CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

Site Acceptance Test Procedure and


Record for SCS System Startup &
Shutdown

TOSHIBA TRANSMISSION & DISTRIBUTION SYSTEMS


VIETNAM. LTD

TOSHIBA
CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0
No.1 General Inspection

1.1 Visual Inspection :

The visual inspection is carried out on all devices and boards to see that there are no damage and foreign matter on them.
All connections are checked for the tightness between main unit and all other devices.
All Installed unit and each devises are checked for conditions according to the assembly drawings.
Each element is checked for their types, ratings and number according to the drawings.

«Criteria»
To be suited with the drawing.

«Result» 1/2

No. Item Result Remarks


1 Panel position OK
2 Panel paint OK
3 Name plate OK
4 Device name, type, rating OK
5 Door opening/closing OK
6 Grounding OK
7 Cable entries, duct OK

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.1 Visual Inspection :

«Result» 2/2

No. Item Result Remarks


1 Panel position OK
2 Panel paint OK
3 Name plate OK
4 Device name, type, rating OK
5 Door opening/closing OK
6 Grounding OK
7 Cable entries, duct OK

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.2 Hardware check list:

Check maufacturer, type, rating and serial number of devices

«Criteria»
To be suited with the specification

«Result» 1/4

SCS STATION LEVEL COMPONENTS


No. Device Manufacturer Type, form Rating Serial Number
1 SC-1/GW-1 Advantech ECU-4784 220VAC
2 SC-2/GW-2 Advantech ECU-4784 220VAC
3 HMI Advantech ECU-4784 220VAC
4 Engineering Advantech ECU-4784 220VAC
5 HIS Server Advantech ACP-4320 220VAC
7 GPS KYLAND PTS-10X-1-11100 220VDC
8 A4 Printer CANON LBP6230DN-NPJA113714 220-240VAC
9 A3 Printer CANON LBP8100N-NDFA005748 220-240VAC
10 ESW A KYLAND SICOM3024P-8M16T-SC05-HV-HV220VDC/VAC
11 ESW B KYLAND SICOM3024P-8M16T-SC05-HV-HV220VDC/VAC
12 ESW 1 KYLAND SICOM3024P-20M4T-SC05-HV-HV220VDC/VAC
13 ESW 2 KYLAND SICOM3024P-20M4T-SC05-HV-HV220VDC/VAC
14 ESW 3 KYLAND SICOM3024P-20M4T-SC05-HV-HV220VDC/VAC
15 ESW 4 KYLAND SICOM3024P-20M4T-SC05-HV-HV220VDC/VAC

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.2 Hardware check list:

«Result» 2/4

AT1
No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-01-768-00-46-30-000-0031-462-7E DC220V VN00750 FM 0002
2 F87T1 TOSHIBA GRT200-31-239-00-46-30-111-303D-462-2E DC220V VN00750 FM 0001-2
3 F87T2 TOSHIBA GRT200-31-239-00-46-30-111-303D-462-2E DC220V VN00750 FM 0001-1
4 F67 TOSHIBA GRD200-41-621-00-46-30-110-403D-462-6E DC220V VN00750 FM 0003
5 F50 TOSHIBA GRD200-51-113-00-46-30-110-503F-462-2E DC220V VN00750 FM 0015
REG-DA-B0-I0-H0-F1-M1-S0-T0-K1-E00-D0
6 F90 A-EBERLE DC220V
-C00-R1-XW95-L0-A2

D00 - 110kV Busbar


No. Device Manufacturer Type, form Rating Serial Number
1 F87BM TOSHIBA GRB200-21-4T2-M2-46-30-110-2032-462-4E DC220V VN00750 FM 0009-1
2 F87BS TOSHIBA GRB200-01-WU4-S0-00-30-110 DC220V VN00750 FM 0010-1

D01 - OHL Phan Thiet 1


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-9
2 F87L SEL SEL-0311L7HC04215X4XX DC220V
3 F21 TOSHIBA GRZ200-11-237-00-46-30-110-1031-462-2E DC220V VN00750 FM 0004-1
4 TM Landis+Gyr ZMD405CR44-0007-C2S4 DC220V
5 O/E CONVERTER RFL Fiber Service Unit DC220V

D02 - OHL Phan Thiet 2


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-10
2 F87L NARI PCS-931-AECA-BCAAXABA-R2.10 DC220V
3 F21 TOSHIBA GRZ200-11-237-00-46-30-110-1031-462-2E DC220V VN00750 FM 0004-2
4 TM Landis+Gyr ZMD405CR44-0007-C2S4 DC220V
5 O/E CONVERTER RFL Fiber Service Unit DC220V

D03 - Vinh Tan 1


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-11
2 F87L SEL SEL-0311L7HC04215X4XX DC220V
3 F21 TOSHIBA GRZ200-11-237-00-46-30-110-1031-462-2E DC220V VN00750 FM 0004-3
4 TM Landis+Gyr ZMD405CR44-0007-C2S4 DC220V
5 O/E CONVERTER RFL Fiber Service Unit DC220V

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.2 Hardware check list:

«Result» 3/4

D04 - Incoming 220kV


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-1
2 F67 TOSHIBA GRD200-41-237-00-46-30-110-403D-462-2E DC220V VN00750 FM 0006-1
3 TM Landis+Gyr ZMD405CR44-0007-C2S4 DC220V

D05 - Vinh Tan 2


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-12
2 F87L NARI PCS-931-AECA-BCAAXABA-R2.10 DC220V
3 F21 TOSHIBA GRZ200-11-237-00-46-30-110-1031-462-2E DC220V VN00750 FM 0004-5
4 TM Landis+Gyr ZMD405CR44-0007-C2S4 DC220V

D06 - 220kV Bus Coupler


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-31-75B-00-46-30-110-3031-462-7E DC220V VN00750 FM 0008-1
2 F21 TOSHIBA GRZ200-11-224-00-46-30-110-1031-462-2E DC220V VN00750 FM 0007-2

E00 - 110kV Busbar


No. Device Manufacturer Type, form Rating Serial Number
1 F87BM TOSHIBA GRB200-21-4T2-M2-46-30-110-2032-462-4E DC220V VN00750 FM 0009-2
2 F87BS1 TOSHIBA GRB200-11-WU8-S0-00-30-110 DC220V VN00750 FM 0013
3 F87BS2 TOSHIBA GRB200-01-WU4-S0-00-30-110 DC220V VN00750 FM 0010-2

E05 - Song Binh


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-3
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 0011-3
3 F21 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 006-3

E06 - Luong Son


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-4
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 0011-2
3 F21 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 006-4

E07 - Phan thiet


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-5
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 0011-3
3 F21 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 0006-5

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.2 Hardware check list:

«Result» 4/4

E08 - Incoming 110kV


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-2
2 F67 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 0006-2

E09 - 110kV Bus Coupler


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-31-75B-00-46-30-110-3031-462-7E DC220V VN00750 FM 0008-2
2 F21 TOSHIBA GRZ200-11-224-00-46-30-110-1031-462-2E DC220V VN00750 FM 0007-1

E10 - 110kV Transfer


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-13
2 F67 TOSHIBA GRD200-41-237-00-46-30-110-403D-462-2E DC220V VN00750 FM 0012
3 F21 TOSHIBA GRZ200-11-237-00-46-30-110-1031-462-2E DC220V VN00750 FM 0004-4

E11 - Tuy Phong


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-6
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 00011-4
3 F67 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 0006-6

E12 - Phan Ri 1
No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-7
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 0011-5
3 F67 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 006-7

E13 - Phan Thiet 2


No. Device Manufacturer Type, form Rating Serial Number
1 BCU TOSHIBA GBU200-21-75B-00-46-30-110-2031-462-7E DC220V VN00750 FM 0005-8
2 F87L TOSHIBA GRL200-11-224-13-46-30-110-1033-462-2E DC220V VN00750 FM 0011-6
3 F67 TOSHIBA GRD200-41-224-00-46-30-110-403D-462-2E DC220V VN00750 FM 0006-8

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

1.3 Software check list:

«Result» 1/1

SW - 1/4 HMI (OWS/EWS) COMPUTER


No. Application Manufacturer Type Version Remarks
1 Operating system Microsoft Windows 10 SP1
2 Application TOSHIBA GSC1000-C G-PC-APL
3 Database table Microsoft Excel 2016
SW - 2/4 ENGINEERING TOOLS
No. Application Manufacturer Type Version Remarks
1 PLC Editor KW Software MultiProg 5.35
2 G2 Relay & BCU TOSHIBA GR-TIEMS 1.01

SW - 3/4 STATION AND GATEWAY COMPUTER (SC & GW)


No. Application Manufacturer Type Version Remarks
1 Operating system Red Hat LINUX 2.4
2 Application TOSHIBA GSC1000-C G-SC-APL
SW - 4/4 BCU
No. Application Manufacturer Type Version Remarks
1 Operating system μITRON
2 Application (main) TOSHIBA

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0
No.2 System Start-Up

Confirm that the system response is correctly during the system startup with unnecessary error.
Turn on the power switch on each system component according to following procedure.

Step-1 Turn on the MASTER CUBICLE


GPS clock will be started ⇒ [Time service] LED turned green.
SC-1/GW-1 will be started ⇒ SC-1/GW-1: [Run] LED turned on.
SC-2/GW-2 will be started ⇒ SC-2/GW-2: [Run] LED turned on.
Ethernet switch will be started.

Step-2 Turn on the BCU, RELAY, ETHERNET SWITCH power (for CRP PANEL)
«Result»
RELAY will be started ⇒ [In Service] LED turned on.

Step-3 Turn on the printers


Printer will be started.

Step-4 Turn on EWS, OWS


EWS will be started.
OWS will be started.
HIS will be started.

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

«Criteria»
Unnecessary error and error message are not detected on each system component during system startup.
The condition of system component after completely startup is as follows.

No System Components Indications Result


1 BCUs [IN SERVICE] LED OK
2 RELAYs [IN SERVICE] LED OK
3 GPS [Power] LED OK
4 ETHERNET SWITCH [Power] LED OK
5 GW-1/SC-1 [Power] LED OK
5 GW-2/SC-2 [Power] LED OK
6 EWS [Power] LED OK
7 OWS [Power] LED OK
8 HIS [Power] LED OK
8 PRINTERS [Power] LED OK

Note : Communication failure will be detected during system startup.

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0
No.3 System Shut-Down

Confirm that the system response is correctly during the system shutdown.
Turn off the power switch on each system component according to following order.

Step-1 Turn off the EWS, OWS


OWS, EWS, HIS will be stopped.

Step-2 Turn off the printers.


Printers will be stopped.

Step-3 Turn off the BCU, RELAY, ETHERNET SWITCH power (for CRP PANEL)
«Result»
RELAY will be stopped.

Step-4 Turn off the MASTER CUBICLE


Ethernet switch will be stopped.
SC-1/GW-1 will be stopped
SC-2/GW-2 will be stopped
GPS clock will be stopped

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

«Criteria»
Unnecessary error and error message are not detected on each system component during system Shutdown.
The condition of system component after completely Shutdown is as follows.

No System Components Indications Result


1 BCUs [IN SERVICE] LED OK
2 RELAYs [IN SERVICE] LED OK
3 GPS [Power] LED OK
4 ETHERNET SWITCH [Power] LED OK
5 Gateway [Power] LED OK
6 EWS [Power] LED OK
7 OWS [Power] LED OK
8 PRINTER [Power] LED OK
Note : Communication failure will be detected during system shutdown.

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0
No.5 Security Management

Confirm that security system permits to access right of password correspond which has four security levels for operations.

«Criteria»
Following operations are permitted according to the respective security levels.

Level 4 View level


View level that it is possible to startup the system, to switch the screen from the top menu screen to the On-line mode
screens and monitor them, to stop an alarm sound, to display on-line help, to take a screen hard copy.

Level 3 Operator level

Level 2 Engineer level


Engineering level which in addition to level 3, this level permits to on-line set-up of upper or lower measurement limits, to
permit the remote access on the EWS, to modify the group of trend graph, to modify the report display Items or data, to
maintenance the auto printing setting on the report screen, to change the relay monitoring screen, to set the plant Item
Information, to switch the test or maintenance mode, manual override function, operate Interlock bypass control.

Level 1 System manager level


System Manager level, which in addition to level 2, this level permits to database maintenance, and user registration.

Level ID Password
4 viewer viewer
3 operator operator
2 engineer engineer
1 SystemManager TSB knows Password

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

Security Management
Security level
4 3 2 1
1 Startup the system x x x x
2 Shutdown the system x x x x
3 Switch and monitor the screen x x x x
4 Stop the audible alarm x x x x
5 Print screen x x x x
6 Display the on-line help x x x x
7 Select the “ACK” on the alarm screen N/A x x x
8 Select the “FILTER” on the event/alarm screen N/A x x x
9 “SAVE”, ”LOAD” and ”PRINT” the event record N/A x x x
10 Control the switchgear and Transformer tap N/A x x x
11 Set the blocking function N/A x x x
12 Set the manual override function N/A N/A x x
13 Set the safety tag N/A x x x
14 Start/Stop Log printer N/A x x x
15 Set the upper and lower limit N/A N/A x x
16 Modify the group of trend graph (EWS) N/A N/A x x
17 Modify the energy report item and data (EWS) N/A N/A x x
18 Set the auto print setting (EWS) N/A N/A x x
19 Set the plant Item Information N/A N/A x x
20 Switch the on-line/test mode of EWS/IED N/A N/A x x
21 Database maintenance (EWS) N/A N/A N/A x
22 Edit the Bay information N/A N/A N/A x
23 Permit the remote access on the EWS N/A N/A N/A x
24 User registration(EWS) N/A N/A N/A x
25 Operate the Interlock/synchronise bypass N/A N/A x x

«Result»

Level Security level Result


4 Viewer level OK
3 Operator level OK
2 Engineer level OK
1 SystemManager level OK

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0
No.6 System Function Test

1 Safety Tag Function Check


>> Right Click the Bay Name Point
>> Open Safety Tag
>> Correct Indicaiton in Bay Display

Result : OK Remarks :

2 Blocking Function
>> Right Click the Bay Name Point
>> Open Blocking List
>> Check Blocking Function Correctly

Result : OK Remarks :

3 Event Save Function


>> Open Event List
>> Click the Save
>> Possible to Open the Save Event

Result : OK Remarks :

4 Counter Value Check


>> Close → Open of each Device ( Q0,Q1 etc...)
>> After Open, Each Device Count Up

Result : OK Remarks :

5 Trend Function Test


>> Open Trend Buttun
>> Possible to Use Each Function Button.

Result : OK Remarks :

6 Report Function Test


>> Open Report Buttun
>> Possible to Use Each Function Button.

Result : OK Remarks :

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA


CLIENT CONSULTANT

END USER CONTRACTOR

Contract No: 17-2019/SPMB-TOSHIBA/T2PR-G06 Project: 220kV Phan Ri Substation


Document: Site Acceptance Test Procedure and Record for SCS System Startup & Shutdown Rev.0

7 HDD Capacity Check


>> Check OWS,EWS [C:Drive] Capacity
>> Check GW/SC [/dev/hdb2] Capacity (command: df -h)
* «Criteria» Over 40 % Spare.

Result : OK Remarks :

8 Time Synchronization Check


* Each Type of IEDs (Ry, BCU, IFU) Check Time Synchronization
>> Change IED Time Setting (E.g. 18:00:00 → 11:00:00)
>> Waiting For Time Synchronization.
>> After Time synchronizaiton, Same as Master Clock Time.
Result : OK Remarks :

9 Login Time Check


Push Login Buttun → Open Display
EWS : 15 s
OWS : 15 s
HIS : 15 s
* «Criteria» Less than 300 s
Result : OK Remarks :

10 Auto Log Out Check


>> Stop the Mouse Operation
>> Check Auto Log out after Setting Time.
Result : OK Remarks :

«Remarks»

Description Name Signature Date


Carried out by TOSHIBA LÊ XUÂN CƯƠNG

Witnessed PTC3 NGUYỄN XUÂN QUÝ

Reviewed SPMB NGUYỄN ANH KHOA