Академический Документы
Профессиональный Документы
Культура Документы
OCT 2018
Document No.: SEWA-E-D-004 Rev.: 0
Revision History:
Sharjah Electricity & Water Authority Page 1 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
CONTENTS:
Sharjah Electricity & Water Authority Page 2 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 3 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
1.1 SCOPE
This specification covers the cable accessory and installation requirements for 11kV and 33 kV A.C. land
power cables with cross-linked polyethylene (XLPE) insulation, supplied to the Sharjah Electricity & Water
Authority (SEWA).
This specification shall be read in conjunction with the following documents which shall be considered as
an integral part of this Specification:
Along with the tender, Contractor shall furnish clause by clause compliance of the specification, complete
the supplementary technical schedules, and, where appropriate, submit additional supporting documents.
Except where modified by this specification, the cable accessory and installation shall conform to following
Standards and any document quoted in these Standards. The standards used shall be current at the date
of tender, together with any amendment issued to that date.
Cable Accessory
1 IEC 60230 ‘Impulse tests on cables and their accessories’
IEC 60502-2 ‘Power cables with extruded insulation and their accessories for rated voltages from
2 6kV (Um = 7.2kV) up to 30kV (Um = 36kV)’ – Part 2: Cables from rated voltages from 6kV (Um = 7.2kV)
up to 30kV (Um = 36kV)
IEC 60502-4 ‘Power cables with extruded insulation and their accessories for rated voltages from
3 6kV (Um = 7.2kV) up to 30kV (Um = 36kV)’ – Part 4: Test requirements on accessories for cables with
rated voltages from 6kV (Um = 7.2kV) up to 30kV (Um = 36kV)
IEEE Std 404 ‘IEEE Standard for extruded and laminated dielectric shielded cable joints rated 2.5 kV
4
to 500 kV’
BS EN 50181 ‘Plug-in type bushings above 1kV up to 52kV and from 250A to 2.5kA for equipment
5
other than liquid filled transformers’
BS EN 61442 ‘Test methods for accessories for power cables with rated voltages from 6kV (Um =
6
7.2kV) up to 36kV (Um = 42kV)’
ENA TS 09 - 13 ‘Performance specification for high voltage heat-shrinkable components for use with
7
high voltage solid type cables up to and including 33000 Volts’
Sharjah Electricity & Water Authority Page 4 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Cable Installation
8 IEC 60287 ‘Electric cables – calculation of the current rating’
IEC 60815 ‘Selection and dimensioning of high-voltage insulators intended for use in polluted
9
conditions’
10 IEC 60853 ‘Calculation of the cyclic and emergency current rating of cables’
IEC 60949 ‘Calculation of thermally permissible short-circuit currents, taking into account non-
11
adiabatic heating effects’
IEC 60986 ‘Short-circuit temperature limits of electric cables with rated voltages from 6kV (Um =
12
7.2kV) up to 30kV (Um = 36kV)’
13 BS EN 2484 ‘Specification for straight concrete and clayware cable covers’
14 BS EN 50522 ‘Earthing of power installations exceeding 1kV a.c.
15 BS 7430 ‘Code of practice for protective earthing of electrical installations’
ENA TS 09 - 02 ‘Specification for the supply, delivery & installation of power cables with operating
16
voltages in the range 33kV to 400kV and associated auxiliary cables’
17 ENA C55 ‘Insulated sheath power cable systems’
18 AEIC CG5 ‘Underground extruded power cable pulling guide’
* The nominal value shall be used during the tendering stage only and site measurement shall be arranged
by Contractor at its own cost after contract award. Solar radiation at cable terminations or unfilled surface
troughs shall be taken into consideration. If required, the Contractor shall design and propose any solar
mitigation measure to avoid deleterious effect on cable circuits.
Both 11kV and 33kV cable shall meet the requirements specified in IEC 60502-2 with copper/ aluminium
conductor, extruded XLPE insulation, and polyethylene oversheath. Refer to ‘Technical Specification for
33kV Underground Cables (Supply)’ and ‘Technical Specification for 11kV Underground Cables (Supply)’ for
detailed cable construction requirements.
● It is preference for 11kV cables, single-core design shall have 500mm2 conductor. Three-core design
shall have either 95mm2 or 400mm2 conductor.
Sharjah Electricity & Water Authority Page 5 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
● It is preference for 33kV cables, single-core design shall have either 240mm2 or 630mm2 conductor.
Three-core design shall have 400mm2 conductor.
● Inside substation area, both 11kV and 33kV cables shall be armour free with copper conductor. Outside
substation area, both 11kV and 33kV cables shall be protected by an armour layer.
The rating calculation should consider at least following aspects, conforming to IEC 60287, IEC 60853 and
IEC 60949:
● Cable continuous rating calculation under proposed circuit configuration (trefoil/ flat, solid/ special
bonding) and installation design (direct burial, duct, surface trough, etc.).
● Cable short circuit rating calculation using the non-adiabatic methodology.
● Cable emergency rating (overloading) calculation, starting from 0.5pu, 0.75pu of continuous rating for
an emergency period of 1hr, 3hr, 6hr, 12hr or any duration indicated by SEWA (if applicable).
● Thermal proximity effect evaluation and derating calculation when external heat sources are present (if
applicable).
The cable installation design shall conform to this specification, and the System Parameters for the rating
calculation are specified in Technical Specification for 11kV Underground Cables (Supply) and Technical
Specification for 33kV Underground Cables (Supply).
The 11kV/ 33kV cables and accessories shall be supplied, if instructed, with suitable spare quantity as
defined in the technical schedules.
Spare cable shall be delivered in a single continuous length. The designated spare cable lengths shall meet
all technical requirements of this document and shall not be of inferior quality to the installed system in
any respect. Acceptance Tests (SATs) shall be performed before handover of spares where reasonably
practicable.
Where cables are provided on drums, one or more steel drum(s) shall be supplied complete with pintle
stand or cradle/ skid and with covering suitable for long term outdoor storage for the design life of the
cable system. The spare cable drum(s) shall have access to the inner cable ends for testing with a tail
length of not less than 3m and shall be suitable for reeling/ unreeling with the use of a pintle stand or
cradle. Cable ends shall be sealed. Sheath repair kits and special tools shall be included in the spares
proposed by the Contractor.
The cable and accessories including spares shall be fully guaranteed for a minimum two years from
handover to SEWA. However, the warranty period shall be extended to five years to cover all defects
attributable to inadequate protection.
In the event of any defect occurring during the above period, the Contractor shall deliver all components
necessary to correct the fault, together with any necessary instructions and specialist assistance, with the
cost being covered by the Contractor.
Sharjah Electricity & Water Authority Page 6 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
2 CABLE ACCESSORIES
This section specifies the technical requirements for 11kV and 33kV underground cable accessories
including terminations and joints. They shall be made by the same cable manufacturer to ensure
compatibility, reliability and responsibility.
The designed life of all cable accessories shall not be less than the associated power cables. Preference is
given to longer life designs and minimum maintenance requests.
In general, the joint design shall be suitable for 11kV and 33kV XLPE insulated cables with nominal
conductor sizes specified in Section 1.4. In addition, following technical requirements shall be met as a
minimum:
● A sufficiently rated current connection between conductors under both normal and fault conditions as
specified in ‘Technical Specification for 33kV Underground Cables’ and ‘Technical Specification for 11kV
Underground Cables’. It shall have a resistance not exceeding that of an equivalent length of
conductor.
● A joint insulation which meets the same performance standard as the cable.
● A high current connection to permit the flow of short circuit current between the two cable sheaths or
screen wires (if applicable). System parameters are specified in Technical Specification for 11kV
Underground Cables and Technical Specification for 33kV Underground Cables.
● A metallic joint shell or screen wire connection electrically insulated from earth potential to match the
insulation integrity of the cable oversheath.
● A protection of the joint and cable insulation against the ingress of water.
● A protection against corrosion of the joint metal work.
● An appropriate screen interruption to assist cable bonding requirement (if applicable).
The joint design shall confirm to IEEE 404 and the test requirements specified in IEC 60502-4. Preference is
given to prefabricated joints (either composite type or pre-moulded type) and heat/ cold shrink sleeve
joints. If heat shrink sleeve joints are proposed, the material performance shall meet the requirements
specified in ENA TS 09 – 13.
All joints shall have the surfaces tinned to prevent oxidization and shall be riveted and soldered, or where
specially approved, bolted and soldered or welded. Each joint shall be permanently clearly labelled
detailing the 1) Feeder Identification 2) Joint Number 3) Joint Phase colour.
The jointing kit shall include splicing instructions and all necessary materials such as consumable material
and other components to complete the jointing work. All materials of cable joints and its associated
consumable equipment shall be environmentally friendly and do not cause any hazard to the personnel
who are carrying out the termination work.
Sharjah Electricity & Water Authority Page 7 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
In general, the termination design shall be suitable for 11kV and 33kV XLPE insulated cables with nominal
conductor sizes specified in Section 1.4. In addition, the following technical requirements shall be met as a
minimum:
● A sufficiently rated current connection from the cable conductor to an external busbar.
● Insulation to the same performance standard as the cable.
● Provision of support to the cable.
● Ability to withstand cable thermomechanical loads and external forces such as wind and
● busbar loading.
● A high current connection to permit the flow of short circuit current from the cable metallic sheath or
shield wires via a bonding lead to the system earth. System parameters are specified in Technical
Specification for 11kV Underground Cables and Technical Specification for 33kV Underground Cables.
● A connection to the cable metallic sheath or earth wires which is electrically insulated from earth
potential to match the insulating integrity of the cable oversheath.
● Protection to the cable insulation and sheath against the ingress of atmospheric water and the ingress
of pressurised dielectric liquid or gas from adjacent metalclad busbar trunking.
Both indoor and outdoor termination design shall confirm to the test requirements specified in IEC 60502-
4. Preference is given to heat/ cold shrink sleeve terminations for connections to air insulated equipment
(e.g. AIB), and plug-in type terminations for connections to metalclad equipment (e.g. GIS). If heat shrink
sleeve terminations are proposed, the material performance shall meet the requirements specified in ENA
TS 09 – 13. If plug-in type terminations are proposed, they should also meet the requirements specified in
BS EN 50181. The specific creepage distance of outdoor insulation shall be not less than 53.7 mm/kV
based on the highest system phase-earth voltage.
For cables terminated into metalclad equipment with special bonding, the termination assembly shall
incorporate sheath sectionalising insulation. Where there is no transformer between the termination and
switchgear the sheath sectionalising insulation shall be protected against voltage flashover during
switching operations. Suitable methods are the use of sheath voltage limiters (SVLs) or short-circuit links.
In the latter case, two or more connections shall be provided no more than 500mm in length evenly
spaced around the sheath sectionalising insulation.
Outdoor cable termination shall not be protected by arc gaps. If the cable may be exposed to transient
voltages, surge arresters shall protect the cable.
All terminations shall have suitable finishes, incl. metal coating, plastic coating, painting, inorganic
treatment, etc., with high resistance to atmospheric conditions for metals liable to corrosion or rusting.
Each termination shall be clearly and permanently labelled detailing the 1) Feeder Identification 2) Joint
Number 3) Joint Phase colour.
The termination kit shall include splicing instructions and all necessary materials such as consumable
material and other components to complete the termination work. All material of cable terminations and
Sharjah Electricity & Water Authority Page 8 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
its associated consumable equipment shall be environmental friendly and do not cause any hazard to the
personnel who are carrying out the termination work.
3 CABLE INSTALLATION
This section specifies the installation requirements for 11kV and 33kV underground cables and
accessories. The installation shall be complete in every respect to allow uninterrupted use of the
equipment installed and to ensure security of electrical supplies. Every precaution shall be taken to ensure
that cables and accessories are not installed in a manner or under conditions likely to cause electrolytic or
other corrosive action or damage to, or be detrimental to the performance of the cables and accessories
during operation.
The work shall be carried out in accordance with the latest SEWA codes of practice and regulations in
relevance, together with any amendments instructed by SEWA. A copy of those documents may be
provided upon request.
The installation works shall be undertaken at all times by qualified staff and supplied with all the necessary
plant, equipment and tools. SEWA shall provide a clear working area and supply cables/accessories, while
the Contractor shall provide all the necessary tools, material and labour required to complete the
installation (incl. Site Acceptance Test).
No welding, filling or plugging of defective parts during the installation shall be permitted without the
approval from SEWA.
Contractor shall coordinate with town planning and other government agencies for the route approval,
minimum route length and route crossing, etc.
Contractor shall be responsible for determining the cable route in agreement with SEWA. A full risk
assessment and cost benefit analysis shall be carried out to ensure optimisation of cable route while
complying with relevant Sharjah road utilisation regulations.
Contractor shall agree with SEWA the position of trial holes along the proposed cable route (s) and
arrange excavation, in particular to fix joint bay and auxiliary equipment positions.
The exact location of each trench excavation and trial pit shall be subject to the approval of SEWA. Notice
shall be given by Contractor, and approval from SEWA shall be obtained before the commence of site
excavation work. During the excavation, relevant SEWA safety rules shall be strictly followed, and the
Contractor shall be responsible for public safety through proper measures approved by SEWA. Unless
otherwise agreed, provision shall be made during excavation for reasonable access of persons and vehicles
Sharjah Electricity & Water Authority Page 9 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
The excavation of trenches shall include the provision of necessary materials/tools/labour and removal of
any nature in all types of soil likely to be met and, thus Contractor may wish to examine the soil and
ground conditions through trial pits, if necessary. In known places of dense existences of electrical/other
services, only manual excavation shall be permitted. A proper management plan for excavated materials
shall be in place and agreed with SEWA, to avoid nuisance, traffic/ road interference, or possible damage
to other infrastructures in affected areas.
The cable trench shall be at least 1.2m depth and kept as straight as possible, conforming to approved
formation and dimension. Each trench shall have vertical sides and, where necessary, shall be timbered or
otherwise secured to avoid subsidence and damage. The trench bottom shall be free of all sharp objects
with a soft fill or sand bed of no less than 150mm. Particularly,
● In cases where subsidence hazards exist, a method of piling and rafting proposed by the Contractor
shall be agreed with SEWA before the cable laying;
● In cases where de-watering is required, the Contractor shall arrange at its own expense for the
required pump and machinery to maintain a dry condition during cable laying.
The Contractor shall be responsible for selecting the most appropriate cable laying method taking full
account of heat generation, thermal conductivity, installation conditions/ requirements, maintenance, and
all other cable performance related issues. A whole life cost analysis cost analysis shall be performed for
the various installation methods to ensure an optimised solution.
As the preferred method, direct burial shall be designed and constructed to ensure the integrity of the
cables and cable accessories, through appropriate trenching and backfilling. The nominal cable burial
depth (to cable/trefoil centre) is 0.8m for 11kV and 1m for 33kV. Under solid bonding, single-core cable
shall be in trefoil formation as shown in the typical installation drawings.
For direct buried cable circuits, there shall be a minimum separation of 500mm between adjacent circuits
(incl. associated pilot cables/multicores) or other unities to enable repairs while adjacent cable circuits
remain energised. Where this separation cannot be achieved, some offer from of physical separation shall
be provided to prevent damage to or physical contact with the energised cables.
All direct buried power cables and pilot cables/multicores shall be protected from external damage by
cable protection covers. Exemptions at certain locations, e.g. road crossings, HDDs, may be allowed where
not reasonably practicable and a written agreement with SEWA shall be sought.
Sharjah Electricity & Water Authority Page 10 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Cable protection covers may either be manufactured from reinforced concrete or from a polymeric
material. Reinforced concrete cable protection covers shall comply with the latest BS EN 2484 or
equivalent. Polymeric cable protection covers shall be interlockable and reasonably free of sharp edges,
burrs or surface projections that are likely to injure the installer.
Along the entire route including bends, the width of the cable protection covers shall be such that there is
a minimum 50mm overlap on each side of the cable or outside cable of a group of cables, if more than one
cover is to be used across the width of the cables the joint between covers shall lay above the space
between the cables and not over the cables. Where a stabilised backfill is used, the complete width of the
backfilled area shall also be covered by cable protection covers.
Identification warning tapes shall be laid 100mm above the cable protection covers with a minimum
thickness of 5mm. Above ground cable marker posts shall be placed at route stright sections in each 80m
and all route bends.
3.3.2 DUCTS
All duct installations shall meet the mechanical requirements of the cable system. For road crossings,
power cable shall be installed in ducts unless otherwise indicated by SEWA. Following minimum technical
requirements shall be met:
● The internal bore and radius of any bends shall not be less than that specified by the cable
manufacturer.
● Non-magnetic duct materials shall be used for single core AC cable installations.
● Duct joints, cable seals and duct mouth seals shall be designed to prevent the ingress of debris, other
materials and vermin. No bentonite refilled is allowed.
● Ducts shall have a smooth internal face and be brushed clean during installation.
● Ducts must remain free of debris during and after cable installation.
PVC/ Polyethylene duct is preferred with suitable marking indicated by SEWA. Concrete duct bank may be
considered where enhanced mechanical protection is required, e.g. road crossings with a minimum
concrete strength grade C20/25, or to improve the cable rating. In case of bridge crossings, the ducts may
be of galvanized steel pipe built into the bridge structure.
During installation, a draw line, or pulling wire, shall be in installed. This draw line shall be made of a
corrosion proof material and have a service live no less than the power cables. When the cable is not
drawn in immediately, the ends of the duct shall be sealed. For trefoil formation, three single ducts shall
be used. Power cable and associated pilot cables shall be in separate ducts.
Unless concrete duck bank has been installed, all direct buried ducts shall be protected from external
damage by cable protection covers, which shall follow the relevant requirements specified in Section
3.2.1.
For long duct runs where it may be necessary in the future to locate sheath faults, the installer shall
Sharjah Electricity & Water Authority Page 11 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
demonstrate that a technique exists that would enable the location of a sheath fault to within a 6 metre
length.
All surface trough installations shall meet the mechanical requirements of the cable system. For direct
burial design, less than 600mm depth, power cable shall be installed in surface trough unless otherwise
indicated by SEWA.
Either filled or unfilled surface trough can be proposed depending on specific rating calculation. The
trough lid shall be 5T rated as a minimum requirement or 11.5T rated if required by SEWA.
Where surface troughs are to be unfilled, the power cables shall be shaded from direct solar radiation,
restrained to prevent movement and the troughs shall be free from debris. Where surface troughs are to
be filled, stabilised backfill with thermal resistivity no more than 1.2K.m/W shall be used.
Cables installation in air shall be designed in such a way that ventilation is maximised. Sunshine shielding
shall be provided to avoid direct solar radiation.
Trench backfilling shall not be commenced until SEWA has inspected and approved the laid cables and
accessories at site. The trench surface shall be temporarily reinstated and maintained by Contractor in a
thoroughly safe condition until complete consolidation of the backfill is achieved.
A suitable backfill supplied by Contractor shall have thermal resistivity no greater than 1.2K.m/W.
Together with suitable cable protection covers; it shall provide sufficient protection against 5T loading as a
minimum or 11.5T loading if under traffic roads. For direct buried cables, a minimum backfill thickness of
75mm shall be provided above, below, and alongside the cables, extending the full width of the trench
and up to the cable protective cover.
As preference, backfill shall be in the form of 150mm layers with each layer being well rammed and
consolidated. Power rammers and metallic plate tampers shall not be used for compacting cable surround
backfill.
Where there is a risk of backfill movement, due to the action of water or soil subsidence, any necessary
precautions shall require the agreement of SEWA, examples of such precautions include:
Sharjah Electricity & Water Authority Page 12 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
A cable pulling calculation, conforming to AEIC CG5 or cable manufacturer recommendations, shall be
submitted to SEWA for approval before cable laying activity. During the laying, power cables shall be
pulled over sufficient rollers and particular attention shall be given to the provision and placing of rollers
at bends, to ensure that the minimum bending radius required by cable manufacturer is not exceeded.
The cable shall not rotate or twist during the laying in any circumstance, as a result of excessive pulling
tension and/ or insufficient rollers. Except for short route lengths agreed with SEWA, the pulling tension
shall not be borne by cable conductor through the application of double-thimble stockings or pulling eyes
wherever possible.
Contractor shall supply and install all the supports, e.g. racks, trays, cleats, clamps, saddles, etc. required
to carry and secure the cables, without risk or damage. The nominal support interval is 1m for rigid fixing
and 5m for flexible fixing, which needs to be agreed with SEWA.
The design of cable supports shall be suitable for either trefoil or flat cable formation and free of rough
edges, burrs and sharp corners. No materials shall be supplied which will cause corrosive impact in
contact. Cleats and/ or cable straps for single core AV cables shall be non-magnetic and be suitably spaced
to withstand forces and prevent damage to the cable during normal and short circuit conditions.
The design of cable supports for in air installation shall consist of vertical steelwork at approved intervals
and secured to walls, floors or ceilings, etc. The steelwork shall be designed to support a total weight no
less than 125% of cables and metallic fixings combined, plus an additional 100kg load at the extremity. The
steel used in construction of cable supports shall be galvanized.
Where cables are fixed to the floor of cable tunnel or basements, they shall be protected by heavy gauge
galvanized steel shrouds with steep sloping top, and firmly secured to the floor. The shrouds shall be
adequately ventilated, and the personal accessibility shall be retained within the confined area through
proper designs.
Cable joint bays shall be provided with a cast-in-situ concrete raft, made from C20/25 concrete, not less
than 150mm thick and with sufficient reinforcement to satisfy the cable system design requirements. To
facilitate the pumping, the raft shall be provided with adequate sump facilities.
The cable shall be suitably supported from the joint to the cable trench to prevent possible strains at the
joint entry due to cable settlement.
Cable identification tags in each 20m length to be provided in exposed trenches, basement cable ladders,
basement cable trays.
Sharjah Electricity & Water Authority Page 13 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Cable bonding design shall follow ENA C55, and solid bonding is generally preferred over special bonding
to avoid sheath induced voltage issue unless properly justified to SEWA.
The bonding and earthing design will ensure that any induced transient sheath voltages will not exceed
the rating of the cable oversheath, joint sheath sectionalising insulation, bonding leads, link housings or
any other part of the cable systems.
To ensure that induced transient sheath voltages do not exceed equipment ratings, sheath voltage limiters
(SVLs) may be installed at following common locations:
Note that an assessment of induced transient sheath voltages shall include the length of bonding leads,
and concentric bonding leads are typically used to minimise the impedance of the bonding lead and lead
length (under 10m).
Induced short circuit sheath voltages shall not exceed the rated SVL withstand voltages or that of any
other part of the cable system during normal, emergency or through fault conditions. It is recognised that
induced short circuit sheath voltages during internal cable faults may exceed the rating of parts of the
cable system, particularly the SVLs. However, any consequential failure shall be contained so that it does
not pose a health or safety risk.
Unless otherwise specified by SEWA, the cable system design shall be such as to ensure that there is a
continuous metallic return path of adequate cross section for the short circuit currents. Except for
connections to SVLs at unearthed positions, the link connections and bonding leads shall be capable of
carrying short circuit current the specified in Technical Specification for 11kV Underground Cables and
Technical Specification for 33kV Underground Cables, without sustaining any permanent damage.
Sheath voltages during single phase to earth short circuit fault conditions are greatly affected by the
grounding resistance at the cable terminations. Contractor shall be responsible for ensuring that the SVL
rated voltages shall not be exceeded during the external single phase to earth short circuit conditions.
Sharjah Electricity & Water Authority Page 14 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Where SVLs are in series, unless the SVLs are matched units, one of the SVLS is likely to be subjected to a
higher voltage than the other. Therefore, where matched SVLs are not used, the matched design SVL rated
voltage shall be increased by 20% to compensate for any such imbalance.
Where the SVLs star point is not connected to earth, transient voltages can occur across two SVLs in series
and the above requirement will apply.
Earth electrodes shall be designed to operate satisfactorily during faults, taking into account the area of
the electrodes in contact with earth, the soil resistivity and earth electrode current magnitude and
duration, in accordance with BS 7430. The fault duration time to be used for rating the electrodes is 3s.
Cable joint bay earth electrode systems shall achieve an earth resistance not greater than 10Ω. The earth
resistance shall be measured as specified in BS 7430.
Where earthing conductors cross over or are laid parallel and touching either power or multicore cables,
they shall be insulated at the point of contact to ensure that any potential rise of the earth conductor
cannot damage the cable sheath. Earthing conductors in air filled troughs shall be positioned so that any
passage of fault current through them shall not damage any multicore or power cables. Copper earthing
conductors likely to come into contact with galvanised steel shall be tinned to prevent electrolytic action.
For mechanical and electrical reasons the minimum cross section for copper earthing conductors shall not
be less than 100mm2. Buried horizontal earth conductors should be installed at depth of not less than
500mm below ground level so as to provide adequate protection against mechanical damage.
Earthing conductor joints shall not have impedance greater than the equivalent length of conductor which
shall be demonstrated to the satisfaction of SEWA. Exposed bolted earth connections shall be prevented
from becoming loose by providing a double bolted connection. To protect against corrosion, a heavy duty
bituminous paint or equivalent shall be applied to all joints below ground level. Brazed joints shall be
inspected prior to the application of the anti-corrosion coating.
At substations and cable sealing end compounds cable sheaths and/or SVL star points shall be bonded to
the substation or compound earthing system. At joint bays cable sheaths and/or SVL star points shall be
bonded to an earth electrode system. A separate earth electrode system shall be provided for each circuit.
The earth resistance of each electrode system shall be measured prior to any backfilling in the vicinity of
Sharjah Electricity & Water Authority Page 15 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
the electrodes.
Link boxes to be sited below ground shall be connected to the SVL star point earth connection or sheath
solid earth bond connection as appropriate.
4 TEST
Cable accessories shall pass the testing requirements specified in IEC 60504-4 and site acceptance test
(SAT) after installation shall be performed following IEC60502-2.
Where required from time to time by SEWA, Contractor shall subject complete portions of the cable
installations to voltage tests during cable laying to prove the integrity of the conductor insulation and the
integrity of the anti-corrosion protective covers. Before and after laying the power cables each drum
length cable shall be mongered with a 5kV megger and the value should be recorded and submitted to
SEWA.
The metallic sheath and armour of multi core cables shall be bonded together and to earth at all
terminating and jointing accessories. Solid bonding connections shall also be made between adjacent
multi core cables at terminations and joints subject to the requirements of anti-corrosion sheath DC
testing.
5 DOCUMENTATION
The following documents shall be submitted as a minimum requirement; SEWA retains the right to
request additional documents. The provision of these documents shall be covered by the contractual
price.
● With Tender (together with additional documents listed in Technical Specification for 11kV
Underground Cables and Technical Specification for 33kV Underground Cables
– Preliminary cable work programme
– Preliminary cable bonding diagram
– Preliminary cable route drawing
– Typical route section drawings
– Preliminary rating calculation under both continuous and fault condition
– Spare parts list (as per format provided, Schedule L)
– SEWA equipment maintenance list (as per format provided, Schedule M)
– SEWA equipment quantity list (as per format provided, Schedule G)
● After Contract Award (together with additional documents listed in Technical Specification for 11kV
Underground Cables and Technical Specification for 33kV Underground Cables
– Detailed cable work programme
– Certificate of compliance with the disposal of waste material (if applicable)
Sharjah Electricity & Water Authority Page 16 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
– Detailed cable route drawing, including existing services along the route, locations of joint bay, link
box chamber, communication chamber, major road/ bridge/ river crossings, crossing arrangement
with other services, and future access points/ routes for maintenance and repairs
– Survey reports and drawings
– Easements/ wayleaves details and drawings
– Local authority and other agreements
– Statutory constraints and work restrictions
– Detailed cable rating calculation as per requested (continuous, cyclic, emergency, fault) under
proposed installation.
– Cable pulling tension calculation
– Proposed cable pulling eye/ stocking
– Proposed cable lubricant for duct installation
– Bonding/ Earthing schematic drawing including phasing
– Bonding lead cross section drawing and technical schedule
– Sheath standing voltage calculations for the cable route (if applicable)
– Method statement describing the full sequence of laying works including excavation, handling of
material, method of laying
– Site test report
– Ducting/ backfill test report
– Spare storage methodology and guidance
– Details of storage facilities to be provided for spares
– Details of shelf life of spares items
All other information necessary for a full understanding and evaluation of the project shall be included.
The contractor shall comply with the following obligations in relation to the submission of any documents,
including but not limited to correspondence, drawings, calculations, letters, method statements, and
programmes:
● All documents shall be submitted in both hard copy and electronic form.
● One hard copy of all documents shall be submitted.
● Electronic copies shall only be submitted to the SEWA’s document management system.
● Contractor shall ensure that uploading shall be carried out at the same time as hard copy transfer so
the SEWA’s document management system reflects the true situation on correspondence transfer.
● Unsecured/ unapproved methods of transmission shall not be used by the contractor.
● Drawings for approval shall be submitted in one copy of paper prints and, after having been approved,
the tenderer shall supply any further copies required by SEWA, one copy at least on a digital media in
AutoCAD format or 3D format as agreed with SEWA.
● All drawings shall be to scale and fully detailed. All key dimensions shall be given and the material of
which each part is to be constructed shall be indicated.
Sharjah Electricity & Water Authority Page 17 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 18 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE B:
Sharjah Electricity & Water Authority Page 19 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Manufacturing test
programme
Prequalification test report
Type test report
Routine test report should be submitted within
Acceptance test report
14days following the completion of the test
Site test report
Backfill test report shall include backfill thermal
Ducting/ backfill test report resistivity and ambient temperature at proposed
burial depth if applicable
Cable delivery programme
Spare storage methodology
and guidance
Details of storage facilities to
be provided for spares
Details of shelf life of spare
items
Sharjah Electricity & Water Authority Page 20 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE C:
Sharjah Electricity & Water Authority Page 21 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE D:
As
As required
Number Description Unit confirmed
by SEWA
by Tenderer
General
1 Cable manufacturer
2 Manufacturing location
3 Place of testing and/or Inspection
4 Manufacturer's drawing and/or type designation
5 Type registration with SEWA
6 Operating frequency Hz 50
7 Voltage Uo/U (Umax) kV U=11kV
8 Power transmission MVA
Conductor
9 Conductor material (Cu/ Al)
10 Number of conductor core (1c/ 3cs)
11 Nominal cross sectional area (240/ 400/ 630) mm2
12 Cross sectional area mm2
13 Longitudinal conductor water blocking distance mm
14 Conductor water blocking material No
15 Conductor diameter mm
16 Number of conductor wires/ construction
Skin effect mitigation method (and/or surface
17
treatment)
18 Wire oxidation period (or other method if utilised)
19 Water blocking method
20 Ks
21 Kp
22 No. Segments (if segmented design)
Conductor Screen
23 Semiconducting binder tape material (if included)
24 Semiconducting binder tape thickness (if included) mm
25 Semiconducting binder tape coverage (if included) %
Conductor screen manufacturer/ compound
26
identification
27 Conductor screen thickness (minimum at a point) mm
28 Conductor screen thickness (nominal) mm
29 Diameter over conductor screen mm
Insulation
30 Insulation material (filled/unfilled XLPE)
31 Insulation material permittivity F/m
Sharjah Electricity & Water Authority Page 22 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 23 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 24 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
screen
Maximum impulse electric stress at conductor
108 kV/mm
screen
Maximum impulse electric stress at insulation
109 kV/mm
screen
110 Conductor dc resistance (20°C) Ω/km
111 Conductor ac resistance (20°C) Ω/km
112 Conductor ac resistance (90°C) Ω/km
113 Conductor ac resistance at operating temperature Ω/km
114 Metallic sheath/ screen dc resistance (20°C) Ω/km
115 Capacitance μF/km
116 Inductance (conductor/ metallic sheath, screen) μH/km
117 Symmetric conductor minimum S/C rating kA 25kA, 3 sec
Sharjah Electricity & Water Authority Page 25 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 26 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE F:
Sharjah Electricity & Water Authority Page 27 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE G:
QUANTITIES
Sharjah Electricity & Water Authority Page 28 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE L:
Sharjah Electricity & Water Authority Page 29 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE M:
Sharjah Electricity & Water Authority Page 30 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE N:
Sharjah Electricity & Water Authority Page 31 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 32 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Determination of the
29 elastic modulus of HEPR
insulation (if applicable)
Routine test
1 Partial discharge test
2 Voltage test
Electrical test on oversheath of
3 the cable
4 Spark test
5 Conductor resistance test
6 Metallic screen resistance test
7 Insulation screen cutting test
8 Cable markings examination
Sample test
9 Conductor examination
Measurement of thickness of
10
cable insulation and oversheath
Measurement of thickness of
11
metal sheath
12 Measurement of diameters
Measurement of electrical
13 resistance of conductor and metal
screen
Measurement of electrical
14 resistance of insulation and
conductor screens
15 Insulation screen strippability test
Irregularities of insulation and
16
screen check
17 Circularity check of insulated core
18 Shrinkage test of insulation
19 Water content test of insulation
Hot set test for XLPE, EPR and
20
HEPR insulations
21 Measurement of capacitance
Measurement of density of HDPE
22
insulation
23 Lightning impulse voltage test
24 Water blocking tape test
25 Water penetration test
Tests on components of cables
26 with a longitudinally applied metal
tape or foil, bonded or the
Sharjah Electricity & Water Authority Page 33 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
oversheath
Sharjah Electricity & Water Authority Page 34 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Tenderer to
confirm that
the tests will
be carried out
according to
Site Tests according to the
No. the testing Comment
relevant IEC standard
plan as
specified in
Schedule C
(confirmed/not
confirmed)
1 DC voltage test of the oversheath
2 AC voltage test of the insulation
Sharjah Electricity & Water Authority Page 35 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
1
2
3
Sharjah Electricity & Water Authority Page 36 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
SCHEDULE P:
TENDER DOCUMENTATION
Sharjah Electricity & Water Authority Page 37 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
sheets
Schedule P: Tendering
Y Y
document list
Schedule Q: Certificate of
Contractor, Engineer and Y
Staff
Sharjah Electricity & Water Authority Page 38 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
Sharjah Electricity & Water Authority Page 39 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
ANNEXURE-1:
Sharjah Electricity & Water Authority Page 40 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
ANNEXURE-2:
Sharjah Electricity & Water Authority Page 41 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
ANNEXURE-3:
Sharjah Electricity & Water Authority Page 42 of 43 All Rights are reserved
Document No.: SEWA-E-D-004 Rev.: 0
ANNEXURE-4:
Sharjah Electricity & Water Authority Page 43 of 43 All Rights are reserved