Mobilisation Schedule - Periodic Maintenance of 110km Road in Lufwnyama

ID Task Task Name Duration Day -1 Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12 Day 13 Day 14 Day 15 Day 16 Day 17 Day 18 Day 19 Day 20 Day 21 Day 22 Day 23 Day 24 Day 25 Day 26 Day 27 Day 28 Day 29 Day 30 Day 31 Day 32 Day 33 Day 34 Day 35 Day 36 Day 37 Day 38 Day 39 Day 40 Day 41
1 MOBILISATION SCHEDULE 30 days MOBILISATION SCHEDULE

2 PREMOBILISATION 16 days PREMOBILISATION

3 Site Possession, Project Guarantees, 16 days


Project Insurance

4 MOBILISATION OF EQUIPMENT 7 days MOBILISATION OF EQUIPMENT

5 Excavator, Bulldozer, TLB, Front End 7 days


Loader, Tippers, Utility pickup, Roller
Compactors, Water bowser, Water pump,
Dumpy leveletc.

6 MOBILISATION OF KEY PERSONNEL 7 days MOBILISATION OF KEY PERSONNEL

7 Project Manager, Site Engineer, General 7 days


Foreman, Bricklayer Foreman, Carpenter
Foreman, Plumbing Foreman

8 SITE ESTABLISHMENT 12 days SITE ESTABLISHMENT

9 Site Isolation, safety warning, 12 days


Accomodation of Traffic

10 ESTABLISHMENT OF SITE OFFICE 7 days ESTABLISHMENT OF SITE OFFICE

11 Accomodation facilities, Power, Water 7 days


Connection, etc

12 RECRUITMENT 14 days RECRUITMENT

13 Recruitment of Skilled Workers and 7 days


General workers

14 Finish Mobilisation 0 days Finish Mobilisation

Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 17. Mobilisation Schedu
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Tue 21/01/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress

WOODLOCK LTD Page 1