Академический Документы
Профессиональный Документы
Культура Документы
Cahill, Jr
Vice President
February 9, 1973
Re Indian Point Unit No. 2
AEC Docket No. 50-247
CKECLK
~ 0240327 73020-'
PDR ADOCK 05000247'
P PDR,
ioer
.7f.
0
Regulatory 'File Cy.
February 9, 1973
1081
IQtJESTION 1
ANSWER
zero and two and has been conservatively taken as 2.0 for Indian
Discuss the validity of the use of ANSI B31.1 for primary plus
secondary stress determination at the junction of the weldolet
and the main steam header for open systems.
ANSWER
test or analysis to
Submit a summary of the results of the
relieving load.
verify the assumed direction of the
ANSWER
forming an extension of
Strain gages mounted on a load cell
shown in Figure 3 were .used
the. valve inlet nozzle section as
the set pressure, the valve
to obtain the measured strains. At
of load cell strains, valve
opened and continuous measurements
temperature were taken, Two
lift, drum pressure and load cell
strains in the plane of
strain gages read direct plus bending
strain in the plane at 9Q0*
bending, two gages rea d the direct
an identical load cell on a
Four dummy gages were mounted on
compensation could be
second steam drum header such that
and pressure during
achieved for any changes in temperature
the tests.
3-1
From Figure 3, the solution of the exit thrusts from measured
values were obtained as follows:
(1)
Po =P -F
M0 =FH xH - Fv H 2 (2)
where:
V2 A
Pv= (mass flow force in the load cell)
v gc
Valve .
1P
M
Po
Load Cell
3-2
t0
The test records show typical valve opening and valve
High speed movies of the exit steam jet from the 330 angle
area and did not divert significantly (lPEss than 2*) from the
3-3
QUESTION 4
ANSWER
4-1
ADLPIPE computes at each point within the piping system the
forces and moments are computed from the root mean square
4-2
AITKEN's method for Lagrange interpolation at unequal interval
technique is employed in performing interpolation along the
4-3
W
QUESTION 5
a) mathematical model
ANSWER
5-1
QUESTION 5
ANSWER
5-2
W = 51.5 AP
where:
is 110 percent of
The pressure to be applied in this formula
the safety valve is
the design pressure of the system on which
allowable over
being installed. This is because the maximum
is designed is
pressure under the-code to which the system
throat area used
110 percent of design pressure. The nozzle
5-3
where:
5-4 -'...
-i.
'(1) Establish the conditions at the valve inlet
P, h? S
where:
W= 51.5 AP
ho = h - n(h - h s )
V o = 223.8 h'
W= VO
5-5
(8) If the mass flow rate calculated above is the same as
the maximum flow capacity of the valve, (from
from the time a safety valve begins to pop open until steady
flow is completely developed. In order to evaluate these
5-6
The FLASH-IV digital computer code (Reference 1) has been used
5-7
4. No Credit is Taken for Power-Operated Relief Valves
Reference:
1. WAPD-TM-80, "Flash-IV: A Fully Implicit Fortran IV Program
for the Digital Simulation of Transients in a Reactor Plant",
T. A. Porsching, J. H. Murphy, J. A. Redfield, V. C. Davis.
5-8
30000
25000
20000,
0 15000
I
0
10000
5000
0
0 .2 .4 .6 .8 1.0
Isentropic Expansion Efficiency
FIGURE 51
5-9
QUESTION 5
ANSWER
examined for the highest combination load and have been found
5-10
QUESTION 6
ANSWER
input have been established in the Indian Point Unit No. 2 FSAR
ANSWER
a series of pulses.
7-1
However, for a symmetrical two-sided pulse, the maximum
dynamic load factor for an undamped single-degree-of-freedom
for actual piping systems, the dynamic load factor for a number
7-2
The lowest fundamental frequency was 10.2 Hz, and the highest
was 23.2 Hz. The dynamic load factor was determined as the
Second, the peak load on each individual leg was chosen, and
systems are less than two as shown in Table 7-1, even though
7-3
with relatively low maximum stresses and those with relatively
Reference
7-4
FflCTOR FOR TYPI.CRL CLOSED
TA81-. -1 ICTUAL p ,j/riic.. LOAD IN A P W R- PLAN'T
5/4FETY r TALLATLON5
VALVrN.
________I
Vite T1 re Wca i-Fmv F . way •
et cr Io
"
ZJ O 0 1, 80 0 r . o
? S__S._____ _
%SAFETY ). L.V-2-
amSE -CTOM 138 - 141 144'"
3 Sy Stresspsi 41, zo Z '100O 31, zOoo Z 7 60
o ve or,L' ',....,' r0 ,
l r
'.U
~: \.:. ~
1
I I I I I I 1 I I I 1"1"T"i17111i
, jIN - - - - -
IL
_.1
4z -.. jiL _
i II H
0
1.6
I . ...
7 .... __ -
-,-i I"
-J _
V. I, - . I' _ "
,. i- l -. -.-
30 c, 4.40
/.0 2.0
Fn c c -. ''o -"ecic
FI.s.-Z ec L,
Rt-o.& , ' 1"*'
s- - vcu o'. -cl / . k,C,:-SY.
t.vz el III- e Iu,
.1
LI
0*
2.0
l.0 3.0
W'o o' FkAsc W'Idlk to sy s t ye r,i 0d, tj 17
D y0(nviii C. L. cc F4A'r j
kc~ti e lU
sy"Cem
t k , 1.zo
7 -3
..L.
LL~
I
.1
0
~~1
ci
0
-j
11
C
£1
0 4 2 4
61 A\QcA to t wo - -.
,;,'I.
CC,A
4c0vrceo i?(Alces
7-9 ',
I
QUESTION 8
ANSWER
used.
8-1
0
/3L//C v/Nc;
. IV: AI,~r.
-. N'I5
CoNFIUVEItA
"FIG.- 8.
8-2 .
-- W EL BW9UP
,I S) L PWF- VAUT
lem
GIO
PaEss~h~e~*~
FIG- B.
8 -4,
J, , I,
(bo H E ) ..... .
IEL.
,L7.7
~4-9LC-1 +
~~
2 Aj4LS 2:k\T 2:>4C%
<-
uioL"-z
SOL
..... . . \ I .V V -. 9
-~ 4.]f)'1
lil-
--.
J-1 .. - 61
14LK T%L.A
R ES TRAI NTADDED.LO
A T"PICAL 5YSTER
8-5' . AFIG.-.8d
AEC DIlIBUTION FOR PART 50 DOCXET MAIAL
(TEMPORARY FORNbO- qmOV N CONTROL NO:_1081.
"CKNOWLEDGEr I ________F1T
DESCilIPTION:' ENCLOSURES:
Ltr re their 07-13-72 submittal and our Additional Info Concerning the Re-analysis
10-17-72 ltr trans the following: of Safety and Relief Valve Installations for
ASME Clas I & Class 2 Systems in Indian Point
Unit No. 2, dtd 02-09-73.
lNWFPTNAT. LDT~rrTRTT
TECH REVIEW JVOLL2MER HAPLESS WADE E
WDENTON SHAFER F&M
C, ROOM P-50)6A SCHROEDER 'GRIMES Fl& M BROWN E
UrUTzI)G/STAFF MACCARY GAMMILL G. WILLIAMS E
CASE kW) KASTNER NUSSBAUMER E.
A/T GOULBOURNE L
-KNIGHT(2)
EXTERNAL DISTRIBUTION
I :CAL PDR Montrose, New York
41-NSIC(BUCHANAN)
)C (9)-NATIONAL LAB'S - 1-DR-SAN/A/NY
1-R. CARROLL-OCq GT-B227 1-GERALD LELLOUCHE
I-ASLB-YORE/SAYRE L-R. CATLIN, E-256-GT BROOKHAVEN NAT. LAB
_WOODWARD/H. ST.
1-CONSULANT'S I-AGMED (WALTER KOESTER,
T'16-CYS ACRS HOLDING (Sent to M. Ser.vice) NEWMARK/BLUME/AGABIAN Rm C-427, GT)
02-14-73 1-RD...MULLER...F-309GT