Name
Date
CONTENTS:
1. PURPOSE
2. SCOPE
3. SPECIFICATIONS
5. MATERIALS
6. GRADE OF CONCRETE
8. CONCRETE PRODUCTION
10.2 PLACING
10.3 COMPACTION
10.4 CURING
14 WATER STOPPER
CONTENTS:
16 FIELD TEST
17 ACCEPTANCE CRITERIA
19 FORMWORK
20 PRECAST ELEMNETS
22 INSPECTION FORMATS
23 DOCUMENTATION.
1 PURPOSE:
The purpose of this procedure is to carry out concreting works at site and to ensure that
proper quality control and quality assurance is achieved at DHDT NUMALIGARH Project.
2 SCOPE:
This procedure covers the various steps involved in executing plain, Reinforced & liquid
retaining structure concreting works for various structures like foundation, pedestals, column,
slabs, precast elements etc. including curing, testing, finishing and repairing of concreting in
DHDT Unit.
3 SPECIFICATION
EIL Specification No.6-68-002 Rev.04 , 6-68-004 Rev-06, 6-68-005 Rev-05
Latest revision of IS: 456, IS 2386, IS 10262,IS 8112,IS12269,IS 455,IS 1489, IS 383, IS 2502,
IS 1786, IS 516, IS3025, IS 3370 (Part 1);1965,and IS2430
Latest revision of IS: 3370, IS:6494, IS:12118, IS:1838,(For Liquid retaining structures)
Approved construction drawings.
QA/ QC Engineer: QA/ QC Engineer shall be responsible for site QA/ QC activities, non-
conformance management and compilation of records
Field Engineers: Field Engineers shall be responsible for the site construction activities and
implementation of all plans following safety & quality standards.
5 MATERIALS
FINE AGGREGATE
COURSE AGGREGATE
CEMENT:
Cement will be Ordinary Portland cement or Portland Pozzolona cement as mentioned in
tender document for super structure and sub structure concrete work. Cement will be stored
in go-downs/Silos at site/Batching plant to protect from dampness and will be made easily
accessible for proper inspection and accounting.
Cement received at site for the work shall have MTC.
Sample of each week number shall be tested at field laboratory for consistency, Setting time
and compressive strength.
CURING COMPOUND:
As alternate arrangement, Curing compound shall be used of approved make in consultation
with EIC. Every batch certificate shall be verified by EIL and accepted through material
Inspection report (IMIR).
STEEL
Tor steel reinforcement shall be procured from approved manufacturer for cement concrete
works conforming to high yield strength deformed steel bars of Gr. Fe 500 of IS: 1786 and
co related with MTC (Manufacturer’s test certificate) and Challan issued by manufacturer.
Material shall be accepted based on manufacturer’s test certificate and review of
certificates/test reports and other documents like delivery order, delivery challan etc. MTC
will be produced for all types of reinforcement steel and for all the consignments coming to
site.
All reinforcement bars will be clean and free from dirt, oil, paints, grease, mill scales and
loose rust. Bar bending schedule will be prepared before cutting.
WATER
The water used for concrete work shall be clean and free from harmful chemicals and
organic material. To ascertain the same, a sample of water will be tested in any of the
approved laboratories prior to the commencement of work and later on in case if any visible
change is found. The water shall be in general conforming to the requirement of IS
456:2000.
It shall be clean and fresh, free from oils, acids, alkalis or other deleterious
material whether in solution or in suspension.
Prepared by Checked by Approved by
ABB ABB ABB
Name
Date
Job Procedure for Job Procedure No Page No: Page 6 of 20
PCC/RCC ABB /NRL/DHDT/SS-9/JP-02, Rev 0
N OWNER
RL ABB INDIA LTD. PMC
ADMIXTURE
6 GRADE OF CONCRETE
Grade of concrete shall be as per drawing
8 CONCRETE PRODUCTION.
For all PCC works, the concrete will be mixed in batching plant or at site using RM-800
Mixture machine with approval of EIL
Before laying PCC, sub base at founding level shall be compacted as Per specification.
Compaction of lean concrete will be done manually using rammers.
Formwork for PCC will be done using battens / wooden planks / Steel channels.
For all the RCC structures, bar bending schedule will be prepared as per drawings.
Batching of cement, coarse aggregates, sand and water will be done in batching
plant. The Engineer in charge will be informed about the concreting program well in
advance and the arrangement and availability of materials and necessary equipment
will be checked before calling for inspection. All information regarding a particular
concrete pour will be incorporated in Concrete program and inspection plan and the
concreting will commence only after due review of relevant QA document.
The ingredients will be mixed in a mechanical mixer. Weigh batcher of batching plant
will measure the coarse and fine aggregates. The mixing time will not be less than 2
minutes for a mixer of 2 cum. capacity and 3 minutes for a mixer of capacity more
than 2 cum. The concrete will be transported and placed on a clean bed or directly in
the Formwork. Concrete will not be dropped from a height of more than 1.5 meter
and will be laid in position in horizontal layers. The concrete, after being laid will be
compacted using vibrators. The whole process will be completed before initial setting
takes place.
Whenever a construction joint as per drawing to be provided in a monolithic structure,
bonding grooves will be formed in the concrete already laid and the surface will be
roughened, cleaned and given a wash of neat cement slurry before laying new
concrete as laid down in clause 12.4.1 of IS: 456.
The construction joint shall be vertical in case of beams & slabs & shall be thoroughly
cleaned & hacked before resuming the concrete works. In case of construction joint, the joint
shall be covered with cement mortar of the ratio same as that of concrete mix, on the
same plane
All inserts, anchors, sleeves and all other embedded items shall be at site prior
to the start of concrete.
10.2 PLACING
The method of placing of concrete shall depend on the quantity of concrete, type
of structure, type of formwork etc.
The concrete pour shall be checked for the position, level, proper
reinforcements, embedded parts, and adequacy of shuttering, Scaffolding etc &
Concreting shall be commenced on approval from engineer in charge.
Concrete shall be laid in layers no greater than 400 mm, and each layer shall be
compacted using appropriate vibrators. Concrete shall not be moved horizontally
by vibration, and care taken to avoid segregation while pouring. Concrete shall
be placed while it is sufficiently plastic for full compaction. It shall be worked
around reinforcements and embedded items
Placement of concrete shall continue until the completion of the concrete in one
pour to avoid cold joints in concrete unless construction joints are specified
The maximum permissible free fall of concrete may be taken as 1.5 mts, In case
shuttering height more than 1.5 Mts shall be poured using boom placer.
Mass concrete shall be planned and discussed with EIC well in advance,
separately with pour sequence, rate of pour, pumping arrangement and
vibrators as required
Concrete shall be placed without segregation ,
The concrete shall be placed in its final position and compacted before initial
setting time of concrete commences after first mixing of water, cement and
aggregates
Water for use in mixing concrete and curing shall comply with the requirements
of IS 456
Wherever construction, contraction and expansion joints occur in the water
retaining concrete structures as per drawings these joints shall be made
watertight.
For Provision of Construction Joint at place other than mentioned in drawing
prior approval shall be taken from Engineer in charge.
No wet concrete shall be placed in flowing water
Concreting shall be carried out continuously up to construction joints
Vertical construction joints shall be formed by the insertion of rigid stopping off
forms.
Any remedial treatment to concrete surfaces shall be agreed with the company
Representative and shall be carried out without delay and before the application
of any curing membrane.
Any concrete surface which is found improper shall be inspected by the
company Rep before treatment.
10.3 COMPACTION
Concrete should be thoroughly compacted and fully worked around the reinforcement,
around embedded fixtures and into corners of the formwork.
Whenever vibration has to be applied externally, the design of formwork and the
disposition of vibrators should receive special consideration to ensure efficient
compaction and to avoid surface blemishes.
10.4 CURING
Curing is the process of preventing the loss of moisture from the concrete whilst
maintaining a satisfactory temperature regime. The curing regime shall also
prevent the development of high temperature gradients within the concrete.
Curing compound of approved brand shall be applied in RCC Exposed surface
structure by spraying and brushing where ever water curing is not possible..
Curing compound shall confirm to the relevant IS code.
Exposed surface of concrete shall be maintained continuously damp or wet
condition at least for7 days.
12 SEPERATION JOINT.
Expansion joints shall be provided at the locations and to the details shown on
Drawings, with the joints filled with approved joint filling material.
14 WATER STOPS.
PVC water stops as per ElL Specification No. 6-68-0002 for materials shall be
accurately cut, fitted and integrally joined as per manufacturer's specifications
to provide a Continuous, watertight diaphragm at all points
Water stops shall be provided at locations as shown in drawing.
Adequate provision shall be made for the support and protection of water stops
during the
Progress of the work. Damaged water stops shall be replaced and/or repaired
as directed
16 FIELD TEST.
Grading test on fine and coarse aggregates shall be carried out as per IS: 2386
& frequency shall be as per ITP
Slump cone shall be used to check the workability of concrete at batching plant
& site as per ITP
Samples from fresh concrete shall be taken as per IS: 1199 and cubes shall be
made. cured and tested at 28 days in accordance with IS: 516.
Generally 1 set of cube (6Nos), 3 cubes for 28 days testing (If required, 3 shall be tested
for 7 days ).
Frequency of sampling shall be 1 set per 50 Cum or 50 batches whichever is greater
frequency of production of concrete for each Grade (as per clause no.6.3.2 of IS: 4926-
2003.
Cube id shall be marked as per EIL Std 6-68-0004 Rev-6, clause no:15.3.6 as follows
First line: AF (Code Assigned By EIC)
Second line: XXXX(Unique integer starting from 0001, if required grade of concrete)
Third line: DD-MM-YEAR (Date of casting of cube)
17 ACCEPTANCE CRITERIA.
The concrete shall be deemed to comply with the strength requirement when both the
Conditions as given in Table-II of IS: 456 for that particular grade of concrete are
simultaneously met. Standard deviation during the routine concreting shall be taken for 30
cubes.
If required, non destructive test shall be conducted, in case concrete sampling cube fails to
meet the acceptance criteria as mentioned in IS;456 Table -II
patch concrete for larger repairs. If required epoxy bondage shall be carried out for
repairing patches, which shall be applied as per manufacturer’s recommendation.
Concrete for larger repairs. If required epoxy bondage shall be carried out for
repairing patches, which shall be applied as per manufacturer’s
recommendation.
The repaired area shall be cured by covering with a wet saturated material, for
a period of 24 hours. The subsequent curing of the repair by sprinkling water
shall continue for at least 7 days.
19 FORMWORK.
been placed and care shall be taken that no oil comes in contact with
reinforcement, while it is being placed in position.
Before concreting is commenced, the formwork shall be carefully examined to
ensure the following:
1 Removal of all dirt, sawdust and other unwanted material by brushing and
blowing air.
2 The correct location of tie bars, bracing and spacers, and especially
Connections of bracing.
Tolerances for formed surfaces shall follow IS 456 clause no 15.3.9.7 &
15.3.9.8 and EIL STD 6-68-0004,Rev-6
Where props are required by the specification to continue to provide support
after the general striking of formwork they shall remain undisturbed till their
final removal.
Formwork shall be removed without causing damage or deflection to the
concrete.
The PVC cone used for alignment of wall shutters shall be removed from the
concrete and ends of the conduit pipes shall be sealed and cone portion shall
be grouted with mortar. Care shall be taken to match the appearance of the
repaired portion to the color of the concrete poured.
20 PRECAST ELEMENTS.
The appropriate area shall be selected for casting precast elements the
Same shall be leveled, graded and compacted
Reinforcement works for precast elements shall be done as per Approved
BBS.
Form work for precast elements shall be done as per clause 18.
A part of form work may be of fixed form work made of concrete / steel to
Reduce the quantum of shuttering and de-shuttering activity
De-shuttering for vertical forms shall be done not before initial setting time of
Concrete.
Concreting shall be done as per clause No. 6 to 15 as mentioned above.
Suitable Serial no & Date of Casting shall be painted on each unit.
Reinforcement & lifting hook shall be provided as shown in drawings
The relocation and lifting of pre-cast members shall be done only after 7
Days of casting
Transportation of pre-cast elements shall be done using appropriate size of
Vehicle.
All the precast elements shall be given appropriate protection while
Transportation to avoid any kind of damage to the elements
Care shall be taken during erection without causing shock, Vibration or
21 DOCUMENTATION
NOTE: In case of any conflict between this procedure and EIL Specifications, the later shall be
governed