Your project has a very aggressive timeline and has adopted the Agile(SCRUM)
way of working. What techniques can help in better learning and sharing?
Ans: All of these (Organize frequent knowledge sharing sessions, Paired
responsibilities, Conduct retrospectives at the end of each sprint)

32. The Product owner in an Agile project...


Ans: Collaborates with the developers over prioritization of features, but he/she
has the final decision

33. Which of the following best describes the approach for determining the
iteration length?
Ans: The team should agree on the length of the iteration taking the size and
complexity of the project into consideration

34. How many roles are defined in a scrum?


Ans: 3.0

35. Which of the following are attributes of an Agile team?


Ans: All of these (Courage to change and adapt, Trust to fellow team members to do
the work, Responsiveness to change)

36. The recommended approach to design in an Agile project is:


Ans: Just enough design upfront

37. During a sprint the developers should be?


Ans: Able to contact to the Product Owner to clarify different aspects of the work

38. What is Kanban?


Ans: A visible chart of work to do, work in progress and work done

39. The Agile way is...


Ans: To produce working product of the right quality, early and incrementally

40. What does NOT match with Agile manifesto?


Ans: Processes and tools over individuals and interactions

41. In the popularization technique called "MoSCoW", the "M" stands for?
Ans: Must Have

42. The reason for holding regular Retrospectives is:


Ans: It allows learning which can be used to improve team performance

43. A development team determines that it has over-committed itself for a sprint.
In such a situation, who should be present when reviewing and adjusting the work
selected?
Ans: The Product Owner and the Development team

44. What do all Agile approaches have in common?


Ans: Iterative and incremental development

45. During an estimation meeting 3 team members are making an estimation for a
story. Individually they estimate the story at 1, 3 and 8 story points. Which
estimate should they use?
Ans: They should continue discussing the story until their estimates gets closer

46. The Agile process...


Ans: Encourages the team to meet regularly
47. Team A finished 43 story points in its last two-week iteration. Team B is
working on a separate project and has twice as many developers. It also completed
43 story points in its last two-week iteration. What does it imply?
Ans: You cannot say anything for sure

48. The Agile approach to documentation is:


Ans: Do the necessary documentation to support the development and use of the
product

49. Scrum master is introducing scrum to new development team. The development team
feels a retrospective is unnecessary. What action should the scrum master take?
Ans: Begin facilitating productive, useful retrospectives

50. An Agile approach advocates which of the following approaches?


Ans: Get something business-valuable delivered as quickly as possible, consistent
with the right level of quality

51. Why is the Daily Scrum held at the same time and same place?
Ans: The consistency reduces complexity and overhead

52. What is the purpose of sprint burn down chart?


Ans: It is used to measure how much work is left to be done

53. Daily standup meetings are not recommended for small items
Ans: False

54. Who is responsible for Product backlog?


Ans: Product Owner

55. The person who addressed ill defined or tricky problems as wicked problems?
Ans: Horst Rittel