Вы находитесь на странице: 1из 1

CALCULO DE CARGAS TRABES DE ACERO DE 300/74 kg PLANTA BAJA

W = ML 74.00
No. EJE DISTANCIA KG/ML TOTAL (W)
TB - 19 1 A-B 6.95 74.00 514.30
TB - 20 1 B-C 4.75 74.00 351.50
TB - 21 A 1-2 3.90 74.00 288.60
TB - 22 B 1-2 3.90 74.00 288.60
TB - 23 C 1-2 3.90 74.00 288.60
TB - 24 2 A-B 6.95 74.00 514.30
TB - 25 2 B-C 4.75 74.00 351.50
TB - 26 A 2-3 4.30 74.00 318.20
TB - 27 B 2-3 4.30 74.00 318.20
TB - 28 C 2-3 4.30 74.00 318.20
TB - 29 3 A-B 6.95 74.00 514.30
TB - 30 3 B-C 4.75 74.00 351.50
TB - 31 A 3-4 5.75 74.00 425.50
TB - 32 B 3-4 5.75 74.00 425.50
TB - 33 4 A-B 6.95 74.00 514.30
TB - 34 A 4-5 2.35 74.00 173.90
TB - 35 B 4-5 2.35 74.00 173.90
TB - 36 5 A-B 6.95 74.00 514.30
Total Kg 6645.20