Академический Документы
Профессиональный Документы
Культура Документы
1 Introduction................................................... 2
2 Applicable Reference Documents................. 3
3 Methodology................................................. 4
4 Responsibility/Workflow................................ 8
5 Data Collection............................................. 10
6 Reporting and Analysis................................ 11
7 Exhibits........................................................ 13
Exhibit I............................................................... 14
Exhibit II.............................................................. 17
Exhibit III............................................................. 19
Exhibit IV............................................................ 20
Exhibit V............................................................. 24
1 Introduction
1.1 Purpose
1.2 Definition
Page 2 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
project is ready for the next phase. This guideline explains in detail
criteria for selection, methodology, timing, data collection, and
reporting/analysis for external project benchmarking.
These “key” inputs include at least the level of project definition quality,
or front end loading (FEL), the role of value improving practices, and the
level of team development.
The latest edition of the following applicable reference documents shall be applied:
Page 3 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
3 Methodology
The analysis shall commence at the appropriate stage of the project, preferably
before approval of the DBSP, comparing key parameters of the project with an
external industry-wide database. The risk analysis will address key project
outcomes and associated risk based on the available information. PMOD/ESD
will make the determination of what projects will be subject to either external or
internal benchmarking.
Page 4 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
"Screening Review"
Benchmarking
(During Study Phase)
ERA
MC OS
DBSP STUDY Project Proposal Detail Design / Procurement
Construction Start-up Operations
FEL-1 FEL-2 FEL-3
"Closeout Review"
"Pacesetter Review" "Readiness Review" "Operability
Benchmarking Review"
"Closeout Review"
Benchmarking Benchmarking Benchmarking Benchmarking
(After Facility has been in
(At First Draft of DBSP) (At 90% PP) operation for at least six months)
Page 5 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Page 6 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
g. Diesel Hydrotreater
h. CCR Platformer
i. Isomerization Unit
Infrastructure
a. Cross Country Pipelines (Gas)
b. Cross Country Pipelines (Oil)
c. Cross Country Pipelines (Water)
d. Process Automation
e. Substation
f. Bulk Plants
g. Water Treatment Plants
Cogeneration Facility
a. Cogeneration
The benchmark report must identify whether the project is a Grass Root
Project or an expansion / revamp of an existing facility. The industry
projects used for benchmarks must be of similar nature as the Aramco
project being benchmarked.
Page 7 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
4 Responsibility/Workflow
4.1 Responsibility
The following sections outline the workflow that will normally be followed to
implement benchmarking:
PMOD/ESD will review the candidate projects with SAPMT and agree
on selected projects for external benchmarking and determine a likely
start date for initiating the benchmarking process. SAPMT must appoint
a designee for contact and coordination. This person will usually be the
Senior Project Engineer.
Page 8 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
paid out of TC-68 funds reserved for this purpose for FEL-1, 2 and 3
benchmarks and from approved ER funds for projects under execution.
Required metrics and data will be collected for the benchmarking effort
at any given stage of a project, Study Phase (FEL-1), DBSP (FEL-2),
Project Proposal (FEL-3) and Project Close-Out.
All cost and schedule data will be provided by PMOD/ESD and SAPMT
according to availability. Any additional data, e.g., schedules (level 1, 2
or 3 [Primavera format]), construction productivity, quantities,
constructability, safety, contractor data, Best Practices, Value
Improvement Practices, etc., will be obtained from PMT or FPD, as
required.
Page 9 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Draft and Final Reports will specifically address the following issues:
Assessment of scope clarity;
Completeness and quality of data available at preceding project
phases (FEL-1, 2, 3) if any;
Scope evolvement between study, DBSP and Project Proposal;
Comparison of Saudi Aramco with Industry averages as well as Gulf
Region averages;
Assess Market Conditions Impact on Projects;
Descriptions of comparable baseline projects in the consultant’s
database;
Benchmarking reports need to share a common format to ensure
consistency of presentation;
Items unique to Saudi Aramco should be identified and excluded
from the project benchmarking.
PMOD/ESD will share the draft report with SAPMT, evaluate its
implications for the project and discuss and agree with SAPMT any
comments and/or measures necessary to implement the consultant’s
recommendations. PMOD/ESD will respond to the Benchmarking
Consultant who will then issue the final agreed report.
5 Data Collection
PMOD/ESD will be the main contact and coordinator for collecting the data to perform
the benchmarking for all projects. The data collected for each phase needs to be
tailored to the phase at which the benchmarking is done. Thus, the questionnaire
provided by the benchmarking consultant needs to be specific to the phase at which the
project is benchmarked. Attached to this guideline are the templates detailing all the
Saudi Aramco required benchmarks (Cost, Schedule, Safety, Productivity, Value
Improving Practices, Others).
Page 10 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Saudi Aramco will provide the following key data at each phase:
The Benchmarking Report should be organized according to the WBS set by Saudi
Aramco in the methodology section of this procedure. Furthermore, the report must
contain all the metrics and analysis set forth in the results and outcome sections of this
report.
Page 11 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
All benchmarking requests and draft/ final reports should review Saudi Aramco’s
deliverables vs. the industry during all the benchmarking phases, study, DBSP, project
proposal and execution.
6.1 Preface
6.3 Introduction
Project Background;
Scope of Work and Project Technology, Assessment of scope clarity;
Retrospective evaluation of completeness and quality of data available at
preceding project phases (FEL-1, 2, 3) if any;
Other Project Issues including Contracting Strategy;
Description of Benchmark Projects and basis for their selection as
benchmarks.
6.5.1 COST
Contingency Allocation/Use;
Cost Performance;
Page 12 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
7 Exhibits
Exhibit I Readiness Form
Exhibit II Guideline for initiating a Service Order
Exhibit III Summary of Project Types/Subtypes
Exhibit IV Sample of Benchmarking Model for Crude Production Facility (GOSP)
Exhibit V Sample of Benchmarking Report for Crude Production Facility (GOSP)
Page 13 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Revision Summary
23 April 2013 Revised the “Next Planned Update” to occur after ATP recommendations. Reaffirmed the
content of the document, and reissued with editorial revision to revise department name.
Page 14 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Exhibit I
READINESS FORM
Project :
Description :
Your project will be performing a benchmarking analysis with IPA. To ensure the
appropriate information will be available for the analysis and make certain IPA’s
benchmarking effort depicts an accurate assessment of the Project, we are requesting
you complete the following questionnaire.
Based on your responses we will recommend an appropriate date for the study and data
collection meeting.
GENERAL ENGINEERING
If Yes, indicate the date when the soil and hydrology analysis planned effort will
be/was completed for the Project. _____________
2. Have all engineering studies been completed and results reflected in the project
scope and appropriate drawings? Yes No
If No, please list the remaining studies that impact project scope, cost or
schedule and note the planned completion date for each study.
______________________________________
______________________________________
______________________________________
______________________________________
Are there any outstanding issues affecting the project scope, cost or schedule
which are anticipated to be performed after ERA? Yes No
3. Indicate the date when the project proposal design drawings will be finalized
and received approval by the Proponent, Maintenance and other Stakeholder
Page 15 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
personnel as appropriate? (Note this does not mean he has to sign all the
drawings rather he is in agreement with the project proposal design effort).
If not what will be the outstanding issues and when will this agreement be
made?
Indicate the date when the ER estimate will be available to transmit to ESD. _________
VIPs
1. Based on the attached list indicate the Value Improvement Practices (VIP) the
PMT are planning to implement during the Project Proposal effort.
______________________________________
______________________________________
______________________________________
______________________________________
______________________________________
______________________________________
2. Indicate the date when all VIP, the project intends to implement, will be
complete _________.
Indicate the date when the Project Execution Plan incorporating all Project Proposal
activities, will be completed, approved and can be transmitted to IPA for the
benchmarking analysis _____________.
Page 16 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
1. Does the Saudi Aramco format of the ER estimate easily translate to a system of
progress measurement and control of cost to Saudi Aramco Cost Codes?
Yes No
4. When will the Cost and Schedule control plans be established and approved and
ready for review by IPA? ____________.
5. Indicate the date when a level III schedule which represents an integrated logic
based CPM network diagram schedule derived from a critical path analysis
incorporating key equipment delivery and milestone dates be available for
transmittal to IPA for the benchmarking analysis. ___________.
If this information is not available, IPA’s analysis will indicate the project has
not reached readiness and although the Project Team is intending to perform
these activities prior to ERA, Management will see poorer results.
Page 17 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Exhibit II
GUIDELINES FOR INITIATING A
BENCHMARKING SERVICE ORDER WITH ASC
To add a project to the process for benchmarking, the following items are first
transmitted to ASC.
1. BI number and name of project.
2. Budget Item scope of work (BISI or equivalent).
3. Benchmark services start date.
4. PMOD/ESD contact name (and alternate)/mailing address/phone/fax.
5. Project specific requirements (e.g. benchmark completion date, etc.).
6. Target date for interview with project team.
Page 18 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
CONTACTS
ASC - Primary Contact:
Name:
E-Mail:
Address: Aramco Services Company
9009 West Loop South
M.S. 1093/Rm. 10147
Houston, Texas 77096
Phone: +1-713-432-4577
Fax: +1-713-432-4041
Page 19 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Exhibit III
Page 20 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Exhibit IV
SAMPLE BENCHMARKING MODEL FOR
CRUDE PRODUCTION FACILITY (GOSP)
UNIT
AREA NAME PARAMETER UOM QUANTITY COST COST
Page 21 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
CRUDE
STABILIZATION UNIT CAPACITY MBD $ $
COGENERATION
FACILITY ISO RATING MW $ $
SITE PREPARATION SM $ $
CONCRETE CM $ $
STRUCTURAL STEEL TONS $ $
FENCING LM $ $
Page 22 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Page 23 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
VALUE
LIST OF VALUE PRACTICES IMPLEMENTED
PRACTICES
Page 24 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Exhibit V
SAMPLE BENCHMARKING REPORT FOR
CRUDE PRODUCTION FACILITY (GOSP)
Unit Cost Analysis Comparison with Worldwide Regions
Page 25 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Ratio to Total
Basic Engineering Cost
Installed Cost
Ratio to Total
Detailed Engineering Cost
Installed Cost
Ratio to Total
Total Material
Installed Cost
Ratio to Total
Total Direct Construction
Installed Cost
Ratio to Total
Total Indirect Construction
Installed Cost
Page 26 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Ratio to Total
Inlet Facility
Installed Cost
Ratio to Total
Production Traps
Installed Cost
Ratio to Total
Gas Gathering
Installed Cost
Ratio to Total
Wet Crude Handling
Installed Cost
Ratio to Total
Condensate Stabilization
Installed Cost
Ratio to Total
Crude Stabilization
Installed Cost
Ratio to Total
Water Injection Facility
Installed Cost
Ratio to Total
Cogeneration Facility
Installed Cost
Ratio to Total
Total Saudi Aramco
Installed Cost
Page 27 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Page 28 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Industry Average
Saudi Aramco
Study FEL-1
DBSP FEL-2
FEL-3
PP
SCHEDULE
Feed Duration/Total Direct Construction Manhours * * * * * * *
Execution Duration/Capacity * * * * * * *
Overall Duration/Capacity * * * * * * *
FEED Duration/Overall Duration * * * * * * *
Detailed Eng. Duration/Overall Duration * * * * * * *
Construction Duration/Overall Duration * * * * * * *
Shutdown Duration * * * * * *
PRODUCTIVITY
Direct Detailed Engr. Manhours / Quantity (by discipline) * * * *
Direct Const. Manhours/Quantity (by discipline) * * * *
Direct Eng Rework Manhours/Total Direct Eng Manhours * * * *
Direct Consat. Rework Manhours/Total Direct Constr.
* * * *
Manhours
Total FEED Eng Manhours/Capacity * * * * *
Total FEED PMT Manhours/Capacity * * * * *
Total PMT Manhours/TIC * * * *
Detailed Engr Manhours/TIC * * * *
Total Direct Const Manhours/TIC * * * *
Process Eng Manhours * * * *
PMT Manhours/Eng Manhours * * * *
Page 29 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Industry Average
Saudi Aramco
Study FEL-1
DBSP FEL-2
FEL-3
PP
SAFETY
Total Recordable Incident Rate * * * *
Dart Rate * * * *
OTHER
Complexity * * * * * * *
Facility Location * * * * * * *
Contract Strategy for FEED * * * * * *
Contract Strategy for EPC * * * * *
Project Team Size * * * * *
Owner Team Size (FTE) and Composition * * * * *
PMT Turnover * * * * *
Equipment Count/Capacity * * * * * * *
Construction Quantity/Capacity * * * * *
Plot Area/Capacity * * * * * * *
Avg. Constr. Craft Hours/Week * * * *
Page 30 of 31
Document Responsibility: Project Management Office Department SAEP-26
Issue Date: 23 April 2013
Next Planned Update: 23 April 2014 Capital Project Benchmarking Guidelines
Industry Average
Saudi Aramco
Study FEL-1
DBSP FEL-2
FEL-3
PP
PROCESS TYPE PARAMETERS
Hydrotreaters * * * * * * *
Recycle Rate * * * * * * *
Design Pressure * * * * * * *
ppm Sulfur Product * * * * * * *
ppm Sulfur Feed * * * * * * *
ppm Nitrogen product * * * * * * *
ppm Nitrogen feed * * * * * * *
Hydrogen consumption * * * * * * *
# of Reactors * * * * * * *
Page 31 of 31