort
should be avoided and the location of noise barriers should be carefully
planned through site investigation and acoustic study; and
- Double glazed windows prove to be very effective measures for noise
attenuation for indoor environment. It seems that to meet the noise standards at
the sensitive receptors, the windows are required to be closed; therefore, the
ventilation must be resolved to ensure the effectiveness of double glazed
window as a noise control measure.
In the following section of Hoang Quoc Viet extension road, noise barrier will be built
Page 28
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Double glazed windows. The experience gained from noise mitigation of the Ring
Road project has showed that noise barrier alone may not be adequate in terms of
noise reduction to the acceptable levels while installation of double glazed windows at
the sensitive receptors is the most effective measure to protect indoor environment
from noise impact. Buoi interchange (including link road Buoi- Hoang Hoa Tham)
with 600 m of road will take such measure to noise mitigation at the most sensitive
receptors.
- Along the Nguyen Thai Hoc street, a bus stop of BRT route will be located near
Primary school when 3 stories classroom building. The first and second floor of
the building will be mostly towards the classrooms on the third and fourth floor.
There are a total of 10 classrooms on these two floors with a total window area
of 120 m2.
- The first building of University of Civil engineering and Hanoi University of
Polytechnic located app. 100 m from the proposed BRT Giai Phong corridor,
however, noise level is expected to be able to meet the applicable standards. No
further mitigation is needed.
- Bach Mai hospital is about 50 m from the proposed BRT road. But it is located
near railway station. The effected noise level in this area caused by train is more
Page 29
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
than by BRT. However, it is recommended that the first building of the hospital
shall be installed by Double glazed windows with an estimated area of 120 m2.
4.1.2 Vibration
We will take the following measures in engineering design to reduce the potential
influences on vibrating environment.
- Potential vibration caused by the expansion seals/joints between pre-fabricated
concrete plates and between concrete plates and bridge columns of the
interchanges will be given sufficient considerations during the design. The
support column design will also affect the vibration which will be considered in
the design as well.
- Greater improvement in the materials spread on the pavement of the road and
the plan ness of the road will be made. The asphalt will be adopted as the
surface material. The smoothness of road surface will be strictly controlled,
because 1 mm decreasing of smoothness contributes to 4 dB reduction of
vibration level.
- The land use along the project roads will be properly arranged. The vibration
sensitive buildings will not be placed within 40 m along project roads. Such
considerations have been incorporated into the Mater Plan of Hanoi City and
will be carried out by and under the supervision of Hanoi Planning Bureau.
Page 30
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
occupied, the trees that can planted in another place must be planted in the another
places as much as possible.
- According to Hanoi Urban Green Regulations, as for the ratio that green land
in this project accounts for in the total area of the land, the road with the width
of under 40 m is not less than 20 per cent, the road with the width between
40~50 m is not less than 25 per cent, the road with the width of over 50 m is not
less than 40 per cent and the bus depots is not less than 25 per cent.
4.1.6 Sunshine
Determine the width of the red line at elevated section according to the design
principle of controlling the sunshine disturbance into the minimum degree and control
the distance between the red line at elevated section and the sensitive buildings close
to the sunshine into 5 m, and this measures will be supervised and performed in the
urban planning and during construction and development of the road at both sides of
elevated section by Hanoi Architect and Planning Bureau.
The following measures to reduce the noise will be performed by the Contractor:
Page 31
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Prohibit using the equipment with high noise at night (22:00~6:00), such as pile
driver crusher, bulldozer, excavator, compactor, generator, electric sew, concrete
electric vibrator and so on. Any operations extended beyond these timeframe as may
be required by the construction needs must apply and receive approval from relevant
authority. This requirement will be strictly enforced in the RR No2 and Hoang Quoc
Viet road construction which will basically eliminate the noise impacts at night, as
well as the after lunch nap time, when the standards exceed would be worst.
Use the machinery with low noise or the equipment equipped with sound eliminator or
sound insulation cover for example, generator used in construction site will be
supplied with sound eliminator or according to the environmental situation around the
construction sites.
Arrange construction time and equipment reasonably to make the construction which
may produce larger noise avoid the sensitive receptors and time of sound environment
and maintain equipment regularly to keep its good working state. As for the
construction sites with a little larger noise, install temporary sound barrier.
As for the large construction structures, especially those used in many viaducts in this
project, they will be prefabricated outside the construction sites and then will be
transported to the construction sites to erect.
As for the construction which is necessary to be performed at night, the Contractor
must submit it to the People’s Government of Hanoi City for approval in advance of
construction. The Project Construction Office will install sound insulation windows at
the impacted sensitive receptors according to the requirements of this environment
management plan ahead of 15 days before construction and release its construction
report on the newspaper before 2 days. The telephone numbers for complaint will be
given on the newspaper and in the construction sites.
Where possible, columns will be installed using excavated holes and onsite casting. If
steam, turbine or hammer style drilling machines must be used for column
construction, the contractors must apply to PMU first and these drilling activities will
be restricted to certain hours of the day (primarily morning and afternoon while
evenings and nap time at noon will be strictly prohibited from using such drillers).
According to the above assessment, Dong Xa ward, Xuan La commue will be the most
seriously impacted sensitive receptors during construction. In fact, the later section of
this report will show they are also the most significantly impacted by noise and motor
vehicle exhaust emissions during the operation period of Ring Road and Hoang Quoc
Viet Road. Specific mitigation measures have been designed and will be taken at these
locations for reduce or avoid the long term impacts during operation phase. These
include relocating Xuan La primary school to an area not to be impacted by the project
Page 32
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
and install double-glazed windows to the first row of the residential housing in Xuan la
commune. To mitigate the noise impacts from construction activities, these measures
will be implemented at the beginning of the construction phase. For example, Xuan La
primary school will be relocated prior to the construction to completely avoid the
impact. Double-glazed windows at the mostly affected houses will also be installed at
the beginning of the construction for noise impact mitigation.
In addition, the following measures will be taken to further avoid or mitigate the
construction noise impacts:
- Structural elements for bridges and elevated viaducts will be made in factories
to avoid on-site concrete mixing and compacting;
- Low noise machinery will be selected where possible. High noise machinery
such as power generators will not be allowed to sue at the site; but if they are
necessary for construction work, noise temporary barriers or silencer will be
installed;
- Appropriately schedule the construction activities to avoid sensitive time and/or
sensitive locations where possible;
- Noise and vibratory activities will be arranged to be completed within the
quickest time possible to reduce the impact length;
- Construction trucks movement will be arranged to avoid residential areas where
possible;
- According to relevant laws and regulations, if the construction noise still
exceeds applicable standards, especially night time construction, the contractors
will apologize and compensate the affected residents, students in classrooms
and dormitory, or others affected.
Page 33
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
- All construction waste will be promptly removed from the sites, daily if
possible;
- Earth and bulk materials transportation will be loaded in such a way they will
not leak during transportation and will be covered.
- Before leaving construction sites, trucks wheels will be washed to clean the dirt
which would otherwise be carried away to the streets;
- Strictly prohibit burning of construction waste at the sites; and
- Asphalt and concrete mixing plants will be located in the area at least 500 m
leeward from the nearest residential or other sensitive receptors to ensure that
the emission from these facilities will impact the sensitive receptors. The
asphalt plants will be required to equip with effective emission control facilities
to meet the emission standards in relevant state and provincial air emission
standards. All these location and emission requirements will be included in the
tendering documents distributed to the bidders for the pavement work and
eventually in their contracts to become contractual obligations for the
contractors working for the project.
During construction, the Hanoi Urban Traffic Management Bureau will do well in
traffic control in urban area. According to construction plan, set warning signs at the
entrance to the city to remind the vehicles of traveling from the external roads around
the city. Do well in traffic control on external roads to ensure the unblocking of the
roads and prevent the traffic congestion so as to reduce the impacts from the tail gas of
the vehicle on the ambient air. If the vehicles are blocked due to the road construction
in urban area, the traffic management department will set up the instant vehicle
traveling management method, for example, regulating the traveling route for the taxi
with odd and even dates, prohibiting turning left at the main crossing and setting one-
way lane and so on.
Page 34
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
- Prohibit storing construction materials and rubbish at the place where the waste
water from the construction sites enters the drains and pay attention to clearing
the accumulating mud to prevent drain pipeline from choking.
- The toilet for constructors in construction site shall set temporary cesspool and
the sewage will be drained into the drain after pretreatment in cesspool.
- Besides enforcing management on the drainage of domestic sewage, the
Contractor shall offer training to the constructor on basic environmental
protection to improve the consciousness and responsibility of environmental
protection.
Page 35
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
- Buildings under demolition will be surrounded with nylon cloth or metal sheets
or wood boards to minimize the visual impacts to the communities as well as
for dust and safety control;
- The project area will be landscaped and planted following the construction. The
green area will be no less than 20% of the total project area. The landscaping
plan will result in a net increase in green space in the project area.
- The most traffic affecting activities such as loading/unloading, beam lifting, and
bulk materials transportation will be scheduled for the time when the traffic on
the roads will be the lightest such as weekends, holidays mid-day around the
noon time or evenings.
- No traffic affecting construction activities will be allowed during the rush hours
in the morning and early evening;
- Public notices in the form of public boards at the construction sties will be
provided to inform the road users of the time, length and type of traffic
affecting construction activities and possible congestion.
- The public notice will also advise the road users of possible detoured roads
identified by the traffic police as alternative routes to avoid the congestion on
the roads affected by the project;
- No construction materials and debris will be allowed to store and pile on the
roads or the pedestrian areas;
- Construction vehicles parking on the roads will not be allowed unless it is
absolutely necessary. Such parking will be kept to the minimum and be
removed as soon as it is possible; and
- During the loading/unloading, viaduct structural lifting and installation, the
contractors will be requested to contact the traffic police to either have the
police on site or have their own staff on-site to help direct the traffic, to
minimize the traffic congestion and to ensure the safety.
4.2.7. Community
The following measures will be taken to mitigate the negative impacts on the
community from the construction of the project.
Page 36
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
- All of the roads under reconstruction in urban area will be constructed in half-
closed manner and leave passages for the pedestrians, bicycles and buses.
- Build temporary roads and temporary bridge for the units and the residents
along the line and set necessary safety measures to ensure the unit and the
residents can go out conveniently and safely. At the same time, perform
centralized construction and quicken the construction progress to reduce the
impacts on the communities.
- As for the section where some schools are located, carry out construction in the
summer holiday or in other holidays to reduce the impact on the going of the
students.
- All of the construction materials will be stored on special yards by categories
and types and kept by designated persons. The discarded materials will be
removed out of the site to reduce space occupation and traffic inconvenience.
- As for the resident areas and the units that are separated due to being removed,
rebuild the fence within one month after accomplishing removing to reduce the
impacts from the external environment on the community security.
- During the construction of ramp of Buoi and Cau giay interchange as well as
Dam and Nhue bridges, build safety passage and take safety measures to ensure
the safety of the pedestrians.
- The hospital can anew establish its gate, so does the school; at the same time,
set some facilities such as gangway and guard fence.
- Road construction will be carefully planned and implemented to avoid damages
to underground utilities. Necessary protection measures will be taken for
various underground pipelines and cables.
- In road sections where traffic will remain, the street lighting will be maintained
at the original levels. No damage or disruption of street lighting will be
allowed.
4.2.8. Others
Other measures to be taken during the construction phase include:
- The contractor will be request to halt the all construction activities immediately
if any archaeological or other cultural properties are found (chance finds)
during excavation and to properly protect the site which such finds are
uncovered. Cultural authority, as well as PMU and EA team, will be noticed
promptly. Only after a thorough investigation by the cultural authority and
specialists and a clearance is provided, will the contractor be allowed to resume
their construction activities at the site.
Page 37
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
4.2.9 Summary
Table 4.4 summarized the proposed mitigation measures and the responsible
organizations for implementation during the construction phase to minimize the
potential environmental impacts.
Page 38
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Implementati
Concerns Mitigation measures on
organization
environmental sensitive receptors shall not be less than 50 m. In the
construction phase, the municipal traffic management departments shall do well
the traffic dredging work. According to construction plan, set warning signs at
the entrance to the city to remind the vehicles of traveling from the external
roads around the city. Do well in traffic management on external roads to ensure
the unblocking of the roads and prevent the traffic jar so as to reduce the
influences from the waste gas of the vehicle on the environment and air. If the
vehicles are blocked due to the road construction in urban area, the traffic
management department can set down the instant vehicle traveling management
method, for example, regulating the traveling route for the taxi with odd and
even date, prohibiting turning left at the main crossing and setting one-way lane
and so on.
Prohibit draining and flowing waste water from construction randomly. Clear
the construction site in time. Only when the waste water from construction is
treated in the temporary sand settlement bank can it be drained into the drains to
prevent some little matters such as sands and some sundries such as some
Water
construction rubbish from being draining into drain pipeline. The toilet for
environmen Constructor
constructors in construction site shall set temporary cesspool and the sewage
t
will be drained into the drain after pretreatment in cesspool. Besides enforcing
management on the drainage of living waste water, the contractor shall offer
training to the constructor on basic environmental protection to improve the
consciousness and responsibility of environmental protection.
As for the green belt damaged by construction activities, if they can be planted
in another place, take protective measures to plant them in another place after
Constructor,
Recovery the construction. If it is necessary to cut them due to the construction need while
Hanoi
of they can not be planted in another places, they will be compensated according to
Landscape
vegetation the principle of "cutting one, compensating two". There will be 378 trees to be
Bureau
cut within the range of the project and 756 trees will be planted as the
compensation after the project is accomplished.
All of the roads under reconstruction in urban area will be constructed in half-
closed manner. Build temporary roads and temporary bridge for the units and
the residents along the line and set necessary safe measures to ensure the unit
and the residents can go out conveniently and safely. As for the section where
some schools are located, carry out construction in the summer holiday or in the
Constructor,
holidays. All of the construction materials will be placed in the special sites in
Project
Community order according to the classification and type, clear and transport the waste from
Managemt.
the construction in time to reduce the influences on the land occupied by the
Office
materials and the traffic. As for the resident areas and the units that are
separated due to being removed, rebuild the fence within one month after
accomplishing removing. During the construction of ramp of Dam River
Bridge and the over cross at Hoang Quoc Viet Road, build safety passage and
take safety measures to ensure the safety of the pedestrians.
When setting down road construction plan, pay attention to planning and
reasonable arrangement; at the same time perform construction in different
TUPWS,
Traffic period to reduce the traffic jam due to the same direction of the vehicles. This
PMU
project will be constructed in half-closed manner and allow the buses and the
bicycles to travel while prohibit the traveling of the vehicles through Hanoi City
Page 39
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Implementati
Concerns Mitigation measures on
organization
to ensure the unblocking of the buses. In the busy section, the crossing of the
road can not be constructed in fully closed manner, but in half-closed manner, at
the same time set one-way street to ensure the unblocking of the bus. Enforce
traffic management and organization. All of the vehicles through Hanoi shall
travel along the external ring route and it is prohibited to cross the urban area to
reduce the traffic pressure of the roads in urban area. Control the variation and
the type of the passing vehicles, set lane on the special sections and increase the
change circle of traffic indication light to try to reduce the traffic flow on the
main truck. Organize circumambulating line and bicycle line. Perform scientific
management and improve the quality of the traffic policemen to enforce traffic
management ability; emphasize on improving the quality of the drivers to
reduce the traffic jar due to the man-made factors. Set iron separation fence at
both sides of the tracks of the roads for vehicles in main urban areas. Enforce
the management on the anchoring vehicles on the road and make it leave as
quickly as possible to avoid the influences on the normal passing of the vehicles
so as to increase the passing ability of the traffic of the roads.
Where possible, columns will be installed using excavated holes and onsite
casting. If steam, turbine or hammer style drilling machines must be used for
column construction, the contractors must apply to PMO first and these drilling
activities will be restricted to certain hours of the day (primarily morning and
afternoon while evenings and nap time at noon will be strictly prohibited from
Vibration using such drillers). Unless there is emergencies (emergent repair, emergent Constructor
rescue), at night (22:00~6:00 we will not use any construction equipment with
great vibration influences. The contractor must set signs at striking sites and
give the telephone for complaint, names of the project, the contractor and the
building unit. Select construction equipment with low noise and vibration, and
maintain it regularly.
2 days before the construction, the contractor releases public notice on
newspaper or television to the public to make preparations. If the water is cut
Municipal PMU.
off over 2 days, we’ll use water supply truck to supply the influenced people
facilities Constructor
with water. Stoppage of power, gas or water that may be caused by construction
will be arranged at night 22:00~6:00 as much as possible.
During the process of construction, the transport vehicles shall run with low
speed in urban area to reduce vibration. All the construction plants shall conduct
civilized construction. The transport vehicles shall be sealed during the process Constructor,
Cultural
of construction to avoid flying dust. The route for vehicles going in and out the Hanoi
relics and
construction sties shall be sprayed water regularly. During the process of Cultural and
historical
construction, the equipment with low noise shall be adopted as far as possible information
sites
and corresponding noise reducing measures shall be adopted. Nighttime Dept.
construction is forbidden. It is forbidden for the construction vehicles whistling
to avoid it distributing the residents.
Page 40
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
4.3.2 Vibration
During operation, under the condition of unchanged ratio of vehicle type and speed,
the vibration level at both sides of the road will increase with damage extent of the
road surface day by day. If the condition of the road surface remains the same, the
vibration level ascents with the increase ratio of the vehicle type (especially the ratio
of large and mediate vehicles), and with the increase of traveling speed. If the road
surface is more deeply damaged and the ratio of vehicle type (especially the proportion
of large and mediate vehicles) and traveling speed increases, the vibration level at both
sides of the road will also largely increase.
To prevent and reduce the impacts on the vibration environment at both sides of the
road during the operation and to make it be in accordance with the requirement of
TCVN 6962-2001 Vibration Standards, it will be required to take the corresponding
measures of traffic management.
The department of traffic police is in charge of establishing the urban road and traffic
control system, for example, it rigidly limits the overload traveling on the vibration-
sensitive road at night and prohibits high speed traveling in the urban area especially
the heavy and mediate vehicle.
Hanoi Urban Management Bureau is in charge of maintaining the road according to
the related regulations.
Page 41
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 42
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
4.3.4. Landscape
This project will protect the trees and green belts along the both sides of the road
reconstructed and expanded to the utmost, as well as plant trees and grass by the two
sides of the newly built road according to different structures of the roads. The work
will be carried out by Hanoi Landscape Bureau.
The principle of compensating the vegetation damaged due to this project is "cutting
one, compensating two".
4.3.5. Sunshine
Continue to strictly control the height of the buildings by the two sides of the roads as
well as the distance between the sunshine sensitive buildings and the red line on the
road.
Page 43
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
4.3.7. Summary
Table 4.5 summarizes the proposed measures and the responsible organizations for
implementation during the operation phase to minimize the potential environmental
impacts.
Page 44
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 45
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
A bill board will be erected in every construction site. This board will briefly explain
the activities on this site, and indicates specifically that public concerns and opinions
on the environment will be welcome. To ensure public concerns, if any, can be
received properly and timely, the board will include specific contact information such
as telephone numbers, email address where possible, and contact persons, which will
be the head and environmental staff of the contractors on that particular site.
Public notice will also be issued in media during the operation stage to inform of the
public with contact information so that they can express their concerns and opinions, if
any, on environmental impacts of road operations. Once again telephone numbers and
Page 46
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
contact persons will be provided. At this stage, the contact information will be those of
that of the road operating company.
Personnel Training
Personnel training will be provided in different stages of project implementation. At
the construction stage, heads and environmental staff from winning contractors and
construction supervision companies will be requested to participate in a mandatory
environmental training program. This request will be included the construction
tendering documents to be issued to the pre-qualified bidders who will be invited to
bid. This training program will include, but not limited to, the following contents:
- Relevant environmental regulations, policies, standards and programs;
- The main findings and recommendations of environmental impacts assessment;
- Relevant environmental control technologies, processes and procedures;
- Key contents of environmental management plan, particularly various
mitigation measures for the construction stage and the implementation;
- Daily environmental monitoring requirements (see section below),
methodology and procedures;
- Environmental reporting requirements; and
- Environmental emergency response and cleanup.
For operation stage, environmental staff from the road operation company and relevant
government organizations which oversee and supervise the road operations will be
provided the training. The training programs will be primarily provided by
professional environmental staff or in local universities.
Page 47
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
runoff, storage and disposal of construction waste, traffic impacts, and construction
safety issues. Hand-hold noise meters will be used to monitor the noise levels at
sensitive receptors during construction. The objective of this daily monitoring program
is to identify environmental issues at the same time as the construction activities on
these sites to that appropriate mitigation actions, if needed, can be initiated and
implemented timely to minimize the impacts.
The formal environmental monitoring plan for both construction and operation stages
is presented in Table 4.7.
As the night time construction is unavoidable, night time construction activities will be
closely monitored, besides other mitigation measures. Dedicated and well trained staff
will be stationed at the night time construction sites to monitor the activities with
regard to mitigation measure implementation, necessary actions for reduce excessive
impacts particularly noise and traffic as well as to receive and respond to any public
complaints.
Page 48
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 49
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
CO 8 4 1 4 50 000 6 400
PM10 8 4 1 4 80 000 10 240
TSP 8 4 1 4 50 000 6 400
Total 29 440
For the one year monitoring for construction and two years for operation (the first two
years), the total analytical costs for the air quality will be 29 440 VND/ year. In
addition, the labor cost, based on four technical staff and one driver + one assistant
driver will be required for the program at 600 000/person- month for technical staff
and VND 1000 000/person-month for the driver and 600 000 for assistant driver will
be estimated to be 48.0 millions VND per year. Therefore, the total estimated costs for
air quality monitoring program will be 77.44 millions VND/year.
Noise, which includes primarily labor cost. Assuming labor cost will be as same as
with Air and it will be 77.44 millions/yea plus equipment depreciation of 10 millions
VND/year.
Night time construction supervision which includes dedicated and well trained staff
going through all construction sites during night time construction. It is estimated that
there will be 90 days when night construction are necessary. At VND 100 000/night ,
the total cost for night construction supervision will be VND 9.0 millions .
Transportation: This is primary the cost of using motor vehicle during conducting the
monitoring program. The basic assumption is that one vehicle is needed for noise and
air quality, respectively. At unit cost of VND100 000 per vehicle per day, the annual
cost will be VND 24.0 millions/year.
Reporting. The estimated cost for report production will be VND 2.4 millions per
year. In case of translation from Vietnamese to English. The translation cost will be
double ( 6.0 millions /year).
Page 50
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Noise Barrier 1000 m x 3.5 m 3 500
Euro windows 1440 m2 x 2 = 2 5 184
880 m2.
Landscaping Tree planting, lawns 10 m wide on both 600
sides
Environmental Labor, materials, one year for 611.7
monitoring transportation reporting etc. construction and
two for operation
Total 9895.7
Organizations Responsibilities
Hanoi TUPWS and Hanoi CPC The ultimate decision making body for all
matters related to environmental
management
Hanoi DONRE • Law and regulations enforcement
• Environmental policy/program
implementation
• Setting up and enforcing discharge standards
• Provide guidance on environmental matters
• Review environmental reports
• Handling environmental emergency
• Project proponent and executing agency
• Day to day operation during construction
PMU including environmental matters
• Will have two full time environmental
specialists
• Prepare contractual requirements and
specification for environmental performance
for contractors and construction supervision
• Implement environmental mitigation measures
Page 51
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP Report
Page 52
HUTDP BRT & ROADS STUDY Draft Feasibility Study and
Preliminary Designs EMP
Report
Page 53