Академический Документы
Профессиональный Документы
Культура Документы
INTRODUCTION
MODULE 1 - INTRODUCTION
Solve PMP Q & A for better prepare
4
07/07/2018
Project Management Framework
The Five Process Groups
1. Initiating
2. Planning
3. Executing
MODULE 1 - INTRODUCTION
4. Monitoring and Controlling
5. Closing
6
07/07/2018
Course Outline
Module 1 Introduction
Module 2 The Environment in Which Projects Operate
Module 3 The Role of The Project Manager
Module 4 Process Groups and Knowledge Areas
Module 5 Initiating Process Group
MODULE 1 - INTRODUCTION
Module 6 Planning Process Group
Module 7 Executing Process Group
Module 8 Monitoring and Controlling Process Group
Module 9 Closing Process Group
Module 10 Agile Practice Guide
8
07/07/2018
Workshop Rules 2/4
MODULE 1 - INTRODUCTION
quickly
10
07/07/2018
Workshop Rules 4/4
MODULE 1 - INTRODUCTION
The Classroom in non-smoking area
12
07/07/2018
PMI offers a comprehensive certification program for practitioners with
different levels of education and experience
MODULE 1 - INTRODUCTION
PMI Risk Management Professional (PMI-RMP)® credential
14
PMP Eligibility Requirements
72 Sec / question
MODULE 1 - INTRODUCTION
25 non-graded questions
18
07/07/2018
Listen, focus and take notes
After each day, read the relative PMBOK
chapters quickly
Re-read PMBOK thoroughly in parallel to
the course material
Solve at least 3-4 full PMP tests
MODULE 1 - INTRODUCTION
Review your answers correct or wrong by
going back to PMBOK
Assess your weaknesses and re-study the
sections you are weak in
When you achieve a score of 80% or more,
you are ready for the test
20
07/07/2018
Projects - Unique product, service or result
All projects produce something unique which has never been produced
before
Example:
MODULE 1 - INTRODUCTION
A project to produce a building has a unique design, location,
resources, etc.
22
07/07/2018
Projects Drive Change
MODULE 1 - INTRODUCTION
24
07/07/2018
Projects Initiation Context
MODULE 1 - INTRODUCTION
Create, improve or fix products, processes or services.
26
Projects Initiation Context
MODULE 1 - INTRODUCTION
Projects either within or outside the program are still considered part of a
portfolio
32
Project
Sub-Project
07/07/2018
Project, Program, Portfolio and Operations
MODULE 1 - INTRODUCTION
Portfolio management focuses on doing the programs
and projects.
34
07/07/2018
Portfolio Management
management refers to the centralized management of one
or more portfolios to achieve strategic .
MODULE 1 - INTRODUCTION
The projects and programs of the portfolio may not necessarily be
interdependent or directly related.
36
07/07/2018
Projects vs. Operations 1/2
MODULE 1 - INTRODUCTION
Differences between Operations and Projects
Operations have any timeline. Projects are temporary have finite time
duration
38
07/07/2018
Organizational Project Management
(OPM) and Strategies
Portfolios, programs and project are aligned with or driven by
organizational strategies.
MODULE 1 - INTRODUCTION
The purpose of OPM is to ensure that organization undertakes the
right projects and allocates critical resources appropriately.
40
07/07/2018
Project Life Cycle
MODULE 1 - INTRODUCTION
Provides the basic framework for managing the project, regardless of
the specific work involved
42
07/07/2018
Project Life Cycle
Characteristics
Cost and staffing levels are low at the start, peak as the work is
carried out, and drop rapidly as the project draws to a close
Risk and uncertainty are greatest at the start of the project, then
decrease over the life of the project
MODULE 1 - INTRODUCTION
Ability to influence is highest at the start of the project and decreases
as the project progresses towards completion
44
07/07/2018
Project Life Cycle
Project Phases
MODULE 1 - INTRODUCTION
underway and to change or terminate the project if necessary.
This point may be referred to as a stage gate, milestone, phase
review, phase gate or kill point
46
07/07/2018
Project Life Cycle
Phase-to-Phase Relationship
Sequential relationship
A phase start only when the previous phase is complete
Overlapping relationship
MODULE 1 - INTRODUCTION
A phase starts prior to completion of the previous one
48
07/07/2018
Project Life Cycle
Predictive Life Cycles
Project scope, time and cost are determined as early in the project life
cycle as practically possible
MODULE 1 - INTRODUCTION
where a product to be delivered in full to have value to stakeholder
groups
50
07/07/2018
Project Life Cycle
Iterative and Incremental Life Cycles
MODULE 1 - INTRODUCTION
High-level vision will be developed for the overall undertaking, but
the detailed scope is elaborated one iteration at a time
MODULE 1 - INTRODUCTION
Example:
Project undertaken to bring a new notebook computer to market is only one
phase in the product life cycle
54
07/07/2018
Project Data and Information
Key terminologies regarding project data and information:
MODULE 1 - INTRODUCTION
process, analyzed in context and integrated based on relationships
across areas (status of deliverables, forecasts estimates to complete)
MODULE 1 - INTRODUCTION
Project management methodologies may be:
MODULE 1 - INTRODUCTION
the project business case document.
60
07/07/2018
Project Management Business Documents
Project Business Case 1/2
MODULE 1 - INTRODUCTION
Helps measure the project success at the end of the project against
the project objectives.
May include:
MODULE 1 - INTRODUCTION
Target benefits (tangible and intangible)
Meeting the agreed-upon financial measures documented in the business case, such as:
MODULE 1 - INTRODUCTION
Internal rate of return (IRR)
66
Achieving stockholders satisfaction
07/07/2018
Project Financial Measures
Return On Investment (ROI)
MODULE 1 - INTRODUCTION
cost)/cost, or (230,000 200,000)/200,000 = 15%
68
07/07/2018
Project Financial Measures
Payback Period (PBP)
a project
If someone owed you $100, you would prefer that they pay it to you
immediately rather than paying you $25 per month for 4 months
MODULE 1 - INTRODUCTION
A shorter payback period is better than a longer one
70
07/07/2018
Financial Matrices Table
MODULE 1 - INTRODUCTION
Net Present Value NPV The biggest number $47,500
(Year are already factored in)
72
07/07/2018
The Project Environment
Overview
MODULE 2
74
07/07/2018
Enterprise Environmental Factors (EEFs)
EEFs refers to conditions, not under the control of the project team,
that influence, or direct the project.
MODULE 2
76
07/07/2018
Enterprise Environmental Factors (EEFs)
EEFs external to the organization:
MODULE 2
Financial considerations (currency exchange rates, interest rates,
inflation)
Governance framework
MODULE 2
Organizational structure types
80
07/07/2018
Organizational Systems
Governance frameworks
Policies
Procedures
Processes
MODULE 2
82
Functional Organization 1/2
MODULE 2
Take control of the project by directly managing the
projects.
Directive
MODULE 3
organization to lead the team that is responsible for achieving the
project objectives.
100
07/07/2018
The Role of The Project Manager
The Project:
The Organization:
Proactively interacts with other project managers (independent or part of the
same program)
MODULE 3
Interacting in the form of human, technical, or financial resources and
deliverables required by the team for project completion.
102
07/07/2018
The Role of The Project Manager
Project Manager Competences
Leadership Skills
Being visionary
Being collaborative
Manage conflicts
Being respectful
MODULE 3
Being a life-long learner
Leadership Styles
Knowledge Areas =
MODULE 4
112
07/07/2018
Project Processes Categories
Project Management Processes: ensure the effective flow of
Note:
MODULE 4
- The PMBOK Guide 6, describes only the project management processes
- There are 49 processes in PMBOK Guide 6
114
Project Management Process Interactions
Develop the project management plan and the project documents that will be used to
carry out the project
As more information are gathered and understood, additional planning will likely be
required
Progressive elaboration, indicating that the planning and documentation are iterative
and ongoing activities
MODULE 4
Updates arising from approved changes during the project (generally during
Monitoring and Controlling processes and specially during the Direct and Manage Project
Work Process) may significantly impact parts of the project management plan and project
118
documents
07/07/2018
Monitoring and Controlling Process Group
Those processes required to track, review, and regulate the progress
MODULE 4
Monitors and controls the work being done, and monitors and
controls the entire project effort
120
07/07/2018
Project Management Framework 1/2
Project Management Process Groups (49 Processes)
Project Integration Develop Project Develop Project Direct and Manage Monitor and Control Close Project or
Management (7) Charter Management Plan Project Work Project Work Phase
Manage Project Perform Integrated
Knowledge Change Control
MODULE 4
Estimate Costs
Determine Budget
122
MODULE 5
GROUP
INITIATING PROCESS
126
07/07/2018
MODULE 5 - INITIATING PROCESS GROUP
Initiating Process Group
128
07/07/2018
Initiating Process Group
1. Develop Project Charter Inputs, Tools, Outputs
130
07/07/2018
Initiating Process Group
1. Develop Project Charter Tools & Techniques
Expert Judgment
Examples:
- Other unit within the organization
- Consultants
132
07/07/2018
Initiating Process Group
1. Develop Project Charter Tools & Techniques
134
07/07/2018
Initiating Process Group
1. Develop Project Charter Outputs
Project Charter
136
07/07/2018
Initiating Process Group
1. Develop Project Charter Outputs
Assumption log
138
07/07/2018
MODULE 5 - INITIATING PROCESS GROUP
Initiating Process Group
2. Identify Stakeholders
140
07/07/2018
Initiating Process Group
2. Identify Stakeholders Inputs, Tools, Outputs
Project documents
144
07/07/2018
Initiating Process Group
2. Identify Stakeholders Tools & Techniques
Data analysis
146
07/07/2018
Initiating Process Group
2. Identify Stakeholders Tools & Techniques
Stakeholder/mapping representation
152
MODULE 5
GROUP
PLANNING PROCESS
156
Stakeholder Stakeholders Engagement Engagement Engagement
Management (4)
07/07/2018
Planning Process Group
List of Processes
19 Identify Risks
158
24 Plan Stakeholder Engagement Project Stakeholder Management
07/07/2018
Planning Process Group
1. Develop Project Management Plan - Introduction
160
07/07/2018
Planning Process Group
1. Develop Project Management Plan - Inputs
Any baselines and subsidiary plans that are an output from other
162
07/07/2018
Planning Process Group
1. Develop Project Management Plan - Tools & Techniques
Meetings
The project kick-off meeting is usually associated with the end of planning
and start of the execution.
164
07/07/2018
Planning Process Group
1. Develop Project Management Plan Outputs
- Schedule baseline
- Cost baseline
166
07/07/2018
Planning Process Group
1. Develop Project Management Plan Outputs
- Project life cycle - Life cycle selected and processes applied to each phase
172
07/07/2018
Planning Process Group
2. Plan Scope Management Inputs, Tools, Outputs
174
07/07/2018
Planning Process Group
2. Plan Scope Management Tools & Techniques
Data analysis
176
07/07/2018
Planning Process Group
2. Plan Scope Management Outputs
The key benefit of this process is that it provides the basis for defining and
180
07/07/2018
Planning Process Group
3. Collect Requirements Inputs
Project documents
182
07/07/2018
Planning Process Group
3. Collect Requirements Tools & Techniques
Decision making
Technique Description
184
07/07/2018
Planning Process Group
3. Collect Requirements Tools & Techniques
Data representation
186
07/07/2018
Planning Process Group
3. Collect Requirements Tools & Techniques
Helpful for detailed processes when the people that use the product
have difficulty to articulate their requirements.
188
07/07/2018
Planning Process Group
3. Collect Requirements Tools & Techniques
Context Diagrams
Requirements Documentation
Describes how individual requirement meet the business need for the
May start out at a high level and become progressively more detailed
as more about the requirements is known
192
07/07/2018
Planning Process Group
3. Collect Requirements Outputs
194
4. Define Scope
Planning Process Group
198
07/07/2018
Planning Process Group
4. Define Scope Outputs
202
07/07/2018
Planning Process Group
4. Define Scope Outputs
- Stakeholder register
- Requirements documentation
204
07/07/2018
Planning Process Group
5. Create WBS - Introduction
206
07/07/2018
Planning Process Group
5. Create WBS Tools & Techniques
Decomposition
The work package is the work defined at the lowest level of the WBS
for which cost and duration can be estimated and managed.
208
07/07/2018
Planning Process Group
5. Create WBS Tools & Techniques
Decomposition
210
07/07/2018
Planning Process Group
5. Create WBS Tools & Techniques
Decomposition
100% Rule
The total of the work at the lowest levels should roll up to the higher
levels so that nothing is left out and no extra work is
performed.
214
07/07/2018
Planning Process Group
5. Create WBS - Outputs
Scope Baseline
Scope Baseline
WBS
218
07/07/2018
Planning Process Group
5. Create WBS - Outputs
Scope Baseline
Control Account
220
07/07/2018
Planning Process Group
5. Create WBS - Outputs
approved changed.
222
07/07/2018
Planning Process Group
List of Processes
19 Identify Risks
224
24 Plan Stakeholder Engagement Project Stakeholder Management
07/07/2018
Planning Process Group
6. Plan Schedule Management - Introduction
226
07/07/2018
Planning Process Group
6. Plan Schedule Management - Tools & Techniques
Data analysis
Determining which scheduling methodology to use.
228
07/07/2018
Planning Process Group
6. Plan Schedule Management - Outputs
- Units of measure. Staff hours, days, weeks for time or meters, tons for quantity
232
07/07/2018
Planning Process Group
7. Define Activities Tools & Techniques
234
07/07/2018
Planning Process Group
7. Define Activities Outputs
Activity Attributes
Extend the description of the activity by identifying the multiple
components associated with each activity.
When completed:
- Activity codes, activity description, predecessor activities, successor activities,
logical relationship, leads and lags, resource requirements, constraints and
assumptions
Can be used to identify the person responsible for executing the work,
geographic area or place where the work has to be performed.
236
07/07/2018
Planning Process Group
7. Define Activities Outputs
Change requests
One the project has been baselined, the progressive elaboration of
238
07/07/2018
MODULE 6 - PLANNING PROCESS GROUP
Planning Process Group
8. Sequence Activities
240
07/07/2018
Planning Process Group
9. Sequence Activities Inputs, Tools, Outputs
242
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
Activity-on-node (AON)
244
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
246
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
248
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
250
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
- Example: the first security guard shift (successor) cannot finish until the
second security guard (predecessor) starts
Activity A Activity B
252
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
254
A summary activity in a network diagram
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
Dependency Determination
Mandatory Dependencies
Discretionary Dependencies
- Established based on knowledge of best practices within a particular
application area
260
07/07/2018
Planning Process Group
8. Sequence Activities Tools & Techniques
264
07/07/2018
MODULE 6 - PLANNING PROCESS GROUP
Planning Process Group
266
07/07/2018
Planning Process Group
9. Estimate Activity Durations - Introduction
268
07/07/2018
Planning Process Group
9. Estimate Activity Durations Inputs, Tools, Outputs
270
assets
07/07/2018
Planning Process Group
9. Estimate Activity Durations Tools & Techniques
Parametric Estimating
Uses a statistical relationship between historical data and other
272
07/07/2018
Planning Process Group
9. Estimate Activity Durations Tools & Techniques
Three-Point Estimating
The expected duration tE can be calculated by using one of the
- Triangular Distribution
- tE = (tO + tM + tP) / 3
274
07/07/2018
Planning Process Group
9. Estimate Activity Durations Tools & Techniques
Bottom-up estimating
It is a method of estimating project duration by aggregating the
276
07/07/2018
Planning Process Group
9. Estimate Activity Durations Tools & Techniques
Reserve Analysis
Contingency Reserves
Decision making
Such as voting.
Project manger ask the team to show their level of support for a decision
by holding up a closed fist (no support) up to five fingers (full support)
If a team member holds up fewer than three fingers, the team member is
given the opportunity to discuss any objections with the team
280
07/07/2018
Planning Process Group
9. Estimate Activity Durations Outputs
Basis of Estimates
284
07/07/2018
Planning Process Group
10. Develop Schedule Inputs, Tools, Outputs
Inputs Tools & Techniques Outputs
Project management plan Schedule network Schedule baseline
- Schedule management plan analysis Project schedule
- Scope baseline Critical path method Schedule data
Project documents Resource optimization Project calendars
Dates Description
288
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
290
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
292
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
294
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Total Float
Free Float
298
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Negative Float
- It tells you that your schedule has problems. It most often occurs
when constraints or milestones are imposed by forces outside the
project, causing an impossible situation.
they include:
- Resource Leveling
- Resource Smoothing
302
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Data analysis
What-if Scenario Analysis
308
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Schedule Compression
It is a technique used to shorten the schedule duration without
It includes:
- Crashing
- Fast tracking
310
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Schedule Compression
Fast Tracking
312
07/07/2018
Planning Process Group
10. Develop Schedule Tools & Techniques
Allows the product owner and team to decide how much needs to be
developed and how long it will take to have a releasable product
based on business goals.
314
07/07/2018
Planning Process Group
10. Develop Schedule Outputs
Schedule Baseline
It is the approved version of a schedule model that can be changed
316
07/07/2018
Planning Process Group
10. Develop Schedule Outputs
Project Schedule
Milestone Charts
318
detailed schedule
07/07/2018
Planning Process Group
10. Develop Schedule Outputs
Project Schedule
Project Calendars
Identifies working days and shifts that are available for scheduled
322
07/07/2018
Planning Process Group
List of Processes
19 Identify Risks
324
24 Plan Stakeholder Engagement Project Stakeholder Management
07/07/2018
Planning Process Group
11. Plan Cost Management - Introduction
326
07/07/2018
Planning Process Group
11. Plan Cost Management Tools & Techniques
Data analysis
Choosing strategic options to fund the project (self-funding,
328
07/07/2018
Planning Process Group
11. Plan Cost Management Outputs
- Level of precision, the degree to which the activity cost estimates will
be rounded up or down (US$100.49 to US$100)
332
07/07/2018
Planning Process Group
12. Estimate Costs Inputs, Tools, Outputs
334
07/07/2018
Planning Process Group
12. Estimate Costs Tools & Techniques
Reserve Analysis
Management Reserves
- They are NOT include in the cost baseline, but they are part of the
overall project budget and funding required for the project.
Cost Estimates
Activity cost estimates are quantitative assessments of the probable
Costs are estimated for all resources that are applied to the activity
cost estimate.
338
07/07/2018
MODULE 6 - PLANNING PROCESS GROUP
Planning Process Group
340
07/07/2018
Planning Process Group
13. Determine Budget Inputs, Tools, Outputs
342
07/07/2018
Planning Process Group
13. Determine Budget Tools & Techniques
Historical Relationships
Any historical relationships that result in parametric or analogous
- Scalable, (work for large project, small projects and phases of a project)
344
07/07/2018
Planning Process Group
13. Determine Budget Tools & Techniques
Financing
Financing entails acquiring funding for projects.
346
07/07/2018
Planning Process Group
13. Determine Budget Outputs
Cost Baseline
348
07/07/2018
Planning Process Group
13. Determine Budget Outputs
Cost Baseline
354
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
356
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
- Implies that the needs of the costumers and stakeholders are defined
and then attempted to satisfy
358
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
Definitions
362
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
Definitions
Standard Deviation
- Standard Deviation SD =
- 6 = 99.9997%
364
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
Definitions
Sigma
- P is Pessimistic, O is Optimistic
366
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
Definitions
- Control limits are set at three standard deviations above and below
the mean. A long as your results fall within the control limits, your
process considered to be in control.
Just-In-Time
Product Maturity
370
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
372
07/07/2018
Planning Process Group
14. Plan Quality Management - Introduction
374
07/07/2018
Planning Process Group
14. Plan Quality Management Tools & Techniques
Cost-Benefit Analysis
The primary benefits of meeting quality requirements include less
376
07/07/2018
Planning Process Group
14. Plan Quality Management Tools & Techniques
380
07/07/2018
Planning Process Group
14. Plan Quality Management Tools & Techniques
Flowcharts
Matrix diagrams
388
07/07/2018
Planning Process Group
List of Processes
392
07/07/2018
Planning Process Group
15. Plan Resource Management Inputs, Tools, Outputs
Outputs
Inputs Tools & Techniques
Resource
Project charter Expert judgment management plan
Project management plan Data representation
394
07/07/2018
Planning Process Group
15. Plan Resource Management Tools & Techniques
Assignment Matrix
396
07/07/2018
Planning Process Group
15. Plan Resource Management Tools & Techniques
Text-oriented formats
398
07/07/2018
Planning Process Group
15. Plan Resource Management Outputs
Resource Management Plan
It is a part of the project management plan, provides guidance on how project human
resources should be defined, staffed, managed and eventually released.
402
07/07/2018
Planning Process Group
15. Plan Resource Management Outputs
404
07/07/2018
Planning Process Group
15. Plan Resource Management Outputs
Team charter
It is a document that establishes the team values, agreements, and
It is include:
- Team values
- Communication guidelines
- Meeting guideline
406
07/07/2018
Planning Process Group
16. Estimate Activity Resources - Introduction
408
07/07/2018
Planning Process Group
16. Estimate Activity Resources Inputs
Cost Estimates
The cost of resources may impact resource selection
410
07/07/2018
Planning Process Group
16. Estimate Activity Resources Tools & Techniques
Alternative Analysis
Alternative methods such as:
412
07/07/2018
Planning Process Group
16. Estimate Activity Resources Outputs
414
07/07/2018
Planning Process Group
List of Processes
418
07/07/2018
Planning Process Group
17. Plan Communication Management Inputs, Tools, Outputs
420
07/07/2018
Planning Process Group
17. Plan Communication Management Tools & Techniques
Communication Technology
Such as: shared portal, video conferencing, audio conferencing,
email/chat.
- Availability of technology.
- Ease of Use.
Communication Models
426
07/07/2018
Planning Process Group
17. Plan Communication Management Tools & Techniques
428
07/07/2018
Planning Process Group
17. Plan Communication Management Outputs
430
07/07/2018
Planning Process Group
List of Processes
19 Identify Risks
Perform Qualitative Risk
20 Project Risk Management
Analysis
Perform Quantitative Risk
21
Analysis
22 Plan Risk Responses
434
07/07/2018
Planning Process Group
18. Plan Risk Management Tools & Techniques
Stakeholder analysis*
436
07/07/2018
Planning Process Group
18. Plan Risk Management Outputs
438
07/07/2018
Planning Process Group
18. Plan Risk Management Outputs
440
07/07/2018
Planning Process Group
18. Plan Risk Management Outputs
Levels of Uncertainty
444
07/07/2018
Planning Process Group
18. Plan Risk Management Outputs
Tracking
Tracking documents how risk activities will be recorded for the benefit of
the current project and how risk management processes will be audited.
446
07/07/2018
Planning Process Group
19. Identify Risks- Introduction
The process should involve the project team so they can develop and
maintain a sense of ownership and responsibility for the risks and
associated risk response actions.
448
07/07/2018
Planning Process Group
19. Identify Risks Inputs
Procurement documentation
If the project requires external procurement of resources, the initial
procurement documentation should be reviewed as procuring goods and
450
07/07/2018
Planning Process Group
19. Identify Risks Tools & Techniques
Delphi technique
It is a way to reach a consensus of experts
The responses are summarized and are then recirculated to the experts for
further comment.
Helps reduce bias in the data and keeps any one person from having
influence on the outcome.
Interviewing
experienced project participants, stakeholders, and subject matter experts
452
07/07/2018
Planning Process Group
19. Identify Risks Tools & Techniques
Identify a problem, discover the underlying causes that lead to it, and
454
07/07/2018
Planning Process Group
19. Identify Risks Tools & Techniques
SWOT Analysis
Risk Register
It is a document in which the results of risk analysis and risk response planning
are recorded.
The level and type of information contained in the risk register increases over time.
It will include:
458
07/07/2018
Planning Process Group
19. Identify Risks Outputs
Risk report
It may include:
Sources of overall project risk
462
07/07/2018
Planning Process Group
20. Perform Qualitative Risk Analysis Tools & Techniques
464
07/07/2018
Planning Process Group
20. Perform Qualitative Risk Analysis Tools & Techniques
Impact of a Risk
Risk Categorization
- Other useful categories (e.g., project phase) to determine the areas of the project
most exposed to the effects of uncertainty
Risks with high probability and high impact will require further analysis
including quantification and aggressive risk management.
Risks scores are then added up to calculate risk exposure for the project.
470
07/07/2018
Planning Process Group
20. Perform Qualitative Risk Analysis Tools & Techniques
476
07/07/2018
Planning Process Group
21. Perform Quantitative Risk Analysis
Inputs, Tools, Outputs
Inputs Tools & Techniques Outputs
Project management plan Expert judgment Project documents
updates
- Risk management plan Data gathering
- Risk report
- Scope baseline - Interviews
- Schedule baseline Interpersonal and team
484
07/07/2018
Planning Process Group
21. Perform Quantitative Risk Analysis Tools & Techniques
486
07/07/2018
Planning Process Group
21. Perform Quantitative Risk Analysis Tools & Techniques
494
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Escalate
Mitigate Transfer
496
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Avoid
498
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Mitigate
- Taking early action to reduce the probability and/or impact of a risk more
effective than trying to repair the damage after the risk has occurred.
500
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Accept
Document the strategy and leaving the project team to deal with the risks as they
occur
- Active acceptance
Escalate
504
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Share
506
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Accept
508
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
Avoid
Transfer/share
Mitigate/enhance
Accept
510
07/07/2018
Planning Process Group
22. Plan Risk Responses Tools & Techniques
19 Identify Risks
516
24 Plan Stakeholder Engagement Project Stakeholder Management
07/07/2018
Planning Process Group
23. Plan Procurement Management - Introduction
518
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
520
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
522
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
- The final contract price is determine after completion of all work based on
the performance.
524
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
Involves payments the seller for all legitimate actual costs incurred
526
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
- Paid only for completed work and does not change due to seller
performance.
528
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
530
07/07/2018
Planning Process Group
23. Plan Procurement Management Inputs
Cost
Fixed Price Time & Material
532
07/07/2018
Planning Process Group
23. Plan Procurement Management Tools & Techniques
534
07/07/2018
Planning Process Group
23. Plan Procurement Management Tools & Techniques
- Qualifications only: applies when the time and cost would not make sense
because the value of procurement is small
540
07/07/2018
Planning Process Group
23. Plan Procurement Management Outputs
Procurement Strategy
- Cost plus contracts are suitable when the work is evolving, likely to change,
or not well defined
- Incentives and awards used to align the objectives of buyer and seller
542
07/07/2018
Planning Process Group
23. Plan Procurement Management Outputs
Bid Documents
Used to solicit proposals from prospective sellers.
544
07/07/2018
Planning Process Group
23. Plan Procurement Management Outputs
Detailed list of all data and services that will be provided to the
contractor by the buyer
546
07/07/2018
Planning Process Group
23. Plan Procurement Management Outputs
Make-or-Buy Decisions
A make-or-buy analysis results in a decision of whether particular
548
07/07/2018
Planning Process Group
23. Plan Procurement Management
19 Identify Risks
552
24 Plan Stakeholder Engagement Project Stakeholder Management
07/07/2018
Planning Process Group
24. Plan Stakeholder Engagement- Introduction
The key benefit of this process is that it provides a clear, actionable plan
to interact with project stakeholders to support the interests.
554
07/07/2018
Planning Process Group
24. Plan Stakeholder Engagement Tools & Techniques
556
07/07/2018
Planning Process Group
24. Plan Stakeholder Engagement Tools & Techniques
558
07/07/2018
Planning Process Group
24. Plan Stakeholder Engagement Outputs
560
07/07/2018
Project Management Framework 1/2
MODULE 7
Develop Schedule
562
Management (3)
07/07/2018
Executing Process Group
List of Processes
MODULE 7
9 Conduct Procurements Project Procurement Management
10 Manage Stakeholder Engagement Project Stakeholder Management
564
07/07/2018
Executing Process Group
1. Direct and Manage Project Work - Introduction
MODULE 7
566
07/07/2018
Executing Process Group
1. Direct and Manage Project Work - Inputs, Tools,
Outputs
Inputs Outputs
Tools & Techniques
Project management plan Deliverables
Expert judgment
- Any component Work performance data
Project management
Project documents Issue log
information system
MODULE 7
Enterprise environmental documentation
factors
- Risk register
Organizational process
assets - Stakeholder register
Organizational process
assets updates
568
07/07/2018
Executing Process Group
1. Direct and Manage Project Work Tools & Techniques
MODULE 7
Automated gathering and reporting on key performance indicators (KPI)
can be part of this system
570
07/07/2018
Executing Process Group
1. Direct and Manage Project Work Outputs
MODULE 7
performance measures, start and finish dates of schedule activities,
number of change requests, number of defects, actual costs, and
actual durations
572
07/07/2018
Executing Process Group
1. Direct and Manage Project Work Outputs
Change Requests
MODULE 7
Requests for a change can be direct or indirect, externally or internally
initiated, and can be optional or legally/contractually mandated
574
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
MODULE 7
576
07/07/2018
Executing Process Group
2. Manage Project Knowledge - Introduction
MODULE 7
578
07/07/2018
Executing Process Group
2. Manage Project Knowledge - Inputs, Tools, Outputs
MODULE 7
factors
Organizational process
assets
580
07/07/2018
Executing Process Group
2. Manage Project Knowledge Tools & Techniques
Information management
MODULE 7
Project management information system (PMIS)
582
07/07/2018
Executing Process Group
2. Manage Project Knowledge Outputs
MODULE 7
At the end of a project or phase, the information is transferred to an
OPAs called a lessons learned repository.
584
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
3. Manage Quality
MODULE 7
586
07/07/2018
Executing Process Group
3. Manage Quality - Introduction
MODULE 7
Uses data created during Plan Quality Management and Control Quality
(Monitoring and Controlling Process Group ) processes
588
07/07/2018
Executing Process Group
3. Manage Quality - Inputs
MODULE 7
Compare the processes used to create the measurements, and
validate actual measurements to determine their level of correctness
590
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
Data Representation
Cause-and-effect diagrams
MODULE 7
to the assignable cause upon which project teams should
implement corrective actions
592
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
Data Representation
Histograms
MODULE 7
- Columns represent an attribute (characteristics of a
problem/situation)
Data Representation
Histograms
MODULE 7
- This rule states that 80% of the problems come from 20% of the
causes.
596
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
Data Representation
Scatter Diagrams
MODULE 7
- The direction may be proportional (positive correlation),
inverse (negative correlation) or no correlation (zero
correlation)
598
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
Data Representation
Scatter Diagrams
- 3rd graph makes sense, more people studied, the higher their scores tended to be.
MODULE 7
- 2nd graph may indicates that the book they are reading is actually having a negative
effect.
600
- 1st graph may indicates that the material being used has no effect at all.
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
Design for X
MODULE 7
602
07/07/2018
Executing Process Group
3. Manage Quality Tools & Techniques
- Six Sigma
MODULE 7
604
07/07/2018
Executing Process Group
3. Manage Quality Outputs
MODULE 7
606
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
4. Acquire Resources
MODULE 7
608
Executing Process Group
07/07/2018
4. Acquire Resources - Inputs, Tools, Outputs
MODULE 7
- Stakeholder register
Enterprise environmental
factors updates
Organizational process
assets updates
610
07/07/2018
Executing Process Group
4. Acquire Resources Tools & Techniques
MODULE 7
612
07/07/2018
Executing Process Group
4. Acquire Resources Tools & Techniques
Virtual Teams
Records the team members and their roles and responsibilities for the
- Names inserted into other parts of the project management plan such as
project organization charts and schedules
MODULE 7
616
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
5. Develop Team
MODULE 7
618
07/07/2018
Executing Process Group
5. Develop Team - Introduction
MODULE 7
- Developing trust among team members
620
- Encouraging collaborative problem solving and decision making
07/07/2018
Executing Process Group
5. Develop Team Tools & Techniques
Colocation
Involves placing many or all of the most active project team members
MODULE 7
post schedules, and other conveniences that enhance communication.
622
07/07/2018
Executing Process Group
5. Develop Team Tools & Techniques
MODULE 7
locations without the benefit of face-to-face contact.
It is a never-ending process
624
07/07/2018
Executing Process Group
5. Develop Team Tools & Techniques
Training
MODULE 7
630
07/07/2018
Executing Process Group
MOTIVATION
MODULE 7
632
07/07/2018
Executing Process Group
Motivation Theory
MODULE 7
environmental factors
updates
Organizational process
assets updates
646
07/07/2018
Executing Process Group
6. Manage Team Tools & Techniques
Conflict Management
MODULE 7
definition.
648
07/07/2018
Executing Process Group
6. Manage Team Tools & Techniques
Conflict Management
Emotional intelligence
MODULE 7
652
07/07/2018
Executing Process Group
6. Manage Team Tools & Techniques
Leadership
MODULE 7
654
07/07/2018
Executing Process Group
List of Processes
MODULE 7
8 Implement Risk Responses Project Risk Management
9 Conduct Procurements Project Procurement Management
10 Manage Stakeholder Engagement Project Stakeholder Management
656
07/07/2018
Executing Process Group
7. Manage Communications - Introduction
MODULE 7
658
07/07/2018
Executing Process Group
7. Manage Communications - Introduction
MODULE 7
660
07/07/2018
Executing Process Group
7. Manage Communications Inputs
MODULE 7
662
07/07/2018
Executing Process Group
7. Manage Communications Tools & Techniques
MODULE 7
office support software, portals, and collaborative work management
tools
664
07/07/2018
Executing Process Group
7. Manage Communications Tools & Techniques
Project Reporting
Examples:
MODULE 7
- Summary of changes approved in the period
666
07/07/2018
Executing Process Group
7. Manage Communications Outputs
Project Communications
influenced by factors such as, the urgency and impact of the message,
its method of delivery, and level of confidentiality
MODULE 7
668
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
MODULE 7
670
07/07/2018
Executing Process Group
8. Implement Risk Responses Inputs, Tools, Outputs
Tools & Techniques Outputs
Inputs
Expert judgment Change requests
Project management plan
Data gathering Project management plan
- Resource management plan
- Interviews updates
- Risk management plan
Interpersonal and team - Schedule management plan
- Cost baseline
MODULE 7
environmental factors - Cost forecasts*
Organizational process - Alternatives analysis
- Lesson learned register
assets - Cost-benefit analysis
- Project schedule
Decision making
- Project team assignments
- Multi-criteria decision
672
analysis - Risk register
- Risk report
07/07/2018
Executing Process Group
8. Implement Risk Responses Tools & Techniques
Escalate
MODULE 7
Share Enhance
674
07/07/2018
Executing Process Group
8. Implement Risk Responses Tools & Techniques
Some responses are designed for use only if certain events occur.
MODULE 7
Risk responses identified using this technique are often called
contingency plans or fallback plans
676
07/07/2018
Executing Process Group
8. Implement Risk Responses Outputs
Cost forecasts
MODULE 7
678
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
9. Conduct Procurements
MODULE 7
680
07/07/2018
Executing Process Group
9. Conduct Procurements - Inputs, Tools, Outputs
MODULE 7
Seller proposals
Enterprise environmental
factors
Organizational process assets
682
07/07/2018
Executing Process Group
9. Conduct Procurements - Inputs
Seller Proposals
MODULE 7
684
07/07/2018
Executing Process Group
9. Conduct Procurements Tools & Techniques
Bidder Conferences
Used to ensure that all prospective sellers have a clear and common
understanding of the procurement requirements
MODULE 7
686
07/07/2018
Executing Process Group
9. Conduct Procurements Tools & Techniques
Procurement Negotiations
Clarify the structure, requirements, and other terms of the purchases prior signing
the contract
MODULE 7
- technical solutions
- overall schedule
- payments and price.
688
07/07/2018
Executing Process Group
9. Conduct Procurements Outputs
Agreements
Includes terms and conditions, and may incorporate other items that
MODULE 7
seller to provide the specified products, services, or results, and
obligates the buyer to compensate the seller
690
07/07/2018
EXECUTING PROCESS GROUP
Executing Process Group
MODULE 7
692
07/07/2018
Executing Process Group
10. Manage Stakeholder Engagement - Introduction
MODULE 7
during the initial stages and gets progressively lower as the project
progresses.
694
07/07/2018
Executing Process Group
10. Manage Stakeholder Engagement Tools & Techniques
Ground Rules
MODULE 7
Example everyone on the project shares responsibility for protecting the
security of project data.
696
07/07/2018
Project Management Framework 1/2
Project Integration Develop Project Develop Project Direct and Manage Monitor and Close Project or
Management (7) Charter Management Plan Project Work Control Project Phase
Manage Project Work
Knowledge Perform
Integrated Change
Control
MODULE
Durations
Develop Schedule
698
Project Quality Plan Quality Manage Quality Control Quality
Management (3) Management
07/07/2018
Monitoring and Controlling Process Group
List of Processes
MODULE
10 Monitor Risks Project Risk Management
11 Control Procurements Project Procurement Management
12 Monitor Stakeholder Engagement Project Stakeholder Management
700
07/07/2018
Monitoring and Controlling Process Group
1. Monitor and Control Project Work - Introduction
MODULE
702
07/07/2018
Monitoring and Controlling Process Group
1. Monitor and Control Project Work - Inputs
MODULE
(BAC)
704
07/07/2018
Monitoring and Controlling Process Group
1. Monitor and Control Project Work - Inputs
MODULE
706
07/07/2018
Monitoring and Controlling Process Group
1. Monitor and Control Project Work Tools & Techniques
Alternatives analysis used to select the corrective actions and/or preventive actions
to implement when a deviation occur.
Cost-benefit analysis help to determine the best corrective action in terms of cost
Root cause analysis focuses on identifying the main reasons for a deviation and the
areas the project manager should focus on.
MODULE
Trend analysis used to forecast future performance based on past results.
MODULE
- Defect repair - activity to modify a nonconforming product or product
component
710
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control - Introduction
MODULE
without consideration to the overall project objectives or plans.
712
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control - Introduction
MODULE
714
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control - Introduction
MODULE
registered, assessed, approved, tracked, and correctly implemented
716
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control - Inputs
MODULE
718
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control Tools & Techniques
Identify changes
Document changes
Decide on changes
Track changes
MODULE
720
07/07/2018
Monitoring and Controlling Process Group
2. Perform Integrated Change Control Outputs
MODULE
722
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
3. Validate Scope
MODULE
724
07/07/2018
Monitoring and Controlling Process Group
3. Validate Scope - Introduction
MODULE
Control Quality is generally performed before Validate Scope
726
07/07/2018
Monitoring and Controlling Process Group
3. Validate Scope - Inputs
MODULE
728
07/07/2018
Monitoring and Controlling Process Group
3. Validate Scope Outputs
MODULE
730
07/07/2018
Monitoring and Controlling Process Group
4. Control Scope - Introduction
The key benefit of this process is that it allows the scope baseline to
be maintained throughout the project.
MODULE
732
07/07/2018
Monitoring and Controlling Process Group
4. Control Scope - Inputs, Tools, Outputs
MODULE
matrix
Work performance data
Organizational process
assets
734
07/07/2018
Monitoring and Controlling Process Group
4. Control Scope Tools & Techniques
MODULE
736
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
5. Control Schedule
MODULE
738
07/07/2018
Monitoring and Controlling Process Group
5. Control Schedule - Introduction
MODULE
Managing the actual changes as they occur
740
07/07/2018
Monitoring and Controlling Process Group
5. Control Schedule - Inputs, Tools, Outputs
MODULE
Resource optimization
Work performance data
Leads and lags
Organizational process
assets Schedule compression
742
07/07/2018
Monitoring and Controlling Process Group
5. Control Schedule Tools & Techniques
MODULE
744
07/07/2018
Monitoring and Controlling Process Group
5. Control Schedule Tools & Techniques
Example: technical writing team can adjust the start of editing the
MODULE
746
07/07/2018
Monitoring and Controlling Process Group
List of Processes
MODULE
10 Monitor Risks Project Risk Management
11 Control Procurements Project Procurement Management
12 Monitor Stakeholder Engagement Project Stakeholder Management
748
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs - Introduction
The key benefit of this process is that it provides the means to recognize
variance from the plan in order to take corrective action and minimize
risk.
Any increase to the authorized budget can only be approved through the
Perform Integrated Change Control process.
MODULE
Analyzing the relationship between the consumption of project funds to
the physical work being accomplished
750
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
Integrates the scope baseline with the cost baseline, along with the
schedule baseline, to form the performance measurement baseline.
MODULE
752
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
MODULE
The total planned value for the project is also known as budget at
completion (BAC)
754
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
MODULE
756
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
The difference between the earned value and the planned value
MODULE
Equation: SV = EV PV
758
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
SPI value less than 1.0 indicates less work was completed than was
planned
SPI greater than 1.0 indicates that more work was completed than was
MODULE
planned
Tools include:
- Charts
- Forecasting
MODULE
762
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
EAC may differ from the budget at completion (BAC) based on the
project performance
EAC = the actual costs incurred for work completed (AC) + estimate
to complete (ETC) the remaining work
MODULE
764
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
EAC forecast for ETC work performed at the present CPI typical
- Assumes what the project has experienced to date can be expected to
continue in the future
MODULE
766
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
MODULE
768
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
MODULE
770
07/07/2018
Monitoring and Controlling Process Group
6. Control Costs Tools & Techniques
MODULE
772
07/07/2018
Monitoring and Controlling Process Group
List of Processes
MODULE
10 Monitor Risks Project Risk Management
11 Control Procurements Project Procurement Management
12 Monitor Stakeholder Engagement Project Stakeholder Management
774
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality - Introduction
MODULE
776
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality - Introduction
Prevention
- keeping errors out of the process
Inspection
- keeping errors out of the hands of the customer
MODULE
778
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality - Introduction
Tolerances
- specified range of acceptable results
Control Limits
- identify the boundaries of common variation in a process
MODULE
780
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality Inputs
Deliverables
They are outputs from the Direct and Manage Project Work process
MODULE
which are inspected and compared to the acceptance criteria defined
in the project scope statement.
782
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality Tools & Techniques
MODULE
784
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality Tools & Techniques
MODULE
specification limits
786
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality Tools & Techniques
MODULE
788
07/07/2018
Monitoring and Controlling Process Group
7. Control Quality Outputs
MODULE
790
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
8. Control Resources
MODULE
792
07/07/2018
Monitoring and Controlling Process Group
8. Control Resources - Inputs, Tools, Outputs
MODULE
- Influencing
Agreements
Project management
Organizational process assets
information systems
794
07/07/2018
Monitoring and Controlling Process Group
8. Control Resources Tools & Techniques
MODULE
Solve. Choose the suitable solution
796
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
9. Monitor Communications
MODULE
798
07/07/2018
Monitoring and Controlling Process Group
9. Monitor Communications - Inputs, Tools, Outputs
MODULE
factors
Organizational process
assets
800
07/07/2018
Monitoring and Controlling Process Group
9. Monitor Communications Outputs
MODULE
802
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
MODULE
804
07/07/2018
Monitoring and Controlling Process Group
10. Monitor Risks - Introduction
MODULE
Contingency reserves for cost or schedule require modification
806
07/07/2018
Monitoring and Controlling Process Group
10. Monitor Risks Inputs
MODULE
Time and cost contingency reserves
* The watch list is within the risk register and provides a list of low-priority risks
808
07/07/2018
Monitoring and Controlling Process Group
10. Monitor Risks Tools & Techniques
MODULE
810
07/07/2018
Monitoring and Controlling Process Group
10. Monitor Risks Outputs
MODULE
with the project management plan
812
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
MODULE
814
07/07/2018
Monitoring and Controlling Process Group
11. Control Procurements - Inputs, Tools, Outputs
MODULE
process assets
updates
816
07/07/2018
Monitoring and Controlling Process Group
11. Control Procurements Inputs
MODULE
818
07/07/2018
Monitoring and Controlling Process Group
11. Control Procurements Tools & Techniques
MODULE
inability to perform work
820
07/07/2018
Monitoring and Controlling Process Group
11. Control Procurements Outputs
The buyer provides the seller with formal written notice that the
contract has been completed.
MODULE
Project management team should have been approved all deliverables
prior to closure.
822
07/07/2018
MONITORING AND CONTROLLING PROCESS GROUP
Monitoring and Controlling Process Group
MODULE
824
Monitoring and Controlling Process Group
07/07/2018
12. Monitor Stakeholder Engagement - Inputs, Tools, Outputs
MODULE
- Cultural awareness
- Leadership
- Networking
826
- Political awareness
Meetings
07/07/2018
Monitoring and Controlling Process Group
12. Monitor Stakeholder Engagement Tools & Techniques
retrospectives
MODULE
828
MODULE 8
GROUP
CLOSING PROCESS
MODULE 9
Project Plan Procurement Conduct Control
Procurement Management Procurements Procurements
Management (3)
832
07/07/2018
CLOSING PROCESS GROUP
Closing Process Group
MODULE 9
834
07/07/2018
Closing Process Group
1. Close Project or Phase - Introduction
Ensuring that all documents are up-to-date and all issues are resolved
Reassigning personnel
MODULE 9
Reallocating project facilities, equipment and other resources
Other Activities:
MODULE 9
Collecting any suggestions for improving the policies and procedures
Data Analysis
MODULE 9
840
07/07/2018
Closing Process Group
1. Close Project or Phase Outputs
Final Report
Quality objectives
Cost objectives
MODULE 9
Schedule objectives
Summary of the validation information for the final product, service or result
MODULE 10
These characteristics present problems for traditional predictive
approaches. Instead, agile approaches were created to solve these
problems.
844
07/07/2018
1. An Introduction to Agile
The agile manifesto and mindset
Increased efficiency checking every task for value added and non-value
added activities
MODULE 10
Team member focus because the work in progress is limited
852
removed
07/07/2018
1. An Introduction to Agile
Scrum
The scrum team consists of product owner, scrum master and cross-
functional development team.
MODULE 10
854
07/07/2018
2. Life Cycle Selection
MODULE 10
856
07/07/2018
2. Life Cycle Selection
Agile life cycle
MODULE 10
- Flow-Based Agile (team pulls features from the backlog based on its capacity.
Each feature may take a different amount of time to finish).
858
07/07/2018
2. Life Cycle Selection
MODULE 10
Try these techniques on a less risky project, then try more
complex one.
864
07/07/2018
Implementing Agile:
3. Creating an Agile Environment
Servant leadership
MODULE 10
Process: don t plan on following the perfect agile process,
but instead look for the result.
866
07/07/2018
Implementing Agile:
3. Creating an Agile Environment
Servant leadership
MODULE 10
Help the team technical activities
868
Implementing Agile:
07/07/2018
3. Creating an Agile Environment
They need also to create a quite spaces for workers who need uninterrupted
MODULE 10
Fishbawl window: setting-up long-lived video conferencing. Start the link at the
begging of the workday and close it at the end.
Team values
MODULE 10
874
07/07/2018
Implementing Agile:
4. Delivering in an Agile Environment
Common agile practices Backlog preparation and refinement
MODULE 10
through a 2-week iteration) used to refine enough stories so the
team understands what the stories are and how large the
stories are in related to each other.
876
07/07/2018
Implementing Agile:
4. Delivering in an Agile Environment
Common agile practices Demonstrations/Reviews
MODULE 10
product at least once every weeks.
878
07/07/2018
Implementing Agile:
4. Delivering in an Agile Environment
Execution practices that help teams deliver value
MODULE 10
Acceptance Test-Driven Development (ATDD). The entire
team discuss the acceptance criteria then create the tests, which
allows the team to write just enough code to meet the criteria
880
07/07/2018
Implementing Agile:
4. Delivering in an Agile Environment
Measurements in agile projects
MODULE 10
Burndown charts represents the remaining work
07/07/2018
AGILE PRACTICE GUIDE
MODULE 10
886
07/07/2018
Implementing Agile:
4. Delivering in an Agile Environment
Measurements in agile projects EVM in Agile