Written CETI - JJGD

METHODOLOGY FOR TESTING OF SCHNEIDER Date AUGUST 13, 2019


MCC BLOKSET Client WYETH PHILIPPINES
SO Number CETI SO2017-090

ITEM DATE TIME ACTIVITIES RISK RISK CONTROL


 Temporary cable may cause trip  Covering cables that cross
Layout of Cables from Proposed
hazard walkways
1:00pm- Location of Genset Rental to
1 8/13/19  Keeping working areas and
6:00pm MCC termination point (See
attached Proposed Location) walkways well lit

 Generator set is not compliant as  Provide inspection checklist as per


9:00am- Pre- Entry Inspection of Rental
2 8/14/19 per requirement the requirement and should be
10:00 am Genset
inspected prior to entry at the plant
-Preparation of Rental Genset  Unauthorized person  Only competent and authorized
3 8/14/19
10:00am- (No Load test)  Electrocution person to do the inspection, ensure
11:00am - Checking of Generator Set notified the client with all necessary
parameters documents.
 Slips, trips and fall at the same  Competent workers to be deployed,
level. supervisor to check the competency
of the workers.
 Use of sharp hand tools.  When doing the termination in
 Competency of electrician/cable existing system ensure that power
jointer. is isolated and no current in the
 Using damaged hand tools/ working place.
Torque wrench  All hand tools must be in good
Termination of Temporary  Using damaged hydraulic condition with valid colour code, no
11:00am - crimping too homemade hand tools to be used at
4 8/14/19 cables to Generator Set and
12:00pm site, supervisor to check.
MCC
 Torque wrench must be in good
condition with calibrated sticker on
it. Supervisor to check.
 Supervisor to ensure the
competency of electrician/cable
jointer.
 Ensure that hydraulic crimping tool
to be used is calibrated and
functional
Written CETI - JJGD
METHODOLOGY FOR TESTING OF SCHNEIDER Date AUGUST 13, 2019
MCC BLOKSET Client WYETH PHILIPPINES
SO Number CETI SO2017-090

 Ensure that crimping tool must be


compatible or same size with the
lugs or connectors.
5 8/14/19 1:00 - Testing of MCC Blokset  Access towards to the testing area
onwards to be barricaded and watchman to
be posted.
 Testing area to be barricaded and
proper sign boards to be placed
which read "TESTING IN
 Unauthorized person. PROGRESS KEEP AWAY".
 Electrocution  Avoid cable joint.
 Ensure that all power power sources
to be connected with ELCB.
 All testing equipments must be in
good condition and with valid test
calibration.
 Clear everybody from the area
where testing is in progress.
 Using damaged testing  All testing equipments must be in
equipment. good condition and with valid
calibration test certificates.
 Slip / Trip / Fall - same level  Maintain good housekeeping
around the working area.
 Walkway and gangway to be kept
free of obstruction.
 All temporary cable should be
properly organized.